TMA Installation EIB

download TMA Installation EIB

of 7

Transcript of TMA Installation EIB

  • 7/28/2019 TMA Installation EIB

    1/7

    TMA Installation

    Prepared by Owner Replace Date Revision Reference

    Usman Amjad (RAN) N.A. 19th Feb 2010 A EIB-XXX-RAN-TMA

    1

    EngineeringInformationBulletin

    EIB-XXX-RAN-TMA

    TMAINSTALLATIONPROJECT

  • 7/28/2019 TMA Installation EIB

    2/7

    TMA Installation

    Prepared by Owner Replace Date Revision Reference

    Usman Amjad (RAN) N.A. 19th Feb 2010 A EIB-XXX-RAN-TMA

    2

    Contents

    Introduction .............................................. ......................................... ................................ 3

    Distribution list ................................................................................................................ 3

    Purpose ........................................... ............................................. ........................................ 4

    Step by Step Procedure ........................................ ................................................. ........ 4

    List of KPIs .......................................................................................................................... 5

    Flow Chart .......................................................................................................................... 6

  • 7/28/2019 TMA Installation EIB

    3/7

    TMA Installation

    Prepared by Owner Replace Date Revision Reference

    Usman Amjad (RAN) N.A. 19th Feb 2010 A EIB-XXX-RAN-TMA

    3

    Introduction

    This EIB describes the Procedure of TMA installation project in CMPak Network

    Distributionlist

    Personals working in the RAN Optimization, RAN Planning, OMC

    Name/Distribution

    List

    Name

    Title

    Mr. Xu Haiyong CTO

    Mr. Zhang Bo Advisor to CTO

    Mr. Cyrus Sikandir Director O&M

    Mr. Arshad Usman Director NP&S

    Mr. Khurram Alvi Director Rollout

    Mr. Syed Ahmed Hassan Sr. Manager O&MMr. Muhammad Adeel Israr Sr. Manager O&M

    Mr. Asim Suleman RCTO North

    Mr. Syed Wajid Ali RCTO South

    Mr. Nasir Qayyum RCTO CentralII

    Mr. Imran Zafar RCTO CentralI

    Mr. Kamran Haider Manager RAN Planning HQ

    Mr. Sumair Chaudhary Manager RAN CentralI

    Mr. Syed Muhammad Bilal Manager RAN North

    Mr. Mudassir Hussain Manager RAN South

    Mr. Muhammad Basharat Ali Team Lead RAN CentralII/III

  • 7/28/2019 TMA Installation EIB

    4/7

    TMA Installation

    Prepared by Owner Replace Date Revision Reference

    Usman Amjad (RAN) N.A. 19th Feb 2010 A EIB-XXX-RAN-TMA

    4

    Purpose

    Tower Mounted Amplifier is used to minimize the path imbalance due to weak uplink signal

    strength on a cell. TMA also enhances the uplink signal strength in order to reduce the ping pong

    handovers due to weak uplink. TMA will be installed in CMPak network to increase uplink signal

    strength and to improve customers perception.

    StepByStepProcedure

    # Step Responsibility DescriptionStep 1 Choose the right Cell* RAN

    Optimization

    This is very important for TMA project to choose the right cell

    for TMA use. RAN Optimization team will select the list of cells

    where TMA is required. This will be done by monitoring cell

    statistical data

    Step 2 EAS Dry Connection

    Availability

    FOPs It is responsibility of FOPs to make sure that at least one dry

    connection is available for selected cell for External Alarm

    Patching. This can also be done by removing already patched

    alarms having least importance.

    Step 3 Project Execution Plan

    and Timeline

    Vendor Final list of cells will be given to the vendor to submit the

    project execution plan and timeline accordingly

    Step 4 Assignment of WorkOrder RANOptimization

    and OMC

    A 12 hours work order will be assigned to vendor to performinstallation activity, as this activity involves sector lock.

    Step 5 Project Execution Vendor TMA installation will be performed by Vendor according to the

    submitted plan

    Step 6 Site Access FOPs CMPak FOPs will be responsible to make access to the sites for

    vendor to install TMA.

    Step 7 TMA Installation and

    EAS Patching

    Vendor Vendor will be responsible for TMA installation and External

    Alarm patching for the cell

    Step 8 Initial Test* FOPs and

    Vendor

    Along with the Vendor Fops will conduct the initial test before

    and after the activity if all installations are done correctly

    Step 9 Removal of Snags, if

    any

    Vendor In case of any service affecting snags it shall be removed

    immediately, for other Vendor will have 2 days to fix the issue.

    Step10

    RF PerformanceAnalysis*

    RANOptimization

    After TMA installation and removal of all Snags, RANOptimization will monitor the stats and prepare benchmark

    report of the change. In case of any ambiguities found FOPS and

    Vendor will be intimated.

    Step

    11

    TMA PAT RAN

    Optimization,

    FOPs

    After monitory for 7 days from installation of TMA, RAN

    Optimization and FOPs will sign the PAT document.

    *Further explained below

  • 7/28/2019 TMA Installation EIB

    5/7

    TMA Installation

    Prepared by Owner Replace Date Revision Reference

    Usman Amjad (RAN) N.A. 19th Feb 2010 A EIB-XXX-RAN-TMA

    5

    Howtochoosetherightcell:

    It is very important to choose the right cell to install TMA. This can be done by analyzing statistical

    data and user behaviour.

    Path Imbalance (ve value) depicts weak uplink signal strength, cells with high pathimbalance values

    High number of ping pong uplink handovers for a cell due to weak uplink signalstrength

    High number of call drop rate due to weak uplink signal strength Poor uplink signal quality due to weak signal strength Average high TA for the cell Recent Alarms on the cell Hardware faults that may impact path balance Cell should be selected on the basis of at least 15 days trend

    InitialTest:

    BeforeTMA

    Installation

    Following test must be conducted before the TMA is installed on the cell. This will be performed by

    vendor and CMPak FOPs

    Complete health check of cell Antenna Physical Parameters (Azimuth, Tilt, Height) VSWR TRX Power Total Output Power Cable Loss

  • 7/28/2019 TMA Installation EIB

    6/7

    TMA Installation

    Prepared by Owner Replace Date Revision Reference

    Usman Amjad (RAN) N.A. 19th Feb 2010 A EIB-XXX-RAN-TMA

    6

    AfterTMAInstallation

    Following test must be conducted after the TMA is installed on the cell. This will be performed by

    vendor and CMPak FOPs

    Complete health check of cell Antenna Physical Parameters (Azimuth, Tilt, Height) VSWR TRX Power Total Output Power Cable Loss Installation should be as per the agreed layout provided by the vendor. Tagging should be complete (for TMA, Alarm cables, Jumpers) Proper grounding of PDU and TMA. Proper power connections of PDU in rectifier with suitable wiring connections and Tee

    Bias.

    All alarms are checked and removed. Cable loss, insertion loss etc. should be as per thebelow the specified threshold.

    Weather proofing and finishing tape on jumper cables and connectors should beinstalled.

    Proper fixing of TMA on mount (with appropriate clamps). Proper cable layout and is arrangement is done cleanly. All snags are removed. External alarms are working. VSWR is below the threshold. Ensure the entire check list is complete. PAT document is filled accurately.

  • 7/28/2019 TMA Installation EIB

    7/7

    TMA Installation

    Prepared by Owner Replace Date Revision Reference

    Usman Amjad (RAN) N.A. 19th Feb 2010 A EIB-XXX-RAN-TMA

    7

    KPIstobemonitored:

    Following are the KPIs to be checked/ verified after installation of TMA

    Path Balance Uplink level & Quality handover performance Downlink level and Quality handovers Call drop rate (Inc and Exc HO) Uplink level and Quality Samples VSWR