Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council...

37
Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect Project Post Design Development Update ATTACHMENT 1 DD3-01 Lower Ground Floor Plan ATTACHMENT 2 DD3-03 Mezzanine Floor Plan ATTACHMENT 3 DD3-02 Ground Floor Plan ATTACHMENT 4 SK701 Northern Boundary Access ATTACHMENT 5 Revised program ATTACHMENT 6 Basement Extension Sketch ATTACHMENT 7 Gawler Connect Design Development Detailed Scheme Report” ATTACHMENT 8 Design Development Plans and Elevations ATTACHMENT 9 Costings / Expenditure ATTACHMENT 10 Project Budget TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016 Page 1 of 37 ATTACHMENTS UNDER SEPARATE COVER

Transcript of Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council...

Page 1: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

Town of Gawler Special Council Meeting Agenda

19 April 2016

ATTACHMENTS UNDER SEPARATE COVER

Item 3.2 – Gawler Connect Project Post Design Development Update

ATTACHMENT 1 DD3-01 Lower Ground Floor Plan

ATTACHMENT 2 DD3-03 Mezzanine Floor Plan

ATTACHMENT 3 DD3-02 Ground Floor Plan

ATTACHMENT 4 SK701 Northern Boundary Access

ATTACHMENT 5 Revised program

ATTACHMENT 6 Basement Extension Sketch

ATTACHMENT 7 Gawler Connect Design Development Detailed Scheme Report”

ATTACHMENT 8 Design Development Plans and Elevations

ATTACHMENT 9 Costings / Expenditure

ATTACHMENT 10 Project Budget

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 1 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 2: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

K

1

2

5

7

F

6

ED HA C

43

JG

STREETLG.01

ACCESSLG.13

STAFFLG.11

STAIR 02LG.08

RESEARCHLG.06

CULTURAL HERITAGE CENTRELG.05

HERITAGE STORELG.04

GENERAL STORELG.18

MEETLG.19

MEETLG.20

MEETLG.22

MEETLG.23

CORRIDORLG.17

CORRIDORLG.16

GAWLER CLUBLG.15

KITC

HEN

ETTE

LG.1

2

LIFT

UTILITYLG.10

B

VOID OVER

VOID OVERVOID OVER

CORRIDORLG.02

CORRIDORLG.07

CORRIDORLG.09

5495 2850 6990 4500 4500 4500 5860 6300 5487

COMMSLG.03

STAIR 03LG.14

EXTERNAL COURTYARD

VOID OVERJO

/04

JO/23

JO/07A

JO/05

JO/01

LF/2

4LF

/24

LF/2

4

LF/2

4LF

/24

LF/04

LF/05

LF/05

LF/05LF/05

LF/05

LF/52

LF/01

LF/01

LF/01 LF/01

LF/01

LF/01 LF/01

LF/01

LF/01 LF/01

LF/01

LF/01

LF/01LF/01

LF/01LF/01LF/01

LF/01

LF/2

3LF

/23

LF/2

3LF

/23

LF/2

3

LF/23 LF/23 LF/23

LF/16LF/16

LF/44 LF/16

LF/16LF/16

LF/16 LF/16LF/16LF/16

LF/16 LF/16

LF/17

LF/17

LF/17

LF/17

LF/17

JO/02

SF/01

SF/01

SF/01 SF/01

SF/01

SF/01

SF/01 SF/01

SF/01SF/01

SF/01 SF/01

SF/01 SF/01 SF/01

SF/01SF/01SF/01

LF/05

LF/05LF/05

LF/05LF/05

LF/05LF/05

LF/05

LF/05

LF/05

LF/05LF/05

LF/05 LF/05

LF/05

LF/05

LF/05

LF/05 LF/05

LF/05LF/04LF/04

LF/04LF/04

LF/26

LF/25

LF/29

LF/29 LF/30

LF/32

LF/32

LF/32

LF/32 LF/32

LF/32

LF/32

LF/32 LF/32

LF/32

LF/31 LF/31

LF/31

PP PP

PPPPPP

S

SS

S

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

(D)

FFE Plan - Lower Ground

Gawler Connect

DD3.011390

no amendment/issue date byD Post-DD Variations 21.03.16

POST DD ISSUE

ATTACHMENT 1

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 2 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 3: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

K

1

2

5

7

HIG

H S

TREE

T

DELIVERYM.12

LOBBYM.10

STOREM.11

F

6

E

TRANSFORMER

STAIR 04G.09

D HA C

43

JGB5495 2850 6990 4500 4500 4500 5860 6300 5487

S

S

LIFT CORRIDORM.09

STAIR 05G.33

BOO

STER

SERVER

YOUTH

BIKE STORE

ACCESS

KITCHENETTES

SCRE

EN

SHOWER

LF/27LF/28

LF/28LF/28

LF/28

LF/28

LF/28

LF/27

LF/53

LF/53

LF/16 LF/16

LF/16LF/16LF/23

LF/16 LF/16

LF/16LF/16LF/23

LF/17LF/17LF/17

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

(D)

FFE Plan - Mezzanine

Gawler Connect

Designer

Checker

DD3.031390

no amendment/issue date byD Post-DD Variations 21.03.16

POST DD ISSUE

ATTACHMENT 2

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 3 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 4: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

K

1

2

5

7

ENTRY

MEETG.32

MEETG.31

MEETG.30

HERITAGE GALLERYG.26

LIBRARYG.06

KITCHENG.14

MALEG.17

CORRIDORG.15FEMALE

G.16

CAFE SEATINGG.23

STAIR 01G.03

READING ROOMG.04

ANTE-ROOMG.05

CORRIDORG.29

MU

RR

AY S

TREE

T

HERITAGE STOREG.28

HIG

H S

TREE

T

LOBBYG.10

F

6

E

GENERAL STOREG.12

LIFT STAIR 04G.09

VOID

LIFT

VOID

VOID

VOID

D HA C

VOID

4

6800

4755

2930

2600

3

J

1003

0

BABY CHANGEG.20

G

ACCESSG.19

FEEDG.21

STOREG.13

CLNRSG.18

LIBRARY STOREG.08

B

VOID OVER

VOID

CORRIDORG.02

LIBRARYG.22

5495 2850 6990 4500 4500 4500 5860 6300 5487

COMMS

STREETG.01

COMPUTERSG.25

CAFEG.24

riserriserCORRIDORG.27

STAIR 03LG.14

VOID

STAIR 02LG.08

LF/05LF/05LF/05LF/05

LF/05 LF/05

LF/05LF/05LF/05LF/05

LF/05

JO/07

B

JO/09

JO/08

JO/11

JO/12

JO/13

JO/14

JO/14

JO/15

JO/10B

LF/05LF/05LF/05LF/05LF/05

LF/05

LF/05 LF/05 LF/05 LF/05 LF/05

LF/05

LF/02

LF/02

LF/02

LF/02

LF/02

LF/14

LF/14

LF/37 LF/37

LF/37LF/37

LF/37 LF/37

LF/37LF/37

LF/36

LF/36

LF/34ALF/34ALF/34ALF/34ALF/34ALF/34ALF/34A

LF/33

LF/16 LF/16 LF/16 LF/16

LF/16LF/16LF/16LF/16

LF/20 LF/20

LF/37 LF/37

LF/37LF/38

LF/37LF/37

LF/37

LF/48 LF/48 LF/48

LF/4

8LF

/48

LF/4

8LF

/48

LF/4

8LF

/48

LF/4

8LF

/48

LF/48 LF/48 LF/48

LF/35 LF/35 LF/35 LF/35 LF/35

LF/3

4BLF

/34B

LF/49

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/3

4BLF

/34B

LF/3

4BLF

/34B

LF/3

4BLF

/34B

LF/3

4BLF

/34B

LF/3

4BLF

/34B

LF/3

4B

LF/34BLF/34BLF/34BLF/34B

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/20

LF/16LF/16

LF/16 LF/16

LF/50LF/50

LF/42

LF/43

LF/43

LF/43

LF/43

LF/42

LF/04 LF/04

LF/05LF/05

LF/05

LF/05LF/05

LF/05LF/05

LF/05

LF/05LF/05

LF/05

LF/05

LF/06 LF/06

LF/47 LF/47 LF/47 LF/47

LF/16 LF/16

LF/16

LF/16

LF/16

LF/16LF/16

LF/16

LF/16

LF/16

LF/15

LF/05LF/05

LF/05

LF/05

LF/05 LF/05

LF/05

LF/05LF/46

LF/44 LF/44

LF/44LF/44

LF/44 LF/44

LF/44LF/44

LF/44 LF/44

LF/44LF/44

LF/44 LF/44

LF/44LF/44

LF/44 LF/44

LF/44LF/44

LF/44

LF/44LF/44

LF/44 LF/44

LF/44LF/44

LF/44 LF/44

LF/44LF/44

LF/21 LF/21 LF/21 LF/21

LF/21LF/21LF/21LF/21

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

9LF

/49

LF/44 LF/44

LF/44

LF/44LF/44

LF/44 LF/38LF/14

LF/4

5

LF/4

5

FB

STAIR 05G.33

LF/22

LF/05

LF/05

LF/39

LF/40

LF/39 LF/39

LF/39

LF/4

7

LF/56

LF/1

8LF

/18

LF/1

8LF

/18

LF/55

LF/44

WORK ROOMG.07

LF/39

LF/39

LF/40

BOOKRETURNS

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/4

7LF

/47

LF/49

JO/08

CUSTOMERSERVICE

LF/4

7LF

/47

LF/4

7LF

/47

ACCESS TO HIGH STREET

NO

M67

2N

OM

175

0

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

(D)

FFE Plan - Ground

Gawler Connect

DD3.021390

no amendment/issue date byD Post-DD Variations 21.03.16

POST DD ISSUE

ATTACHMENT 3

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 4 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 5: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

UP

DD5.03

3

DD5.02

2DD5.01

1

DD5.04

4

K

1

2

5

7

3

DD6.03

1

DD6.01

1

DD6.02

F

6

E

1

DD6.04

-

D HA C

4

1

DD6.07

1

DD6.05

1

DD6.06

3

J

1

DD6.08

G

1

DD4.06

B

-

-

-

-

ENTRY

MU

RR

AY S

TREE

T

HIG

H S

TREE

T

VOID

VOID

VOID

VOID

6800

4755

2930

2600

1003

0

5495 2850 6990 4500 4500 4500 5860 6300 5487

1810300

1250

1190

460

MEETG.32

MEETG.31

MEETG.30

HERITAGE GALLERYG.26

LIBRARYG.06

KITCHENG.14

MALEG.17

CORRIDORG.15FEMALE

G.16

CAFE SEATINGG.23

STAIR 01G.03

READING ROOMG.04

ANTE-ROOMG.05

CORRIDORG.29

HERITAGE STOREG.28

LOBBYG.10

GENERAL STOREG.12

LIFT STAIR 04G.09

LIFT

BABY CHANGEG.20ACCESS

G.19

FEEDG.21

STOREG.13

CLNRSG.18

LIBRARY STOREG.08

CORRIDORG.02

LIBRARYG.22

WORK ROOMG.07

STREETG.01

COMPUTERSG.25

CAFEG.24

riserriser

CORRIDORG.27

STAIR 03LG.14

STAIR 02LG.08

LN/01

LN/03LN/03

LN/03

WT/01 WT/01 WT/01WT/01 WT/01 WT/01 WT/01 WT/01

WT/01

WT/01

WT/01

WT/01

WT/01

WT/01

WT/01

WT/01

WT/01

CA/01 CA/01 CA/01

CA/03

RE/01

CS/01 CS/01

CS/01

CS/01

CS/01

RE/01 CS/02

CS/02

CS/02CA/01

CA/01

CA/01 CA/01

RE/01 TL/01

TL/01 TL/01

CA/01CA/01

CS/02

CS/02

TAC

_01

PT/01PT/01

CO/02

CO/02

CS/01

STAIR 05G.33

TAC_01TAC_01

CO/01 CO/01PT/01

PT/06

PT/06

PT/02

BT/01

BT/02

BT/01BT/01

BT/01

BT/01

TAC_01

TAC_01

TAC

_01

COMMS

STOREG.11

RE/01

RE/01

670

NO

M

1750

mm

CLE

ARZO

NE

FENCE LINE

1200

ACCESS

NEW STAIR TO BEPROVIDED

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

Ground Floor - Northern BoundaryAccess

Gawler Connect

SJ

BLV

SK7011390

no amendment/issue date by POST DD ISSUENORTHERN BOUNDARY ACCESS

ATTACHMENT 4

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 5 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 6: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

G C P I N D I C A T I V E P R O G R A M 2016 J A N F E B M A R A P R M A Y J U N J U L A U G S E P O C T N O V D E CM 4 11 18 25 1 8 15 22 29 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26

ACTIVITY F 8 15 22 29 5 12 19 26 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30

GC PROJECTPost DD Project Amendments & Report to CounccilCouncil Resolution 19 April 2016Brief Design ConsultantsDevelopment Plan ConsentREOIs and Assessment for Building ContractorsConstruction DocumentationBuilding Rules ConsentDevelopment ApprovalTendering Tender AssessmentCouncil Report Council Resolution on TendersConstruction - Start by December 2016

12-April-2016

ATTACHMENT 5

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 6 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 7: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

ATTACHMENT 6

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 7 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 8: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

1

REPORT: GAWLER HERITAGE COLLECTION COMMITTEE RESPONSE TO THE GAWLER CONNECT PROJECT DESIGN DEVELOPMENT DETAILED SCHEME   

1.0 Background 

The purpose of this report is to provide feedback regarding the Gawler Connect Design Development Detailed Report prepared by MPH Architects (Adelaide)  in February 2016 as part of the Gawler Connect Project.  

This  is  the  next  phase  of  the  design  development  process  for  the  Gawler  Connect Project following the tabling of the  initial Schematic Concept Design Report developed by MPH in October 2015. 

MPH  has  stated  that  the  design  brief  for  the  Gawler  Connect  Project  remains  ‘live’ during this important phase of consultation and that it is still open to modification and negotiation before the Town of Gawler Council is required to authorise the final design plans.  The  Committee  acknowledges  the willingness  of MPH  to  present  and  discuss these  detailed  design  plans  on  a  number  of  occasions  and  has  appreciated  this opportunity to respond in good faith. 

It  is also acknowledged by members of the Gawler Heritage Collection Committee that the Gawler Connect Project  is  required  to meet  the necessary milestones, as per  the documentation,  pertaining  to  the  Gawler  Connect  Australian  Government’s  National Stronger Regions Grant Fund Agreement. 

This  report  is  an  important  opportunity  to  review  the  design  and  to  coordinate  the Committee’s response in order to finalise the design prior to beginning the construction phase of  the project. This  is an  important part of  the Committee’s  terms of  reference and deliberations. 

From the time the Gawler Heritage Collection Committee was convened in early August 2015,  it  identified  a  number  of  key  areas  for  discussion  regarding  the  systematic development and management of the Gawler Heritage Collection but had not resolved initially how these would impact on the Gawler Connect Project. 

The issues identified by the Gawler Heritage Collection Committee in August 2015 arose specifically out of  the Town of Gawler Cultural Heritage Collection Management Plan (Schumann 2013) which was formally adopted by Town of Gawler Council in September 2013. 

The Town of Gawler Cultural Heritage Collection Management Plan 2013 put forward 21 recommendations for the Town of Gawler Council’s consideration and adoption. 

A number of  these  recommendations have been  successfully  implemented  as part of the Gawler Heritage Collection Action Plan 2014, while others are directly  relevant  to the outcomes of the innovative Gawler Connect Project. 

ATTACHMENT 7

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 8 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 9: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

2

The  recommendations  that  formed  part  of  The  Town  of  Gawler  Cultural  Heritage Collection Management Plan in 2013 and which have a bearing on the redevelopment of the  State  Heritage  listed  Gawler  Institute  and  Gawler  Town  Hall  buildings  through Gawler Connect are: 

“Extract from Town of Gawler Cultural Heritage Management Plan 2013: 

Recommendation 2 It is recommended that work be undertaken to clarify the legal relationship between the Gawler Public Library, the Town of Gawler Corporation, and the entity called the Gawler Heritage Collection. 

Recommendation 3 It  is  recommended  that work be undertaken  to determine and document whether  the Gawler Heritage  Collection  under  the  Local Government  Act  requires  a  committee  of Council as part of the governance model. 

Recommendation 11 It  is  recommended  that  current  storage  facilities  be  reorganised  and  temporary measures implemented regarding preventive conservation practices. 

Recommendation 12 It  is  recommended  that approaches  to  the  storage and display of  the Gawler Heritage Collection  demonstrate  an  appropriate  understanding  of  the  significance  of  the collection and the environmental requirements of individual items. 

Recommendation 13 It  is  recommended  that  all  items  assessed  in  the  collection  as  highly  significant  are valued by an insurance assessor and insured within two years of this report. 

Recommendation 15 It  is  recommended  that  an  appropriate  level  of  recurrent  funding  be  allocated  to  the ongoing management and development of the Gawler Heritage Collection. 

Recommendation 16 It  is recommended that the Gawler Heritage Collection’s significant themes, stories and key collection areas are  identified, researched, documented and presented  in a written plan to guide future interpretation. 

Recommendation 18 It  is recommended that the Gawler Heritage Collection be used to build capacity within the community through cultural exchanges, skills development and cultural programs. 

Recommendation 19 It  is  recommended  that  the Town of Gawler as  custodian of  this  significant  collection explore how  the Gawler Heritage Collection  can be used  to develop  ‐  cultural  tourism 

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 9 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 10: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

3

infrastructure,  in  place‐making  projects  and  in  branding  and  marketing  the  Gawler region.  Recommendation 20 It  is  recommended  that  for  the Town of Gawler  to  realise  the  cultural,  economic and social value of the Gawler Heritage Collection that additional resources are required to implement  these  recommendations  and  to  undertake  special  project work  to  support new initiatives arising from the collection.  Recommendation 21 It  is  recommended  that  the  Town  of  Gawler  investigate  options  and  funding  for  the development of a permanent cultural gallery, heritage  research centre and designated onsite archival and storage facility for the Gawler Heritage Collection.  The Town of Gawler Cultural Heritage Collection Management Plan (Schumann 2013).”  The  adoption  of  the  Town  of  Gawler  Cultural  Heritage  Management  Plan  in  2013 enabled the Council to think strategically about the Gawler Heritage Collection and how it could be developed as a cultural heritage asset. This is related to the Gawler Connect Project.  The  Council  proceeded  to  not  only  endorse  the  collection  management  report  but finally addressed the fundamental issue of the Gawler Heritage Collection’s legal status, governance and future development.  In May 2015,  in  response  to  the Town of Gawler Cultural Heritage Management Plan 2013 and as a direct result of a report into the history of the legal status of the Gawler Heritage Collection, the Town of Gawler adopted the motion that a new committee of Council be established.  This Committee would advise and oversee the management of the entity now known as the Gawler Heritage Collection.  The Committee of Council would be  known  as  –  The Town of Gawler Heritage Collection Committee.   This was timely as on 14 May 2015 it was also announced that the Town of Gawler was successful  in  receiving  $5.7  million  from  the  Federal  Government  for  regional infrastructure development.   This was under  the Australian Government’s National Stronger Regions Fund and was for the Gawler Connect Project.  In  fact,  it  is a matter of public record that  the Gawler Connect Project had its origins in a workshop conducted in 2012 on the Gawler Heritage Collection.  Following the announcement in May 2015 that the Town of Gawler had been successful in  achieving  funding  for  Gawler  Connect  tenders  were  called  for  architectural submissions regarding the design and development of the project.  

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 10 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 11: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

4

It was against this backdrop that in October 2015 the Gawler Connect Schematic Design Report by MPH Architects (Adelaide) was submitted to the Town of Gawler Council for discussion.  The Gawler Heritage Collection Committee as a key stakeholder was asked to respond to the report. The proposed Gawler Connect Schematic Design Report made reference to  a  number  of  new  heritage  facilities  and  heritage  services within  both  the Gawler Institute and Town Hall buildings.   Intertwined with  the proposed redevelopment of  the  Institute and Town Hall  facilities was  the  issue of  the Gawler Heritage Collection and  the question of how  it could slot into an integrated shared services model of operations for the Town of Gawler.  The Gawler Heritage  Collection  Committee  considered  that  it was  important  to  note that  the  architects  for  the Gawler  Connect  Project  ‐ MPH,  under  the  terms  of  their engagement with  the Council, were  required  to develop a design strategy  that had  to meet the vision as outlined in the Gawler Connect Project Brief:  “It  is the Council’s Vision to transform the  iconic State Heritage listed Gawler Town Hall and Gawler  Institute Buildings through a combination of adaptive reuse and conservation to create an architecturally  significant  hub  for  Government,  Economic,  and Social Enterprise that will act as the renaissance catalyst for the Gawler CBD to take its place as the Cultural and Business Centre for the Greater Region.”   Gawler  Connect  Project, Design Development Detailed  Report, The Town of Gawler, MPH Architecture, February 2016.   A series of workshops and committee meetings were held in November and December 2015 for the Gawler Heritage Collection Committee.  These workshops were  to provide direction  to Committee members as  they grappled with  the difficult  task of  trying  to understand  the  complex design brief  and how  key heritage facilities would be adapted and reworked within the design model.  All of these issues were directly related to the management and strategic development of  the  Gawler  Heritage  Collection  which  has  been  identified  as  of  national  cultural heritage significance. (Town of Gawler Cultural Heritage Management Plan 2013)  At a meeting of the Gawler Heritage Collection Committee, on the 7 of December 2015, it  reviewed  the  Gawler  Connect  Schematic  Design  Report  (MPH)  and  the  proposed development of a new heritage gallery facility and gallery store  in the Town of Gawler Council Chamber.  The report also proposed that a designated public heritage research room be located in a small meeting room in the Gawler Institute Basement. 

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 11 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 12: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

5

 There was also discussion concerning the designated archival storeroom  located  in the Gawler  Institute basement area which would be accessed through what was proposed to  be  the  ‘Youth  Gaming  Room’  or  via  a  separate  entrance  located  near  the main corridor to the rear of the existing lift.  The  Gawler  Connect  Schematic  Design  Report  (MPH)  also  pitched  the  idea  that  the refurbishment of the 19th century  Institute Reading and Ante Room would operate as an extension of the Gawler Public Library.  In  response,  the Gawler Heritage Collection Committee  asserted  that with  respect  to these significant areas the concept of ‘spatial delineation’ was a significant characteristic to be considered as it denoted that these ‘rooms’ were perceived as historically distinct from the library.   In reviewing the Gawler Connect Schematic Design Report (MPH) a number of important issues were raised by members of the Gawler Heritage Committee.  1.1 Return Brief & Gawler Heritage Collection Committee Response to Gawler Connect Schematic Design Report (MPH) December 2015   One of the main issues concerned the critical relationship between the Gawler Heritage Collection and  the preservation of key heritage values associated with  the history and fabric of the buildings themselves.  The  crux  of  the  issue was  how  the  proposed  contemporary  design  treatment  of  the Gawler  Institute  and  Town  Hall  building  advocated  by  MPH  would  preserve  these heritage values.  The Committee in its discussion made the observation that these 19th century buildings provided  evidence  of  a  tangible  past  and  a  set  of  specific  social  ideals  that  have contributed to Gawler’s cultural identity and needed to be enhanced and preserved.  In response, the Chief Executive Officer of the Town of Gawler requested a ‘Return Brief’ be prepared which would assist the concept development and fit out of the designated heritage areas that formed part of the Gawler Connect Project.  The  ‘Return  Brief’  was  tabled  at  the  meeting  of  the  Gawler  Heritage  Collection Committee on 21 December 2015.   The  development  of  the  ‘Return  Brief’  formed  part  of  the  process  of  reviewing  the proposed  layout,  design  and  function  of  designated  key  heritage  areas  within  the Gawler Connect Schematic Design Report (MPH).    

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 12 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 13: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

6

The  ‘Return Brief’ noted  that  the designated heritage areas within  the Gawler Connect Schematic Design Report (MPH) were able to be conserved and adapted and reworked.  The key purpose  in developing the  ‘Return Brief’ was to ensure that the recommended design strategies for each of the designated heritage areas would:  •  enhance and reveal the character of these designated heritage places  •  maintain  a  sense  of  historical  identity  and  continuity  in  these  places  to  allow 

their  use,  enjoyment  and  benefit  without  compromising  the  ability  of  future generations to do the same 

 •  be a catalyst for shaping and regenerating interest in the cultural heritage of the 

Town of Gawler.  Members of the Gawler Heritage Collection Committee reiterated that any proposed major intervention that would impact ‐ or alter the built fabric and the social meaning of the Gawler and Town Hall facilities ‐ must not in the final analysis diminish the historical significance and the heritage value of the buildings.  Through the ‘Return Brief’ the Gawler Heritage Collection Committee requested that the Council’s Project Manager for the Gawler Connect Project consider the following areas in the next stage of design development with respect to the designated heritage areas:  

Proposed Layouts & Operational Considerations Specify  the  proposed  layouts  for  each  facility  particularly  operational considerations  and  functionality  requirements  of  each  regarding  public  access and movement through areas within the facility. 

 

Lighting Considerations The ability to control and regulate  lighting  in gallery areas, display areas and  in archival  storage areas was a  critical  requirement. Consideration of natural and artificial  light with  special measures  to exclude heat  transmission, daylight and UV  rays. Exhibition, gallery or display  spaces  to operate on  specific  light  levels and to be flexible. 

 

Mechanical Services Considerations Mechanical services, Communication and data points and  IT requirements must be  in  accordance  with  current  standards  of  emergency  services  regulatory requirements but also have regard to impact on the heritage values of each site. Designated  areas  must  be  able  to  monitor,  adjust  and  regulate  mechanical services.  

Heating and Cooling Requirements Consideration must be given to the level of environmental stability and interior climatic conditions required for the ongoing care of heritage collections and the exhibition of artefacts. Temperature should be in the range of 19‐23c (maximum 

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 13 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 14: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

7

of 4 degrees) and  relative humidity 55‐60% max degrees.   The main objective being to minimise any great fluctuations  in temperatures as  it  is extremes that impact on the conservation of items. This is an important element in any gallery or heritage museum facility. 

 At this meeting in December a request was made by the Committee for a site trip to be organised for early January 2016. The purpose was to visit a number of State Heritage properties  to  see  how  they  had  been  upgraded,  redesigned  and  redeveloped  to  be wholly functional and accessible buildings of public importance.  1.2 Gawler Heritage Collection Committee & Site Visits 

On  the 7 of  January, 2016,  the Gawler Heritage Collection Committee  conducted  site visits to the following facilities:   Old Parliament House, North Terrace Adelaide  Adelaide Institute Building, North Terrace Adelaide  State Library of South Australia  Ayers House, North Terrace Adelaide  St Peters Town Hall Complex, Payneham Road, St Peters  Urrbrae House University of Adelaide, Waite Campus, Urrbrae.  Committee Members visited each site  taking  into account exterior and  interior design considerations and how each site had been upgraded and the impact on service delivery and functionality of the various buildings.  A debrief session was held at Urrbrae House ‐ part of the University of Adelaide Waite Campus.  Following  the  field  trip  a  resolution  incorporating  the  Gawler  Heritage Collection Committee’s  findings and supported by detailed photographs was  tabled at the Gawler Heritage Collection Committee Meeting held on the 18 of January 2016.  This  resolution  of  the  Gawler  Heritage  Collection  Committee  was  subsequently forwarded to Council for its consideration.  In  February  2016,  MPH  Architects  released  the  Gawler  Connect  Project  Design Development Detailed Report which they presented to a meeting of the Gawler Heritage Collection Committee on 15 February 2016.  The  Gawler  Connect  Project  Design  Development  Detailed  Report  (MPH)  with attachments is 398 pages.  Following the meeting in February with MPH the Gawler Heritage Collection Committee decided  that a site visit of  the Gawler  Institute and Town Hall would be conducted so Committee Members  could  reconcile MPH’s  detailed  design  report with  the  physical reality of the existing buildings.   This onsite tour of the Gawler Institute and Town Hall buildings by the Gawler Heritage Collection Committee members with Council staff occurred on the 18 of February 2016. 

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 14 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 15: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

8

The insights and responses regarding all of the Committee’s deliberations and site visits form part of the discussion and commentary of this report.   The  purpose  of  the  current  report  is  to  provide  feedback  and  recommendations regarding the Gawler Connect Project Design Development Detailed Report (MPH).   Given  the complexity of  the Gawler Connect Project  it  is appropriate  to state  that  the detailed design  report  is  continually being  reassessed  in  the  light of new  information regarding modifications to the external and internal proposed layout and other relevant considerations.   

2.0  Comment & Discussion  The following commentary aligns with the Gawler Connect Project Design Development Detailed Report (MPH) and pertains to the areas that have been designated as proposed ‘Heritage  Spaces’.  This  information  is  presented  to  further  assist  Council  in  its deliberations regarding the Gawler Connect Project.  The Gawler Heritage Collection Committee commented on the following areas:  

The Gawler Institute Ground Floor Reading Room 

The Gawler Institute Ground Floor Ante Room 

The Gawler Institute Basement – Heritage Research Room 

The Gawler Institute Basement – Heritage Archival and Collection Store 

The Gawler Institute Basement – Lift Facility 

The Gawler Town Hall Ground Floor – Gallery 

The Gawler Town Hall Ground Floor Heritage Store/Strong Room 

The Gawler Town Hall Basement Walkway & Meeting Rooms.  

2.1 Gawler Heritage Collection Committee & Gawler Connect Design Philosophy  The Gawler Heritage Collection Committee stated that it wished the designated heritage areas and the buildings generally be upgraded in a manner that reflects and is sensitive to the heritage character, heritage values and historical context of each building.  The Committee has concluded that there are key elements relating to the interior design that  could be used  to highlight heritage  features  in a number of ways. This approach would reveal and enhance these features rather than transforming them.  2.1.1 The Entrance Voids  One  of  the major  design  concerns  commented  on  by  the Gawler Heritage  Collection Committee with  respect  to  the Gawler  Connect  Project Design Development Detailed Report  (MPH) was  the use of  voids  as  a  contemporary design element  in  the Gawler Connect Project.  The  Committee  expressed  a  concern  that  in  the main  entrance  there  are  two  voids linking the ground floor to the  lower basement areas of each building and noted their 

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 15 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 16: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

9

impact not only on restricting pedestrian access to the building but that the positioning of  these  voids  ran  counter  to  the  notion  that  this  space  is  designated  a major  civic entrance space. It was felt that these two voids impacted on this area as a public realm and as a major civic entrance to the building from the mainstreet.  Given the revised use of the spaces in the basement for heritage purposes, it questioned the suitability of  the entrance voids  linking  this area vertically and also  the associated pedestrian and disability issues with respect to the Disability Discrimination Act (DDA).  The question was  raised within  the Gawler Heritage Collection Committee  about  the term  ‘best possible  access’,  as opposed  to minimum  requirements, with  respect  to  a path being wide enough  for a person using a motorised wheelchair or  frame or other mobility  aid  to pass  someone  else or  a  group of people  in  the main  entrance of  the buildings.   The  Committee  found  it  hard  to  reconcile  these  specific  entrance  voids  and  their enclosure, and  the necessary  restriction of  space, with  the  stated design  intention of opening up the buildings and making them accessible.  2.1.2 Interior Design Palette 

 The Committee discussed  the  interior design palette and  finishes as  listed  in  the MPH schedules contained in the Gawler Connect Project Design Development Detailed Report (MPH) which  is  referred  to  as  contemporary  in  style.  The Gawler Heritage  Collection Committee noted that  in the appendices of the report that a schedule of furniture and fittings and supplier details were specified – most examples were contemporary in style.  In  response  to  this generic  list of corporate  furniture and  fittings  the Gawler Heritage Collection Committee identified that there is an exciting opportunity for other suppliers to be involved in the Gawler Connect Project.   The  Committee  felt  that  similar  to  specialist  commissioned  ‘public  artworks’  specialist design fittings, furnishings and cabinetry could be commissioned for the historic Reading Room and Ante Room and the Heritage Research Room.  This competitive process could reflect a bespoke design by a South Australian supplier or a  local  regional  supplier  in  line  with  local  government  procurement  processes.    The Committee reiterated the importance of the Gawler Connect Project as a regional project and its ability to stimulate the local economy.  2.1.3 Proposed Change to Recommended Room Configuration  With respect to the allocation of specific areas within the upgraded buildings the Gawler Heritage Collection Committee recommended one change to the proposed configuration outlined in the Gawler Connect Project Design Development Detailed Report (MPH). This concerned  the  location  of  the Heritage  Research  facility  in  the  basement  area  of  the Gawler Institute building.  

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 16 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 17: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

10

 The proposed change  to  the  location of  the Heritage Research Room was made on  the basis  of  continuity  of  space,  functionality,  effectiveness  of  work  practices  and complementary services.  The Gawler Heritage Collection Committee  recommended  that  the proposed  floor plan outlined  in  the  Gawler  Connect  Project  Design  Development  Detailed  Report  (MPH) consider moving  the Youth Gaming  area  LG.05  from  the basement  to  a more  suitable location within the new civic complex.  2.1.4 Youth & Gaming Area LG.05 to become Heritage Research Facility   The Gawler Heritage Collection Committee  recommended  that  the  area  in  the Gawler Institute Basement  currently designated  Youth & Gaming  LG.05  in  the DD Plan  (MPH) become  the  Heritage  Research  Room.  (The  Heritage  Research  Room  is  currently designated LG.06.)  The  Committee  noted  that  this  space was more  suited  to  public  use  and will  solve  a number of  storage  issues with  respect  to housing  the Gawler Heritage Collection. This room  LG.05  is adjacent  to  the Heritage  Store  LG.04 making  the  case  that  it  is a much more  complementary  space  in  terms of  clientele and  service  than  its existing use as a Youth & Gaming area. 

 The dimensions of this space are 10.2 metres X 6.9 and should be able to accommodate archives and  records  from  the Gawler Heritage Collection  in purpose designed archival compliant cabinetry and bookcases.   The Gawler Local History Collection can also be  rehoused and  relocated  to  this area  in purpose designed cabinetry reducing the requirement for additional storage facilities.  Other cabinetry and office fittings would need to be adapted to the requirements of this facility as a publicly accessible workspace including disability access and use. 

 The  relocated  research  facility  is  adjacent  to  what  is  intended  to  be  the  Heritage Collections Store and  is close  to  the designated Library and Customer staff workspaces utilising an integrated service model.   The  issue of the varying floor  levels within this area has been addressed  in the detailed design report by raising the level 600mm thus resolving access to this area.  The  issue  of  raising  the  doorways  and  reinstating  the  archways  from  this  area  to  the adjoining  store,  widening  the  entrance  to  both  LG.06  and  Corridor  LG.O2  is  also recommended and reiterated later in this report.   The location of the Heritage Research Room in the basement is also put on the basis that there is minimal light exposure or temperature fluctuations.  

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 17 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 18: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

11

  The  issue  of  the  basement  to  first  floor  lift  being  adapted  to  servicing  this  area  is addressed later in the report in Section 3.   3.0 Recommendations Regarding Designated Heritage Areas Gawler  Institute & Town Hall Buildings  3.1 Ground Floor Areas  3.1.1 Gawler Institute Reading Room G.04  The main concern with the Reading Room  is to make sure the  interior design palette  is sympathetic  to  the  heritage  context  and  that  service  delivery  is  appropriate  to  this significant heritage asset.  The  interior  design  palette  refers  to  paint  colours which  the  Committee  has  broadly indicated to the Council in previous resolutions referring to examples such as within Old Parliament House and at Urrbrae House located within the University of Adelaide Waite Campus.  The Committee also reiterated that design treatments such as carpet, painting and soft furnishings could be used to  identify designated heritage areas  from other areas  in the Institute and Town Hall buildings and be a  subtle  form of way  finding. The Committee noted that this was a key feature of Old Parliament House, Adelaide.  The Gawler Heritage Collection Committee recommends  that  the original bookcases on the  southern wall  should be  relocated  to  the Ante Room G.05  as  this was  the Gawler Institute library in the 19th century.  

 This  relocation  of  the  existing  Gawler  Institute  Library  Collection  then  opens  up  the southern wall in the Reading Room to be used for displaying historic art works from the Gawler Heritage Collection.   These  19th  century  artworks  require  a  purpose  designed  hanging  system  for  the southern wall. Many  of  the works  are  too  large  and weigh  too much  for  a  normal commercial gallery rail system. Specifications regarding an appropriate hanging system will form part of the exhibition design plan for this area.  On the northern wall of the Reading Room the Committee recommends that all joinery be removed from this wall as it is not original and that this area can become a focus for interpreting the history and stories of the former Gawler Institute and its collection.   It  is proposed that a bespoke designed museum showcase be a feature on this wall to accommodate  the  display  of  significant  heritage  artefacts  and  that  this  meet  the Australian National Standards for Museums and Galleries. Specifications will be part of the exhibition design plan for this area.  

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 18 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 19: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

12

 The DD Plan  (MPH)  schedule has  specified  lighting  for  this area but  it appears  that  it should  be  compliant  with  gallery  or  museum  display  lighting  and  needs  to  be reconsidered according to gallery and museum standards given the intention to display historic artworks.  The  lighting  should  be  a  combination  of  diffuse  room  lighting  and  directional  spot lighting and a  lighting plan should be developed based on proposed display areas and room function.  Issues have been  raised about  the air‐conditioning  system particularly  the  location of the return air grill on the southern wall which  is where the significant artworks will be displayed. This needs to be reconsidered.   The Committee  requires  further  information concerning  the operational nature of  the proposed air conditioning system and how  it can be zoned to specific requirements  in designated  heritage  areas.  This  should  include  information  explaining  how  individual sites  can be autonomous  so  that areas  such as  the Reading Room do not experience major fluctuations in temperature.  The Committee has determined that all windows and doors in the Reading Room facing Murray Street must address the issue of UV light, temperature fluctuations, security and noise abatement. The Committee noted that glazing and the ability to control light from outside is critical.  Currently the DD Plan (MPH) states that with reference to the Gawler Institute Building that ‘only broken or low level glass will be replaced with glass that is the compliant with the glazing  code’. This means  that  the Reading Room windows and  fan  lights are not going to be glazed and are not compliant.  The  floor  in  the Reading Room  is  currently designated as  floor boards  in  the DD Plan (MPH). The Committee’s  recommendations  recognise  the acoustic  issues  raised  in  the Bestec Report and  recommends broadloom carpet as  the preferred  treatment  for  the Reading Room floors.  Again,  the Committee  referred  to  the example  in Old Parliament House where carpet was  used  to  solve  a  number  of  noise  issues  and  used  for  way  finding.  Even more important was its use to indicate the heritage value of various spaces.  The  location  of  communications  and  IT  service  points  will  need  to  be  carefully considered  regarding  the  flexible  use  of  this  space  but  having  consideration  that placement should be discreet and enhance the heritage values of the room.  Exact location of fire sprinklers in the ceiling will need to be reconsidered regarding the use of the walls for artworks.  The issue of concealed sprinklers was raised in seeking to keep to a minimum the intrusion of such services on ceiling spaces.  

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 19 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 20: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

13

The Acoustic design  report by Bestec  raised  the  issue of noise  in  this area and other areas  and  noted  that  there  were  concerns  about  the  feasibility  of  sound  insulation treatment with respect to the floor in the Reading Room. This requires further analysis and consideration.  It  is  noted  that  the  Committee  specifies  the  retention  and  conservation  of  the  19th century  brass  hanging  rail  in  the  Reading  Room  though  this  is  not  specified  in  the schedule of heritage works in the DD Plan (MPH).  

  3.1.2 Ante Room G.05   The main recommendation regarding this area is the relocation of the historic bookcases currently held in the Reading Room. Early photographs reveal this as the original Gawler Institute Library and  thus  the Committee  felt  it appropriate  to  restore  it  to  its  former use.  The bookcases will have to be retrofitted so that they can accommodate the historically significant Gawler Institute Collection with regard to housing, conservation, security and display. Additional cases will need to be commissioned and will be purpose designed in keeping with the original room.    These bookcases should be compliant with museum standards  including museum glass as they will contain the original Gawler Institute Collection. They will need to minimise external  environmental  factors  such  as  dust  and  insect  entry  and  will  need  to  be secured.  The  issue of  lighting needs to be reconsidered given the heritage function of this room and  the  housing  of  the  collection  in  bookcases  and  its  display.  Lighting  should  be  a combination of diffuse room lighting and directional spot lighting and a creative lighting plan  should be developed  to  co‐ordinate with proposed bookcase  joinery and display areas.  The  Gawler  Heritage  Collection  Committee  reiterated  that  the  current  furnishing treatments contained in the DD Plan (MPH) should not reflect the contemporary design palette as  indicated  in  the MPH  report schedule where  this area  is considered part of the  library complex. The  interior design and fit out should enhance the heritage values of the room.  The Committee noted  there was an opportunity  for bespoke  furniture  reinforcing  the heritage context of this room as the original 19th century Gawler Institute Library. 

 The committee recommended that the paint colour would be the same as that for the Reading Room.  Floor  treatment would  be  the  same  as  that  for  the  Reading  Room with  broadloom carpet recommended to assist with noise abatement. 

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 20 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 21: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

14

 The Committee recommends that the  location of communications and  IT service points would have to be carefully considered regarding the flexible use of this space but having consideration that placement should be discreet and enhance the heritage values of the room. 

 With respect to the proposed  location of air conditioning ducts  in the Bestec Plan and the capacity to control this area as a zoned area the Committee reiterated that this issue was critically  important given the housing of the Gawler  Institute Archives  in this area. The will need to be reviewed given the installation of the bookcases.  The Committee Also noted that the issue of CCTV needs to be considered for this area.  3.1.3 Main Heritage Gallery G.26  Current  specifications  in  the  DDP  (MPH)  schedule  indicate  black  track  lighting  code LT/03. This lighting is spot lighting which uses hard edged directional light to accentuate individual  items.  Lighting  in gallery and museums  requires, and particularly  in historic buildings where  the height of walls  is a  consideration, a  combination of diffuse  room lighting and directional spot lighting.   Museum gallery  lighting  systems using  spot  lighting  require additional attachments as lenses and filters etc. The system listed on the finishes and codes in the DD Plan (MPH) requires further refining as in most situations museums and galleries lighting do not use wholly diffuse or wholly directional but a combination of both.  Directional is a defined beam while diffuse washes a room with light.  The Gawler Heritage Collection Committee stated that the lighting system was a critical component  if  the  intention  is  to  host  national  or  touring  exhibitions  in  the Heritage Gallery area.  The  interior  design  palette  of  the  room  must  be  neutral  with  the  Committee recommending  that  it  should  link  to  the  Reading  Room  through  the  interior  design palette to designate it as a significant heritage area.   The existing ornate paint  finish  in  the  current Council  chamber dates  from  the 1980s and  such  a  paint  scheme  is  inappropriate  for  its  use  in  a  public  gallery  or museum display area.  With respect to this area functioning as a major gallery the Committee would like MPH to  explore  the  feasibility  of  a  ‘flexible  display  wall’  that  could  be  reconfigured  or removed as required to change the spatial layout of the gallery area.  Major art galleries and museums have purpose designed  fittings  so  that a  ‘temporary wall or partition’ can be secured to the floor as required. The Committee recommends that this option be explored as part of the schedule of works for the Heritage Gallery.  

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 21 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 22: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

15

The Gawler Heritage Collection Committee recommends the development of a detailed plan for electrical and communication services prepared specifically for this space as part of the internal design and its long time use as a gallery and museum space.  A Gallery Exhibition Design Plan would incorporate specifications for museum and display cases that meet National Standards for Australian Museums and Galleries (Melbourne 2011).    Requirements for audio/visual services would also need to be detailed in the Gallery Exhibition Design Plan. The existing audio visual  rack and other equipment would of  course need  to be removed from this area.   While the area has designated CCTV coverage the main entrance doors will require some form of electronic security and revised locking mechanism.  Marmoleum  is  an  appropriate  floor  treatment  though  again  the  ‘Acoustic  Report’  by  Bestec raised  serious  issues  of  noise  levels  for  this  area  and  options  for  sound  insulation.  The Committee requested further information and clarification regarding this matter.  Another acoustic sound  issue was the  lack of glazing to the northern windows to the Heritage Gallery  to  limit  noise  from  other  sources  such  as  the  café  and  customer  service  areas.  The Committee wants this issue addressed.  Fire Protection  services  indicate  sprinkler pipework  and  fire hose  reel pipework  to penetrate wall  above  Heritage  Gallery.  The  Committee  found  that  the  siting  of  pipework  above  the Heritage Gallery was  cause  for  risk  assessment  given  the Heritage Gallery would be used  for display of significant artefacts and works.   The Committee recommended that proper consideration be given to relocating this pipe work from  this  space  above  the  Heritage  Gallery.  Also  the  issue was  raised  of  the  possibility  for concealed sprinklers in the Heritage Gallery.  3.1.4 Corridor Entrance G.27 

 The Committee noted  in  the DDP  (MPH) Plan  that  in  the public access corridor  leading  to  the Heritage Gallery,  that  is Corridor G.27, a Services Distribution Board  is  indicated  for  the main wall at the entrance.   The Committee felt this was a very unsympathetic location and unsightly for such a distribution board considering it is the main access to the Heritage Gallery.   The Committee  recommends  that  this distribution board should be  relocated as  it  impacts on the main access and entrance to the Heritage Gallery and the aesthetics.  3.1.5 Heritage Gallery Store G.28  The Heritage Gallery Store is the former strong room on the ground floor of the Gawler Town Hall.  It  is appropriately placed  to service  the Heritage Gallery. This room will be 

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 22 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 23: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

16

used to store intended equipment or fittings associated with exhibitions in the Heritage Gallery – it will act as a holding and storage bay.  The Committee reiterated that it is important that the new doorway to this area will be as wide  and  as high  as possible  to  accommodate  exhibition display panels  and other large items and to ensure that loading in and loading out is optimised.   The current specifications appear to denote that it is a standard door.   The Committee also  recommended  that special security  fittings be considered  for  this doorway as it is in a public access area.  The Committee recommends that the interior slate shelving should be removed and the walls fitted with purpose designed storage racks. Space needs to be allowed for use of mechanical  aids  such  as  a  picture  trolley  and  a  small  dolly  in  order  to  assist  with movement of artworks and artefacts to and from the gallery.  The walls and  ceiling of  the designated  storage area  should be  lined as a measure  to minimise  concrete, mortar  and  brick  dust,  pest  infestations  and  control  damp.  This facility will need to be clean, waterproof and secure.  Higher levels of illuminance are required and no lower than 300 lux for this area as part of  safety  procedures  for  visually  locating  and  temporarily  moving  materials  and equipment to and from the gallery.  The issue of the design of the door needs to be considered given the movement of items and the need for security.  4.0 Review of Designated Heritage Areas Gawler Institute & Town Hall Buildings  Lower Ground Areas  4.1.1 Heritage Research & Local History Room LG.05  The Committee recommends relocating the Heritage Research Room from LG.06 to the former designated Youth & Gaming Space in this lower ground floor area.   This  room  is  more  suitable  than  the  adjacent  space,  as  the  increased  area  can accommodate most of the archival and reference collection that makes up the Gawler Heritage Collection.   Ancillary records such as  the  local history collection can be accommodated within  this space.   This area  is more suited to  ‘Public’ and  ‘Professional’ research activity and so with the change in use all of the current specifications regarding joinery, cabinetry and furniture will need to be revised given this new function.  

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 23 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 24: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

17

 All cabinetry will need to be compliant with museum and archival standards as they will contain  the  part  of  the  Gawler  Institute  Collection.  Cabinetry will  need  to minimise external  environmental  factors  such  as  dust  and  insect  entry  and  will  need  to  be secured. Bookcases will incorporate special design features to accommodate public use such as supported book holds.  This  room  is also adjacent  the Heritage Collections Store LG.04 which allows  for more effective service delivery. CCTV coverage is indicated in the plan.  Structural  consideration must  be  given  to  widening  the  existing  entrances  between LG.05 and the adjoining LG.06. (The former Research Room LG.06 will be used by staff as a meeting and quiet area.) T  The Committee reiterated  that  the widening of  this access doorway would allow  for a more  effective  transition  from  one  space  to  the  other  and  improve  access  and movement between spaces.  The Committee also recommended that consideration be given to widening the existing entrances  between  LG.05  and  the  adjoining  corridor  LG.02  to  give  better  access  for mechanical devices  such  as  trolleys or dollies  that would be used  to move  collection items.  The  Committee  recommended  that  the width  of  this  area  and  the  corridor which  is LG.02  should  be  as  a wide  as  possible  to  accommodate wheelchair  access  from  the corridor.  The proposed  lighting treatment for LG.05 was considered still appropriate even though there was a change of use. Data and electrical services need to be revised with respect to the provision of research services and public use. 

 The  Committee  noted  that  while  the  floor  is  being  raised  600mm  there  exists  an opportunity  to  highlight  the  fireplace  as  a  pre‐existing  heritage  element.  (The Committee specifically noted this treatment of remnant fabric in Old Parliament House.)  The Committee also discussed  the  issue of  the doorway  leading  from LG.05  to LG.04. The Committee recommends the raising of the doorway and reinstatement of the brick archway  and  quoins.  This  door  into  the  Heritage  Store  will  need  to  be  smoke  and fireproof.   4.1.2 Main Heritage Collections Store LG.04  The issue of the proposed floor level was raised by the Committee but it was noted that this would  be  part  of  the  new  concrete  slab  for  this  area.  The  detailed  design  plan makes no reference to the proposed works for this area so the Committee recommends that  the  whole  basement  area  be  raised  accordingly  –  including  the  Heritage  Store LG.04. 

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 24 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 25: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

18

 The Committee recommends that the floor level which is to be addressed as part of the concrete slab structure  in the basement must be able to handle the  load requirements of the compactus units.  The Committee also discussed the issue of the doorway leading from LG.04 to LG02. The Committee requires the raising of the doorway and reinstatement of the brick archway.   The Committee  recommends  that  the door  leading  from  the Heritage  Store  LG.04  to Corridor LG.02 will need to be smoke and fireproof.   The Main Heritage Store will also need to be fully lined with respect to walls and ceilings to meet museum and archival storage standards. The area will need to be waterproof and secure.  This  area  is  large enough  to house existing metal  storage  compactus units  and other metal storage cupboards. The Committee recommends that all shelving should be metal for this archival area.   Current descriptions  in the DD Plan  (MPH) do not state whether there  is a designated work station area for staff or interior work benches but this is a requirement.  These  fittings  should  be  specifically  designed  and  adapted  to  cater  for  collection requirements and ongoing management of the heritage collection items in situ.   Access to appropriate electrical, IT data services etc will be required.  

 The  Committee  recommended  clarification  regarding  air  conditioning  services  to  this area as again  it  reiterated  that  it will need  to be zoned  to meet  requirements and  to avoid temperature fluctuations. 

 Lighting requirements may need to be revised depending on location of compactus and other shelving units and workstations.  Relatively high illuminance is an important safety measure  for  handling  items  in  storage  or  collection  areas  as  it  facilitates  visual perception and location.  This  area  should  have  no  sprinkler  systems  but  should  be  fitted with  a  fireproof  door with appropriate  electronic  security  features.  This  area  requires  restricted  supervised  access  so  it should  not  house  any mechanical,  electrical,  communications,  fire  protection  service  switch boards or distribution boards.   4.1.3 Corridor LG.02 & Lift Basement  The  Committee  following  its  examination  of  the  Heritage  Research  Room  and  the Heritage  Collections  Store  felt  that  it  was  critical  for  staff  and  public  access  that consideration should be given to making the existing service lift from the ground floor to 

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 25 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 26: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

19

the  basement  two‐way.  Currently  it  only  opens  to  LG.08  restricting  efficient  and effective access, accessibility and movement to the designated heritage facilities.  The Committee recommends that the designated doorway (currently non‐existent)  and access  from Corridor LG.02  to  the public Heritage Research Facility LG.05 be made as high and wide as possible to facility movement and to cater for disabled access through these areas.  4.1.4 Walkway LG.01  The  Committee  recommends  that  the  area  designated  LG.01  be  utilised  for  the interpretation and display of the Town of Gawler’s War Memorabilia including memorial honour boards and other heritage items and that it be known as the ‘Walk of Honour ‘.  The  Committee  recommends  the  review  of  lighting  arrangements  noting  its  use  as  a proposed gallery and display space.   4.1.5 Meeting Rooms LG.20 & 22   With respect to these designated meeting rooms aligned to Murray Street  in the Town Hall  basement  area  the  Committee  felt  that  interpretive  displays  could  be accommodated if required.   The  Committee  resolved  that  within  the  historic  Gawler  Institute  and  Town  Hall buildings  there  were  many  opportunities  to  celebrate  Gawler’s  unique  history  and cultural diversity through creative display strategies.   The Gawler Heritage Collection Committee  reiterates  that  this  is part of  its  remit and the Committee would address this as part of the Gawler Cultural Heritage Management Plan.   Conclusion  The  Committee’s  deliberations  have  been made  in  good  faith  and  each member  has affirmed their excitement and support for the Gawler Connect Project and for the vision that  forms  an  important  part  of  the  Gawler  Connect  Project  Design  Development Detailed Report (MPH 2016).   

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 26 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 27: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

K

1

2

5

7

ROOM 3 - SWING SPACE1.06

ROOM 4 - COUNCIL CHAMBER /VIDEO CONFERENCE FACILITY

1.07

MEET1.26

MAYOR1.25 CEO

1.24

RECEPTION1.20

MALE1.10

ACCESS1.09

FEMALE1.08

ROOM 1 - JAMES MARTIN ROOM1.02

SERVERY

STEP LIFT1.21

ROOF VOIDUTILITY1.22

BALC

ON

Y1.

03BA

LCO

NY

1.27

VOID

VOID

VOID

F

6

E

VOID

STAIR 04G.09

LIFT

6800

7685

2600

1003

0

D HA C

4

2930

KITCHEN1.12

DIGITAL HUB1.11

3

J

CORRIDOR1.23

GB

OFFICE1.17

QUIET1.18

UTILITY1.13

SMART OFFICE1.14

5495 2850 6990 4500 4500 4500 5860 6300 5487

ROOM 2 - HALL1.05

STAFF1.19

CO

MM

S1.

04

STREET1.01

STAIR 03LG.14

DIGITAL HUB1.16

STAIR 01G.03

JO/19

JO/18

JO/14

JO/14

LF/02

LF/02

LF/02LF/02

LF/02 LF/02

LF/03LF/01LF/02

LF/02

LF/03

LF/09 LF/09 LF/09 LF/09

LF/09LF/09LF/09LF/09 LF/09

LF/09LF/09LF/09LF/09

LF/08 X 10LF/08 X 10LF/08 X 10LF/08 X 10

LF/08 X 10 LF/08 X 10 LF/08 X 10 LF/08 X 10 LF/08 X 10

LF/08 X 10LF/08 X 10LF/08 X 10LF/08 X 10

LF/08 X 56

LF/11 LF/11

LF/12LF/12

LF/12 LF/12LF/12 LF/12

LF/12LF/12

LF/01

LF/01 LF/01

LF/01 LF/01

LF/01 LF/01

LF/01

LF/01

LF/05LF/05

LF/01

SF/01

LF/01

SF/01

LF/01LF/01

SF/01

SF/01

LF/01

SF/04

SF/

03

SF/

03

SF/

03

SF/

03

SF/

03

SF/

03S

F/03

SF/

03

SF/05

LF/18

LF/01

SF/

06A

SF/06B

FB

SF/02

PPPP

COMMS

JO/20

JO/21

LF/18 LF/18

LF/18 LF/18 LF/18

FHR DB

MEET1.15

LF/14

LF/13 LF/13

JO/17LF/13LF/13

LF/01

LF/01LF/01

LF/01

LF/01

LF/01

LF/04

LF/18

LF/02LF/02

LF/02 LF/02

LF/03

LF/02 LF/02

LF/03

LF/02LF/02

LF/05LF/05LF/05LF/05LF/05

LF/05

LF/05

LF/05LF/05LF/05LF/05LF/05

LF/05 LF/05

LF/07 LF/07 LF/07

LF/07LF/07LF/07

LF/07

SF/08

S

LF/01

LF/05

LF/05LF/05

LF/05

LF/05

LF/05LF/05

LF/05LF/05

SS

S

SCRE

EN

SCREEN

SCRE

ENSC

REEN

LF/05

LF/05LF/07

LF/05

MONITOR

MONITOR

SMAR

T TV

W/BOARD W/BOARD

INFI

LLIN

FILL

LF/01

W/BOARD

LF/03

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

FFE Plan - First

Gawler Connect

Designer

Checker

DD3.041390

no amendment/issue date by POST DD ISSUE

ATTACHMENT 8

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 27 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 28: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

K

1

2

5

7

ROOF VOID

F

6

E

MALE2.05

FEMALE2.07

ACCESS2.06

LIFT STAIR 04G.09

OFFICE2.04

ADMIN2.01

QUIET2.09

OFFICE2.08

VOIDVOID

D HA C

2930

2600

1003

0

4

UTILITY2.03

3

J

CO

MPA

CTU

S

GB5495 2850 6990 4500 4500 4500 5860 6300 5487

STAIR 03LG.14

JO/21

JO/14

JO/14

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01 SF/01

LF/01 LF/01

LF/01LF/01

LF/01 LF/01

LF/01LF/01

LF/01 LF/01

LF/01LF/01

LF/01 LF/01

LF/01LF/01

LF/01 LF/01

LF/01LF/01

LF/01 LF/01

LF/1

9

LF/01LF/01

SF/02SF/02

LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18

LF/23 LF/23 LF/23 LF/23 LF/23

LF/10 LF/10 LF/10 LF/10

COMMSFHR DB

LF/18LF/18LF/18

LF/23 LF/23

SF/08

S

S S

SF/01

SF/01

SF/01

SF/01

LF/01LF/01

LF/01 LF/01

LF/18LF/18LF/18

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

FFE Plan - Second

Gawler Connect

Designer

Checker

DD3.051390

no amendment/issue date by POST DD ISSUETOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 28 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 29: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

K

1

2

5

7

F

6

E

ROOF VOID

VOID

ROOF VOID ROOF VOID

FEMALE3.07

MALE3.05

ACCESS3.06 LIFT STAIR 04

G.09

D HA C

4

KITCHEN3.02

OFFICE3.04

3

J

PLO

TTER

GB5495 2850 6990 4500 4500 4500 5860 6300 5487

ADMIN3.01

STAIR 03LG.14

JO/20

JO/21

JO/14

JO/14

LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18 LF/18

LF/23 LF/23 LF/23 LF/23 LF/23

LF/16

LF/16

LF/16

LF/16LF/16

LF/16

LF/16

LF/16

LF/15

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

SF/01

LF/01 LF/01

LF/01LF/01

LF/01 LF/01

LF/01LF/01

LF/01 LF/01

LF/01LF/01

LF/01 LF/01

LF/01LF/01

LF/01 LF/01

LF/01LF/01

LF/10LF/10

SF/02

LF/01

LF/01

SF/01

UTILITY3.03

FHR COMMS DB

LF/18 LF/18 LF/18LF/18 LF/18 LF/18LF/18 LF/18 LF/18

LF/01 LF/01 LF/01 LF/01 LF/01

LAYO

UT

BEN

CH

LF/23

SF/01SF/01 SF/01 SF/01 SF/01

S

S

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

FFE Plan - Third

Gawler Connect

Designer

Checker

DD3.061390

no amendment/issue date by POST DD ISSUETOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 29 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 30: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

CLD/01

SC/01

WT/03

PA/01 TO ALL STEELWORK

AN/01 TO ALL ALUMINIUM

CO/02

RT/02

GL/02

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

External Elevation - West

Gawler Connect

Designer

Checker

DD5.011390

1 : 100DD1.10

West Elevation1

no amendment/issue date by DD ISSUETOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 30 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 31: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

TRANSFORMER

CLD/02

CO/02

EXISTING BRICKWORK

EXISTING ROOF

SC/01

WT/03

SLIDING DELIVERY DOORBLACK ALUMINIUM SLATSWITH BLACK POWDERCOAT

SC/02

SC/02

SC/02

CO/02

CO/01

CO/02

CO/02

PA/01 TO ALL STEELWORK

AN/01 TO ALL ALUMINIUM

BLACK PAINTED RENDERON BLOCKWORK

RT/02

GL/02

PT/12DR/01

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

External Elevation - East

Gawler Connect

Designer

Checker

DD5.021390

1 : 100DD1.10

East Elevation2

no amendment/issue date by DD ISSUETOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 31 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 32: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

IB Ground Floor

49298

IB First Floor

54466

Lower Ground Floor

46198

K F E

Third Floor

62266

DH ACJ G B

High St RL

51130

Parapet

67066

CO/02

CLD/01

EXISTING BRICKWORK

EXISTING ROOF

SC/01

CLD/01

EXISTING BLOCKED INFIRST FLOOR OPENINGSREINSTATED WITHGLAZING, SIZED TOEXISTING COINWORK

EXISTING ROOF

EXISTING STONE

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

External Elevation - North

Gawler Connect

Designer

Checker

DD5.031390

1 : 100DD1.10

North Elevation3

no amendment/issue date by DD ISSUETOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 32 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 33: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

TH Ground Floor

49123

TH First FL

53362

IB First Floor

54466

Lower Ground Floor

46198

High St Mezzanine

51381

KFE

Third Floor

62266

D HA C JGB

Parapet

67066

CO/02

CO/01

CLD/01

ZINC GUTTER

SC/01

PA/01 TO ALL STEELWORK

scale

date

title

project

drawn

checked

drawing

project

ABN 16 759 676 449

5 Vardon Avenue Adelaide South Australia 5000

Telephone 08 8418 1600

www.mpharchitects.com.au

materne pennino hoare ©

Do not scale. Verify all dimension prior to commencement.

Refer any discrepancies to materne pennino hoare before

proceeding. Read with all project documentation.

legend

@A1 1 : 100

External Elevation - South

Gawler Connect

Designer

Checker

DD5.041390

1 : 100DD1.10

South Elevation4

no amendment/issue date by DD ISSUETOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 33 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 34: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

G A W L E R C O N N E C T P R O J E C T COST CENTRE $ BUDGET / COSTS 2014 / 2015 2015 2016

JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUNCOSTS TO JUNE 2015Project Management 109500 109500Legal Fees 4500 4500TOTAL 114000 114000

DESIGN CONSULTANTSContract FeeSub-Total 845,280 3700 47068.80 110625.70 10881.50 0.00 128,651.75 0

Additional FeesFlow Meter 530.91 530.91Staff Briefing Sessions 4,944.88 4944.88Heritage Architect Meeting 693.00 693.00Additional Floor / Incr Scope 137,562Sub-Total 143730.79

Temporary AccommodationStudy 24,510Inventories 5,490 5,490Sub-Total 30,000

TOTAL 1,019,010.79Total per Month 3700 52558.80 110625.70 10881.50 5475.79 129344.75 0Total to Date 3700 56258.80 166884.50 177766.00 183241.79 312586.54 312586.54

SUSTAINABILITY CONSULTANTContract FeeSub-Total 26627 6343.20 5872.80

Additional FeesClimate Change 2500 2000

Sub-Total 2500TOTAL 29127Total per Month 6343.20 7872.80Total to Date 6343.20 14216.00

COST CONSULTANTContract Fee 5000 7000 4500 6570Sub-Total 91000

Additional FeesAdditional Floor / Incr Scope 7000Sub-Total 7000TOTAL 98000Total per Month 5000 7000 4500 6570Total to Date 5000 12000 16500 23070

TRAFFIC CONSULTANTContract Fee 2400 2400DAC Meetings 2600

TOTAL 5000Total per Month 2400Total to Date 2400

LEGAL Norman Waterhouse 1,591.50 1,591.50

3,408.50Norman Waterhouse 5000.00

TOTAL 5000.00Total per Month 1591.50Total to Date 1591.50

PROJECT MANAGEMENTContract Fee 375,000 12,500 12,500 12,500 12,500 12,500 12,500

TOTAL 375,000Total per Month 12,500 12,500 12,500 12,500 12,500 12,500Total to Date 12,500 25,000 37,500 50,000 62,500 75,000

OTHER COSTSDestructive Investigations 15623.50 15623.50

5456.10Sub-Total 21079.60Chubb - Rec Centre Doors 5400 5400Asbestos Review 390 390Contracts 131.02 131.02J Fleming 2160 2160Catering 100.45 100.45

190 19063 63

102.88 102.881,644.12

Sub-Total 2,000.00CITB Levy 29,000TOTAL 60160.62Total per Month 231.47 2350 21023.50 390 165.88Total to Date 231.47 2581.47 23604.97 23994.97 24160.85

ATTACHMENT 9

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 34 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 35: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

TEMPORARY ACCOMMODATIONMIMP Cable 1,583.50 1583.50Reconfigure Phone lines 2,970.00Relocation Costs 225,446.50TOTAL 230,000.00Total per Month 1583.50Total to Date 1583.50

CONSTRUCTION 11,593,000

INFRASTRUCTURE UPGRADES 107,000

IT EQUIPMENT 100,000

TOTAL PROJECT 13735298.41Total per Month 65290.27 138410.40 52988.50 26238.59 146344.75 21635.88Total to Date 117700 182990.27 321400.67 374389.17 400627.76 546972.51 568608.39Budget 14,300,000Contingency 564701.59

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 35 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 36: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

GAWLER CONNECT PROJECTBUDGET ESTIMATES 20-January-2016

ORIGINAL SCHEME ADDITIONAL FLOORCOSTS TO 30 JUNE 2015

Project Management 109,500 109,500.00 ActualLegal Fees 4,500 4,500.00 Actual

Sub-Total 114,000 114,000.00

BUILDING WORKSTarget Building Contract Sum 9,500,000 11,600,000.00 Estimate

Sub-Total 9,500,000 11,600,000.00

PROJECT MANAGEMENTFrom July 2015 to December 2017 375,000 375,000.00 Actual

Sub-Total 375,000 375,000.00

PROFESSIONAL FEESDesign Consultants

Contract Fee 845,280 845,280.00 ActualAdditional Fees Flow Meter 530.91 Actual Staff Briefing Sessions 4,944.88 Actual Heritage Architect Meeting 693.00 Actual Additional Floor 137,562.00 EstimateSub-Total 0 143,730.79

Temporary Accommodation Study 30,000 24,510.00 EstimateInventories 5,490.00Sub-Total 30,000.00TOTAL 875,280 1,019,010.79

Sustainability ConsultantContract Fee 26,627 26,627.00 ActualAdditional Fees 0 2,500.00 ActualTOTAL 26,627 29,127.00

Cost ConsultantConract Fee 91,000 91,000.00 ActualAdditional Fees 0 7,000.00 ActualTOTAL 91,000 98,000.00

Traffic ConsultantConract Fee 2,400 2,400.00 ActualDAC Meetings 2,600 2,600.00 EstimateTOTAL 5,000 5,000.00

Legal 0 1,591.50 Actual0 3,408.50 Estimate

TOTAL 0 5,000.00

C:\Users\chaynes\AppData\Local\Hewlett‐Packard\HP TRIM\TEMP\HPTRIM.4304\CR16 17113  19‐04‐2014 Special Council Item x.x 

Attachment 10 ‐ Project Budget.XLSX

ATTACHMENT 10

TOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 36 of 37 ATTACHMENTS UNDER SEPARATE COVER

Page 37: Town of Gawler Special Council Meeting Agenda · 2017. 9. 8. · Town of Gawler Special Council Meeting Agenda 19 April 2016 ATTACHMENTS UNDER SEPARATE COVER Item 3.2 – Gawler Connect

IT EQUIPMENTSub-Total 200,000 100,000.00 Estimate

TEMPORARY ACCOMMODATIONMIMP Cable 1,583.50 ActualReconfigure Phone lines 2,970.00 ActualRelocation Costs 230,000 225,446.50 Estimate

Sub-Total 230,000 230,000.00

INFRASTRUCTURE UPGRADESSub-Total 300,000 107,000.00 Estimate

OTHER COSTSDestructive Investigations 15,000 15,623.50 Actual

5,456.10 ActualSub-Total 21,079.60Rec Centre Doors 0 5,400.00 ActualAsbestos Review 0 390.00 ActualContracts 0 65.51 ActualCITB Levy 25,500 29,000.00 EstimateCatering etc 0 190.00 Actual

63.00 Actual102.88 Actual

1,644.12 EstimateSub-Total 2,000.00J Fleming 0 2,160.00 Actual

Sub-Total 40,500 60,095.11

TOTAL 11,757,407 13,742,232.90BUDGET 12,800,000 14,300,000.00Project Contingency 1,042,593 557,767.10Contingency % 8.87 4.06

C:\Users\chaynes\AppData\Local\Hewlett‐Packard\HP TRIM\TEMP\HPTRIM.4304\CR16 17113  19‐04‐2014 Special Council Item x.x 

Attachment 10 ‐ Project Budget.XLSXTOWN OF GAWLER SPECIAL COUNCIL MEETING 19 APRIL 2016

Page 37 of 37 ATTACHMENTS UNDER SEPARATE COVER