‘Tracks’ are actually 5 metre wide roads of crushed stone with soil and rubble piled alongside.
-
Upload
sheila-kelly -
Category
Documents
-
view
213 -
download
1
Transcript of ‘Tracks’ are actually 5 metre wide roads of crushed stone with soil and rubble piled alongside.
‘Tracks’ are actually 5 metre wide roads of crushed stone with soil and rubble piled alongside
Construction of turbine basesConstruction of turbine bases
Turbine base with concrete (note person top left)Turbine base with concrete (note person top left)
Turbine sections en route (1) Turbine sections en route (1)
Turbine sections en route (2)Turbine sections en route (2)
Getting turbine sections up hillsGetting turbine sections up hills
Delivery of generator section (Nacelle)
Huge machine holds turbine sections upright
Erected column & nacelle
Erection of columns. Moudy Mea in 2010?
Delivery of turbine bladesDelivery of turbine blades
Blade attachment
Almost complete
Black Law w/f, Forth, Scotland. 12 turbines 330 ft high – note Transit van
ConclusionsConclusions1. Building wind power stations is heavy
engineering on a massive scale
2. There will be inevitable damage and destruction
3. The risk of siltation and run off is high
4. Such structures cannot be ‘mitigated’
5. The visual damage will last a generation or more
OutlineOutline1. A brief look at the proposal
2. Building a wind power station on Moudy Mea
3. Misconceptions and myths about wind power
MISCONCEPTIONSMISCONCEPTIONS
Britain has a huge wind resource which can meet most of our power needs
WRONG
Annual 1971-2000
2.3 to 8.0
8.0 to 11.5
11.5 to 16.1
16.1 to 20.7
20.7 to 27.6
27.6 to 34.5
34.5 to 36.0
Mph
Guernsey = 14.1 mph
Jersey = 13.0 mph
‘The climate of the UK and recent trends’. Published by the UK Climate Impacts Programme and the Meteorological Office. December 2007
MET OFFICE UK WIND SPEEDS
0
10
20
30
40
50
60
70
80
90
100
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38
Windspeed (miles/hour)
Da
ys
/yr
(ye
llo
w)
110 days
Wind speeds in the UK – Met Office data
0
10
20
30
40
50
60
70
80
90
100
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38
Windspeed (miles/hour)
po
we
r (r
ed
)73% 27%
Typical wind turbine power curve
0
10
20
30
40
50
60
70
80
90
100
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38
Windspeed (miles/hour)
Da
ys
/yr
(ye
llo
w)
& p
ow
er
(re
d)
73% 27%
What this means for electricity supplyWhat this means for electricity supply
• A wind farm will produce no electricity for up to 110 days a year (3.5 months)
• It will run at less than 25% of its potential output for a further 150 days (5 months)
• So we will only have significant electricity production for about 100 days a year
So how do we manage on low wind days?So how do we manage on low wind days?
We use BACK UP using
coal and gas fired power stations
Homes suppliedHomes suppliedDevelopers always state that a certain number of
homes will be supplied. In reality;• NO homes will be supplied for 110 days a year• Only about a quarter of those claimed will be
supplied for another 150 days.
• WITHOUT BACK UP FROM COAL OR GAS-FIRED POWER STATIONS WIND WOULD TOTALLY FAIL DOMESTIC USERS
A lesson from Germany
MYTHMYTH• Wind farms can replace nuclear power
WRONG
Base load and demandBase load and demand
Maximum ever UK demand was for 54,431 MW
on December 10th 2002
BASE LOAD – MAINLY
NUCLEAR
Submission to the House of Lords Economic Affairs Submission to the House of Lords Economic Affairs Committee Inquiry into the Economics of Renewables Committee Inquiry into the Economics of Renewables
from Eon (UK)from Eon (UK)
‘…if the UK required 40,000MW of wind capacity to met its renewables target by 2020, only 8% (3,600MW) could be relied upon to meet peak winter demand. This means that 36,400MW of renewable capacity would need to be backed up by thermal plant’.
Ref: SC/07-08/EA311
What does this mean?What does this mean?
• 36,400MW of new back up would require the building of;
• 20 to 30 new coal-fired new power station OR
• 40 to 70 new gas-fired power station
TOTAL COST = over £200 billion
MISCONCEPTIONMISCONCEPTION
Wind power stations reduce greenhouse gas emissions
VERY LITTLE IF ANY
VANISHING COVANISHING CO22 SAVINGS SAVINGS
0.98
0.86
0.65
0.270.37
0
0.2
0.4
0.6
0.8
1
1.2
A B C D E
ton
nes
/MW
hMid-
1990s
Dirty coal
1995-2007
BWEA2000DTI mix
OFGEM, DEFRA &
GOVT
TODAY DEFRA 2010
Quotation from the UKERC Report, The Costs and Impacts of Intermittency’ , March 2006
‘Actual CO2 savings are dependent on what fossil fuel plant is displaced, reduced by efficiency losses in thermal plant ……’
---------------------------------------------------------------------------
Seimens, Science in Parliament 60/2, April 2003
‘A 2% loss of efficiency in a coal-fired power station can increase CO2 emissions by 10%’
ARE THERE ANY SAVINGS?ARE THERE ANY SAVINGS?
“When plant is de-loaded to balance the system, it results in a significant proportion of the plant operating relatively inefficiently……
…..it has been estimated that the entire benefit of the renewables programme has been negated by the increased emissions from part loaded plant…….”
David Tolley (Innogy plc), Jan 2003, Address to the Institution of Mechanical Engineers
CATOTELM
ACROTELM
DRAINAGE AT CEFN CROES
Ditching round a turbine base
COCO22 pay back time for Stainmore wind pay back time for Stainmore wind
power stationpower station
if no peat on site = 2.3yrs
If average peat depth is 1 metre = 11.5yrs
If average peat depth is 2 metres = 21.6yrs
Assumptions 12 X 2.5MW turbines, LF = 30%, 12km of ‘track’, 1 borrow pits, 15,000 tonnes of aggregate, 12,000 concrete, CO2 displaced at 0.37t/MWh
What does the COWhat does the CO22 saving really mean? saving really mean?
If Stainmore is 12 x 2.5MW turbines the developer will claim a
saving of 29,170 tonnes of CO2 each year (based on 0.37t/MWh)
You may well say that is a lot to save BUTlook at it another way
What does the COWhat does the CO22 saving really mean? saving really mean?
If Stainmore saves 29,170 tonnes of CO2 each year
The Kingsnorth coal-fired power station proposed for
Kent will emit 21,978 tonnes per DAY
MYTHMYTH
• We can’t meet our future targets without a massive wind power
programme
FALSE