TOPA-I

download TOPA-I

of 9

Transcript of TOPA-I

  • 7/23/2019 TOPA-I

    1/9

    1 | P a g e

    NATIONAL LAW INSTITUTE UNIVERSITY

    PROPERTY LAW - I

    Case Analysis:

    St. Mary's Educational Society

    Vs

    Dr. Qutubuddin Ahmed & Ors.

    SUBMITTED TO: SUBMITTED BY:

    AKSHEY JOSE DR. SANJAY KUMAR YADAV

    2013 B.A.LLB 39 ASSOCIATE PROFESSOR

  • 7/23/2019 TOPA-I

    2/9

    2 | P a g e

    Contents

    MATERIAL FACTS ................................................................................................................... 3

    LEGAL ISSUES .......................................................................................................................... 5

    ARGUMENTS ADVANCED ..................................................................................................... 6

    Defendants .................................................................................................................................6

    Plaintiffs......................................................................................................................................6

    LEGAL PROVISIONS................................................................................................................ 7

    JUDGEMENT ............................................................................................................................. 9

  • 7/23/2019 TOPA-I

    3/9

    3 | P a g e

    MATERIAL FACTS

    The material facts of the case are as follows:

    1.

    The plaintiffs are the owners of premises bearing Door No. 3-6-137, Himayatnagar,

    Hyderabad, admeasuring 1,612 sq. yards, with an old building, thereon.

    The 1st defendant is an Educational Society and Defendants 2 and 3 are its members.

    2.

    With a view to establish and run a Junior College in the said premises, Defendants 1 to3 (for short "the defendants") approached the plaintiffs. Both of them agreed on certain

    terms, such as, that the suit schedule property shall be leased for a period of 15 years,

    with effect from 2-10-1987 to the defendants, that a building shall be constructed by the

    defendants, with their own funds, in accordance with the plan to be sanctioned in the

    name of the plaintiffs by the Municipal Corporation of Hyderabad, that the defendants

    shall deposit a sum of Rs. 50,000/-, and that the monthly rent shall be Rs. 7,000/-.

    Initially, an agreement was entered into on 11-8-1986. Thereafter, a lease deed was

    executed on 2-10-1987, but it was not registered.

    3. The defendants were inducted into possession and construction was undertaken. Few

    years thereafter, notices were exchanged between the parties, in the matter of payment

    of certain additional amounts, as advance to the plaintiffs. Alleging that the defendants

    constructed large halls in the 5th floor of the building, without permission from the

    Municipal Corporation of Hyderabad, failed to demolish an old structure, which too

    was a condition imposed by the Municipal Corporation, for undertaking new

    construction, and that they have subleased part of the premises in favour of Defendants

    4 and 5, the plaintiffs got issued legal notice dated 20-2-1997. The defendants, in turn,

    issued a reply dated 3-3-1997, denying the allegations contained in the notice. Not

    being satisfied with the reply issued by the defendants, the plaintiffs filed the suit for

    the reliefs referred to above.

  • 7/23/2019 TOPA-I

    4/9

    4 | P a g e

    4.

    On behalf of the defendants, a common written statement was filed. It was alleged that

    on their own accord, the plaintiffs have agreed to extend the period of lease till the year

    2017, beyond the initial period of 15 years, and received a sum of Rs. 6,00,000 as

    advance. As regards the alleged deviation from the plan, they pleaded that the plaintiffs

    themselves filed a suit in the Court of X Assistant Judge, City Civil Court, Hyderabad,

    and obtained a decree for regularization of a minor deviation. It is stated that while

    extending the period of lease, several conditions, such as, increase of the rent by 15%

    for every span of 5 years, was agreed to. They flatly denied the sublease of the premises

    in favour of the Defendants 4 and 5. They contended that the plaintiffs are in the habit

    of making unreasonable and unjust demands for payment of huge amounts, without any

    basis, and that the suit is not maintainable, since it is filed before the expiry of agreed

    period. The rate at which the mesne profits were claimed is stated to be excessive and

    unreasonable.

    5. Through its judgment dated 20-1-2003, the trial Court decreed the suit, directing that

    the plaintiffs shall pay a sum of Rs. 30,00,000/- towards cost of construction, within

    three months, from the date of decree, and refund within three months, all the amounts

    received by the plaintiffs as advance, and thereupon, the defendants shall deliver vacant

    possession of the premises. It awarded mesne profits at the rate of Rs. 8/- per sq. feet,

    per month, over an area of 15,000 sq. feet from the date of filing of the suit, till the date

    of delivery of possession. A direction was issued as to adjustment of Rs. 6,00,000/-, at

    the rate of Rs. 4,000/- per month, with effect from 2-10-1992 till 1-4-1997.

    6.

    The defendants filed an appeal aggrieved by the decree passed by the trial Court. The

    plaintiffs, on the other hand, filed in the same Court, aggrieved by the decree passed bythe trial Court, insofar as it awarded mesne profits at the rate of Rs. 8/- per sq. feet, as

    against their claim of Rs. 35/- per sq. feet, over a larger extent.

  • 7/23/2019 TOPA-I

    5/9

    5 | P a g e

    LEGAL ISSUES

    1. Whether the plaintiffs are entitled for the ejectment of the defendants and delivery of

    vacant possession of the suit schedule property?

    2. Whether the plaintiff is entitled for mesne profits at the rate of Rs. 8,400/- p.m., for the

    period from 2-4-1997 to 8-4-1997 amounting to Rs. 1960/-?

    3. Whether the plaintiff is entitled for future mesne profits pendente lite until delivery of

    possession?

    4. Whether the plaintiffs had received Rs. 6 lakhs with regard to extension of lease from

    2002 to 2017 from the defendants, as pleaded by D-1 to D-4 in their written statement?

    5.

    Whether the notice dated 20-2-1997 issued by the plaintiffs is not proper and valid?

    6.

    Whether the plaintiffs are entitled for future mesne profits at Rs. 35/- per SFT from the

    date of the suit till delivery of possession of the suit schedule property?

  • 7/23/2019 TOPA-I

    6/9

    6 | P a g e

    ARGUMENTS ADVANCED

    Defendants

    Learned Advocate-General, appearing for the defendants, submits that the suit itself was not

    maintainable, since there existed an agreement between the parties that the lease shall be in

    force, till the year 2017. He contends that the defendants were ready and willing to perform

    their part of the contract, for execution of lease deed, and that they were not liable to be

    evicted from the premises. He contends that the findings recorded by the Courts below, on

    the allegations as to making of unauthorized constructions, or failure to demolish the oldstructure, are without any basis. He submits that the plaintiffs got the deviations regularized,

    through process of compounding, by filing a suit. About the plea as to subleasing of the

    premises, the learned Advocate-General submits that there was absolutely no truth in it, and

    the Courts below have proceeded on assumptions.

    Plaintiffs

    Learned Counsel for the plaintiffs, on the other hand, submits that admittedly there did not

    exist any registered lease deeds, and the defendants cannot rely upon any condition,

    incorporated in an unregistered document. He contends that the plea of part performance

    was not at all raised in the written statement, and even otherwise, the defendants are not

    entitled for protection, thereunder. Learned Counsel further submits that, even if the benefit

    under Section 53-A of the Transfer of Property Act (for short "the Act") is to be extended,

    the fact remains that the very document, on which reliance is placed, provided for eviction

    on payment of cost of construction, and thereby, it became permissible for the plaintiffs to

    seek eviction.

  • 7/23/2019 TOPA-I

    7/9

    7 | P a g e

    LEGAL PROVISIONS

    Transfer of Property Act, 1882 - Section 53A

    Part performance

    Where any person contracts to transfer for consideration any immovable property by writing

    signed by him or on his behalf from which the terms necessary to constitute the transfer can

    be ascertained with reasonable certainty, and the transferee has, in part performance of the

    contract, taken possession of the property or any part thereof, or the transferee, being

    already in possession, continues in possession in part performance of the contract and has

    done some act in furtherance of the contract, and the transferee has performed or is willing

    to perform his part of the contract, then, notwithstanding that the contract, though required

    to be registered, has not been registered, or, where there is an instrument of transfer, that the

    transfer has not been completed in the manner prescribed therefor by the law for the time

    being in force, the transferor or any person claiming under him shall be debarred from

    enforcing against the transferee and persons claiming under him any right in respect of the

    property of which the transferee has taken or continued in possession, other than a rightexpressly provided by the terms of the contract.

    Transfer of Property Act, 1882 - Section 106

    Duration of certain leases in absence of w ri tten contract or local usage

    In the absence of a contract or local law or usage to the contrary, a lease of immovable

    property for agricultural or manufacturing purposes shall be deemed to be a lease from year

    to year, terminable, on the part of either lessor or lessee, by six months' notice expiring with

    the end of a year of the tenancy; and a lease of immovable property for any other purpose

    shall be deemed to be a lease from month to month, terminable, on the part of either lessor

    or lessee, by fifteen days' notice expiring with the end of a month of the tenancy.

  • 7/23/2019 TOPA-I

    8/9

    8 | P a g e

    Transfer of Property Act, 1882 - Section 107

    Leases how made

    A lease of immovable property from year to year, or for any term exceeding one

    year or reserving a yearly rent, can be made only by a registered instrument.

    All other leases of immovable property may be made either by a registered

    instrument or by oral agreement accompanied by delivery of possession.

    Where a lease of immovable property is made by a registered instrument, such

    instrument or, where there are more instruments than one, each such instrument shall

    be executed by both the lessor and the lessee.

  • 7/23/2019 TOPA-I

    9/9

    9 | P a g e

    JUDGEMENT

    The trial Court shall appoint a Commissioner, who shall be a Civil Engineer, or

    Contractor, for the purpose of ascertaining the value of the building, constructed by

    the Defendants 1 and 2, on the plaint schedule property.

    The defendants shall vacate the suit schedule premises, on deposit of cost of the

    building by the plaintiffs as assessed under Clause (a), or by the end of May 2007,

    whichever is later.

    There shall be a decree for a sum of Rs. 1,960/- representing mesne profits, up to the

    date of filing of the suit.

    It shall be open to the plaintiffs to file an application for ascertainment of mesne profits

    for the suit schedule property, for the period, from the date of filing of the suit, till the

    date of recovery of possession. On such ascertainment, a decree for the said amount

    shall ensue.

    The parties shall bear their own costs.