Topic I - Paper - 6

download Topic I - Paper - 6

of 7

Transcript of Topic I - Paper - 6

  • 8/2/2019 Topic I - Paper - 6

    1/7

    DEVELOPMENT OF PHASE SHIFTING TRANSFORMERS

    FOR SCOTTISH AND SOUTHERN ENERGY plc

    Krishnamurthy Vijayan, Waldemar Ziomek, Juan Carlos Garcia Willi Felber

    Pauwels Canada Inc., Winnipeg, Canada Felber Engineering, Austria

    INTRODUCTION

    Reliability of power systems are strengthened by large

    interconnected networks. Effective control of power flow

    in these networks is essential for improving stability,

    enhancing reliability and optimizing capabilities of such

    large interconnected systems. The voltage variation

    provided by load tap changers in transformers can help to

    control only reactive power flow where as Phase Shifting

    Transformers (PSTs) are proven solution for control of real

    power flow in interconnected systems.

    In 2004, Pauwels Canada Inc. successfully developed 240

    MVA and 150 MVA PSTs for Scottish and Southern Energy

    plc, Scotland. This paper describes briefly the general

    principle and basic types of PSTs. It also describes specific

    details on the design, manufacture and testing process of

    the PSTs delivered to Scottish and Southern Energy plc.

    PRINCIPLE OF PSTs

    Purpose

    PSTs are primarily used to control flow of real power inparallel lines or interconnected systems by introducing a

    phase angle shift between the Primary (Source) and

    Secondary (Load) terminals. This is achieved by providing

    a boost voltage in quadrature (perpendicular) to line

    voltage.

    Application

    Consider the current distribution between two parallel lines

    as shown below

    When power flows between these two systems, Individual

    line loading depends on the impedance of the lines. More

    power flows through the path with lower impedance. This

    may cause individual line overloading and is usually

    contrary to efficient system operation. If it is desired to

    balance the current by increasing i1

    by Di, and therefore

    decreasing the current in line 2 to i2-Di, it is necessary to

    introduce a circulating current Di in the system. This can

    be done with the introduction of a PST in series with one

    of the lines (see Fig. 2). An expression for the circulatingcurrent is

    (1)

    Where DV is the quadrature boost voltage provided by the

    PST. This voltage needs to be almost perpendicular to the

    line voltage so that control of real power flow can be

    achieved. By using on load tap changers in PSTs DV can

    be varied or even reversed so that a full range of power

    flow control is possible between parallel lines.

    Another important application of PSTs is the control of

    power flow between two large independent grids. The flow

    of active power between two interconnected systems is

    given by (2).

    VS

    i1 Z1

    i2Z2 iTOTAL

    VL

    Fig. 1 Current distribution in parallel lines

    Fig. 2 Current distribution in parallel lines with PST

    i1+i Z1

    i2-i Z2 iTOTAL

    VS VL

    VLVPSTPST

    1 2

    Vi

    Z Z

    =

    +

    V1 V2

    P

    System 1 System 2

    Fig. 3 Two independent grids

    ( )1 2 sinVVP Z

    = (2)Therefore, the flow of real power between two systems

    can be effectively controlled by varying the phase angle

    difference (j).

    Equivalent circuit and phasor diagram

    Before understanding the phasor diagram it is essential to

    understand the following terminologies

    Advance phase angle : The phase angle that results when

    Session I Paper 6

    I-28

  • 8/2/2019 Topic I - Paper - 6

    2/7

    the PST's Load terminal voltage leads the Source voltage

    terminal. This condition produces an increase in the line's

    source to load power flow. Fig. 4 shows the vector diagram

    for this case.

    Retard phase angle: The phase angles those results when

    the Load terminal voltage lags the Source terminal voltage.

    This condition produces a decrease of the line's source toload power flow.

    Like any transformer, PSTs have inherent impedance which

    varies with the phase angle. Generally, PSTs have their

    minimum impedance at zero phase shift which increase

    with the phase angle. PSTs can be considered as voltage

    sources with internal impedances that vary with phase angle

    shift.

    As can be seen in the vector diagram, under load condition,

    the phase angle shift is affected by the PST's internal

    impedance. The internal phase shift b of the PST can be

    calculated as [2]

    (3)

    Where cos(f) is the load power factor.

    The effective phase shift under load is given by

    These relations not only have impact on the transformer

    design but also on the selection of load tap changer. The

    PSTs rated phase-shift is generally defined at no-load but

    as can be seen from the equations, it is not possible to

    achieve this phase angle under load in advance position.

    Also if the no-load angle is exceeded in retard position,

    over excitation will occur in parts of PST.

    TYPES OF PSTs

    The different types of PSTs can be better understood if

    certain terminologies are defined.

    Symmetrical PST: Under no-load the magnitude of the

    PST's source and load voltages are equal, independently

    of the phase angle between them.

    Quadrature: It refers to the boost voltage introduced by

    the PST being perpendicular to the line voltage at one

    terminal.

    The basic types of PSTs can be Symmetrical or non-

    symmetrical, they can be single core or dual core and they

    can be single tank or dual tank.

    There are also many other types or design possibilities

    which makes the subject of PST development very

    challenging.

    Types of Phase shifting transformers

    Non-symmetrical quadrature type

    iLRPST+jXPST

    VS VL VLeff

    VS

    iLXPST

    iL

    VL iLRPST

    VLeff

    Load

    No Load

    Fig. 4 PST equivalent circuit and phasor diagram

    ( ) ( )

    ( ) ( )

    cos sinarctan

    sin cos

    L PST PST

    L L PST PST

    I X R

    V I X R

    = +

    ADVANCE

    LOAD NO LOAD =

    RETARDLOAD NO LOAD = +

    Phase shifting

    transformer

    Quadrature

    symmetricalQuadrature

    non symmetrical

    Single core Two core

    Single Tank Dual tank

    Fig. 5 Types of PSTs

    Fig. 6 Asymmetrical PST

    I-29

    Session I Paper 6

  • 8/2/2019 Topic I - Paper - 6

    3/7

    I-30

    Session I Design For Reliability

    In this type of PST the quadrature voltage is achieved by

    connecting the regulating winding of phase B to the Delta

    connection point of phase A and B and so on. The

    advantage of this type is that it has no exciting transformer.

    The major disadvantage of this type is the tap changer and

    regulating winding being directly exposed to system

    disturbances. Special measures are required to ensure their

    impulse withstand capability.

    Symmetrical quadrature type single-core

    This is an extension of the non-symmetrical type whichcan be achieved with an additional tap changer.

    Two-core symmetrical quadrature PST

    This is the standard and classical solution with series and

    exciting transformers each built on its own core but with

    windings electrically interconnected.

    Single tank/Dual tank

    These are possible design options for 2 core designs.

    Depending on size, voltage class, etc., the Series and

    Exciting transformers could be housed in the same tank or

    in separate tanks. Obviously housing in separate tanks has

    the disadvantages of being more expensive and that the

    inter-connection between the units needs to be redone at

    site.

    PSTs FOR SCOTTISH AND SOUTHERN ENERGY

    plc

    Application

    In the Scottish power system, two double-circuit 275kV

    parallel lines run north to south via the east coast to

    transport Hydroelectric and Wind energy. One double-circuit 132kV line runs north to south via the west coast

    and a single 132 kV line runs north to south via the east

    coast for the same purpose. When there is a fault on one of

    the 275kV lines the power tries to flow through the 132kV

    system since its impedance is smaller under that condition.

    This leads to over loading of the 132kV lines.

    In this case three PSTs were needed to control the active

    (real) power flows in the non faulty lines so that each of

    these lines could be used to its rated capacity without over

    loading the 132kV lines.

    The PSTs will be bypassed using bypass switch undernormal condition. Thus there is possible impulse condition

    with both Source and Load terminals connected together.

    Ratings and special requirements

    Basic ratings

    Site1 (Fiddes substation)

    1 x 150 MVA, 132 kV class, 50 Hz, 550 kV BIL with

    phase angle shift under load of +/-15, using load tap

    changer with +/-8 steps

    Site2 (Errochty substation)2 x 240MVA, 132 kV class, 50 Hz, 550 kV BIL with phase

    angle shift under load of +10/-20, using load tap changer

    with +/-8 steps

    Special requirements

    l Transformers to comply with IEC 76 standards.

    Requirements specific to PSTs to be as per IEEE

    C57.135 [2], which are the only available standards

    for this kind of applications.

    Fig. 7 Symmetrical PST

    Fig. 8 Quadrature-booster PST

  • 8/2/2019 Topic I - Paper - 6

    4/7

    I-31

    Session I Paper 6

    l Dual core with separate series and exciting

    transformer, Quadrature booster designs preferred.

    l Dual tank design anticipated due to transportation

    limitations. A maximum height of 4.87 m and weight

    of 220 T is allowed on the roads approaching the

    final site in UK. Single tank designs meeting these

    transportation limits are acceptable.l Use of non-linear voltage limiting devices to control

    internal voltages to be avoided.

    l 115% chop wave test required

    l Special impulse test required with both Source and

    Load terminals connected together to simulate the

    PST bypass condition.

    l The ratio of zero sequence to positive sequence

    impedance to be smaller than 9 (Z0/ZP< 9)

    l 110% over voltage and frequency variation of 47.5

    to 52 Hz

    Design approach

    l A classical design concept of a two-core symmetrical

    Quadrature booster was applied

    l An extremely compact design concept was applied

    in order to house both, series and exciting units in a

    single tank while meeting size and weight

    transportation requirements. Such compactness was

    achieved by using tall and slim design concept with

    low impedance. Special care was taken to assure

    withstand capability against short circuits.

    l Series transformer and exciting transformer are built

    on separate 3 leg cores with electrical interconnection

    between them

    l A tertiary delta winding was introduced in the

    exciting transformer in order to meet the zero

    sequence impedance requirement

    l Use of a special dual multi-layer design on the series

    transformer delta winding to achieve controlled

    dielectric stresses during lightning impulse condition.

    l Center-fed exciting winding so that the high voltageconnection with the series winding is made at the

    center, away from core ground potential. The two

    transformer heights and dimensions were closely

    matched to facilitate the interconnection inside the

    tank

    l Fully interleaved exciting winding

    l Special 2 layer tap winding with leads connected to

    high speed resistance type tap changer.

    Design details

    Basic design

    The winding disposition on the two cores is indicated

    below.

    Impedance calculation and loss control

    FEM based leakage flux analyses were used to determine

    size and position of tank shunts and clamp shunts.

    Impedance calculations were performed with the help of

    field calculation tool based on Bessel functions.

    a) Series transformer b) Exciting transformer

    Dielectric design

    Impulse calculations using LC network based software

    were performed for each of the following conditions: a)

    Impulse on S (or L) terminal with the other terminal

    grounded b) Impulse on S & L terminals connected

    (bypassed PST). For condition b) the center connection

    point voltage was estimated to rise to 1034kV during the

    550 kV full wave impulse test.

    Electrostatic stress analyses were performed for all critical

    locations and special contouring and insulation components

    were used wherever necessary.

    DELTA

    SERIES

    LTC2

    LTC1

    TERTIARY

    EXCITER

    Series unit Exciting unit

    Fig. 9 PST windings layout

    Fig. 10 Electromagnetic FEM simulations.

    a) b)

  • 8/2/2019 Topic I - Paper - 6

    5/7

    I-32

    Session I Design For Reliability

    Design reviews were conducted at every stage of the

    development process.

    Manufacturing

    l All windings and core were built to close dimensional

    tolerance

    l Pre-fit of the units inside tank was necessary to make

    measurements for final interconnection at center.

    l After final housing of the units, special contoured

    high voltage inter connection was done by skilled

    person inside the tank. Connections inspected and

    approved by Quality Assurance and Engineering by

    physical inspection inside tank.

    l Special manufacturing process evolved by buildinga prototype for the dual multi-layer type delta

    winding.

    Photograph below shows the two units assembled and

    housed inside the common tank.

    Testing

    Special features of some of the factory tests are highlighted

    here

    Phase angle measurement

    Phase angles were measured according to proposed method

    in IEEE C57.135 [2]. The phase shift was also recorded inoscilogram, see figure below.

    Dielectric tests

    Lightning impulse

    Low voltage recurrent surge impulse tests were done with

    both series and excitation units electrically connected to

    verify impulse voltage calculations. Some of these

    measurements were done with both assemblies outside the

    tank and inside the tank. The measured values were close

    to calculated values.

    Fig. 11 Typical stress plot: Series transformer main gap

    at highest stress region

    Fig. 12 Series and exciting transformers assembled

    inside tank

    Fig. 13 S and L wave shapes when S leads L

    S

    N

    L

    S

    N

    L

    Fig. 14 Lightning impulse test on S (or L) terminal and

    on S+L terminals (bypassed PST)

    Fig. 15 Low voltage recurrent surge impulse-test.

    Impulse response at the exciter T connection point

  • 8/2/2019 Topic I - Paper - 6

    6/7

    I-33

    Session I Paper 6

    Besides impulse test on S and L terminal, special lightning

    impulse test including 115% chop wave condition were

    applied to (S+L) connected together. The calculated and

    RSG test results at the T point for 1.2/50s full wave

    impulse applied to (S+L) is shown in Fig. 15. The

    maximum values by test are lower than calculated values.

    The difference is attributed to a) Measurement for this case

    was done in air outside tank and b) Our calculations do

    not consider damping.

    Induced voltage test

    For this test the unit was energized through a set of

    temporary test bushings brought out of the tap windings.

    Both 1-phase and 3-phase induced tests were conducted

    as per IEC standard [3].

    Loss measurement

    In PST the loss distribution in series and exciting units

    vary with the phase angle. Typical loss distribution of the

    measured values for 240MVA unit is shown in table.

    Temperature rise test

    With single tank design, temperature rise test for obtaining

    oil rise values do not pose any difficulties. But measurement

    of gradients of each of the windings needs special methods.

    Gradient of each winding including the LTC winding was

    measured either by direct or indirect measurements.

    1. Resistance of Series winding of ST can be measured

    directly between S & L ( R+R= 2R in the diagram

    below)

    2. For the Exciting winding it will be an indirect

    measurement as follows

    S & L terminals to be connected & resistance to neutral

    was measured. This will give (R/2 + Re) ohms. Since R is

    known, Re can be calculated.

    3. Resistance of Delta winding & LTC winding are

    measured using temporary test bushings connected

    to LTC.

    Test frequency

    The phase shifters were designed for frequency of 50Hz

    to suit the Scottish system. However the test frequency at

    the Pauwels Canadian plant was 60Hz and hence

    conversion factors were applied to the tests results in orderto get guaranteed design parameters at 50Hz. Useful

    guidance was taken from IEEE Tutorial for the conversion

    factors [3].

    Test summary

    All the tests on both the ratings were very successful. All

    three units passed all tests first time right.

    l The measured phase angles were within 1% of the

    guaranteed values.

    l The maximum P.D level was 103 pC.

    l The maximum hot spot temperature was 68.50C.l The special zero sequence impedance ratio

    requirement of Zo-open /Z positive was fully met.

    (Photo of unit under test)

    CONCLUSIONS

    As can be seen the design and development of Phase

    shifting transformers are unique. It was a challenge to meet

    Table 1 Summary of tested losses on 240 MVA PST

    Series Exciting Total

    unit unit

    No load loss kW

    Zero phase shift 0 26.8 26.8

    Maximum phase shift 21.2 26.8 48

    Load loss kW

    Zero phase shif 224.3 0 224.3

    Maximum phase shift 224.3 268.7 493

    Total loss kW

    Zero phase shif 224.3 26.8 251.1

    Maximum phase shift 245.5 295.5 541

    Series winding on ST

    Excitingwinding Re []

    R []R []

    S L

    N

    Fig. 16 T network used to calculate the exciting winding

    resistance

    Fig. 17 240 MVA phase shifter on site.

    Courtesy of Scottish and Southern Energy plc

  • 8/2/2019 Topic I - Paper - 6

    7/7

    I-34

    Session I Design For Reliability

    the transport limits with the single-tank design. Considering

    various advantages it was worth the efforts since this

    approach gives the best satisfaction to the ultimate

    customer. All the three units have reached site and they

    are presently undergoing field trials.

    REFERENCES

    1. W. Seitlinger, "Phase Shifting Transformers,

    Discussion of Specific Characteristics", CIGRE

    Session 1998

    2. IEEE Std C57.135-2001 "IEEE Guide for the

    Application, Specification, and Testing of Phase-

    Shifting Transformers", IEEE Power Engineering

    Society, 2002

    3. E.G. teNyenhuis, R.S. Girgis, "50Hz to 60Hz

    conversion factors for transformer performance

    parameters". IEEE/PES Transformer Committee

    Tutorial session April 16,2002

    4. IEC standard 60076 IEC: 2000 "Power transformers".

    5. Axel Kramer "On-Load Tap-changers for Power

    transformers by (MR publication)"

    6. Scottish Hydro-Electric Transmission Ltd"Specification for Quadrature booster transformers".

    Enquiry No:C33995/01

    ACKNOWLEDGEMENTS

    The authors express their sincere thanks to Scottish and

    Southern Energy plc., for providing the system details and

    site photographs.

    The authors also acknowledge the support provided by the

    management and colleagues at Pauwels Canada Inc.,