Tocardo Project Information Summary Jan 2017 v3 1 Tocardo EMEC installation Project Information Summary For general information and application for consent Project: P0044 – Tocardo EMEC installation Report number: 2016R0030 Version: v2016-2112 Author: Thijs Mandersloot Filename: Tocardo Project Information Summary Jan 2017 v3 Check & approval Name Signature Date Created: Thijs Mandersloot Checked: Nikki Meek Checked: Sjoerd Keijser Approved: Pieter de Haas Version history Release Description Date 1.0 First release 13-12-2016 1.1 Significant additional updates 12-1-2017

Transcript of Tocardo EMEC installation Project Information...

  • Tocardo Project Information Summary Jan 2017 v3 1

    Tocardo EMEC installation Project Information Summary

    For general information and application for consent

    Project: P0044 – Tocardo EMEC installation

    Report number: 2016R0030 Version: v2016-2112

    Author: Thijs Mandersloot

    Filename: Tocardo Project Information Summary Jan 2017 v3

    Check & approval

    Name Signature Date

    Created: Thijs Mandersloot

    Checked: Nikki Meek

    Checked: Sjoerd Keijser

    Approved: Pieter de Haas

    Version history Release Description Date

    1.0 First release 13-12-2016

    1.1 Significant additional updates 12-1-2017

  • Tocardo Project Information Summary Jan 2017 v3 2

    Contents

    1. COMPANY BACKGROUND ............................................................................................................... 3

    1.1 Technology background .................................................................................................................... 3 1.2 Project background ........................................................................................................................... 4

    2. PROJECT DESCRIPTION .................................................................................................................... 5

    2.1 Consenting Schedule ......................................................................................................................... 5 2.2 Project Location ................................................................................................................................. 7

    3. DEVICE DESCRIPTIONS .................................................................................................................... 8

    3.1 Hardware items ................................................................................................................................. 8 3.2 Turbine specifications ........................................................................................................................ 9

    3.2.1 Phase 1 – TFS Device ................................................................................................................ 10 3.3 Phase 2 – Universal Foundation Structure (UFS)............................................................................. 13 3.4 Cables .............................................................................................................................................. 14 3.5 Mooring Principles ........................................................................................................................... 15

    3.5.1 Phase 1 TFS Device .................................................................................................................. 15 3.5.2 Phase 2 UFS Device .................................................................................................................. 15

    3.6 Materials used ................................................................................................................................. 17 3.7 Mounting scientific equipment ....................................................................................................... 18

    4. INSTALLATION METHOD ............................................................................................................... 19

    4.1 Phase 1: ........................................................................................................................................... 19 4.2 Phase 2: ........................................................................................................................................... 19 4.3 Anticipated Vessel traffic to site ...................................................................................................... 19 4.4 Device Monitoring Control and Maintenance System .................................................................... 20 4.5 Decommissioning Method............................................................................................................... 20 4.6 Environmental and Navigational Risk Considerations ..................................................................... 21

    4.6.1 Environmental Risks ................................................................................................................ 21 4.6.2 Navigational Risks .................................................................................................................... 21

    4.7 Project timeline milestones ............................................................................................................. 21

    APPENDIX A ......................................................................................................................................... 22

  • Tocardo Project Information Summary Jan 2017 v3 3

    1. Company background Tocardo International B.V. was founded in the Netherlands in 2008 as a commercial spin-off from the engineering company Teamwork Technology B.V. Founder and CEO of the company, Hans van Breugel has a long history in maritime and renewables sectors. The founding team come from a long background in shipping, ship building and civil engineering. This bedrock of knowledge, experience and methodical approach to technology development has enabled the company to design and develop a turbine technology based on robust marine installation and operational principles. The turbines are simple, efficient and reliable. Tocardo works with strong partners in project development, engineering, installation and maintenance to deliver turnkey turbine solutions to fit each project perfectly. The range of water turbines generate electricity at the lowest cost per kWh, through minimised maintenance and maximised power generation technology. Tocardo builds on the Netherlands’ proud reputation for civil water engineering, with a proven track record of 12 successful years developing renewable hydro-power devices.

    1.1 Technology background Currently Tocardo has 9 turbines operational at four different demonstration sites ranging from 103 kW (single turbine) to 1.2 MW (5 turbines) installed capacity. Tocardo aims at providing low maintenance solutions and reliable technology. Turbines are sized according to the site characteristics regarding water flow conditions. This mainly concerns the blade rotor diameter. Tocardo currently has three models available:

    - T1 Bi-directional free flow turbine. Ranges from 42kW to 98kW

    - R1 Uni-directional free flow (river). Ranges from 42kW to 98kW

    - T2 Bi-directional free flow turbine. Ranges from 103kW to 372kW

    Tocardo installed five T2 tidal turbines (totalling 1.2MW) in the Eastern Scheldt storm surge barrier. This installation is the largest tidal energy project in the Netherlands (www.tocardo.com/projects). The 50-meter-long and 20-meter-wide structure was transported over water. Taking into account the water levels, the tides and the weather and using the sides of the storm surge barrier, the tidal power plant was placed within a window of just two hours and with high precision. Tocardo is also currently working on the final pre-construction stage of a floating-array-project lined up for Canada which are to be installed in 2017-18. The intended use of the turbine is to generate electrical power from bi-directional tidal flows, while being completely below the water surface. The turbine can be installed single or in an array on different types of foundations, both fixed and floating. The (economic) design life time of the turbines is 20 years. The turbine is intended to be integrated in a tidal power plant that distributes the generated electrical power to a grid. Tocardo has been developing an offshore tidal unit, the Universal Foundation Structure (UFS), which it now wishes to bring to the UK for sea trials at the EMEC tidal test facility in the Fall of Warness. However, in order to benefit sufficiently from the site and the connection to the electrical grid at Eday, Tocardo intend to carry out the project in two phases: the first utilizing the Temporary Foundation Structure (TFS) floating foundation which would enable a single T2 turbine to operate at the site and generate power to the grid. The intention is to install this first turbine prior to 31st March 2017. The second phase will transfer the first turbine from

    http://www.tocardo.com/projects_and_showcases/oosterschelde_storm_barrier.html

  • Tocardo Project Information Summary Jan 2017 v3 4

    the TFS foundation to Tocardo’s UFS foundation which will hold a total of 5 T2 turbines and generate 1.4MW of electrical power.

    1.2 Project background The objective of the project at EMEC is to demonstrate the power generation and reliability of the Tocardo tidal technology in an offshore location along with its ability to operate passively with the surrounding environment with minimal/no impact to the biota. Peak power output at the typical 4 m/s tidal current flows at the site, is 275kW for the TFS unit and 1.4MW for the UFS unit. In summary, the project will be built out in two phases: Phase 1 (Duration max. 18 months) – Installation of the TFS Platform and a single 275kW turbine prior to 31st March 2017. This unit will be located at a temporary location within the Fall of Warness which will utilize ScotRenewables Tidal Power Ltd’s existing SR250 cable. The Platform will be moored to the seabed using a 4-point mooring system. This unit will be operated and then decommissioned within the 18 month period. Phase 2 (Duration max. 18.5 years) – Removal of the TFS foundation unit and turbine transferred to the UFS unit along with 4 additional turbines (the TFS unit will then be transported back to the Netherlands, minus the turbine). The UFS, including the 5 turbines, will then be installed at berth 6 at the Fall of Warness where the tidal flows are slightly higher and more suited to the 5 turbine foundation unit. The UFS will be anchored in place using 2 gravity anchors. This unit will remain on station for a further 18.5 years. All equipment will be removed from the site and decommissioned during the 18.5 year period. Both Phase 1 and Phase 2 will involve the turbines being connected to the local electrical grid at EMEC’s Eday substation. Tocardo will be utilizing the existing subsea cables at the Fall of Warness. Both foundation units will be connected to the subsea cables using dynamic umbilical cables. The total duration for the project in its entirety will be 20 years, therefore the Marine Licence application for which this document is supporting, is for the full 20 years.

  • Tocardo Project Information Summary Jan 2017 v3 5

    2. Project Description On 23nd of February 2016, Tocardo International B.V. and EMEC Ltd. signed a contract for the deployment and operation of its floating tidal stream technology within the Fall of Warness Tidal Test Site for a total duration of 20 years. Since signing this agreement Tocardo and EMEC have worked together to develop the plan and scheduling for the intended project. Due to the lack of Contracts for Difference (CfD), set by the Government, to replace the Renewable Obligation Certificates (ROC) scheme, it has been decided that Tocardo will need to undertake their intended project in the 2 phases as outlined in the previous section. Phase 1 must be installed prior to 31st March 2017 in order to qualify for the ROCs scheme. Without this the project will not be financially viable and Tocardo will lose a significant opportunity to invest in the UK marine renewables market. As previously stated, Tocardo wish to install the TFS unit for a duration of up to 18 months when it will be removed and then replaced with the UFS which will remain operating at the test site for a further 18.5 years. During this time Tocardo will remotely monitor the units through on-board sensors. A preventative maintenance schedule is being developed at present and will be made available at an appropriate time. It is not envisaged that the units will need to be removed from their berth during the lease period unless the units have encountered significant damage or significant component failure. All electrical/sensor maintenance and repair can be carried out on site without removal of the units.

    2.1 Consenting Schedule Due to Tocardo’s requirement to secure consent for the development as a single project (which includes Phase 1 and Phase 2) as well as install and commission Phase 1 prior to the end of the ROC’s regime (31st March 2017), Tocardo plan to apply for the full project within the one marine licence application. The intention is to install and commission Phase 1 prior to the end of the ROC’s regime (31st March 2017). The proposed consenting schedule, along with supporting documentation, is detailed within the below flow chart. The approach outlined has been discussed with Marine Scotland’s Licensing Operations Team (MS-LOT).

  • Tocardo Project Information Summary Jan 2017 v3 6

    Proposed consent submission schedule

    Project Information Summary (covering Phase 1 and 2)

    Phase 1 Project-specific Navigation Risk Assessment (NRA) addendum

    Submit EPS and Basking Shark Applications to MS-LOT for Phase 1

    Consultation with EMEC and MS-LOT

    Draft Decommissioning Plan (covering Phase 1 and 2)

    Phase 1 Project-specific Environmental Monitoring Programme (PEMP)

    Submit Marine Licence Application to MS-LOT for the full project (Phase 1 and 2) (with the following supporting documentation)

    Phase 1 Third Party Verification (TPV)

    Consultation with Scottish Natural Heritage on PEMP and Maritime Coastguard Agency and NLB on NRA for Phase 1

    Issue of Marine, EPS and Basking Shark Licences by MS-LOT

    January 2017 (Latest)

    January 2017

    February 2017

    Deployment of Phase 1 February/March 2017

    June 2017

    Deployment of Phase 2 Summer 2018

    Phase 2 Project-specific Environmental Monitoring Programme (PEMP)

    Submission of the following supporting information for Phase 2 (as conditioned in the Marine Licence)

    Phase 2 Third Party Verification

    Phase 2 Project-specific Navigation Risk Assessment (NRA) addendum

    Submit Phase 2 EPS and Basking Shark Applications to MS-LOT

    Issue EPS and Basking Shark Licences for Phase 2 by MS-LOT September 2017

    Discharge of Marine License conditions to enable deployment of Phase 2

    Discharge of marine licence conditions to enable deployment of Phase 1 February 2017

  • Tocardo Project Information Summary Jan 2017 v3 7

    2.2 Project Location The table below illustrates the intended licence boundaries of the proposed tidal project at EMEC’s Fall of Warness.

    Phase Latitude Longitude

    Phase 1 (TFS) 59° 8.771’N 2° 48.560’W

    59° 8.771’N 2° 48.125’W

    59° 8.378’N 2° 48.125’W

    59° 8.378’N 2° 48.447’W

    59° 8.600’N 2° 48.503’W

    59° 8.614’N 2° 48.532’W

    Phase 2 (UFS) 59° 9.082’N 2° 49.998’W

    59° 9.083’N 2° 49.409’W

    59° 8.813’N 2° 50.000’W

    59° 8.814’N 2° 49.410’W

    Coordinates of marine license boundary for Phase 1 and 2

    Phase 1: The TFS has a sway circle with diameter of < 30m about the installed location. (The coordinates of the final installed location will be provided to Marine Scotland once deployed). The mooring spread of the TFS is 190m each side, so 380m in total (end to end). The mooring lines of the TFS run to two gravity anchor points upstream, and two gravity anchor points downstream. Phase 2: The UFS sway circle is < 50m maximum. The coordinates of the final installed location will be provided to Marine Scotland once deployed). The mooring spread of the UFS is 250m each side, so 500m in total (end to end). The mooring lines of the UFS run to one gravity anchor point upstream, and one gravity anchor point downstream. The following image shows the proposed Marine Licence boundary for each phase of the entire project. The anchor locations shown are indicative and the final installed coordinates will be provided via the FEP5, to Marine Scotland following deployment.

  • Tocardo Project Information Summary Jan 2017 v3 8

    Location of berth 6 and Temporary siting station (8), with associated marine licence boundary.

    3. Device Descriptions In this chapter, a high-level overview of the intended tidal power plant installation is given. As previously mentioned, Tocardo wish to install two different floating foundations at the tidal site in a 2 phase project. Phase 1 will see the TFS unit with a single T2 turbine installed which will be operated and generating power to the grid at Eday for up to 18 months. This unit (including turbine) will then be removed prior to Phase 2 commencing with the installation of the UFS unit which will include the initial T2 turbine alongside 4 more, giving a total of 5 turbines on the UFS. Although the foundations themselves are different, the turbine technology will be consistent, using the T2 turbine as described below.

    3.1 Hardware items The main hardware device items of the intended installation are: Phase 1

    - TFS moored floating foundation - 1 x T2 turbine design series on the TFS - 4 x mooring lines with associated gravity anchors.

  • Tocardo Project Information Summary Jan 2017 v3 9

    - Dynamic and static intra-berth subsea cable. The dynamic subsea cable is connected between the foundation and the subsea connection hub. The dynamic subsea cable will be fitted with protection systems.

    - Navigational aids, in line with requirements by the MCA and NLB, will be installed on the TFS platform. This will also include an AIS tracking system.

    Phase 2 - UFS moored floating foundation - 5 x T2 turbine design series - 2 x mooring lines and 2 gravity anchors. - Subsea connection hub - Dynamic and static intra-berth subsea cable. The dynamic subsea cable is connected between the

    foundation and the subsea connection hub. The dynamic subsea cable will be fitted with protection systems.

    - Navigational aids, in line with requirements by the MCA and NLB, will be installed on the UFS platform. This will also include an AIS tracking system.

    3.2 Turbine specifications Tocardo intends to use turbines of their series type T2, rated for speeds from 2.0 m/s to 4.5m/s. During survival mode, the turbine brakes kick in and prevent the rotor from turning. Blade rotor sizing depends on the site flow characteristics and is currently being analysed. Preliminary sizing of the turbine for the EMEC project has resulted in the following specifications:

    TECHNICAL SPECIFICATIONS DIMENSIONS

    GENERAL GENERAL Technical name:

    DD1002HT+ cQP-2.4

    Nacelle diameter (minus rotors):

    1.34 m

    Max power output: 280 kW Length (nose-tail): 6.00 m Rotor diameter: 9.85m (max) Weight (dry): 13.5 tons

    Turbine principle:

    Gearless, variable speed, fixed pitch

    ROTOR Type: Bi-directional, fixed pitch

    No. of blades: 2 Swept area: 45.8 m2

    Rotational speed: Variable, 22 – 86.5 rpm

    Blade material: Composite

    9850

  • Tocardo Project Information Summary Jan 2017 v3 10

    3.2.1 Phase 1 – TFS Device

    Deployed picture and 3D picture of TFS with T2 turbine as deployed recently in the Netherlands

    The Temporary Foundation Structure (TFS) is based on the existing BlueTec device that was installed at Texel, The Netherlands. The deployment will be for a duration of 12 months, with a maximum of 18 months whilst the final foundation system, the UFS, is being constructed. The TFS will incorporate a Tocardo T2 tidal turbine as shown below.

    After 12 months the UFS will replace the TFS. The turbine and electrical system of the TFS will be transferred to the UFS unit during Phase 2 of the project. The UFS will be installed at berth 6.

  • Tocardo Project Information Summary Jan 2017 v3 11

  • Tocardo Project Information Summary Jan 2017 v3 12

    Sc

    Schematic of TFS unit with Tocardo T2 turbine attached. For illustrative purposes only.

    The BlueTec floating foundation has been operating successfully in waters off the shore at Texel in the Netherlands since June 2015. The floating tidal turbine foundation was developed by Bluewater and the demonstration project was realized by a consortium of partners. Tocardo was part of this consortium. Following this project in the Netherlands, Tocardo are now looking to clean and refurbish this device and transport it to EMEC in order to demonstrate its capability in a higher current flow regime as experienced in the Fall of Warness. The TFS will be held on station using 4 taut mooring lines consisting of nylon rope, steel chain, a steel anchor base frame with further chain loaded on top to form the gravity base clump anchor. Being a surface floating platform, which is directly accessible with a boat, it offers relatively good, easy access to the on-board turbine power system for O&M.

  • Tocardo Project Information Summary Jan 2017 v3 13

    3.3 Phase 2 – Universal Foundation Structure (UFS) For the second phase of the project Tocardo will install its Universal Foundation Structure (UFS). This unit is designed to support five Tocardo T2 turbines using a semi-submersible structure which is stabilised by its low centre of gravity and the mooring system (see following pictures). The semi-sub is a low-wave motion floating device. Inside the watertight hull, all low-voltage and medium voltage power systems are fitted and accessible for commissioning and maintenance.

    Illustration of UFS with 5 T2 turbines

    3D image of UFS unit moored in position

  • Tocardo Project Information Summary Jan 2017 v3 14

    When in normal operation, the U-shaped body is largely submerged. Only the two turrets are visible at the surface of the water. The design is aimed at safe and easy access using small vessels. Also, deployment and installation of the device is done with small vessels of the multi-cat type. The device can be towed from the deployment harbour to the offshore installation site. At the site the mooring system will be pre-installed and there will only be a quick hook-up operation required of connection mooring lines and subsea cable. Servicing requirements of the turbines themselves should be very limited during its life time. This will only occur due to unforeseen damage or unforeseen breakdown. All underwater parts are designed for 20 years maintenance free. Most servicing actions are expected to be on the electronics of the power and control systems that are inside the hull of the floating foundation and can be easily accessed using a small vessel. Still, it is expected that during its 18.5 year operational life time inspection and repairs are required on the turbines. For this Tocardo is developing safe and low-risk marine operations. For some repairs it will be required to remove the platform from its mooring system and tow it back to the harbour. Any required repairs on the turbines may be executed offshore by lifting the turbines above water using special tools. Tilting the UFS can be done at a nearby, more sheltered area. This can be near the pier of Eday or at the Shapinsay test berth of EMEC. No deposits will be made on the seabed during this operation. Details of the operation and location will be worked out in an O&M manual.

    3.4 Cables

    At both berths, a subsea cable is already present. The cable works in this project will involve connection of cable tails to this existing cable. Phase 1: The cable of the temporary siting station (Scotrenewables SR250 berth) is capable of transporting the power of one T2 turbine to EMEC’s shore station at Eday. After hoisting up the end of the cable, a cable connector will be fitted. On the other side of the connector a tail-cable is connected that will form the ‘dynamic’ cable between existing cable end on seabed, up to the TFS. The tail cable will have rubber bend restrictors over it that stiffen the cable. The cable is then protected against chafing against parts of the TFS and against bending of the cable. The tail cable is aligned in the direction of the current to minimize sideways loading. Enough space will be available to install and de-install the cable and/or mooring lines without interference between them. Phase 2: The cable at berth 6 is the standard installed export cable from EMEC. A recent study indicated that the current status is good. At the end of this cable a connector is attached. A tail cable with protection likely to be similar to that described for the TFS, will be installed from the connector to the UFS. The exact type of protection is currently being investigated by a specialist company. The assumption is that Split Shells from iron will be used.

    TECHNICAL SPECIFICATIONS

    GENERAL

    Technical name: UFS5T

    Weight operational: 490t

    Dry weight: 410t

    Number of turbines 5

    Total power output 1,4MW

    DIMENSIONS

    Depth below water surface: 23,7m

    Piercing height above water level: 3m

    Width between center verticals 12,9m

    Width with turbines 35,7m

    length 10m

  • Tocardo Project Information Summary Jan 2017 v3 15

    3.5 Mooring Principles The TFS will be installed at a temporary siting station that will utilise the cable currently owned and maintained by Scotrenewables. Discussions have been held with the company and an agreement has been reached for Tocardo to be able use this cable on a temporary basis for 12 months whilst the UFS unit is being constructed for deployment at EMEC’s berth 6. Once the UFS is ready for installation, the TFS will be removed prior to the UFS installation.

    3.5.1 Phase 1 TFS Device Tocardo intend to use a mooring system consisting of four anchor points holding the TFS in line. Depending on the final site positioning at a temporary siting station, all anchor points will be located at a water depth of approximately 37m. The mooring system will consist of nylon lines that run to ground chain which in turn attach to an anchor. The mooring spread of the TFS is approximately 380m total from end to end. Each mooring line will therefore be around 190m. As drilled anchors are not preferred due to the temporary character of phase 1, gravity (box) anchors are the best available option. The anchor will consist of a stiff welded, open box, max 8m x 8m, containing 73mm link mooring chains up to 100t per box. The area that will be in contact with the seabed will therefore be 256m2.

    Indicative mooring view of TFS (not to scale). Gravity anchors not shown here but will be used.

    3.5.2 Phase 2 UFS Device For the future phase 2, Tocardo intend to use a mooring system consisting of a similar principle as the TFS (and where feasible using components of the TFS system). It will consist of two anchor points holding the UFS in line. The mooring spread of the UFS is approximately 500m total. The length of the mooring lines will therefore be 250m. The anchor points will be located in water depths at approximately 34m. Different from the TFS, the mooring lines of the UFS will run to a bridle first, and from the bridle to a floater. From the floater, chains run to the anchor point.

    190m

    66m

  • Tocardo Project Information Summary Jan 2017 v3 16

    Sketch of UFS unit moored in position

    The UFS will be anchored in position using 2 anchor points each consisting of 500t steel chain contained within a steel frame of 12m x 12m. The height is low (up to 2m) as it is only the weight of the chain resting on the steel frame that will create the holding capacity. From the anchor, a chain is connected to a mid-column floater. The floater connects to a nylon mooring line. 40 Meters in front of the UFS, the nylon line ends in a bridle plate and then two mooring lines go to each side of the UFS. This set-up can handle extreme load cases with relative ease due to the elastic nature of the nylon and the mid column floater that keeps the necessary tension in the lines. The volume of the mooring line floater is: 15t The distance between UFS and the floater is: 100m The depth of the mooring line floater is: 15m The gravity anchor consists of a stiff low profile, open box similar to that utilised for the TFS. In the box, heavy chain is lowered. The chain can be lowered controllably and results in enough weight to keep the anchor in place. The required weight of the clump chain is 500t per anchor. This set-up is tested for different sea conditions, not only for EMEC, but also for the other known sites. The simulation was run in Orcaflex®. A recent model tank test confirmed the model and the ability to handle the extreme load cases.

    Gravity anchor

    Chain Floater Nylon line to

    connection points Bridle plate

    Nylon line

  • Tocardo Project Information Summary Jan 2017 v3 17

    3.6 Materials used Below are two tables containing the lists of materials used for installation of the devices. Table A – TFS Device All below mentioned materials are calculated with the current status of the design.

    Type of Deposit

    Nature of Deposit (P = Permanent for 12 months, T = Temporary)

    Deposit Quantity (tonnes, m3, etc.) Maximum quantities stated

    Steel/Iron

    P 35t chains (4x 70m)

    P 400t (4 x 100t) chain as clump weight anchors including box.

    P 55t steel structure (TFS)

    T 2t Installation vessel anchor (drag)

    P 1t cable connector

    Plastic/Synthetic P 10t Nylon mooring lines (4 x 40m)

    T 1t Mooring lines installation vessel

    Cable P 100m tail cable. The existing cable is already installed.

    Turbine P 1 x 16t

    No other types of deposits (composites, plastics, timber, stone, gravel, sand, silt, rock, other metals than steel) are foreseen. Table B – UFS Device All below mentioned materials are calculated with the current status of the design.

    Type of Deposit

    Nature of Deposit (P = Permanent for 18.5 years, T = Temporary)

    Deposit Quantity (tonnes, m3, etc) Maximum quantities stated

    Steel/Iron

    P 1300 t chains for anchors including box anchors

    P 450t chain between box anchor and floater

    P 2 x 60t mid-column floater

    P 390t steel UFS

    T 2t Installation vessel anchor (drag)

    P 5t cable connector as per spec EMEC

    Plastic/Synthetic P 20t Nylon mooring lines (2 x 100m + 4 x 40m = 360m)

    T 1t Mooring lines installation vessel

    Cable P 600m tail cable

    Turbines P 16t per turbine, 80t total

    Titanium/Aluminium P Active sonar. 32cm x 15cm (Dimension) 12kg (Weight)

    stainless steel and plastic with lead weights, or concrete

    P Gravity mounts for ADCP sonar equipment above

  • Tocardo Project Information Summary Jan 2017 v3 18

    No other types of deposits (composites, plastics, timber, stone, gravel, sand, silt, rock, other metals than steel) are foreseen. No materials installed as part of Tocardo’s proposed project will be left on the seabed at the berths following decommissioning of the project.

    3.7 Mounting scientific equipment Further details of monitoring equipment are found within the Phase 1 Project-specific Environmental Monitoring Programme (PEMP) issued with the Marine Licence application. It is planned to install and operate one or two Acoustic Doppler Current Profilers (ADCPs) similar to that shown in Figure 2.5 of the Project-specific Environmental Monitoring Programme (PEMP) if required for Phase 2. The ADCPs will be installed on the TFS device and mounted in a horizontal position. This allows Tocardo to examine the effects on water currents up and downstream of the device. No seabed mounting is required for the TFS. For Phase 2 deployment, it is planned that scientific equipment (including ADCPs) will be deployed on stand-alone gravity mounts located on the seafloor 30 - 45m in front of and behind the UFS device. The PEMP for Phase 2 will be developed in consultation with Marine Scotland and Scottish Natural Heritage (SNH) and submitted at least 3 months prior to construction.

  • Tocardo Project Information Summary Jan 2017 v3 19

    4. Installation method Both the TFS and UFS are floating devices which makes installation relatively simple and can be undertaken using smaller workboat type vessels such as multi-cats and tugs. Installation of both devices respectively, at the EMEC site will be undertaken in key stages beginning with the installation of the anchors. An installation plan is currently being developed in cooperation with EMEC and Leask Marine such that it will fit within the consent envelope and within the agreed dates. Further detail can be seen in the project Construction Method Statement which will be submitted with the Marine Licence Application.

    4.1 Phase 1: Hatston Pier is the preferred location for assembling and launch of the TFS unit due to the water depth at the pier and proximity in relation to the actual site at the Fall of Warness. Assembly and launch of the TFS at the pier will likely take a week or two after which it will be towed into position at EMEC’s test site, in the selected deployment location. The following activities are proposed:

    Construction and installation o Installation of vessel moorings (expected duration 2 days) o Installation of anchor frames, chain and attach moorings to anchors; (expected duration 4

    days) o Connection of TFS to moorings; (expected duration 0.5 day) o Connection of tail cable to Scotrenewables subsea cable; (expected duration 0.5 day) o Commissioning; (expected duration 2 days)

    Operation and maintenance (see Navigational Risk Assessment document and Project Environmental Monitoring Programme for further detail)

    Removal of TFS platform, umbilical cable, moorings and anchors; (expected duration 3 days)

    4.2 Phase 2: The UFS will be pre-fabricated, most likely in mainland Scotland (Nigg Yard) and will be transported fully assembled minus 1 turbine to Orkney. The UFS will be moored alongside Hatston Pier for assembly of the turbine and until safe installation can be undertaken.

    Construction and installation o Installation of vessel moorings. This may require the use of either a multicat workboat or an

    Anchor Handling Vessel (AHV) (expected duration 2 days) o Installation of anchor frames, chain and attach moorings to anchors; (expected duration 3

    days) o Connection of UFS to moorings; (expected duration 1 day) o Connection of umbilical cable to EMEC’s subsea cable; (expected duration 1 day) o Commissioning (expected duration 5 days)

    Operation and maintenance (Onboard inspection: once per 2 years, component replacement: once 10 year)

    Decommissioning of UFS device and equipment; (expected duration 3 days) Tocardo aims to use minimal vessels and vessel movements.

    4.3 Anticipated Vessel traffic to site Installation of each device will take several days (further detail on this can be found in the accompanying Construction Method Statement (CMS) submitted with the Marine licence application). Actions are planned such, that a minimum of vessels (movements) is needed. Despite the difference in size, both devices are deployed with the same method and the same fleet. It is expected that all installation phase durations are

  • Tocardo Project Information Summary Jan 2017 v3 20

    very equal. The UFS has more weight per anchor to install, but only requires 2 anchors. Connection subsea connectors and TFS or UFS require the same handling procedures. It is likely that the loadout of the devices and their respective moorings will take place from Hatston Pier, Kirkwall (Orkney) which is already well established as a loadout and O&M base for other tidal energy developers who have used the Fall of Warness test site. A transit route map for the vessel’s route options will be submitted with the Project Environmental Monitoring Programme (PEMP). The optimal route to the test site, which is also currently used by other developers, passes to the south of Shapinsay. Currently, the multicats of Leask Marine are incorporated in the installation plan. These are the MV C-Odyssey and the MV C-Chariot. Please see Appendix A for specifications. However, depending on the final weight of the Phase 2 UFS anchors, an Anchoring Handling Vessel (AHV) may be required to install these anchors. This will be confirmed within the next 6 months but for the purpose of this licence application, Tocardo wish to include the AHV as a potential vessel to be used.

    4.4 Device Monitoring Control and Maintenance System The complete TFS (and subsequent UFS) system with its sub-systems and their performances, are monitored online from Tocardo headquarters in Den Oever, The Netherlands. By analyzing the data, the performance of the systems is checked and in case of failure, these are identified. Changes in control strategies can be uploaded by Tocardo remotely. The EMEC control station at Eday will also be used to monitor the status and the performance of both the TFS during Phase 1 and then the UFS system in its entirety during Phase 2. The mooring lines for both units are designed for a single failure event, but in case of failure of a mooring line, an automatic alarm will be triggered enabling that appropriate emergency response to be actioned. The Emergency Response Plan (ERP) for Phase 1 has been developed and is submitted with the Marine Licence application. This Plan will be thoroughly communicated with EMEC, relevant stakeholders and involved third parties prior to deployment and installation. The ERP for Phase 2 is in draft and will be submitted prior to the commencement of Phase 2. Onsite maintenance for Phase 1 and the subsequent Phase 2, can be undertaken from a small workboat capable of enabling at least 2 personnel to be transferred to the unit for onboard inspection. During the maintenance visits, the systems will be visually checked for any inconsistencies. Re-calibration actions and check-up measurements will guarantee the performance of the system and its monitoring devices.

    4.5 Decommissioning Method Tocardo will provide a decommissioning plan set-up with a marine operations specialist. Tocardo will comply with site regulations and requirements regarding removal of the device and equipment on the seabed. For decommissioning of the system, the followings items can be considered:

    1. The tail cable on TFS is disconnected 2. The subsea connector and tail cable are hoisted up. 3. The connector and cables are disconnected from the export cable 4. The export cable is properly capped and lowered down. The location of the end-cap is reported. 5. The TFS is disconnected from its mooring lines and tugged to a harbor for dismantling. 6. The mooring lines are disconnected from their anchor points and removed from site. 7. Removal of gravity anchors, and installed at berth 6.

    A draft decommissioning plan will be submitted to BEIS prior to construction of Phase 1 of this project.

  • Tocardo Project Information Summary Jan 2017 v3 21

    4.6 Environmental and Navigational Risk Considerations EMEC has developed Navigational Risk Assessment and Environmental Appraisal for the Fall of Warness test site and together with their project team, Tocardo has developed Phase 1 and Phase 2 project specific annexes to these assessments. Key factors that Tocardo are aware of are proximity to the local ferry routes, fishing vessels operating in the area and other developers undertaking operations at the test site. Lessons are learned from the navigational risk assessment of ScotRenewables who installed their floating SR250 device (same size as TFS), at the same location as the TFS.

    4.6.1 Environmental Risks A Project-specific Environmental Monitoring Programme (PEMP) for Phase 1, has been developed by Aquatera Ltd and will be submitted with the Marine Licence application. A separate PEMP will be prepared for Phase 2 in consultation with Marine Scotland and SNH. This document will be submitted and agreed with MS-LOT and SNH at least 3 months prior to installation of the Phase 2 UFS unit.

    4.6.2 Navigational Risks Tocardo is providing an addendum to EMEC’s existing Navigational Risk Assessment for the Fall of Warness site. The Phase 1 project specific NRA will be submitted along with the Marine Licence application and will follow the EMEC guidance code. The Phase 2 NRA is being drafted and will be submitted prior to commencement of Phase 2. Both Phase 1 TFS unit and the Phase 2 UFS unit are floating, moored structures. Risks associated with loss of station, under keel clearance and collision will be fully considered in the NRA addendums.

    4.7 Project timeline milestones Table of (proposed) milestones:

    Contractual date [ref]

    Project date (information)

    X Effective date * 23 February 2016

    [3.7] PHASE 1 Mobilisation date * 1 February 2017

    [4.1.4] Installation date ** 28th February 2017

    [4.1.5] Cable Connection date ** 10 March 2017

    X First floating system producing 31 March 2017

    PHASE 2 Decommissioning of TFS followed by installation of UFS

    Summer 2018 Allow 3 months for works to be completed (includes weather windows etc.)

    [4.1.6] Disconnection date ** 1 April 2037

    [4.1.7] Decommissioning start date** 1 April 2037

    [4.1.7] Decommissioning end date** 31 May 2037

    [4.1.8] Demobilization date (= Mobilization date + 20 years) * 1 February 2037

    * Fixed ** Proposal