toshiba VRF Commsiioning Sequence.pdf

4
Commissioning sequence overview - SMMS and SHRM For further details, please contact Toshiba Customer Service on 0870 8430333 Bulletin VRF Commsiioning Sequence 1 of 4 26 February 2008 Commissioning sequence overview - SMMS and SHRM Provide power to the outdoor unit (crank case heater power supply) System pressure test Connect service hoses to (discharge), liquid and gas service valves (and balance circuit if used). Pressurise the system with oxygen-free nitrogen (OFN). All times shown are minimum - no maximum times apply Pressure Duration 1 50 psig 5 minutes 2 200 psig 5 minutes 3 450 psig 5 minutes 4 600 psig 1 hour 5 500 psig 24 hours Any loss of pressure indicates a leak, which must be identified, repaired and re-tested. When all tests have been successfully undertaken, vent nitrogen to atmosphere – with care. De-hydration by vacuum pump (triple evacuation) 6 Evacuate to 10 Torr 7 Break vacuum with OFN and pressurise to 15 psig 8 Evacuate to 6 Torr 9 Break vacuum with OFN and pressurise to 15 psig 10 Evacuate to 4 Torr (3 Torr if ambient temperature is < 10ºC) 11 Isolate pump and check that vacuum is maintained for 30 minutes Refrigerant charging When all tests have been successfully undertaken, break vacuum with the required quantity of R410A NOTE 1 . Clean refrigerant must be used, and added only by weight and in liquid state. 12 Add refrigerant into the liquid circuit 13 Slowly open all isolation valves (fully) on all outdoor units, remove service hoses and leak test 14 The system's first operation will be in the cooling mode Indoor units (can be checked while the outdoor unit is being pressure tested/dehydrated) Check that fans rotate freely Check that water drains correctly. High static ducted models o Check that a U trap is fitted o Connect fan tapping as required (shipped at medium speed) Provide power to the indoor unit when safe to do so. Addressing system from master outdoors unit Systems must be addressed separately, from the master outdoor unit o Disconnect relay connector (as shipped) If connected to U1/U2 network, central control devices must be disconnected or powered off. A system identity will be provided during the automatic addressing process. This will be 1 for all systems unless configured through switches SW13 and SW14 NOTE 2 Leave/set service switches to 1 – 1 – 1 (as shipped) Leave/set switch SW30-2 to ON (as shipped) Product Bulletin 520-0508

Transcript of toshiba VRF Commsiioning Sequence.pdf

Page 1: toshiba VRF Commsiioning Sequence.pdf

Commissioning sequence overview - SMMS and SHRM For further details, please contact Toshiba Customer Service on 0870 8430333

Bulletin VRF Commsiioning Sequence 1 of 4 26 February 2008

Commissioning sequence overview - SMMS and SHRM Provide power to the outdoor unit (crank case heater power supply) System pressure test Connect service hoses to (discharge), liquid and gas service valves (and balance circuit if used). Pressurise the system with oxygen-free nitrogen (OFN). All times shown are minimum - no maximum times apply

Pressure Duration

1 50 psig 5 minutes

2 200 psig 5 minutes

3 450 psig 5 minutes

4 600 psig 1 hour

5 500 psig 24 hours

Any loss of pressure indicates a leak, which must be identified, repaired and re-tested. When all tests have been successfully undertaken, vent nitrogen to atmosphere – with care. De-hydration by vacuum pump (triple evacuation)

6 Evacuate to 10 Torr

7 Break vacuum with OFN and pressurise to 15 psig

8 Evacuate to 6 Torr

9 Break vacuum with OFN and pressurise to 15 psig

10 Evacuate to 4 Torr (3 Torr if ambient temperature is < 10ºC)

11 Isolate pump and check that vacuum is maintained for 30 minutes

Refrigerant charging When all tests have been successfully undertaken, break vacuum with the required quantity of R410A NOTE 1. Clean refrigerant must be used, and added only by weight and in liquid state.

12 Add refrigerant into the liquid circuit

13 Slowly open all isolation valves (fully) on all outdoor units, remove service hoses and leak test

14 The system's first operation will be in the cooling mode

Indoor units (can be checked while the outdoor unit is being pressure tested/dehydrated) Check that fans rotate freely Check that water drains correctly. High static ducted models

o Check that a U trap is fitted o Connect fan tapping as required (shipped at medium speed)

Provide power to the indoor unit when safe to do so. Addressing system from master outdoors unit

Systems must be addressed separately, from the master outdoor unit o Disconnect relay connector (as shipped)

If connected to U1/U2 network, central control devices must be disconnected or powered off. A system identity will be provided during the automatic addressing process. This will be 1 for all

systems unless configured through switches SW13 and SW14 NOTE 2 Leave/set service switches to 1 – 1 – 1 (as shipped) Leave/set switch SW30-2 to ON (as shipped)

Product Bulletin 520-0508

Page 2: toshiba VRF Commsiioning Sequence.pdf

Commissioning sequence overview - SMMS and SHRM For further details, please contact Toshiba Customer Service on 0870 8430333

Bulletin VRF Commsiioning Sequence 2 of 4 26 February 2008

All indoor units in every group linked (directly or indirectly) to the system must be energised (otherwise addressing will be incomplete).

Press SW15 for 2 seconds - system is now addressed from outdoor unit (may take 10 minutes). LEDs display A U T O 1 , A U T O 2 ………A U T O 9 When complete, master outdoor unit displays U 1 - slave units display U 2 U 3 U 4 Use data retrieval to show that system capacity and the number of connected indoor units are correct.

o 1 – 2 – 3 shows system capacity (combined outdoor units) o 1 – 3 – 3 shows the number of outdoor units o 1 – 3 – 3 shows the number of indoor units (and how many require cooling) o 2 – 5 – 1 press SW04 and indoor units demand cooling (40% demand for 1 hour) o 2 - 14 - 2 press SW04 adds un-addressed indoor units to the system o Set service switched to 1 - 1 - 1 when complete

Other systems can be addressed in the same way - but always separately To determine the address of each indoor unit (optional – unless system is to be centrally controlled) The address is two part: system # - indoor #

For single indoor units under a standard controller (RBC-AMT21/31E), pressing UNIT while the controller is active will display the address

For multiple indoor units under a standard controller, press TEST (spanner icon) + external fan control for 4 sec. ALL is now displayed and all indoor fans in the group operate. Press UNIT and the master unit's address is displayed, while it's fan (alone) runs. Press UNIT to scroll through group in the same manner. Press TEST (spanner icon) to exit.

For indoor units/groups under simple, wireless or central (only) control, temporarily connect a standard controller RBC-AMT21/31E to terminals A-B and repeat the procedures shown above. A fault code (E09) may be generated after 10 minutes. This can be avoided by setting the controller as a slave).

Group configuration(s) may now be made - through a standard controller by pressing TEST (spanner icon) + SET + CL simultaneously for 4 seconds. Changes made will be held by the master outdoor unit - which will broadcast these settings to all other controllers used.

Standard Simple Wireless Central

Dipswitch configurations (master outdoor unit only)

SW10-1 SW10-2 SW10-4 SW11-2 SW11-3 SW11-4 Mode selection (SMMS) Float switches Fan power Low noise options

Off/off = heating priority On/off = cooling priority Off/on = majority priority On/on = indoor unit priority

Off = system shutdown On = single unit stopped

Off = 15 Pa On = 45 Pa

On = compressor range reduced

On = outdoor air flow reduced

Page 3: toshiba VRF Commsiioning Sequence.pdf

Commissioning sequence overview - SMMS and SHRM For further details, please contact Toshiba Customer Service on 0870 8430333

Bulletin VRF Commsiioning Sequence 3 of 4 26 February 2008

PCBs TCB-PCM02E 4 possible applications within the master outdoor units – each allows an external switch to change the system’s performance – depending on which PCB connection is used. Up to 4 of these PCBs may be used if necessary

CN508 night set back 50 dBA CN509 runs the outdoor fan at low speed (snow control)

o Continuous connection between COOL and COM CN510 operating mode (SMMS)

o COOL ONLY by continuous connection of COOL and COM o HEAT ONLY by continuous connection of HEAT and COM o Normal operation by breaking

CN512 starts/stops all indoor units o Start by pulsed connection between COOL and COM o Stop by pulsed connection between HEAT and COM

TCB-PCDM2E Load shedding control for SMMS or SHRM A PCB that can be installed in the master outdoor unit. One or two, normally open switches may be connected to its two circuits. Compressor speed is limited as a function of these switches being connected in combination. A number of options are available by Dipswitch however assuming interface PCB SW07 bits 1 and 2 are both ON, load shedding will have this effect:

SW01 SW02 Compressor limit

off off 100%

on off 85%

off on 75%

on on 60%

Page 4: toshiba VRF Commsiioning Sequence.pdf

Commissioning sequence overview - SMMS and SHRM For further details, please contact Toshiba Customer Service on 0870 8430333

Bulletin VRF Commsiioning Sequence 4 of 4 26 February 2008

NOTE 1 Refrigeration charge calculation Liquid pipe size SMMS SHRM

1/4" 0.025 kg/m 0.033 kg/m 3/8" 0.055 kg/m 0.072 kg/m 1/2" 0.105 kg/m 0.137 kg/m 5/8" 0.160 kg/m 0.208 kg/m 3/4" 0.250 kg/m 0.325 kg/m 7/8" 0.350 kg/m 0.455 kg/m

System refrigerant charge correction table (SMMS and SHRM2)

NOTE 2 System address settings Setting system address by Dipswitches. Default address is 1 – addresses can be 1 – 28 SW14-1 SW14-2 SW14-3 SW14-4 SW13-4 Address increase 1 2 4 8 16

1 0 4 0 0 E.g. system 6 is 1 +

ON OFF ON OFF OFF

-5.01010101040068822-6.08101010383.01010204.012121236081018-6.08810103608816

2.01212121248-4.0881026010121212467.0121224

-2.01010121244-4.088824-4.010101012425.0101222

3.01012123406814-6.088810343.512121.0101012322.51010-6.08888321.588010101030066

-2.08101028055correction4321HPcorrection321HP

-5.01010101040068822-6.08101010383.01010204.012121236081018-6.08810103608816

2.01212121248-4.0881026010121212467.0121224

-2.01010121244-4.088824-4.010101012425.0101222

3.01012123406814-6.088810343.512121.0101012322.51010-6.08888321.588010101030066

-2.08101028055correction4321HPcorrection321HP

-3.0881026-4.5888242.0101020081018

010101030-1.58101028

-1.588163.01212 2.510102.088

correction321HP

-3.0881026-4.5888242.0101020081018

010101030-1.58101028

-1.588163.01212 2.510102.088

correction321HP