Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
SEWER EXTENSSEWER EXTENSION & HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVIS 394 25-May-14 A 22-Jun-15 A -184
PRELIMINARIESPRELIMINARIES 394 25-May-14 A 22-Jun-15 A -184
P1000 Project start 0 25-May-14 A 0
P1020 Project documentation 15 25-May-14 A 10-Jun-14 A 0
P1030 Accommodation for Engineer's Staff 15 25-May-14 A 10-Jun-14 A 0
P1090 Mobilisation 30 25-May-14 A 28-Jun-14 A -15
P1021 Performance bond & insurance 30 25-May-14 A 28-Jun-14 A 0
P1022 Government permits/Authori approval 30 25-May-14 A 28-Jun-14 A 0
P1100 Surveying work 150 26-May-14 A 23-Nov-14 A 0
P1110 Dewatering 203 29-Jun-14 A 01-Mar-15 A -62
P1120 Other general maintenance & facilities 215 29-Jun-14 A 15-Mar-15 A -74
P1130 Revised Programme 02 0 31-Mar-15 A
P1080 Safety measures 285 25-May-14 A 30-Apr-15 A -114
P1040 Engineering site facilities 271 11-Jun-14 A 02-May-15 A -115
P1050 Contractor's site facilities 271 11-Jun-14 A 02-May-15 A -115
P1060 Testing of work 271 11-Jun-14 A 02-May-15 A -115
P1070 Testing of materials 271 11-Jun-14 A 02-May-15 A -115
P1010 Project finish 0 22-Jun-15 A -183
CHANGE ORDER INCHANGE ORDER INSTRUCTION NO.01 0 12-Jul-14 A 12-Jul-14 A
RC.1000 Changing RC pipe dia for all scope (618 lm) from 200 mm to 300 mm 0 12-Jul-14 A SI-1
RC.1010 Changing VC pipe dia for 62% of scope (453 lm) from 200 mm to 300 mm 0 12-Jul-14 A SI-1
RC.1020 Additional work by adding 18% of pipe length (136 lm) 0 12-Jul-14 A SI-1
RC.1030 Changing VC pipe dia for for all scope (105 lm) from 150 mm to 200 mm 0 12-Jul-14 A SI-1
ISSUANCE OF PERISSUANCE OF PERMITS 167 15-Jul-14 A 29-Dec-14 A
SEWER IN TRENCSEWER IN TRENCH PHASE-1 167 15-Jul-14 A 29-Dec-14 A
RC.1040 Issuance of Excavation Permit for (15/1/28/12/6 to 15/1/28/12/5) 0 15-Jul-14 A Ps
RC.1050 Issuance of Excavation Permit for (15/1/28/12/5 to 15/1/28/12/4) 0 15-Jul-14 A Ps
RC.1060 Issuance of Excavation Permit for (15/1/28/12/4 to 15/1/28/12/3) 0 16-Nov-14 A Ps
RC.1070 Issuance of Excavation Permit for (15/1/28/12/3 to 15/1/28/12/2) 0 26-Nov-14 A Ps
RC.1080 Issuance of Excavation Permit for (15/1/28/12/2 to 15/1/28/12/1) 0 16-Dec-14 A Ps
RC.1090 Issuance of Excavation Permit for (Not Yet Issuued) 0 29-Dec-14 A Ps
SEWER IN TRENCSEWER IN TRENCH PHASE-2 135 16-Aug-14 A 29-Dec-14 A
Feb Mar Apr May Jun Jul Aug
2015
Revised Programme 02
Project finish
m
00 mm
0 mm
Permit for (15/1/28/12/4 to 15/1/28/12/3)
on Permit for (15/1/28/12/3 to 15/1/28/12/2)
xcavation Permit for (15/1/28/12/2 to 15/1/28/12/1)
of Excavation Permit for (Not Yet Issuued)
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 1 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
RC.1110 Issuance of Excavation Permit for (15/1/28/15 to 15/1/28/14) 0 16-Aug-14 A Ps
RC.1100 Issuance of Excavation Permit for (15/1/28/16 to 15/1/28/15) 0 16-Sep-14 A Ps
RC.1120 Issuance of Excavation Permit for (15/1/28/14 to 15/1/28/13) 0 20-Dec-14 A Ps
RC.1130 Issuance of Excavation Permit for (Not Yet Issued) 0 29-Dec-14 A Ps
SEWER IN TRENCSEWER IN TRENCH PHASE-3 0 29-Dec-14 A 29-Dec-14 A
RC.1140 Issuance of Excavation Permit for Whole Phase (Not Yet Issued) 0 29-Dec-14 A Ps
TIME IMPLICATED TIME IMPLICATED FOR 46 12-Apr-15 A 28-May-15 A
EOT3.1000 Procession of Site (Should have been poccessed on 12.April.2015) 39 12-Apr-15 A 21-May-15 A Ps
SI2.1010 Site Instruction No 2 0 28-May-15 A SI-2
ENGINEERINGENGINEERING 99 25-May-14 A 31-Aug-14 A -18
SUBCONTRACTORSUBCONTRACTORS' PRE-QUALIFICATION 43 25-May-14 A 06-Jul-14 A 0
SUBMITTAL OF SSUBMITTAL OF SUBCONTRACTORS' PRE-QUALIFICATION 14 25-May-14 A 07-Jun-14 A 0
EN.S/A.SB1020 Submittal subconractor for Reinstatement 14 25-May-14 A 07-Jun-14 A 0
EN.S/A.SB1000 Submittal subconractor for Micro Tunneling 14 25-May-14 A 07-Jun-14 A 0
APPROVAL OF SAPPROVAL OF SUBCONTRACTORS' PRE-QUALIFICATION 21 08-Jun-14 A 06-Jul-14 A 0
EN.S/A.SB1030 Aproval subconractor for Micro Tunneling 21 08-Jun-14 A 06-Jul-14 A 0
EN.S/A.SB1010 Aproval subconractor for Reinstatement 21 08-Jun-14 A 06-Jul-14 A 0
METHOD STATEMMETHOD STATEMENT/GENERAL PLANS 43 25-May-14 A 06-Jul-14 A 0
SUBMITTAL OF MSUBMITTAL OF METHOD STATEMENT 14 25-May-14 A 07-Jun-14 A 0
EN.S.M1000 Submittal of method statement 14 25-May-14 A 07-Jun-14 A 0
APPROVAL OF MAPPROVAL OF METHOD STATEMENT 21 08-Jun-14 A 06-Jul-14 A 0
EN.A.M1000 Approval of method statement 21 08-Jun-14 A 06-Jul-14 A 0
GENERAL PLANSGENERAL PLANS 43 25-May-14 A 06-Jul-14 A 0
SUBMITTAL OF GSUBMITTAL OF GENERAL PLANS 14 25-May-14 A 07-Jun-14 A 0
EN.S.GP1000 Submittal of QA/QC plans 14 25-May-14 A 07-Jun-14 A 0
EN.S.GP1010 Submittal of health & safety plans 14 25-May-14 A 07-Jun-14 A 0
EN.S.GP1020 Submittal of Environmental plans 14 25-May-14 A 07-Jun-14 A 0
APPROVAL OF GAPPROVAL OF GENERAL PLANS 21 08-Jun-14 A 06-Jul-14 A 0
E.A.GP1000 Approval of QA/QC plans 21 08-Jun-14 A 06-Jul-14 A 0
E.A.GP1010 Approval of health & safety plans 21 08-Jun-14 A 06-Jul-14 A 0
E.A.GP1020 Approval of Environmental plans 21 08-Jun-14 A 06-Jul-14 A 0
SHOP DRAWING SSHOP DRAWING SUBMITTAL AND APPROVAL 64 29-Jun-14 A 31-Aug-14 A -18
Feb Mar Apr May Jun Jul Aug
2015
8/14)
6 to 15/1/28/15)
Excavation Permit for (15/1/28/14 to 15/1/28/13)
of Excavation Permit for (Not Yet Issued)
of Excavation Permit for Whole Phase (Not Yet Issued)
Site Instruction No 2
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 2 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
ENSDSA1000 Shop drawing submittal 30 29-Jun-14 A 31-Jul-14 A -18
ENSDSA1010 Shop drawing approval 21 03-Aug-14 A 31-Aug-14 A -12
PROCUREMENTPROCUREMENT 280 25-May-14 A 28-Feb-15 A -81
MATERIAL SUBMIMATERIAL SUBMITTAL 55 25-May-14 A 18-Jul-14 A -41
EMS1000 Readymix concrete 7 25-May-14 A 31-May-14 A 0
EMS1010 Steel reinforcement 7 25-May-14 A 31-May-14 A 0
EMS10100 Pipe bedding 7 25-May-14 A 31-May-14 A 0
EMS1070 Epoxy Products 7 01-Jun-14 A 07-Jun-14 A 0
EMS1080 Tanking 7 01-Jun-14 A 07-Jun-14 A 0
EMS1090 Bitumen Primer 7 01-Jun-14 A 07-Jun-14 A 0
EMS1120 DI Manhole Cover & Frame 7 01-Jun-14 A 07-Jun-14 A 0
EMS1130 Surface Box 7 01-Jun-14 A 07-Jun-14 A 0
EMS10600 Marker/warning tape 7 01-Jun-14 A 07-Jun-14 A 0
EMS1100 6mm Plywood 7 01-Jun-14 A 07-Jun-14 A 0
EMS1040 VC Pipe & Fittings 7 12-Jul-14 A 18-Jul-14 A -48 SI-1
EMS1050 GRP Lined RC Jacking Pipes 7 12-Jul-14 A 18-Jul-14 A -48 SI-1
EMS1060 GRP Products 7 12-Jul-14 A 18-Jul-14 A -48 SI-1
MATERIAL APPROMATERIAL APPROVAL 56 01-Jun-14 A 20-Aug-14 A -30
EMA1000 Readymix concrete 21 01-Jun-14 A 29-Jun-14 A 0
EMA1010 Steel reinforcement 21 01-Jun-14 A 29-Jun-14 A 0
EMA10100 Pipe bedding 21 01-Jun-14 A 29-Jun-14 A 0
EMA1070 Epoxy Products 21 08-Jun-14 A 06-Jul-14 A 0
EMA1080 Tanking 21 08-Jun-14 A 06-Jul-14 A 0
EMA1090 Bitumen Primer 21 08-Jun-14 A 06-Jul-14 A 0
EMA1100 6mm Plywood 21 08-Jun-14 A 06-Jul-14 A 0
EMA1120 DI Manhole Cover & Frame 21 08-Jun-14 A 06-Jul-14 A 0
EMA1130 Surface Box 21 08-Jun-14 A 06-Jul-14 A 0
EMA10600 Marker/warning tape 21 08-Jun-14 A 06-Jul-14 A 0
EMA1050 GRP Lined RC Jacking Pipes 21 20-Jul-14 A 20-Aug-14 A -35 SI-1
EMA1060 GRP Products 21 20-Jul-14 A 20-Aug-14 A -35 SI-1
EMA1040 VC Pipe & Fittings 21 20-Jul-14 A 20-Aug-14 A -35 SI-1
PROCURE MATERPROCURE MATERIAL 63 30-Jun-14 A 03-Sep-14 A -42
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 3 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
PMP1000 Readymix concrete 14 30-Jun-14 A 13-Jul-14 A 0
PMP1010 Steel reinforcement & Formwork 14 30-Jun-14 A 13-Jul-14 A 0
PMP10100 Pipe bedding 14 30-Jun-14 A 13-Jul-14 A 0
PMP1070 Epoxy Products 14 07-Jul-14 A 20-Jul-14 A 0
PMP1080 Tanking 14 07-Jul-14 A 20-Jul-14 A 0
PMP1090 Bitumen Primer 14 07-Jul-14 A 20-Jul-14 A 0
PMP1100 6mm Plywood 14 07-Jul-14 A 20-Jul-14 A 0
PMP1120 DI Manhole Cover & Frame 14 07-Jul-14 A 20-Jul-14 A 0
PMP1130 Surface Box 14 07-Jul-14 A 20-Jul-14 A 0
PMP10600 Marker/warning tape 14 07-Jul-14 A 20-Jul-14 A 0
PMP1040 VC Pipe & Fittings 14 21-Aug-14 A 03-Sep-14 A -49 SI-1
PMP1060 GRP Products 14 21-Aug-14 A 03-Sep-14 A -49 SI-1
PMP1050 GRP Lined RC Jacking Pipes 14 21-Aug-14 A 03-Sep-14 A -49
MATERIAL DELIVEMATERIAL DELIVERY TO SITE 236 30-Jun-14 A 28-Feb-15 A -79
PMD1000 Readymix concrete 157 30-Jun-14 A 09-Dec-14 A 0
PMD1050 GRP Lined RC Jacking Pipes 141 21-Aug-14 A 12-Jan-15 A -50 SI-1
PMD1010 Steel reinforcement 236 30-Jun-14 A 28-Feb-15 A -86
PMD1040 VC Pipe & Fittings 187 21-Aug-14 A 28-Feb-15 A -91 SI-1
PMD1060 GRP Products 187 21-Aug-14 A 28-Feb-15 A -124 SI-1
PMD1070 Epoxy Products 229 07-Jul-14 A 28-Feb-15 A -204
PMD1080 Tanking 229 07-Jul-14 A 28-Feb-15 A -128
PMD1090 Bitumen Primer 229 07-Jul-14 A 28-Feb-15 A -175
PMD1100 6mm Plywood 229 07-Jul-14 A 28-Feb-15 A -182
PMD10100 Pipe bedding 236 30-Jun-14 A 28-Feb-15 A -222
PMD1120 DI Manhole Cover & Frame 229 07-Jul-14 A 28-Feb-15 A -215
PMD1130 Surface Box 229 07-Jul-14 A 28-Feb-15 A -215
PMD10600 Marker/warning tape 229 07-Jul-14 A 28-Feb-15 A -124
CONSTRUCTIONCONSTRUCTION 359 29-Jun-14 A 22-Jun-15 A -184
SEWER IN TRENCSEWER IN TRENCH 359 29-Jun-14 A 22-Jun-15 A -196
PHASE 1: FROM PHASE 1: FROM MH 15/1/28/12/6 TO MH 15/1/28/12 287 29-Jun-14 A 11-Apr-15 A -216
VC PIPE WORKSVC PIPE WORKS: FROM MH 15/1/28/12/6 TO MH 15/1/28/12 283 29-Jun-14 A 07-Apr-15 A -238
200mm NOMINA200mm NOMINAL BORE 33.88m: From MH 15/1/28/12/6 to MH 15/1/28/12/5 219 29-Jun-14 A 19-Mar-15 A -198
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 4 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CST1010 Excavation & disposal of materials 5 29-Jun-14 A 03-Jul-14 A 4
CST1020 Bedding preparation prior to VC pipe laying 2 05-Jul-14 A 06-Jul-14 A 4
CST1030 Laying VC pipes & fittings and pre-testing 2 12-Jul-14 A 13-Jul-14 A 0
CST1040 Granular & concrete surrounds 2 14-Jul-14 A 15-Jul-14 A 0
CST1050 Backfilling 3 16-Jul-14 A 19-Jul-14 A 0
CST1060 SRC 20 concrete backfill 2 20-Jul-14 A 21-Jul-14 A 0
CST1070 Marker tape installation 2 18-Mar-15 A 19-Mar-15 A -198
200mm NOMINA200mm NOMINAL BORE 90.09m: From MH 15/1/28/12/5 to MH 15/1/28/12/4 205 15-Jul-14 A 19-Mar-15 A
CST1930 Excavation & disposal of materials 9 15-Jul-14 A 24-Jul-14 A
CST1940 Bedding preparation prior to VC pipe laying 2 26-Jul-14 A 27-Jul-14 A
CST1950 Laying VC pipes & fittings and pre-testing 2 31-Jul-14 A 02-Aug-14 A
CST1960 Granular & concrete surrounds 2 03-Aug-14 A 04-Aug-14 A
CST1970 Backfilling 3 05-Aug-14 A 07-Aug-14 A
CST1980 SRC 20 concrete backfill 2 09-Aug-14 A 10-Aug-14 A
CST1990 Marker tape installation 2 18-Mar-15 A 19-Mar-15 A
300mm NOMINA300mm NOMINAL BORE 50.37m: From MH 15/1/28/12/4 to MH 15/1/28/12/3 185 11-Aug-14 A 19-Mar-15 A -198
CST1080 Excavation & disposal of materials 9 11-Aug-14 A 20-Aug-14 A -34
CST1090 Bedding preparation prior to VC pipe laying 2 21-Aug-14 A 23-Aug-14 A -34
CST1100 Laying VC pipes & fittings and pre-testing 2 24-Aug-14 A 25-Aug-14 A -34
CST1110 Granular & concrete surrounds 2 26-Aug-14 A 27-Aug-14 A -34
CST1120 Backfilling 3 28-Aug-14 A 31-Aug-14 A -34
CST1130 SRC 20 concrete backfill 2 01-Sep-14 A 02-Sep-14 A -34
CST1210 Marker tape installation 2 18-Mar-15 A 19-Mar-15 A -198
300mm NOMINA300mm NOMINAL BORE 42.20m: From MH 15/1/28/12/3 to MH 15/1/28/12/2 185 11-Aug-14 A 19-Mar-15 A -193
CST1150 Excavation & disposal of materials 5 11-Aug-14 A 16-Aug-14 A -25
CST1160 Bedding preparation prior to VC pipe laying 2 24-Aug-14 A 25-Aug-14 A -31
CST1170 Laying VC pipes & fittings and pre-testing 2 26-Aug-14 A 27-Aug-14 A -31
CST1180 Granular & concrete surrounds 2 28-Aug-14 A 30-Aug-14 A -31
CST1190 Backfilling 3 01-Sep-14 A 03-Sep-14 A -32
CST1200 SRC 20 concrete backfill 2 04-Sep-14 A 06-Sep-14 A -32
CST1280 Marker tape installation 2 18-Mar-15 A 19-Mar-15 A -193
300mm NOMINA300mm NOMINAL BORE 34.48m: From MH 15/1/28/12/2 to MH 15/1/28/12/1 100 22-Nov-14 A 19-Mar-15 A -183
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 5 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CST1220 Excavation & disposal of materials 4 22-Nov-14 A 25-Nov-14 A -99
CST1230 Bedding preparation prior to VC pipe laying 3 27-Nov-14 A 30-Nov-14 A -101
CST1240 Laying VC pipes & fittings and pre-testing 2 04-Dec-14 A 06-Dec-14 A -104
CST1250 Granular & concrete surrounds 2 09-Dec-14 A 10-Dec-14 A -106
CST1260 Backfilling 4 10-Dec-14 A 14-Dec-14 A -106
CST1270 SRC 20 concrete backfill 2 17-Dec-14 A 20-Dec-14 A -108
CST1350 Marker tape installation 2 18-Mar-15 A 19-Mar-15 A -183
300mm NOMINA300mm NOMINAL BORE 59.46m: From MH 15/1/28/12/1 to MH 15/1/28/12 88 10-Jan-15 A 07-Apr-15 A -238
CST129 Recovery 0 10-Jan-15 A
CST1290 Excavation & disposal of materials 2 01-Mar-15 A 02-Mar-15 A -180
CST129.10 Delay: Issuance of Excavation permit 75 10-Jan-15 A 25-Mar-15 A
CST1300 Bedding preparation prior to VC pipe laying 4 28-Mar-15 A 31-Mar-15 A -203
CST1310 Laying VC pipes & fittings and pre-testing 5 28-Mar-15 A 01-Apr-15 A -202
CST1320 Granular & concrete surrounds 6 28-Mar-15 A 02-Apr-15 A -201
CST1330 Backfilling 7 28-Mar-15 A 04-Apr-15 A -199
CST1340 SRC 20 concrete backfill 8 29-Mar-15 A 06-Apr-15 A -199
CST1420 Marker tape installation 1 07-Apr-15 A 07-Apr-15 A -199
FUTURE CONNEFUTURE CONNECTION 46 16-Feb-15 A 09-Apr-15 A
FC-01FC-01 46 16-Feb-15 A 09-Apr-15 A
CST2330 SRC 20 concrete backfill 1 16-Mar-15 A 16-Mar-15 A
CST2280 Excavation & disposal of materials 42 16-Feb-15 A 05-Apr-15 A
CST2290 Bedding preparation prior to VC pipe laying 40 18-Feb-15 A 05-Apr-15 A
CST2300 Laying VC pipes & fittings and pre-testing 39 19-Feb-15 A 05-Apr-15 A
CST2310 Granular & concrete surrounds 38 21-Feb-15 A 05-Apr-15 A
CST2320 Backfilling 38 22-Feb-15 A 06-Apr-15 A
CST2340 Marker tape installation 2 08-Apr-15 A 09-Apr-15 A
MANHOLE CONSMANHOLE CONSTRUCTION 204 26-Jul-14 A 29-Mar-15 A -178
MANHOLE: 15/1MANHOLE: 15/1/28/12/6 25 26-Jul-14 A 26-Aug-14 A -14
CSTM1010 Excavation & disposal of materials 4 26-Jul-14 A 02-Aug-14 A -14
CSTM1020 Blinding 1 03-Aug-14 A 03-Aug-14 A -14
CSTM1030 Reinforcement, shuttering, concreting 4 04-Aug-14 A 07-Aug-14 A -14
CSTM1040 Pipe connection to manhole & pre-testing of section 2 09-Aug-14 A 10-Aug-14 A -14
Feb Mar Apr May Jun Jul Aug
2015
very
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 6 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSTM10400 Benching work 2 11-Aug-14 A 12-Aug-14 A -14
CSTM1050 Bitumen primer 1 13-Aug-14 A 13-Aug-14 A -14
CSTM1060 Tanking membrane 1 14-Aug-14 A 14-Aug-14 A -14
CSTM1070 Epoxy mortor & sealant 2 16-Aug-14 A 17-Aug-14 A -14
CSTM1080 GRP accessories 2 18-Aug-14 A 19-Aug-14 A -14
CSTM1090 DI Manhole Cover & Frame 2 20-Aug-14 A 21-Aug-14 A -14
CSTM1100 Backfilling 3 23-Aug-14 A 25-Aug-14 A -14
CSTM1330 SRC 20 concrete backfill 1 26-Aug-14 A 26-Aug-14 A -14
MANHOLE: 15/1MANHOLE: 15/1/28/12/5 25 03-Aug-14 A 31-Aug-14 A
CSTM28210 Excavation & disposal of materials 4 03-Aug-14 A 06-Aug-14 A
CSTM28220 Blinding 1 07-Aug-14 A 07-Aug-14 A
CSTM28230 Reinforcement, shuttering, concreting 4 09-Aug-14 A 12-Aug-14 A
CSTM28240 Pipe connection to manhole & pre-testing of section 2 13-Aug-14 A 14-Aug-14 A
CSTM28250 Benching work 2 16-Aug-14 A 17-Aug-14 A
CSTM28260 Bitumen primer 1 18-Aug-14 A 18-Aug-14 A
CSTM28270 Tanking membrane 1 19-Aug-14 A 19-Aug-14 A
CSTM28280 Epoxy mortor & sealant 2 20-Aug-14 A 21-Aug-14 A
CSTM28290 GRP accessories 2 23-Aug-14 A 24-Aug-14 A
CSTM28300 DI Manhole Cover & Frame 2 25-Aug-14 A 26-Aug-14 A
CSTM28310 Backfilling 3 27-Aug-14 A 30-Aug-14 A
CSTM28320 SRC 20 concrete backfill 1 31-Aug-14 A 31-Aug-14 A
MANHOLE: 15/1MANHOLE: 15/1/28/12/4 24 21-Aug-14 A 17-Sep-14 A -32
CSTM1350 Excavation & disposal of materials 4 21-Aug-14 A 25-Aug-14 A -34
CSTM1360 Blinding 1 26-Aug-14 A 26-Aug-14 A -34
CSTM1370 Reinforcement, shuttering, concreting 4 27-Aug-14 A 31-Aug-14 A -34
CSTM1380 Pipe connection to manhole & pre-testing of section 2 01-Sep-14 A 02-Sep-14 A -32
CSTM13800 Benching work 2 03-Sep-14 A 04-Sep-14 A -32
CSTM1390 Bitumen primer 1 06-Sep-14 A 06-Sep-14 A -32
CSTM1400 Tanking membrane 1 07-Sep-14 A 07-Sep-14 A -32
CSTM1410 Epoxy mortor & sealant 1 08-Sep-14 A 08-Sep-14 A -32
CSTM1420 GRP accessories 2 09-Sep-14 A 10-Sep-14 A -32
CSTM1430 DI Manhole Cover & Frame 2 11-Sep-14 A 13-Sep-14 A -32
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 7 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSTM1440 Backfilling 3 14-Sep-14 A 16-Sep-14 A -32
CSTM1450 SRC 20 concrete backfill 1 17-Sep-14 A 17-Sep-14 A -32
MANHOLE: 15/1MANHOLE: 15/1/28/12/3 32 17-Aug-14 A 22-Sep-14 A -32
CSTM1470 Excavation & disposal of materials 4 17-Aug-14 A 20-Aug-14 A -25
CSTM1480 Blinding 1 28-Aug-14 A 28-Aug-14 A -31
CSTM1490 Reinforcement, shuttering, concreting 4 01-Sep-14 A 04-Sep-14 A -33
CSTM1500 Pipe connection to manhole & pre-testing of section 2 06-Sep-14 A 07-Sep-14 A -32
CSTM15000 Benching work 2 08-Sep-14 A 09-Sep-14 A -32
CSTM1510 Bitumen primer 1 10-Sep-14 A 10-Sep-14 A -32
CSTM1520 Tanking membrane 1 11-Sep-14 A 11-Sep-14 A -32
CSTM1530 Epoxy mortor & sealant 1 13-Sep-14 A 13-Sep-14 A -32
CSTM1540 GRP accessories 2 14-Sep-14 A 15-Sep-14 A -32
CSTM1550 DI Manhole Cover & Frame 2 16-Sep-14 A 17-Sep-14 A -32
CSTM1560 Backfilling 3 18-Sep-14 A 21-Sep-14 A -32
CSTM1570 SRC 20 concrete backfill 1 22-Sep-14 A 22-Sep-14 A -32
MANHOLE: 15/1MANHOLE: 15/1/28/12/2 27 21-Dec-14 A 20-Jan-15 A -122
CSTM1690 SRC 20 concrete backfill 1 21-Dec-14 A 21-Dec-14 A -96
CSTM1590 Excavation & disposal of materials 4 25-Dec-14 A 29-Dec-14 A -123
CSTM1600 Blinding 1 30-Dec-14 A 30-Dec-14 A -123
CSTM1610 Reinforcement, shuttering, concreting 4 31-Dec-14 A 04-Jan-15 A -123
CSTM1620 Pipe connection to manhole & pre-testing of section 2 05-Jan-15 A 06-Jan-15 A -123
CSTM16200 Benching work 2 07-Jan-15 A 08-Jan-15 A -123
CSTM1630 Bitumen primer 1 10-Jan-15 A 10-Jan-15 A -123
CSTM1640 Tanking membrane 1 11-Jan-15 A 11-Jan-15 A -123
CSTM1650 Epoxy mortor & sealant 1 12-Jan-15 A 12-Jan-15 A -123
CSTM1660 GRP accessories 2 13-Jan-15 A 14-Jan-15 A -123
CSTM1670 DI Manhole Cover & Frame 2 15-Jan-15 A 17-Jan-15 A -123
CSTM1680 Backfilling 3 18-Jan-15 A 20-Jan-15 A -123
MANHOLE: 15/1MANHOLE: 15/1/28/12/1 81 24-Dec-14 A 29-Mar-15 A -178
CSTM1710 Excavation & disposal of materials 4 24-Dec-14 A 28-Dec-14 A -122
CSTM1720 Blinding 2 28-Dec-14 A 29-Dec-14 A -122
CSTM1730 Reinforcement, shuttering, concreting 4 31-Dec-14 A 04-Jan-15 A -123
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 8 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSTM1740 Pipe connection to manhole & pre-testing of section 3 05-Jan-15 A 07-Jan-15 A -124
CSTM17400 Benching work 2 08-Jan-15 A 10-Jan-15 A -124
CSTM1750 Bitumen primer 1 13-Jan-15 A 13-Jan-15 A -126
CSTM1760 Tanking membrane 1 29-Jan-15 A 29-Jan-15 A -139
CSTM1770 Epoxy mortor & sealant 1 25-Feb-15 A 25-Feb-15 A -160
CSTM1780 GRP accessories 2 26-Feb-15 A 28-Feb-15 A -160
CSTM1800 Backfilling 4 24-Feb-15 A 28-Feb-15 A -155
CSTM1790 DI Manhole Cover & Frame 3 21-Mar-15 A 23-Mar-15 A -178
CSTM1810 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -178
MANHOLE: 15/1MANHOLE: 15/1/28/12 79 25-Dec-14 A 28-Mar-15 A
CSTM28330 Excavation & disposal of materials 5 25-Dec-14 A 30-Dec-14 A
CSTM28340 Blinding 1 01-Jan-15 A 01-Jan-15 A
CSTM28350 Reinforcement, shuttering, concreting 4 03-Jan-15 A 06-Jan-15 A
CSTM28360 Pipe connection to manhole & pre-testing of section 2 07-Jan-15 A 08-Jan-15 A
CSTM28370 Benching work 2 10-Jan-15 A 11-Jan-15 A
CSTM28380 Bitumen primer 1 12-Jan-15 A 12-Jan-15 A
CSTM28390 Tanking membrane 1 13-Jan-15 A 13-Jan-15 A
CSTM28400 Epoxy mortor & sealant 2 19-Mar-15 A 21-Mar-15 A
CSTM28410 GRP accessories 3 21-Mar-15 A 23-Mar-15 A
CSTM28420 DI Manhole Cover & Frame 3 23-Mar-15 A 25-Mar-15 A
CSTM28430 Backfilling 4 24-Mar-15 A 28-Mar-15 A
CSTM28440 SRC 20 concrete backfill 2 26-Mar-15 A 28-Mar-15 A
REINSTATEMENTREINSTATEMENT 41 23-Feb-15 A 11-Apr-15 A -180
ASPHALTASPHALT 39 23-Feb-15 A 08-Apr-15 A -182
CSTR1110 90mm Base course 38 23-Feb-15 A 07-Apr-15 A -186
CSTR1120 70mm Wearing course 27 09-Mar-15 A 08-Apr-15 A -182
KERBSTONEKERBSTONE 18 22-Mar-15 A 11-Apr-15 A -186
CSTR1130 Excavation & concrete foundation for kerbs 16 22-Mar-15 A 08-Apr-15 A -186
CSTR1140 Kerbs installation 17 22-Mar-15 A 09-Apr-15 A -186
CSTR1150 Backing concrete 18 22-Mar-15 A 11-Apr-15 A -186
PAVING/CONCRPAVING/CONCRETE PAVING 2 18-Mar-15 A 19-Mar-15 A -163
CSTR1160 Formation preparation 2 18-Mar-15 A 19-Mar-15 A -165
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 9 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSTR1170 Paving interlock 2 18-Mar-15 A 19-Mar-15 A -163
PLANT AND GRPLANT AND GRASS 2 18-Mar-15 A 19-Mar-15 A -161
CSTR1180 Excavation for plants 2 18-Mar-15 A 19-Mar-15 A -163
CSTR1190 Planting/grass 2 18-Mar-15 A 19-Mar-15 A -161
PHASE 2: FROM PHASE 2: FROM MH 15/1/18/12 TO 15/1/28/16 225 16-Aug-14 A 10-May-15 A -162
VC PIPE WORKSVC PIPE WORKS: 15/1/18/12 TO 15/1/28/16 180 16-Aug-14 A 18-Mar-15 A -145
300mm NOMINA300mm NOMINAL BORE 56.99m: From MH 15/1/28/12 to MH 15/1/28/13 29 25-Jan-15 A 28-Feb-15 A
CST2030 Granular & concrete surrounds 2 29-Jan-15 A 31-Jan-15 A
CST2040 Backfilling 3 28-Jan-15 A 31-Jan-15 A
CST2050 SRC 20 concrete backfill 2 29-Jan-15 A 31-Jan-15 A
CST2000 Excavation & disposal of materials 9 25-Jan-15 A 03-Feb-15 A
CST2010 Bedding preparation prior to VC pipe laying 9 03-Feb-15 A 14-Feb-15 A
CST2020 Laying VC pipes & fittings and pre-testing 9 05-Feb-15 A 16-Feb-15 A
CST2060 Marker tape installation 25 29-Jan-15 A 28-Feb-15 A
300mm NOMINA300mm NOMINAL BORE 55.00m: From MH 15/1/28/13 to MH 15/1/28/14 52 01-Dec-14 A 31-Jan-15 A
CST2070 Excavation & disposal of materials 8 01-Dec-14 A 09-Dec-14 A
CST2080 Bedding preparation prior to VC pipe laying 2 10-Dec-14 A 11-Dec-14 A
CST2090 Laying VC pipes & fittings and pre-testing 3 13-Dec-14 A 15-Dec-14 A
CST2100 Granular & concrete surrounds 2 17-Dec-14 A 20-Dec-14 A
CST2110 Backfilling 4 22-Dec-14 A 25-Dec-14 A
CST2120 SRC 20 concrete backfill 2 27-Dec-14 A 28-Dec-14 A
CST2130 Marker tape installation 2 29-Jan-15 A 31-Jan-15 A
200mm NOMINA200mm NOMINAL BORE 36.30m: From MH 15/1/28/14 to MH 15/1/28/14/1 29 25-Jan-15 A 28-Feb-15 A
CST2140 Excavation & disposal of materials 9 25-Jan-15 A 03-Feb-15 A
CST2190 SRC 20 concrete backfill 10 14-Feb-15 A 24-Feb-15 A
CST2150 Bedding preparation prior to VC pipe laying 11 11-Feb-15 A 24-Feb-15 A
CST2160 Laying VC pipes & fittings and pre-testing 11 11-Feb-15 A 24-Feb-15 A
CST2170 Granular & concrete surrounds 11 11-Feb-15 A 24-Feb-15 A
CST2180 Backfilling 10 14-Feb-15 A 24-Feb-15 A
CST2200 Marker tape installation 2 26-Feb-15 A 28-Feb-15 A
200mm NOMINA200mm NOMINAL BORE 41.20m: From MH 15/1/28/14/1 to MH 15/1/28/14/2 45 25-Jan-15 A 18-Mar-15 A
CST2210 Excavation & disposal of materials 9 25-Jan-15 A 03-Feb-15 A
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 10 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CST2220 Bedding preparation prior to VC pipe laying 11 11-Feb-15 A 24-Feb-15 A
CST2230 Laying VC pipes & fittings and pre-testing 11 11-Feb-15 A 24-Feb-15 A
CST2240 Granular & concrete surrounds 11 11-Feb-15 A 24-Feb-15 A
CST2250 Backfilling 11 11-Feb-15 A 24-Feb-15 A
CST2260 SRC 20 concrete backfill 10 14-Feb-15 A 24-Feb-15 A
CST2270 Marker tape installation 2 17-Mar-15 A 18-Mar-15 A
300mm NOMINA300mm NOMINAL BORE 71.5m: From MH 15/1/28/14 to MH 15/1/28/15 180 16-Aug-14 A 18-Mar-15 A -148
CST1360 Excavation & disposal of materials 5 16-Aug-14 A 20-Aug-14 A 15
CST1370 Bedding preparation prior to VC pipe laying 5 26-Aug-14 A 31-Aug-14 A 8
CST1380 Laying VC pipes & fittings and pre-testing 3 28-Aug-14 A 31-Aug-14 A 10
CST1390 Granular & concrete surrounds 2 31-Aug-14 A 01-Sep-14 A 11
CST1400 Backfilling 3 02-Sep-14 A 04-Sep-14 A 11
CST1410 SRC 20 concrete backfill 3 06-Sep-14 A 08-Sep-14 A 10
CST1490 Marker tape installation 2 17-Mar-15 A 18-Mar-15 A -148
300mm NOMINA300mm NOMINAL BORE 60m: From MH 15/1/28/15 to MH 15/1/28/16 153 16-Sep-14 A 18-Mar-15 A -145
CST1430 Excavation & disposal of materials 134 16-Sep-14 A 24-Feb-15 A -141
CST1440 Bedding preparation prior to VC pipe laying 130 21-Sep-14 A 24-Feb-15 A -139
CST1450 Laying VC pipes & fittings and pre-testing 131 23-Sep-14 A 28-Feb-15 A -140
CST1460 Granular & concrete surrounds 129 25-Sep-14 A 28-Feb-15 A -136
CST1470 Backfilling 127 28-Sep-14 A 28-Feb-15 A -132
CST1480 SRC 20 concrete backfill 124 01-Oct-14 A 28-Feb-15 A -130
CST1560 Marker tape installation 2 17-Mar-15 A 18-Mar-15 A -145
FUTURE CONNEFUTURE CONNECTION 70 18-Feb-15 A 10-May-15 A
FC-02FC-02 46 18-Feb-15 A 12-Apr-15 A
CST2350 Excavation & disposal of materials 14 18-Feb-15 A 05-Mar-15 A
CST2360 Bedding preparation prior to VC pipe laying 12 21-Feb-15 A 06-Mar-15 A
CST2370 Laying VC pipes & fittings and pre-testing 11 22-Feb-15 A 06-Mar-15 A
CST2380 Granular & concrete surrounds 11 23-Feb-15 A 07-Mar-15 A
CST2390 Backfilling 10 24-Feb-15 A 07-Mar-15 A
CST2400 SRC 20 concrete backfill 1 09-Apr-15 A 09-Apr-15 A
CST2410 Marker tape installation 2 11-Apr-15 A 12-Apr-15 A
FC-03FC-03 45 21-Feb-15 A 13-Apr-15 A
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 11 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CST2420 Excavation & disposal of materials 12 21-Feb-15 A 06-Mar-15 A
CST2430 Bedding preparation prior to VC pipe laying 11 23-Feb-15 A 07-Mar-15 A
CST2440 Laying VC pipes & fittings and pre-testing 10 24-Feb-15 A 07-Mar-15 A
CST2450 Granular & concrete surrounds 10 25-Feb-15 A 08-Mar-15 A
CST2460 Backfilling 9 26-Feb-15 A 08-Mar-15 A
CST2470 SRC 20 concrete backfill 1 11-Apr-15 A 11-Apr-15 A
CST2480 Marker tape installation 1 12-Apr-15 A 13-Apr-15 A
FC-04FC-04 66 23-Feb-15 A 10-May-15 A
CST2490 Excavation & disposal of materials 36 23-Feb-15 A 05-Apr-15 A
CST2500 Bedding preparation prior to VC pipe laying 34 25-Feb-15 A 05-Apr-15 A
CST2510 Laying VC pipes & fittings and pre-testing 34 26-Feb-15 A 06-Apr-15 A
CST2520 Granular & concrete surrounds 33 28-Feb-15 A 06-Apr-15 A
CST2530 Backfilling 33 28-Feb-15 A 06-Apr-15 A
CST2540 SRC 20 concrete backfill 24 12-Apr-15 A 09-May-15 A
CST2550 Marker tape installation 24 13-Apr-15 A 10-May-15 A
FC-05FC-05 29 08-Mar-15 A 09-Apr-15 A
CST2560 Excavation & disposal of materials 26 08-Mar-15 A 06-Apr-15 A
CST2570 Bedding preparation prior to VC pipe laying 23 11-Mar-15 A 06-Apr-15 A
CST2580 Laying VC pipes & fittings and pre-testing 22 12-Mar-15 A 06-Apr-15 A
CST2590 Granular & concrete surrounds 21 14-Mar-15 A 06-Apr-15 A
CST2600 Backfilling 21 14-Mar-15 A 06-Apr-15 A
CST2610 SRC 20 concrete backfill 21 16-Mar-15 A 08-Apr-15 A
CST2620 Marker tape installation 20 18-Mar-15 A 09-Apr-15 A
MANHOLE CONSMANHOLE CONSTRUCTION 98 01-Dec-14 A 26-Mar-15 A -140
MANHOLE: 15/1MANHOLE: 15/1/28/13 73 03-Dec-14 A 28-Feb-15 A
CSTM28450 Excavation & disposal of materials 4 03-Dec-14 A 07-Dec-14 A
CSTM28460 Blinding 2 08-Dec-14 A 09-Dec-14 A
CSTM28470 Reinforcement, shuttering, concreting 5 08-Dec-14 A 13-Dec-14 A
CSTM28480 Pipe connection to manhole & pre-testing of section 3 15-Dec-14 A 17-Dec-14 A
CSTM28490 Benching work 3 20-Dec-14 A 22-Dec-14 A
CSTM28500 Bitumen primer 2 23-Dec-14 A 24-Dec-14 A
CSTM28510 Tanking membrane 1 02-Feb-15 A 02-Feb-15 A
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 12 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSTM28520 Epoxy mortor & sealant 1 03-Feb-15 A 03-Feb-15 A
CSTM28530 GRP accessories 2 04-Feb-15 A 05-Feb-15 A
CSTM28550 Backfilling 3 09-Feb-15 A 11-Feb-15 A
CSTM28560 SRC 20 concrete backfill 2 18-Feb-15 A 19-Feb-15 A
CSTM28540 DI Manhole Cover & Frame 2 26-Feb-15 A 28-Feb-15 A
MANHOLE: 15/1MANHOLE: 15/1/28/14 71 04-Dec-14 A 26-Feb-15 A
CSTM28570 Excavation & disposal of materials 4 04-Dec-14 A 08-Dec-14 A
CSTM28580 Blinding 2 11-Dec-14 A 13-Dec-14 A
CSTM28590 Reinforcement, shuttering, concreting 4 14-Dec-14 A 17-Dec-14 A
CSTM28600 Pipe connection to manhole & pre-testing of section 2 17-Dec-14 A 20-Dec-14 A
CSTM28610 Benching work 3 21-Dec-14 A 23-Dec-14 A
CSTM28620 Bitumen primer 2 08-Jan-15 A 10-Jan-15 A
CSTM28630 Tanking membrane 2 12-Jan-15 A 13-Jan-15 A
CSTM28640 Epoxy mortor & sealant 1 14-Jan-15 A 14-Jan-15 A
CSTM28650 GRP accessories 2 15-Jan-15 A 17-Jan-15 A
CSTM28670 Backfilling 3 04-Feb-15 A 07-Feb-15 A
CSTM28680 SRC 20 concrete backfill 2 19-Feb-15 A 21-Feb-15 A
CSTM28660 DI Manhole Cover & Frame 2 25-Feb-15 A 26-Feb-15 A
MANHOLE: 15/1MANHOLE: 15/1/28/14/1 31 22-Jan-15 A 28-Feb-15 A
CSTM28690 Excavation & disposal of materials 4 22-Jan-15 A 26-Jan-15 A
CSTM28700 Blinding 1 02-Feb-15 A 02-Feb-15 A
CSTM28710 Reinforcement, shuttering, concreting 4 03-Feb-15 A 07-Feb-15 A
CSTM28720 Pipe connection to manhole & pre-testing of section 2 08-Feb-15 A 09-Feb-15 A
CSTM28730 Benching work 2 10-Feb-15 A 11-Feb-15 A
CSTM28740 Bitumen primer 1 14-Feb-15 A 14-Feb-15 A
CSTM28750 Tanking membrane 1 15-Feb-15 A 15-Feb-15 A
CSTM28760 Epoxy mortor & sealant 1 16-Feb-15 A 16-Feb-15 A
CSTM28770 GRP accessories 2 17-Feb-15 A 18-Feb-15 A
CSTM28790 Backfilling 3 22-Feb-15 A 24-Feb-15 A
CSTM28800 SRC 20 concrete backfill 1 25-Feb-15 A 25-Feb-15 A
CSTM28780 DI Manhole Cover & Frame 1 27-Feb-15 A 28-Feb-15 A
MANHOLE: 15/1MANHOLE: 15/1/28/14/2 32 21-Jan-15 A 28-Feb-15 A
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 13 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSTM28810 Excavation & disposal of materials 4 21-Jan-15 A 25-Jan-15 A
CSTM28820 Blinding 1 02-Feb-15 A 02-Feb-15 A
CSTM28830 Reinforcement, shuttering, concreting 4 03-Feb-15 A 07-Feb-15 A
CSTM28840 Pipe connection to manhole & pre-testing of section 2 08-Feb-15 A 09-Feb-15 A
CSTM28850 Benching work 2 10-Feb-15 A 11-Feb-15 A
CSTM28860 Bitumen primer 1 14-Feb-15 A 14-Feb-15 A
CSTM28870 Tanking membrane 1 15-Feb-15 A 15-Feb-15 A
CSTM28880 Epoxy mortor & sealant 1 16-Feb-15 A 16-Feb-15 A
CSTM28890 GRP accessories 2 17-Feb-15 A 18-Feb-15 A
CSTM28910 Backfilling 3 22-Feb-15 A 24-Feb-15 A
CSTM28920 SRC 20 concrete backfill 1 26-Feb-15 A 26-Feb-15 A
CSTM28900 DI Manhole Cover & Frame 2 26-Feb-15 A 28-Feb-15 A
MANHOLE: 15/1MANHOLE: 15/1/28/15 75 01-Dec-14 A 28-Feb-15 A -121
CSTM1950 Excavation & disposal of materials 4 01-Dec-14 A 04-Dec-14 A -70
CSTM1960 Blinding 2 06-Dec-14 A 07-Dec-14 A -71
CSTM1970 Reinforcement, shuttering, concreting 5 09-Dec-14 A 14-Dec-14 A -73
CSTM1980 Pipe connection to manhole & pre-testing of section 3 15-Dec-14 A 17-Dec-14 A -74
CSTM19800 Benching work 3 17-Dec-14 A 21-Dec-14 A -74
CSTM1990 Bitumen primer 2 24-Dec-14 A 25-Dec-14 A -77
CSTM2000 Tanking membrane 2 27-Dec-14 A 28-Dec-14 A -78
CSTM2010 Epoxy mortor & sealant 1 08-Feb-15 A 08-Feb-15 A -113
CSTM2020 GRP accessories 2 09-Feb-15 A 10-Feb-15 A -113
CSTM2040 Backfilling 3 15-Feb-15 A 17-Feb-15 A -113
CSTM2030 DI Manhole Cover & Frame 2 26-Feb-15 A 28-Feb-15 A -125
CSTM2050 SRC 20 concrete backfill 1 28-Feb-15 A 28-Feb-15 A -121
MANHOLE: 15/1MANHOLE: 15/1/28/16 45 02-Feb-15 A 26-Mar-15 A -140
CSTM2070 Excavation & disposal of materials 3 02-Feb-15 A 04-Feb-15 A -122
CSTM2080 Blinding 1 05-Feb-15 A 05-Feb-15 A -122
CSTM2090 Reinforcement, shuttering, concreting 4 07-Feb-15 A 10-Feb-15 A -122
CSTM2100 Pipe connection to manhole & pre-testing of section 2 11-Feb-15 A 14-Feb-15 A -118
CSTM21000 Benching work 2 15-Feb-15 A 16-Feb-15 A -118
CSTM2110 Bitumen primer 1 17-Feb-15 A 17-Feb-15 A -118
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 14 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSTM2120 Tanking membrane 1 18-Feb-15 A 18-Feb-15 A -118
CSTM2130 Epoxy mortor & sealant 1 19-Feb-15 A 19-Feb-15 A -118
CSTM2140 GRP accessories 2 21-Feb-15 A 22-Feb-15 A -118
CSTM2160 Backfilling 3 25-Feb-15 A 28-Feb-15 A -118
CSTM2170 SRC 20 concrete backfill 3 25-Feb-15 A 28-Feb-15 A -117
CSTM2150 DI Manhole Cover & Frame 2 25-Mar-15 A 26-Mar-15 A -144
REINSTATEMENTREINSTATEMENT 54 11-Feb-15 A 15-Apr-15 A -141
ASPHALTASPHALT 54 11-Feb-15 A 15-Apr-15 A -147
CSTR1010 90mm Base course 49 11-Feb-15 A 09-Apr-15 A -147
CSTR1020 70mm Wearing course 6 09-Apr-15 A 15-Apr-15 A -147
KERBSTONEKERBSTONE 2 09-Apr-15 A 11-Apr-15 A -145
CSTR1030 Excavation & concrete foundation for kerbs 2 09-Apr-15 A 11-Apr-15 A -147
CSTR1040 Kerbs installation 2 09-Apr-15 A 11-Apr-15 A -146
CSTR1050 Backing concrete 2 09-Apr-15 A 11-Apr-15 A -145
PAVING/CONCRPAVING/CONCRETE PAVING 3 09-Apr-15 A 12-Apr-15 A -142
CSTR1060 Formation preparation 3 09-Apr-15 A 12-Apr-15 A -144
CSTR1070 Paving interlock 3 09-Apr-15 A 12-Apr-15 A -142
PLANT AND GRPLANT AND GRASS 5 09-Apr-15 A 14-Apr-15 A -140
CSTR1080 Excavation for plants 3 09-Apr-15 A 12-Apr-15 A -140
CSTR1090 Planting/grass 3 12-Apr-15 A 14-Apr-15 A -140
PHASE 3: FROM PHASE 3: FROM MH 15/1/28/17 TO 15/1/28/25 155 19-Jan-15 A 22-Jun-15 A -196
VC PIPE WORKSVC PIPE WORKS: 15/1/28/17 TO 15/1/28/21 127 16-Feb-15 A 22-Jun-15 A -217
300mm NOMINA300mm NOMINAL BORE 70m: From MH 15/1/28/16 to MH 15/1/28/17 55 19-Feb-15 A 14-Apr-15 A -195
CST1500 Excavation & disposal of materials 10 19-Feb-15 A 02-Mar-15 A -137
CST1510 Bedding preparation prior to VC pipe laying 1 28-Mar-15 A 28-Mar-15 A -157
CST1520 Laying VC pipes & fittings and pre-testing 1 28-Mar-15 A 28-Mar-15 A -155
CST1530 Granular & concrete surrounds 1 28-Mar-15 A 28-Mar-15 A -153
CST1540 Backfilling 1 12-Apr-15 A 12-Apr-15 A -191
CST1550 SRC 20 concrete backfill 1 13-Apr-15 A 13-Apr-15 A -190
CST1630 Marker tape installation 1 14-Apr-15 A 14-Apr-15 A -190
200mm NOMINA200mm NOMINAL BORE 45.93m: From MH 15/1/28/17 to MH 15/1/28/18 39 12-Apr-15 A 30-May-15 A -198
0000.30 As per Al Jazeera, TCTC shall be allowed to work 0 12-Apr-15 A
Feb Mar Apr May Jun Jul Aug
2015
As per Al Jazeera, TCTC shall be allowed
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 15 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CST1570 Excavation & disposal of materials 39 12-Apr-15 A 21-May-15 A -203 Ps
CST1580 Bedding preparation prior to VC pipe laying 34 17-Apr-15 A 22-May-15 A -202 Ps
CST1590 Laying VC pipes & fittings and pre-testing 33 18-Apr-15 A 23-May-15 A -200 Ps
CST1600 Pipe Connection to MH 32 19-Apr-15 A 25-May-15 A -200 Ps
CST1610 Granular surrounds and Air Test 30 21-Apr-15 A 26-May-15 A -197 Ps
CST1620 Backfill and SRC 20 concrete backfill 28 23-Apr-15 A 29-May-15 A -198 Ps
CST1700 Marker tape installation 24 27-Apr-15 A 30-May-15 A -198 Ps
200mm NOMINA200mm NOMINAL BORE 20.00m: From MH 15/1/28/18 to MH 15/1/28/19 29 12-Apr-15 A 10-May-15 A
0000.40 As per Al Jazeera, TCTC shall be allowed to work 0 12-Apr-15 A
CST2840 Excavation & disposal of materials 6 12-Apr-15 A 17-Apr-15 A
CST2850 Bedding preparation prior to VC pipe laying 1 18-Apr-15 A 18-Apr-15 A
CST2860 Laying VC pipes & fittings and pre-testing 1 19-Apr-15 A 19-Apr-15 A
CST2880 Granular surrounds and Air Test 2 22-Apr-15 A 23-Apr-15 A
CST2870 Pipe Connection to MH 15 20-Apr-15 A 04-May-15 A
CST2890 Backfill and SRC 20 concrete backfill 4 06-May-15 A 09-May-15 A
CST2900 Marker tape installation 1 10-May-15 A 10-May-15 A
200mm NOMINA200mm NOMINAL BORE 20.00m: From MH 15/1/28/19 to MH 15/1/28/19/1 26 28-May-15 A 22-Jun-15 A
CST2910 Excavation & disposal of materials 7 28-May-15 A 03-Jun-15 A SI-2
CST2920 Bedding preparation prior to VC pipe laying 2 04-Jun-15 A 05-Jun-15 A SI-2
CST2930 Laying VC pipes & fittings and pre-testing 2 06-Jun-15 A 07-Jun-15 A SI-2
CST2940 Pipe Connection to MH 2 08-Jun-15 A 09-Jun-15 A SI-2
CST2950 Granular surrounds and Air Test 2 10-Jun-15 A 11-Jun-15 A SI-2
CST2960 Backfill and SRC 20 concrete backfill 5 12-Jun-15 A 16-Jun-15 A SI-2
CST2970 Marker tape installation 1 17-Jun-15 A 17-Jun-15 A SI-2
CST3050 Reinstatement 5 18-Jun-15 A 22-Jun-15 A
200mm NOMINA200mm NOMINAL BORE 29.58m: From MH 15/1/28/19 to MH 15/1/28/20 43 16-Feb-15 A 30-Mar-15 A -135
CST1710 Excavation & disposal of materials 11 16-Feb-15 A 28-Feb-15 A -98
CST1720 Bedding preparation prior to VC pipe laying 11 19-Feb-15 A 03-Mar-15 A -100
CST1730 Laying VC pipes & fittings and pre-testing 1 17-Mar-15 A 17-Mar-15 A -110
CST1740 Granular & concrete surrounds 2 17-Mar-15 A 18-Mar-15 A -110
CST1750 Backfilling 2 17-Mar-15 A 18-Mar-15 A -107
CST1760 SRC 20 concrete backfill 2 17-Mar-15 A 18-Mar-15 A -106
Feb Mar Apr May Jun Jul Aug
2015
As per Al Jazeera, TCTC shall be allowed
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 16 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CST1840 Marker tape installation 2 29-Mar-15 A 30-Mar-15 A -133
200mm NOMINA200mm NOMINAL BORE 14.68m: From MH 15/1/28/20 to MH 15/1/28/21 27 22-Feb-15 A 24-Mar-15 A -107
CST1780 Excavation & disposal of materials 11 22-Feb-15 A 05-Mar-15 A -100
CST1790 Bedding preparation prior to VC pipe laying 11 24-Feb-15 A 08-Mar-15 A -101
CST1800 Laying VC pipes & fittings and pre-testing 1 14-Mar-15 A 14-Mar-15 A -104
CST1810 Granular & concrete surrounds 1 15-Mar-15 A 15-Mar-15 A -104
CST1820 Backfilling 1 24-Mar-15 A 24-Mar-15 A -109
CST1910 Marker tape installation 1 24-Mar-15 A 24-Mar-15 A -107
CST1830 SRC 20 concrete backfill 1 24-Mar-15 A 24-Mar-15 A -108
FUTURE CONNEFUTURE CONNECTION 11 04-Apr-15 A 14-Apr-15 A
FC-06FC-06 11 04-Apr-15 A 14-Apr-15 A
CST2980 Excavation & disposal of materials 2 04-Apr-15 A 05-Apr-15 A
CST2990 Bedding preparation prior to VC pipe laying 1 06-Apr-15 A 06-Apr-15 A
CST3000 Laying VC pipes & fittings and pre-testing 1 07-Apr-15 A 07-Apr-15 A
CST3010 Granular & concrete surrounds 1 09-Apr-15 A 09-Apr-15 A
CST3020 Backfilling 1 11-Apr-15 A 11-Apr-15 A
CST3030 SRC 20 concrete backfill 1 12-Apr-15 A 12-Apr-15 A
CST3040 Marker tape installation 2 13-Apr-15 A 14-Apr-15 A
MANHOLE CONSMANHOLE CONSTRUCTION 152 19-Jan-15 A 19-Jun-15 A -197
MANHOLE: 15/1MANHOLE: 15/1/28/17 38 09-Mar-15 A 15-Apr-15 A -179
CSTM2190 Excavation & disposal of materials 1 09-Mar-15 A 09-Mar-15 A -140
CSTM2200 Blinding 1 10-Mar-15 A 10-Mar-15 A -140
CSTM2210 Reinforcement, shuttering, concreting 1 11-Mar-15 A 11-Mar-15 A -137
CSTM2220 Pipe connection to manhole & pre-testing of section 1 12-Mar-15 A 12-Mar-15 A -136
CSTM22200 Benching work 1 12-Mar-15 A 12-Mar-15 A -134
CSTM2230 Bitumen primer 1 14-Mar-15 A 14-Mar-15 A -134
CSTM2240 Tanking membrane 1 14-Mar-15 A 14-Mar-15 A -133
CSTM2250 Epoxy mortor & sealant 1 14-Mar-15 A 14-Mar-15 A -132
CSTM2260 GRP accessories 1 12-Apr-15 A 12-Apr-15 A -181
CSTM2270 DI Manhole Cover & Frame 1 13-Apr-15 A 13-Apr-15 A -180
CSTM2280 Backfilling 1 14-Apr-15 A 14-Apr-15 A -178
CSTM2290 SRC 20 concrete backfill 1 15-Apr-15 A 15-Apr-15 A -177
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 17 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
MANHOLE: 15/1MANHOLE: 15/1/28/18 120 19-Jan-15 A 18-May-15 A -175
0000.10 Delay: Issuance of Excavation permit 35 19-Jan-15 A 22-Feb-15 A
0000.20 Delay: Al Jazeera Stopped the Work 37 23-Feb-15 A 31-Mar-15 A
CSTM2310 Excavation & disposal of materials 2 12-Apr-15 A 13-Apr-15 A -161
CSTM2320 Blinding/Tanking & Screeding 3 14-Apr-15 A 16-Apr-15 A -163
CSTM2330 Reinforcement, shuttering, concreting (Base & Wall) 4 01-May-15 A 04-May-15 A -177
CSTM2340 Pipe connection to manhole & Backdrob 4 05-May-15 A 08-May-15 A -178
CSTM23400 Bitumen primer 1 09-May-15 A 09-May-15 A -177
CSTM2350 Tanking membrane 1 10-May-15 A 10-May-15 A -177
CSTM2360 Backfilling 4 11-May-15 A 14-May-15 A -180
CSTM2370 DI Manhole Cover & Frame 1 15-May-15 A 15-May-15 A -179
CSTM2380 SRC 20 concrete backfill 1 16-May-15 A 16-May-15 A -178
CSTM2390 Benching work 1 17-May-15 A 17-May-15 A -177
CSTM2410 GRP accessories 1 18-May-15 A 18-May-15 A -173
MANHOLE: 15/1MANHOLE: 15/1/28/19 19 12-Apr-15 A 30-Apr-15 A
CSTM29290 Excavation & disposal of materials 2 12-Apr-15 A 13-Apr-15 A
CSTM29300 Blinding/Tanking & Screeding 3 14-Apr-15 A 16-Apr-15 A
CSTM29310 Reinforcement, shuttering, concreting (Base & Wall) 4 17-Apr-15 A 20-Apr-15 A
CSTM29320 Pipe connection to manhole & Backdrob 4 21-Apr-15 A 24-Apr-15 A
CSTM29330 Bitumen primer 1 25-Apr-15 A 25-Apr-15 A
CSTM29340 Tanking membrane 1 26-Apr-15 A 26-Apr-15 A
CSTM29350 Backfilling 4 27-Apr-15 A 30-Apr-15 A
CSTM29360 DI Manhole Cover & Frame 1 30-Apr-15 A 30-Apr-15 A
CSTM29370 SRC 20 concrete backfill 1 30-Apr-15 A 30-Apr-15 A
CSTM29380 Benching work 1 30-Apr-15 A 30-Apr-15 A
CSTM29390 GRP accessories 1 30-Apr-15 A 30-Apr-15 A
MANHOLE: 15/1MANHOLE: 15/1/28/19/1 23 28-May-15 A 19-Jun-15 A
CSTM29410 Excavation & disposal of materials 2 28-May-15 A 29-May-15 A SI-2
CSTM29420 Blinding/Tanking & Screeding 3 30-May-15 A 01-Jun-15 A SI-2
CSTM29430 Reinforcement, shuttering, concreting (Base & Wall) 4 02-Jun-15 A 05-Jun-15 A SI-2
CSTM29440 Pipe connection to manhole & Backdrob 4 06-Jun-15 A 09-Jun-15 A SI-2
CSTM29450 Bitumen primer 1 10-Jun-15 A 10-Jun-15 A SI-2
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 18 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSTM29460 Tanking membrane 1 11-Jun-15 A 11-Jun-15 A SI-2
CSTM29470 Backfilling 4 12-Jun-15 A 15-Jun-15 A SI-2
CSTM29480 DI Manhole Cover & Frame 1 16-Jun-15 A 16-Jun-15 A SI-2
CSTM29490 SRC 20 concrete backfill 1 17-Jun-15 A 17-Jun-15 A SI-2
CSTM29500 Benching work 1 18-Jun-15 A 18-Jun-15 A SI-2
CSTM29510 GRP accessories 1 19-Jun-15 A 19-Jun-15 A SI-2
MANHOLE: 15/1MANHOLE: 15/1/28/20 63 16-Feb-15 A 19-Apr-15 A -139
CSTM2550 Excavation & disposal of materials 2 16-Feb-15 A 17-Feb-15 A -85
CSTM2560 Blinding 2 24-Mar-15 A 25-Mar-15 A -115
CSTM2570 Reinforcement, shuttering, concreting 1 25-Mar-15 A 25-Mar-15 A -111
CSTM2580 Pipe connection to manhole & pre-testing of section 2 28-Mar-15 A 29-Mar-15 A -112
CSTM25800 Benching work 1 12-Apr-15 A 12-Apr-15 A -143
CSTM2590 Bitumen primer 1 13-Apr-15 A 13-Apr-15 A -143
CSTM2600 Tanking membrane 1 14-Apr-15 A 14-Apr-15 A -143
CSTM2610 Epoxy mortor & sealant 1 15-Apr-15 A 15-Apr-15 A -142
CSTM2620 GRP accessories 1 16-Apr-15 A 16-Apr-15 A -141
CSTM2630 DI Manhole Cover & Frame 1 17-Apr-15 A 17-Apr-15 A -140
CSTM2640 Backfilling 1 18-Apr-15 A 18-Apr-15 A -137
CSTM2650 SRC 20 concrete backfill 1 19-Apr-15 A 19-Apr-15 A -137
MANHOLE: 15/1MANHOLE: 15/1/28/21 66 14-Feb-15 A 20-Apr-15 A -137
CSTM2670 Excavation & disposal of materials 13 14-Feb-15 A 28-Feb-15 A -91
CSTM2680 Blinding 1 12-Mar-15 A 12-Mar-15 A -101
CSTM2690 Reinforcement, shuttering, concreting 2 15-Mar-15 A 16-Mar-15 A -100
CSTM2700 Pipe connection to manhole & pre-testing of section 1 26-Mar-15 A 26-Mar-15 A -107
CSTM27000 Benching work 1 13-Apr-15 A 13-Apr-15 A -140
CSTM2710 Bitumen primer 1 14-Apr-15 A 14-Apr-15 A -140
CSTM2720 Tanking membrane 1 15-Apr-15 A 15-Apr-15 A -140
CSTM2730 Epoxy mortor & sealant 1 16-Apr-15 A 16-Apr-15 A -140
CSTM2740 GRP accessories 1 17-Apr-15 A 17-Apr-15 A -139
CSTM2750 DI Manhole Cover & Frame 1 18-Apr-15 A 18-Apr-15 A -137
CSTM2760 Backfilling 1 19-Apr-15 A 19-Apr-15 A -135
CSTM2770 SRC 20 concrete backfill 1 20-Apr-15 A 20-Apr-15 A -135
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 19 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
REINSTATEMENTREINSTATEMENT 45 19-Apr-15 A 02-Jun-15 A -174
ASPHALTASPHALT 32 19-Apr-15 A 01-Jun-15 A -178
CSTA1010 90mm Base course 32 19-Apr-15 A 01-Jun-15 A -179 Ps
CSTA1020 70mm Wearing course 32 19-Apr-15 A 01-Jun-15 A -178 Ps
KERBSTONEKERBSTONE 1 01-Jun-15 A 01-Jun-15 A -180
CSTC1000 Excavation & concrete foundation for kerbs 1 01-Jun-15 A 01-Jun-15 A -182 Ps
CSTC1010 Kerbs installation 1 01-Jun-15 A 01-Jun-15 A -181 Ps
CSTC1020 Backing concrete 1 01-Jun-15 A 01-Jun-15 A -180 Ps
PAVING/CONCRPAVING/CONCRETE PAVING 2 01-Jun-15 A 02-Jun-15 A -176
CSTP1010 Paving interlock 2 01-Jun-15 A 02-Jun-15 A -176 Ps
CSTP1000 Formation preparation 2 01-Jun-15 A 02-Jun-15 A -179 Ps
PLANT AND GRPLANT AND GRASS 2 01-Jun-15 A 02-Jun-15 A -174
CSTPG1000 Excavation for plants 2 01-Jun-15 A 02-Jun-15 A -176 Ps
CSTPG1010 Planting/grass 2 01-Jun-15 A 02-Jun-15 A -174 Ps
SEWER IN MICTRSEWER IN MICTROTUNNEL 262 12-Jul-14 A 30-Mar-15 A -104
PHASE 1: FROM PHASE 1: FROM MH 15/1/28 TO 15/1/28/4 262 12-Jul-14 A 30-Mar-15 A -160
JACKING PIPESJACKING PIPES: FROM MH 15/1/28 TO 15/1/28/4 82 12-Jul-14 A 21-Oct-14 A -44
L-300mm NOMIL-300mm NOMINAL BORE IN M.TUNNEL 59.26m: From MH 15/1/28/1 to MH Ex.15/1/28 43 12-Jul-14 A 02-Sep-14 A -36
CSMJ1010 Excavation for launch shaft & material disposal 7 12-Jul-14 A 19-Jul-14 A -13
CSMJ1020 Concrete for platform & trust wall 3 20-Jul-14 A 22-Jul-14 A -13
CSMJ1030 Jacking GRP lined RC pipe 9 21-Aug-14 A 31-Aug-14 A -36
CSMJ10300 Testing Prior to Annulus Grouting 1 01-Sep-14 A 01-Sep-14 A -36
CSMJ1040 Annulus grouting 1 02-Sep-14 A 02-Sep-14 A -36
300mm NOMINA300mm NOMINAL BORE IN M.TUNNEL 60m: From MH 15/1/28/1 to MH 15/1/28/2 19 24-Aug-14 A 14-Sep-14 A -37
CSMJ1070 Excavation for receiver shaft 7 24-Aug-14 A 31-Aug-14 A -36
CSMJ1080 Concrete for platform & trust wall 1 01-Sep-14 A 01-Sep-14 A -36
CSMJ1090 Jacking GRP lined RC pipe 9 02-Sep-14 A 11-Sep-14 A -37
CSMJ10900 Testing Prior to Annulus Grouting 1 13-Sep-14 A 13-Sep-14 A -37
CSMJ1100 Annulus grouting 1 14-Sep-14 A 14-Sep-14 A -37
L-300mm NOMIL-300mm NOMINAL BORE IN M.TUNNEL 60m: From MH 15/1/28/3 to MH 15/1/28/2 21 01-Sep-14 A 24-Sep-14 A -38
CSMJ1130 Excavation for launch shaft & material disposal 7 01-Sep-14 A 08-Sep-14 A -38
CSMJ1140 Concrete for platform & trust wall 3 09-Sep-14 A 11-Sep-14 A -37
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 20 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSMJ1150 Jacking GRP lined RC pipe 9 13-Sep-14 A 22-Sep-14 A -38
CSMJ11500 Testing Prior to Annulus Grouting 1 23-Sep-14 A 23-Sep-14 A -38
CSMJ1160 Annulus grouting 1 24-Sep-14 A 24-Sep-14 A -38
300mm NOMINA300mm NOMINAL BORE IN M.TUNNEL70m: From MH 15/1/28/3 to MH 15/1/28/4 22 23-Sep-14 A 21-Oct-14 A -44
CSMJ1190 Excavation for receiver shaft 9 23-Sep-14 A 02-Oct-14 A -44
CSMJ1200 Concrete for platform & trust wall 1 07-Oct-14 A 07-Oct-14 A -44
CSMJ1210 Jacking GRP lined RC pipe 10 08-Oct-14 A 19-Oct-14 A -44
CSMJ12100 Testing Prior to Annulus Grouting 1 20-Oct-14 A 20-Oct-14 A -44
CSMJ1220 Annulus grouting 1 21-Oct-14 A 21-Oct-14 A -44
MANHOLE CONSMANHOLE CONSTRUCTION 187 25-Sep-14 A 30-Mar-15 A -182
MANHOLE: 15/1MANHOLE: 15/1/28/1 123 27-Nov-14 A 29-Mar-15 A -222
CSMM1840 Preparing shaft for MH construction 2 27-Nov-14 A 29-Nov-14 A -107
CSMM1850 Blinding 1 30-Nov-14 A 30-Nov-14 A -107
CSMM184 Recovery 0 10-Jan-15 A
CSMM1860 Reinforcement, shuttering, concreting 44 01-Dec-14 A 21-Jan-15 A -147
CSMM1870 Pipe connection to manhole & pre-testing of section 3 21-Jan-15 A 24-Jan-15 A -146
CSMM18700 Benching work 2 31-Jan-15 A 01-Feb-15 A -151
CSMM1880 Bitumen primer 1 02-Feb-15 A 02-Feb-15 A -151
CSMM1890 Tanking membrane 1 03-Feb-15 A 03-Feb-15 A -151
CSMM1900 Epoxy mortor & sealant 1 04-Feb-15 A 04-Feb-15 A -151
CSMM1930 Backfilling 3 23-Feb-15 A 25-Feb-15 A -159
CSMM1910 GRP accessories 2 25-Feb-15 A 26-Feb-15 A -167
CSMM1920 DI Manhole Cover & Frame 3 23-Mar-15 A 25-Mar-15 A -188
CSMM1940 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -185
MANHOLE: 15/1MANHOLE: 15/1/28/2 122 25-Sep-14 A 19-Feb-15 A -137
CSMM1950 Preparing shaft for MH construction 1 25-Sep-14 A 25-Sep-14 A -38
CSMM1960 Blinding 1 27-Sep-14 A 27-Sep-14 A -38
CSMM1970 Reinforcement, shuttering, concreting 96 28-Sep-14 A 21-Jan-15 A -130
CSMM1980 Pipe connection to manhole & pre-testing of section 3 26-Jan-15 A 28-Jan-15 A -134
CSMM19800 Benching work 2 02-Feb-15 A 03-Feb-15 A -137
CSMM1990 Bitumen primer 1 04-Feb-15 A 04-Feb-15 A -137
CSMM2000 Tanking membrane 1 05-Feb-15 A 05-Feb-15 A -137
Feb Mar Apr May Jun Jul Aug
2015
very
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 21 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSMM2010 Epoxy mortor & sealant 1 07-Feb-15 A 07-Feb-15 A -137
CSMM2020 GRP accessories 2 08-Feb-15 A 09-Feb-15 A -137
CSMM2030 DI Manhole Cover & Frame 2 10-Feb-15 A 11-Feb-15 A -137
CSMM2040 Backfilling 5 14-Feb-15 A 18-Feb-15 A -137
CSMM2050 SRC 20 concrete backfill 1 19-Feb-15 A 19-Feb-15 A -137
MANHOLE: 15/1MANHOLE: 15/1/28/3 103 22-Oct-14 A 21-Feb-15 A -125
CSMJ1840 Preparing shaft for MH construction 1 22-Oct-14 A 22-Oct-14 A -44
CSMJ1850 Blinding 1 23-Oct-14 A 23-Oct-14 A -44
CSMJ1860 Reinforcement, shuttering, concreting 76 25-Oct-14 A 21-Jan-15 A -116
CSMJ1870 Pipe connection to manhole & pre-testing of section 3 31-Jan-15 A 02-Feb-15 A -124
CSMJ18700 Benching work 2 04-Feb-15 A 05-Feb-15 A -125
CSMJ1880 Bitumen primer 1 07-Feb-15 A 07-Feb-15 A -125
CSMJ1890 Tanking membrane 1 08-Feb-15 A 08-Feb-15 A -125
CSMJ1900 Epoxy mortor & sealant 1 09-Feb-15 A 09-Feb-15 A -125
CSMJ1910 GRP accessories 1 10-Feb-15 A 10-Feb-15 A -125
CSMJ1920 DI Manhole Cover & Frame 2 11-Feb-15 A 14-Feb-15 A -125
CSMJ1930 Backfilling 5 15-Feb-15 A 19-Feb-15 A -125
CSMJ1940 SRC 20 concrete backfill 1 21-Feb-15 A 21-Feb-15 A -125
MANHOLE: 15/1MANHOLE: 15/1/28/4 72 05-Jan-15 A 30-Mar-15 A -151
CSMJ1950 Preparing shaft for MH construction 2 05-Jan-15 A 06-Jan-15 A -102
CSMJ1960 Blinding 2 18-Jan-15 A 19-Jan-15 A -112
CSMJ1970 Reinforcement, shuttering, concreting 4 04-Feb-15 A 08-Feb-15 A -125
CSMJ1980 Pipe connection to manhole & pre-testing of section 2 09-Feb-15 A 10-Feb-15 A -125
CSMJ19800 Benching work 2 11-Feb-15 A 14-Feb-15 A -125
CSMJ1990 Bitumen primer 1 15-Feb-15 A 15-Feb-15 A -125
CSMJ2000 Tanking membrane 1 16-Feb-15 A 16-Feb-15 A -125
CSMJ2010 Epoxy mortor & sealant 1 17-Feb-15 A 17-Feb-15 A -125
CSMJ2020 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -131
CSMJ2040 Backfilling 4 24-Feb-15 A 28-Feb-15 A -126
CSMJ2030 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -156
CSMJ2050 SRC 20 concrete backfill 3 28-Mar-15 A 30-Mar-15 A -151
REINSTATEMENTREINSTATEMENT 12 16-Mar-15 A 29-Mar-15 A -134
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 22 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
ASPHALTASPHALT 5 24-Mar-15 A 29-Mar-15 A -146
CSMTR1510 90mm Base course 3 24-Mar-15 A 26-Mar-15 A -146
CSMTR1520 70mm Wearing course 3 26-Mar-15 A 29-Mar-15 A -146
KERBSTONEKERBSTONE 2 16-Mar-15 A 17-Mar-15 A -130
CSMTR1530 Excavation & concrete foundation for kerbs 2 16-Mar-15 A 17-Mar-15 A -134
CSMTR1540 Kerbs installation 2 16-Mar-15 A 17-Mar-15 A -132
CSMTR1550 Backing concrete 2 16-Mar-15 A 17-Mar-15 A -130
PAVING/CONCRPAVING/CONCRETE PAVING 2 16-Mar-15 A 17-Mar-15 A -126
CSMTR1560 Formation preparation 2 16-Mar-15 A 17-Mar-15 A -128
CSMTR1570 Paving interlock 2 16-Mar-15 A 17-Mar-15 A -126
PLANT AND GRPLANT AND GRASS 1 16-Mar-15 A 16-Mar-15 A -123
CSMTR1580 Excavation for plants 1 16-Mar-15 A 16-Mar-15 A -124
CSMTR1590 Planting/grass 1 16-Mar-15 A 16-Mar-15 A -123
PHASE 2: FROM PHASE 2: FROM MH 15/1/28/4 TO 15/1/28/12 221 21-Aug-14 A 29-Mar-15 A -103
JACKING PIPE FJACKING PIPE FROM MH 15/1/28/4 TO 15/1/28/12 183 21-Aug-14 A 19-Feb-15 A -110
L300mm NOMINL300mm NOMINAL BORE IN M.TUNNEL 45.35m: From MH 15/1/28/5 to MH 15/1/28/4 26 15-Dec-14 A 10-Jan-15 A -128
CSMJ1250 Excavation for launch shaft & material disposal 6 15-Dec-14 A 22-Dec-14 A -104
CSMJ1260 Concrete for platform & trust wall 4 23-Dec-14 A 27-Dec-14 A -100
CSMJ1270 Jacking GRP lined RC pipe 4 29-Dec-14 A 01-Jan-15 A -101
CSMJ12700 Testing Prior to Annulus Grouting 1 03-Jan-15 A 03-Jan-15 A -101
CSMJ1280 Annulus grouting 2 06-Jan-15 A 07-Jan-15 A -104
CSMJ125 Recovery 0 10-Jan-15 A
300mm NOMINA300mm NOMINAL BORE IN M.TUNNEL 30.43m: From MH 15/1/28/5 to MH 15/1/28/6 22 04-Jan-15 A 28-Jan-15 A -116
CSMJ1310 Excavation for receiver shaft 4 04-Jan-15 A 07-Jan-15 A -106
CSMJ1320 Concrete for platform & trust wall 2 10-Jan-15 A 11-Jan-15 A -108
CSMJ1330 Jacking GRP lined RC pipe 8 18-Jan-15 A 26-Jan-15 A -116
CSMJ1340 Annulus grouting 2 27-Jan-15 A 28-Jan-15 A -116
CSMJ13300 Testing Prior to Annulus Grouting 2 27-Jan-15 A 28-Jan-15 A -117
L-300mm NOMIL-300mm NOMINAL BORE IN M.TUNNEL 61.78m: From MH 15/1/28/7 to MH 15/1/28/6 19 06-Jan-15 A 27-Jan-15 A -108
CSMJ1370 Excavation for launch shaft & material disposal 8 06-Jan-15 A 14-Jan-15 A -107
CSMJ1380 Concrete for platform & trust wall 4 11-Jan-15 A 14-Jan-15 A -104
CSMJ1390 Jacking GRP lined RC pipe 10 14-Jan-15 A 25-Jan-15 A -108
Feb Mar Apr May Jun Jul Aug
2015
very
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 23 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSMJ13900 Testing Prior to Annulus Grouting 2 25-Jan-15 A 26-Jan-15 A -108
CSMJ1400 Annulus grouting 2 26-Jan-15 A 27-Jan-15 A -108
300mm NOMINA300mm NOMINAL BORE IN M.TUNNEL 55.74m: From MH 15/1/28/7 to MH 15/1/28/8 106 21-Aug-14 A 27-Dec-14 A -75
CSMJ1430 Excavation for receiver shaft 6 21-Aug-14 A 27-Aug-14 A 17
CSMJ1440 Concrete for platform & trust wall 1 28-Aug-14 A 28-Aug-14 A 17
CSMJ1450 Jacking GRP lined RC pipe 8 30-Aug-14 A 07-Sep-14 A 14
CSMJ14500 Testing Prior to Annulus Grouting 1 08-Sep-14 A 08-Sep-14 A 14
CSMJ1460 Annulus grouting 2 25-Dec-14 A 27-Dec-14 A -75
L-300mm NOMIL-300mm NOMINAL BORE IN M.TUNNEL 35.13m: From MH 15/1/28/9 to MH 15/1/28/8 102 28-Aug-14 A 29-Dec-14 A -71
CSMJ1490 Excavation for launch shaft & material disposal 3 28-Aug-14 A 31-Aug-14 A 19
CSMJ1500 Concrete for platform & trust wall 3 04-Sep-14 A 07-Sep-14 A 16
CSMJ1510 Jacking GRP lined RC pipe 4 08-Sep-14 A 11-Sep-14 A 16
CSMJ15100 Testing Prior to Annulus Grouting 1 13-Sep-14 A 13-Sep-14 A 16
CSMJ1520 Annulus grouting 2 28-Dec-14 A 29-Dec-14 A -71
300mm NOMINA300mm NOMINAL BORE IN M.TUNNEL 32.74m: From MH 15/1/28/9 to MH 15/1/28/10 95 09-Sep-14 A 01-Jan-15 A -68
CSMJ1550 Excavation for receiver shaft 3 09-Sep-14 A 11-Sep-14 A 16
CSMJ1560 Concrete for platform & trust wall 1 13-Sep-14 A 13-Sep-14 A 16
CSMJ1570 Jacking GRP lined RC pipe 5 14-Sep-14 A 18-Sep-14 A 16
CSMJ15700 Testing Prior to Annulus Grouting 1 20-Sep-14 A 20-Sep-14 A 16
CSMJ1580 Annulus grouting 2 31-Dec-14 A 01-Jan-15 A -68
L-300mm NOMIL-300mm NOMINAL BORE IN M.TUNNEL 50.23m: From MH 15/1/28/11 to MH 15/1/28/10 93 13-Sep-14 A 03-Jan-15 A -62
CSMJ1610 Excavation for launch shaft & material disposal 7 13-Sep-14 A 20-Sep-14 A 14
CSMJ1620 Concrete for platform & trust wall 3 21-Sep-14 A 23-Sep-14 A 14
CSMJ1630 Jacking GRP lined RC pipe 7 24-Sep-14 A 01-Oct-14 A 12
CSMJ16300 Testing Prior to Annulus Grouting 1 02-Oct-14 A 02-Oct-14 A 12
CSMJ1640 Annulus grouting 2 01-Jan-15 A 03-Jan-15 A -62
300mm NOMINA300mm NOMINAL BORE IN M.TUNNEL 54.53m: From MH 15/1/28/11 to MH 15/1/28/12 123 24-Sep-14 A 19-Feb-15 A -93
CSMJ1670 Excavation for receiver shaft 7 24-Sep-14 A 01-Oct-14 A 12
CSMJ1680 Concrete for platform & trust wall 1 02-Oct-14 A 02-Oct-14 A 12
CSMJ1690 Jacking GRP lined RC pipe 8 07-Oct-14 A 15-Oct-14 A 12
CSMJ16900 Testing Prior to Annulus Grouting 1 16-Oct-14 A 16-Oct-14 A 12
CSMJ1700 Annulus grouting 1 19-Feb-15 A 19-Feb-15 A -93
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 24 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
MANHOLE CONSMANHOLE CONSTRUCTION 86 17-Dec-14 A 29-Mar-15 A -103
MANHOLE: 15/1MANHOLE: 15/1/28/5 79 27-Dec-14 A 29-Mar-15 A -144
CSMJ2060 Preparing shaft for MH construction 2 27-Dec-14 A 28-Dec-14 A -88
CSMJ2070 Blinding 1 20-Jan-15 A 20-Jan-15 A -107
CSMJ2080 Reinforcement, shuttering, concreting 4 31-Jan-15 A 03-Feb-15 A -115
CSMJ2090 Pipe connection to manhole & pre-testing of section 2 15-Feb-15 A 16-Feb-15 A -123
CSMJ20900 Benching work 2 17-Feb-15 A 18-Feb-15 A -123
CSMJ2100 Bitumen primer 1 19-Feb-15 A 19-Feb-15 A -123
CSMJ2110 Tanking membrane 1 21-Feb-15 A 21-Feb-15 A -123
CSMJ2120 Epoxy mortor & sealant 1 22-Feb-15 A 22-Feb-15 A -123
CSMJ2130 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -125
CSMJ2150 Backfilling 6 22-Feb-15 A 28-Feb-15 A -120
CSMJ2160 SRC 20 concrete backfill 3 25-Mar-15 A 28-Mar-15 A -143
CSMJ2140 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -150
MANHOLE: 15/1MANHOLE: 15/1/28/6 72 04-Jan-15 A 29-Mar-15 A -137
CSMJ2170 Preparing shaft for MH construction 2 04-Jan-15 A 05-Jan-15 A -88
CSMJ2180 Blinding 2 27-Jan-15 A 28-Jan-15 A -107
CSMJ2190 Reinforcement, shuttering, concreting 4 31-Jan-15 A 03-Feb-15 A -108
CSMJ2200 Pipe connection to manhole & pre-testing of section 2 04-Feb-15 A 05-Feb-15 A -108
CSMJ22000 Benching work 2 07-Feb-15 A 08-Feb-15 A -108
CSMJ2210 Bitumen primer 1 09-Feb-15 A 09-Feb-15 A -108
CSMJ2220 Tanking membrane 1 10-Feb-15 A 10-Feb-15 A -108
CSMJ2230 Epoxy mortor & sealant 1 11-Feb-15 A 11-Feb-15 A -108
CSMJ2240 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -118
CSMJ2260 Backfilling 6 22-Feb-15 A 28-Feb-15 A -113
CSMJ2250 DI Manhole Cover & Frame 3 25-Mar-15 A 28-Mar-15 A -142
CSMJ2270 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -137
MANHOLE: 15/1MANHOLE: 15/1/28/7 75 31-Dec-14 A 29-Mar-15 A -131
CSMJ2300 Reinforcement, shuttering, concreting 4 31-Dec-14 A 04-Jan-15 A -76
CSMJ2310 Pipe connection to manhole & pre-testing of section 3 05-Jan-15 A 07-Jan-15 A -77
CSMJ23100 Benching work 2 08-Jan-15 A 10-Jan-15 A -77
CSMJ2280 Preparing shaft for MH construction 2 12-Jan-15 A 13-Jan-15 A -89
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 25 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSMJ2320 Bitumen primer 2 13-Jan-15 A 14-Jan-15 A -80
CSMJ2290 Blinding 2 27-Jan-15 A 28-Jan-15 A -101
CSMJ2330 Tanking membrane 1 31-Jan-15 A 31-Jan-15 A -93
CSMJ2340 Epoxy mortor & sealant 1 01-Feb-15 A 01-Feb-15 A -93
CSMJ2350 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -112
CSMJ2370 Backfilling 5 23-Feb-15 A 28-Feb-15 A -107
CSMJ2360 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -137
CSMJ2380 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -131
MANHOLE: 15/1MANHOLE: 15/1/28/8 74 01-Jan-15 A 29-Mar-15 A -125
CSMJ2400 Blinding 2 01-Jan-15 A 03-Jan-15 A -73
CSMJ2410 Reinforcement, shuttering, concreting 4 04-Jan-15 A 07-Jan-15 A -73
CSMJ2390 Preparing shaft for MH construction 2 08-Jan-15 A 10-Jan-15 A -80
CSMJ2420 Pipe connection to manhole & pre-testing of section 3 07-Jan-15 A 10-Jan-15 A -73
CSMJ24200 Benching work 2 10-Jan-15 A 11-Jan-15 A -72
CSMJ2430 Bitumen primer 2 11-Jan-15 A 12-Jan-15 A -72
CSMJ2440 Tanking membrane 1 31-Jan-15 A 31-Jan-15 A -87
CSMJ2450 Epoxy mortor & sealant 1 01-Feb-15 A 01-Feb-15 A -87
CSMJ2460 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -106
CSMJ2480 Backfilling 6 22-Feb-15 A 28-Feb-15 A -101
CSMJ2470 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -131
CSMJ2490 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -125
MANHOLE: 15/1MANHOLE: 15/1/28/9 86 17-Dec-14 A 29-Mar-15 A -119
CSMJ2510 Blinding 2 17-Dec-14 A 20-Dec-14 A -55
CSMJ2520 Reinforcement, shuttering, concreting 5 22-Dec-14 A 27-Dec-14 A -57
CSMJ2530 Pipe connection to manhole & pre-testing of section 2 29-Dec-14 A 30-Dec-14 A -58
CSMJ25300 Benching work 2 01-Jan-15 A 03-Jan-15 A -59
CSMJ2500 Preparing shaft for MH construction 2 04-Jan-15 A 05-Jan-15 A -70
CSMJ2540 Bitumen primer 2 05-Jan-15 A 06-Jan-15 A -61
CSMJ2550 Tanking membrane 1 31-Jan-15 A 31-Jan-15 A -81
CSMJ2560 Epoxy mortor & sealant 1 01-Feb-15 A 01-Feb-15 A -81
CSMJ2570 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -100
CSMJ2590 Backfilling 6 23-Feb-15 A 01-Mar-15 A -96
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 26 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSMJ2580 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -125
CSMJ2600 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -119
MANHOLE: 15/1MANHOLE: 15/1/28/10 70 06-Jan-15 A 29-Mar-15 A -112
CSMJ2610 Preparing shaft for MH construction 2 06-Jan-15 A 07-Jan-15 A -65
CSMJ2620 Blinding 2 27-Jan-15 A 28-Jan-15 A -82
CSMJ2630 Reinforcement, shuttering, concreting 4 31-Jan-15 A 03-Feb-15 A -83
CSMJ2640 Pipe connection to manhole & pre-testing of section 2 04-Feb-15 A 05-Feb-15 A -83
CSMJ26400 Benching work 2 07-Feb-15 A 08-Feb-15 A -83
CSMJ2650 Bitumen primer 1 09-Feb-15 A 09-Feb-15 A -83
CSMJ2660 Tanking membrane 1 10-Feb-15 A 10-Feb-15 A -83
CSMJ2670 Epoxy mortor & sealant 1 11-Feb-15 A 11-Feb-15 A -83
CSMJ2680 GRP accessories 1 25-Feb-15 A 25-Feb-15 A -93
CSMJ2700 Backfilling 6 22-Feb-15 A 28-Feb-15 A -88
CSMJ2690 DI Manhole Cover & Frame 3 26-Mar-15 A 29-Mar-15 A -118
CSMJ2710 SRC 20 concrete backfill 3 26-Mar-15 A 29-Mar-15 A -112
MANHOLE: 15/1MANHOLE: 15/1/28/11 33 13-Jan-15 A 21-Feb-15 A -72
CSMJ2720 Preparing shaft for MH construction 2 13-Jan-15 A 14-Jan-15 A -62
CSMJ2730 Blinding 2 27-Jan-15 A 28-Jan-15 A -73
CSMJ2750 Pipe connection to manhole & pre-testing of section 2 31-Jan-15 A 01-Feb-15 A -70
CSMJ2740 Reinforcement, shuttering, concreting 5 28-Jan-15 A 02-Feb-15 A -73
CSMJ27500 Benching work 2 02-Feb-15 A 03-Feb-15 A -70
CSMJ2760 Bitumen primer 1 04-Feb-15 A 04-Feb-15 A -70
CSMJ2770 Tanking membrane 1 05-Feb-15 A 05-Feb-15 A -70
CSMJ2780 Epoxy mortor & sealant 1 07-Feb-15 A 07-Feb-15 A -70
CSMJ2790 GRP accessories 1 08-Feb-15 A 08-Feb-15 A -70
CSMJ2800 DI Manhole Cover & Frame 2 09-Feb-15 A 10-Feb-15 A -70
CSMJ2810 Backfilling 5 11-Feb-15 A 17-Feb-15 A -70
CSMJ2820 SRC 20 concrete backfill 2 19-Feb-15 A 21-Feb-15 A -72
MANHOLE: 15/1MANHOLE: 15/1/28/12 3 16-Mar-15 A 18-Mar-15 A -109
CSMJ2830 Beaking MH and Pipe connection 3 16-Mar-15 A 18-Mar-15 A -109
REINSTATEMENTREINSTATEMENT 11 16-Mar-15 A 28-Mar-15 A -85
ASPHALTASPHALT 3 25-Mar-15 A 28-Mar-15 A -89
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 27 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CSMTR1360 90mm Base course 3 25-Mar-15 A 28-Mar-15 A -91
CSMTR1370 70mm Wearing course 3 25-Mar-15 A 28-Mar-15 A -89
PAVING/CONCRPAVING/CONCRETE PAVING 2 16-Mar-15 A 17-Mar-15 A -76
CSMTR1410 Formation preparation 2 16-Mar-15 A 17-Mar-15 A -77
CSMTR1420 Paving interlock 2 16-Mar-15 A 17-Mar-15 A -76
KERBSTONEKERBSTONE 1 16-Mar-15 A 16-Mar-15 A -76
CSMTR1380 Excavation & concrete foundation for kerbs 1 16-Mar-15 A 16-Mar-15 A -78
CSMTR1400 Backing concrete 1 16-Mar-15 A 16-Mar-15 A -76
CSMTR1390 Kerbs installation 1 16-Mar-15 A 16-Mar-15 A -77
PLANT AND GRPLANT AND GRASS 2 16-Mar-15 A 17-Mar-15 A -76
CSMTR1430 Excavation for plants 2 16-Mar-15 A 17-Mar-15 A -76
CSMTR1440 Planting/grass 2 16-Mar-15 A 17-Mar-15 A -76
HOUSE CONNECTHOUSE CONNECTION 162 08-Jan-15 A 18-Jun-15 A -184
SEWER IN TRENCSEWER IN TRENCH (AREA) 159 11-Jan-15 A 18-Jun-15 A -184
HOUSE CONNECHOUSE CONNECTION PHASE 1 144 11-Jan-15 A 03-Jun-15 A -170
SURVEY AND DSURVEY AND DEMOLISH 54 11-Jan-15 A 15-Mar-15 A -87
CHG1000 Plot survey 2 11-Jan-15 A 12-Jan-15 A -37
CHG1010 Demolition of ext. underground structures 3 12-Mar-15 A 15-Mar-15 A -87
PIPE WORK IN PIPE WORK IN TRENCH-HC 01 67 24-Feb-15 A 01-May-15 A -242
CSHCP1010 Excavation & disposal of materials 43 24-Feb-15 A 07-Apr-15 A -232
CSHCP1020 Bedding preparation prior to pipe laying 43 26-Feb-15 A 09-Apr-15 A -231
CSHCP1030 Laying pipe & connecting to new manhole 42 28-Feb-15 A 10-Apr-15 A -228
CSHCP1040 Granular & concrete surrounds 44 28-Feb-15 A 12-Apr-15 A -227
CSHCP1050 Backfilling 46 28-Feb-15 A 14-Apr-15 A -227
CSHCP1060 Concrete backfill 63 28-Feb-15 A 01-May-15 A -242
PIPE WORK IN PIPE WORK IN TRENCH-HC 02 70 28-Feb-15 A 08-May-15 A
CSHCP1070 Excavation & disposal of materials 30 28-Feb-15 A 29-Mar-15 A
CSHCP1080 Bedding preparation prior to pipe laying 43 28-Feb-15 A 11-Apr-15 A
CSHCP1090 Laying pipe & connecting to new manhole 50 28-Feb-15 A 18-Apr-15 A
CSHCP1100 Granular & concrete surrounds 52 28-Feb-15 A 20-Apr-15 A
CSHCP1110 Backfilling 54 28-Feb-15 A 22-Apr-15 A
CSHCP1120 Concrete backfill 70 28-Feb-15 A 08-May-15 A
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 28 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
PIPE WORK IN PIPE WORK IN TRENCH-HC 03 98 24-Feb-15 A 01-Jun-15 A
CSHCP1130 Excavation & disposal of materials 86 24-Feb-15 A 22-May-15 A Ps
CSHCP1140 Bedding preparation prior to pipe laying 84 26-Feb-15 A 24-May-15 A Ps
CSHCP1150 Laying pipe & connecting to new manhole 84 26-Feb-15 A 26-May-15 A Ps
CSHCP1160 Granular & concrete surrounds 84 26-Feb-15 A 28-May-15 A Ps
CSHCP1170 Backfilling 50 07-Apr-15 A 30-May-15 A Ps
CSHCP1180 Concrete backfill 2 31-May-15 A 01-Jun-15 A Ps
PIPE WORK IN PIPE WORK IN TRENCH-HC 04 99 25-Feb-15 A 03-Jun-15 A
CSHCP1190 Excavation & disposal of materials 48 25-Feb-15 A 13-Apr-15 A
CSHCP1200 Bedding preparation prior to pipe laying 49 26-Feb-15 A 15-Apr-15 A
CSHCP1210 Laying pipe & connecting to new manhole 51 26-Feb-15 A 17-Apr-15 A
CSHCP1220 Granular & concrete surrounds 53 26-Feb-15 A 19-Apr-15 A
CSHCP1230 Backfilling 53 28-Feb-15 A 21-Apr-15 A
CSHCP1240 Concrete backfill 2 02-Jun-15 A 03-Jun-15 A Ps
INSPECTION CHINSPECTION CHAMBER 1 21 14-Apr-15 A 04-May-15 A -139
CHCC1010 Excavation & disposal of materials 1 14-Apr-15 A 14-Apr-15 A -133
CHCC1020 Blinding 1 15-Apr-15 A 15-Apr-15 A -133
CHCC1030 Reinforcement, shuttering, concreting 1 16-Apr-15 A 16-Apr-15 A -132
CHCC1040 Pipe connection to manhole & pre-testing of section 1 17-Apr-15 A 17-Apr-15 A -132
CHCC10400 Benching work 1 18-Apr-15 A 18-Apr-15 A -130
CHCC1050 Bitumen primer 1 19-Apr-15 A 19-Apr-15 A -130
CHCC1060 Tanking membrane 1 20-Apr-15 A 20-Apr-15 A -130
CHCC1070 Epoxy mortor & sealant 1 21-Apr-15 A 21-Apr-15 A -130
CHCC1080 GRP accessories 1 22-Apr-15 A 22-Apr-15 A -130
CHCC1090 DI Manhole Cover & Frame 1 03-May-15 A 03-May-15 A -139
CHCC1100 Backfilling 1 04-May-15 A 04-May-15 A -139
INSPECTION CHINSPECTION CHAMBER 2 44 15-Apr-15 A 28-May-15 A -163
CHCC1120 Excavation & disposal of materials 1 15-Apr-15 A 15-Apr-15 A -134
CHCC1130 Blinding 1 16-Apr-15 A 16-Apr-15 A -134
CHCC1140 Reinforcement, shuttering, concreting 1 17-Apr-15 A 17-Apr-15 A -133
CHCC1150 Pipe connection to manhole & pre-testing of section 1 18-Apr-15 A 18-Apr-15 A -133
CHCC11500 Benching work 1 03-May-15 A 03-May-15 A -145
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 29 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
CHCC1160 Bitumen primer 1 23-May-15 A 23-May-15 A -164 Ps
CHCC1170 Tanking membrane 1 24-May-15 A 24-May-15 A -164 Ps
CHCC1180 Epoxy mortor & sealant 1 25-May-15 A 25-May-15 A -164 Ps
CHCC1190 GRP accessories 1 26-May-15 A 26-May-15 A -164 Ps
CHCC1200 DI Manhole Cover & Frame 1 27-May-15 A 27-May-15 A -163 Ps
CHCC1210 Backfilling 1 28-May-15 A 28-May-15 A -163 Ps
INSPECTION CHINSPECTION CHAMBER 3 11 03-May-15 A 13-May-15 A
CHCC11510 Excavation & disposal of materials 1 03-May-15 A 03-May-15 A
CHCC11520 Blinding 1 04-May-15 A 04-May-15 A
CHCC11530 Reinforcement, shuttering, concreting 1 05-May-15 A 05-May-15 A
CHCC11540 Pipe connection to manhole & pre-testing of section 1 06-May-15 A 06-May-15 A
CHCC11550 Benching work 1 07-May-15 A 07-May-15 A
CHCC11560 Bitumen primer 1 08-May-15 A 08-May-15 A
CHCC11570 Tanking membrane 1 09-May-15 A 09-May-15 A
CHCC11580 Epoxy mortor & sealant 1 10-May-15 A 10-May-15 A
CHCC11590 GRP accessories 1 11-May-15 A 11-May-15 A
CHCC11600 DI Manhole Cover & Frame 1 12-May-15 A 12-May-15 A
CHCC11610 Backfilling 1 13-May-15 A 13-May-15 A
INSPECTION CHINSPECTION CHAMBER 4 28 17-Apr-15 A 14-May-15 A
CHCC11620 Excavation & disposal of materials 1 17-Apr-15 A 17-Apr-15 A
CHCC11630 Blinding 1 18-Apr-15 A 18-Apr-15 A
CHCC11640 Reinforcement, shuttering, concreting 1 04-May-15 A 04-May-15 A
CHCC11650 Pipe connection to manhole & pre-testing of section 1 05-May-15 A 05-May-15 A
CHCC11660 Benching work 1 06-May-15 A 06-May-15 A
CHCC11670 Bitumen primer 1 07-May-15 A 07-May-15 A
CHCC11680 Tanking membrane 1 08-May-15 A 08-May-15 A
CHCC11690 Epoxy mortor & sealant 1 09-May-15 A 09-May-15 A
CHCC11700 GRP accessories 1 10-May-15 A 10-May-15 A
CHCC11710 DI Manhole Cover & Frame 1 11-May-15 A 11-May-15 A
CHCC11720 Backfilling 1 14-May-15 A 14-May-15 A
REINSTATEMENREINSTATEMENT FOR CHAMBERS 1 31-May-15 A 31-May-15 A -165
CHCC1220 Reinstatement around constructed chamber 1 31-May-15 A 31-May-15 A -165
Feb Mar Apr May Jun Jul Aug
2015
Project ID: IAD-HC13/14C076G.Project Name: SEWER EXTENSION HOUSE CONNECTIONS-AL JAZEERA/QATAR TELEVISION STATIONS(COI-01)
Remaining Level of Effort
Actual Level of Effort
Primary Baseline
Second Baseline
Actual Work
Remaining Work
Criti...
Mile...
Date Revision Checked ApprovedDocument Tittle: Progress Update as per Revised Programme 02Page 30 of 35Data Date: 22-Jun-15
-
Activity ID Activity Name OriginalDuration
Start Finish TotalDelays
Pocess Total Float SI-1 SI-2
HOUSE CONNECHOUSE CONNECTION PHASE 2 128 21-Jan-15 A 28-May-15 A
SURVEY AND DSURVEY AND DEMOLISH 125 21-Jan-15 A 25-May-15 A
C.HC.P221000 Plot survey 3 21-Jan-15 A 24-Jan-15 A
C.HC.P221010 Demolition of ext. underground structures 3 23-May-15 A 25-May-15 A
PIPE WORK IN PIPE WORK IN TRENCH-HC 05 94 24-Feb-15 A 28-May-15 A
CSHCP1250 Excavation & disposal of materials 75 24-Feb-15 A 09-May-15 A
CSHCP1260 Bedding preparation prior to pipe laying 76 25-Feb-15 A 11-May-15 A
CSHCP1270 Laying pipe & connecting to new manhole 79 24-Feb-15 A 13-May-15 A
CSHCP1280 Granular & concrete surrounds 81 24-Feb-15 A 15-May-15 A
CSHCP1290 Backfilling 82 25-Feb-15 A 17-May-15 A
CSHCP1300 Concrete backfill 93 25-Feb-15 A 28-May-15 A
INSPECTION CHINSPECTION CHAMBER 5 0 0
REINSTATEMENREINSTATEMENT FOR CHAMBERS 2 25-May-15 A 26-May-15 A
C.HC.P221020 Reinstatement around constructed chamber 2 25-May-15 A 26-May-15 A
HOUSE CONNECHOUSE CONNECTION PHASE 3 148 22-Jan-15 A 18-Jun-15 A -184
SURVEY AND DSURVEY AND DEMOLISH 108 22-Jan-15 A 09-May-15 A -157
CSTH1070 Plot survey 2 22-Jan-15 A 24-Jan-15 A -45
CSTH1080 Demolition of ext. underground structures 3 07-May-15 A 09-May-15 A