TPM Road Map
Transcript of TPM Road Map
Confederation of Indian Industry © Rajesh Parim
TPM Club India
TPM Implementation Road Mapfor Cluster projects
(2 years Period)
TPM Club India
Confederation of Indian Industry © Rajesh Parim
TPM Club India
Activity Output/Result
Methodology of carrying out1S & 2S activities
1S&2S implementation
Clean & neat factory
Methodology for selection ofModel machine basedOn P,Q,C,D,S,M
Selection of ManagerModel Machine(s)
• An ideal machine(s) is (are) selected.
• Activities to make it “as it should be”.
• Estimation of losses• Setting targets
Education to all employees
TPM topicsMonth 1-4
Employees tuning towards TPM
TPM Basic activities
• TPM Policy• TPM promotion
organisation and sub committees formation
• TPM Targets• Draft master plan
Details about TPM basic activities
Result
Not OK
OK
Time period
TPM Implementation Road Map for cluster projects
Input Consulting Training
• 1S,2S• Basics of TPM
• TPM Facilitators Programme
• Data Collection• 4-5 participants
per company
• Autonomous Maintenance Workshop
• Focussed Improvement
• 4-5 participants per company
Month 1-4
Month 5-6
Confederation of Indian Industry © Rajesh Parim
TPM Club India
• 1-3 Steps of JH• KK• QM• PM• E&T• Monitoring
implementation• Guidance• Course correction
Implementation of Activities on
Manager Model Machine(s)
Are the Targets achieved
Is the Further Scope
Possible
• Clean m/c, visual operation
• No break downs• No quality defects• Elimination /
reduction of losses• Machine is “as it
should be condition”• OEE improvement
• Managers fully conversant with the activities to be carried out on machines.
• The results of Model machines creates the confidence on TPM
Kick off activity
• Revisit Master plan and firm up
• Categorizing machines
Input Consulting Training Activity Output/Result
Yes
No
Yes
No
Time period
Basics of • Planned
Maintenance• Quality
Maintenance• Education &
Training• 4-5 participants
per company
Month 7-12
TPM Implementation Road Map for cluster projects
Confederation of Indian Industry © Rajesh Parim
TPM Club India
• Monitoring implementation
• Guidance• Course
correction
Implementation of TPM across the company
Are targetsachieved
Inputs on• 1-4 Steps of JH• KK• QM• PM• E&T• Monitoring
implementation• Guidance• Course
correction
• Clean m/c, visual operation
• No break downs• No quality defects• Elimination / reduction
of losses• Machine is “as it
should be condition”• OEE improvement• Achieving target21-24
months
Sustaining with activities & further improvements
Activity Output/ResultTime period
Yes
No
Input Consulting Training
• Planned Maintenance
• Quality Maintenance
• Education & Training
• 4-5 participants per company
Month 12-20
TPM Implementation Road Map for cluster projects