14 March 2017
Mr. Riyaadh Kara
Small Harbours and Coastal Property Development Unit
TNPA Port of Saldanha SEA Workshop
2
SMALL HARBOURS DEVELOPMENT UNIT
3
STRUCTURE OF THE PRESENTATION
1. BACKGROUND
2. HIGH LEVEL ROLL-OUT PLAN
3. REPAIR PROGRAMME
4. PROJECT PROGRESS
5. WAY FORWARD
4
1. BACKGROUND
• The Small Harbours Unit was established in 2015 toensure the development of the proclaimed fishingharbours as well as the development of new harbours.
• Spatial and Economic Development Frameworks(SEDFs) were completed in 2014 for all 12 proclaimedfishing harbours.
• The SEDFs allow for a long term development plan atthe proclaimed fishing harbours.
• Coega Development Corporation was appointed inMarch 2016 to act as an implementing agent for theprogramme.
5
1. BACKGROUND
• Scope of Work
o Infrastructure Repairs & Maintenance
o Shore Crane Maintenance
o Maintenance to Slipways
o Shore Crane Replacement
o Dredging of Harbour Basins
o Removal of Sunken Vessels
6
2. HIGH LEVEL ROLL-OUT PLAN
• 2016/17 FY
‒ Planning 13No. Harbours
o Stage 1: Inception (End Oct)
o Stage 2: Concept & Viability (End Nov)
o Stage 3: Design Development (Mid Jan)
o Stage 4: Documentation (End Feb) & Procurement
(End May)
7
2. HIGH LEVEL ROLL-OUT PLAN
• Appointment of Contractors May 2017.
‒ Execution: 13No. Harbours
o Stage 5: Execution / Construction (Start – July/Aug ‘17)
o Stage 6: Close-Out & Handover (End of Project)
‒ Maintenance 13No. Harbours (Programme B)
o Planning & Procurement (Aug ‘16 – Mar ’17)
o Planned & Unplanned Maintenance / Facilities Management
(April ‘17 – March ‘19)
8
3. PROJECT PROGRESS – SALDANHA BAY
9
4. SEDF for Saldanha Harbour
CITY OF CAPE TOWN - 05 SEPTEMBER 2015
10
4. SEDF for Saldanha Harbour
1. The retention of current activities east of thegovernment jetty.
2. The development of a boat building and boatrepair hub around the slipway.
3. The development of a local mixed commercialservice node centrally within the harbour, toimprove local amenity and provide services for theharbour working population.
4. The development of office commercial land-useson the ridge taking advantage of physical locationand strategic position in a working harbour.
11
5. WAY FORWARD
Review and finalization of SEDFs:
o Review and analyse current SEDFs for the three (3)Proclaimed Fishing Harbours in the Saldanha BayMunicipality:
• Saldanha Bay
• Pepper Bay
• St Helena Bay
o Update SEDFs to align with the municipalities current IDP
o Work in conjunction with SBM to finalize and approve theroll out of SEDFs and produce a list of priority projects withinthe respective harbours.
o Adoption of SEDFs into Municipal IDPs
12
5. WAY FORWARD
o DPW is currently in the process of convening its ownOperation Phakisa: Small Harbours and State CoastalProperty Development Laboratory.
o Within the scope of the Laboratory, DPW intends todevelop new harbours along the coastline of South Africain the following areas:
• Port Nolloth – Northern Cape
• Port St Johns – Eastern Cape
• Port Edward – KwaZulu Natal
13
• National Department of Public Works (NDPW)
• Head Office: Public WorksCGO BuildingCnr Bosman and MadibaPretoria CentralPrivate Bag X65Pretoria0001
• Website: http://www.publicworks.gov.za
THANK YOU
END