TR Scan No. 8 (Scope of Work) Redacted_Part2

1
Page 2 of3 Dear Tribes, scope_of_wcirk_for_archaeological_fieldwork_6-28-2013.docx Cathy asked that we prepare a scope of work (SOW) that better explains how we plan to conduct the surveys together this summer. Please refer to the attached file, and let myself, Alisa Reynolds, or Mark Robinson know if you have any questions or comments. We look forward to working with those of you who have expressed an interest, and we still have slots open for the sessions from August 12-August 21 and August 26-September 4. Thank you very much, and have a wonderful. weekend and holiday. Rick RICHARD STARZAK I Senior Architectural Historian{Technlcal Director I +1. direct I @icfi.com I icfi.com ICF INTERNATIONAL I 601 West 5th Street, Los Angeles, CA 90071 I +1. mobile Note n ew address and direct line. Connect with us on social media. From: [email protected] [mailto:[email protected]] Sent: Friday, June 07, 2013 9:57 AM To: Cc: [email protected]; Starzak, Richard; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; Summerville, Alan; Subject: Summer Archaeological Field Work - Tongue River Railroad Construction Project Importance: High Dear Tribes, Soon, we plan to begin the archaeological surveys to identify sites within each of the alternatives under consideration in the Tongue River Railroad Construction (TRRC) Project. The survey work will be conducted between mid-July and September. The archaeological surveys will be lead by ICF International, our third-party contractor for this project. Rick Starzak, of ICF, is the overall project director for the cultural resources portion of the TRRC Project and is currently organizing the field effort. I know that ICF has already contacted some of you regarding the summer field work. But there will be a total of four survey teams, each of which will be working during 10-day periods. I have attached a schedule of the work plan for your review. To ensure parity, each crew will consist of four ICF staff archaeologists and four tribal participants. The crews will be lead by senior ICF archaeologists. We have 16 potential slots for paid tribal representatives ( 4 field sessions and 4 tribal participants per session). This would be the case in the event we have different tribes make up each of the 16 tribal slots (unlikely, I know). To begin though, we are asking for one participant from each tribe to ensure that each interested tribe has an opportunity to provide at least one representative. Once we give each tribe an option to send one person, we will then look at our remaining needs and fill htm 1/11/')()1'

description

FOIA Document production from Surface Transportation Board request no. 15-012

Transcript of TR Scan No. 8 (Scope of Work) Redacted_Part2

Page 2 of3

Dear Tribes,

scope_of_wcirk_for_archaeological_fieldwork_6-28-2013.docx Cathy asked that we prepare a scope of work (SOW) that better

explains how we plan to conduct the surveys together this summer. Please refer to the attached file, and let myself, Alisa Reynolds, or Mark Robinson know if you have any questions or comments. We look forward to working with those of you who have expressed an interest, and we still have slots open for the sessions from August 12-August 21 and August 26-September 4.

Thank you very much, and have a wonderful. weekend and holiday. Rick

RICHARD STARZAK I Senior Architectural Historian{Technlcal Director I +1. direct I @icfi.com I icfi.com

ICF INTERNATIONAL I 601 West 5th Street, Los Angeles, CA 90071 I +1. mobile

Note new address and direct line. Connect with us on social media.

From: [email protected] [mailto:[email protected]] Sent: Friday, June 07, 2013 9:57 AM To:

Cc: [email protected]; Starzak, Richard; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; Summerville, Alan;

Subject: Summer Archaeological Field Work - Tongue River Railroad Construction Project Importance: High

Dear Tribes,

Soon, we plan to begin the archaeological surveys to identify sites within each of the alternatives under consideration in the Tongue River Railroad Construction (TRRC) Project. The survey work will be conducted between mid-July and September.

The archaeological surveys will be lead by ICF International, our third-party contractor for this project. Rick Starzak, of ICF, is the overall project director for the cultural resources portion of the TRRC Project and is currently organizing the field effort.

I know that ICF has already contacted some of you regarding the summer field work. But there will be a total of four survey teams, each of which will be working during 10-day periods. I have attached a schedule of the work plan for your review. To ensure parity, each crew will consist of four ICF staff archaeologists and four tribal participants. The crews will be lead by senior ICF archaeologists.

We have 16 potential slots for paid tribal representatives ( 4 field sessions and 4 tribal participants per session). This would be the case in the event we have different tribes make up each of the 16 tribal slots (unlikely, I know). To begin though, we are asking for one participant from each tribe to ensure that each interested tribe has an opportunity to provide at least one representative. Once we give each tribe an option to send one person, we will then look at our remaining needs and fill

file:///C:/Users/nadalsc/AooData/Local/Temn/1/notesOFOFAQ/~wp,h777"i htm 1/11/')()1'