TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... ·...

13
14 March 2017 Mr. Riyaadh Kara Small Harbours and Coastal Property Development Unit TNPA Port of Saldanha SEA Workshop

Transcript of TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... ·...

Page 1: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

14 March 2017

Mr. Riyaadh Kara

Small Harbours and Coastal Property Development Unit

TNPA Port of Saldanha SEA Workshop

Page 2: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

2

SMALL HARBOURS DEVELOPMENT UNIT

Page 3: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

3

STRUCTURE OF THE PRESENTATION

1. BACKGROUND

2. HIGH LEVEL ROLL-OUT PLAN

3. REPAIR PROGRAMME

4. PROJECT PROGRESS

5. WAY FORWARD

Page 4: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

4

1. BACKGROUND

• The Small Harbours Unit was established in 2015 toensure the development of the proclaimed fishingharbours as well as the development of new harbours.

• Spatial and Economic Development Frameworks(SEDFs) were completed in 2014 for all 12 proclaimedfishing harbours.

• The SEDFs allow for a long term development plan atthe proclaimed fishing harbours.

• Coega Development Corporation was appointed inMarch 2016 to act as an implementing agent for theprogramme.

Page 5: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

5

1. BACKGROUND

• Scope of Work

o Infrastructure Repairs & Maintenance

o Shore Crane Maintenance

o Maintenance to Slipways

o Shore Crane Replacement

o Dredging of Harbour Basins

o Removal of Sunken Vessels

Page 6: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

6

2. HIGH LEVEL ROLL-OUT PLAN

• 2016/17 FY

‒ Planning 13No. Harbours

o Stage 1: Inception (End Oct)

o Stage 2: Concept & Viability (End Nov)

o Stage 3: Design Development (Mid Jan)

o Stage 4: Documentation (End Feb) & Procurement

(End May)

Page 7: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

7

2. HIGH LEVEL ROLL-OUT PLAN

• Appointment of Contractors May 2017.

‒ Execution: 13No. Harbours

o Stage 5: Execution / Construction (Start – July/Aug ‘17)

o Stage 6: Close-Out & Handover (End of Project)

‒ Maintenance 13No. Harbours (Programme B)

o Planning & Procurement (Aug ‘16 – Mar ’17)

o Planned & Unplanned Maintenance / Facilities Management

(April ‘17 – March ‘19)

Page 8: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

8

3. PROJECT PROGRESS – SALDANHA BAY

Page 9: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

9

4. SEDF for Saldanha Harbour

CITY OF CAPE TOWN - 05 SEPTEMBER 2015

Page 10: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

10

4. SEDF for Saldanha Harbour

1. The retention of current activities east of thegovernment jetty.

2. The development of a boat building and boatrepair hub around the slipway.

3. The development of a local mixed commercialservice node centrally within the harbour, toimprove local amenity and provide services for theharbour working population.

4. The development of office commercial land-useson the ridge taking advantage of physical locationand strategic position in a working harbour.

Page 11: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

11

5. WAY FORWARD

Review and finalization of SEDFs:

o Review and analyse current SEDFs for the three (3)Proclaimed Fishing Harbours in the Saldanha BayMunicipality:

• Saldanha Bay

• Pepper Bay

• St Helena Bay

o Update SEDFs to align with the municipalities current IDP

o Work in conjunction with SBM to finalize and approve theroll out of SEDFs and produce a list of priority projects withinthe respective harbours.

o Adoption of SEDFs into Municipal IDPs

Page 12: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

12

5. WAY FORWARD

o DPW is currently in the process of convening its ownOperation Phakisa: Small Harbours and State CoastalProperty Development Laboratory.

o Within the scope of the Laboratory, DPW intends todevelop new harbours along the coastline of South Africain the following areas:

• Port Nolloth – Northern Cape

• Port St Johns – Eastern Cape

• Port Edward – KwaZulu Natal

Page 13: TNPA Port of Saldanha SEA Workshop - Amazon S3s3-eu-west-1.amazonaws.com/s3live.slrconsulting... · 2. HIGH LEVEL ROLL-OUT PLAN • Appointment of Contractors May 2017. ‒ Execution:

13

• National Department of Public Works (NDPW)

• Head Office: Public WorksCGO BuildingCnr Bosman and MadibaPretoria CentralPrivate Bag X65Pretoria0001

• Website: http://www.publicworks.gov.za

THANK YOU