TM 661 Engineering Economics for Managers InvestmentWorth Investment Worth.

73
TM 661 Engineering TM 661 Engineering Economics for Managers Economics for Managers Investment Investment Worth Worth

Transcript of TM 661 Engineering Economics for Managers InvestmentWorth Investment Worth.

  • Slide 1
  • TM 661 Engineering Economics for Managers InvestmentWorth Investment Worth
  • Slide 2
  • Investment Worth MARR Suppose a company can earn 12% / annum in U. S. Treasury bills No way would they ever invest in a project earning < 12% Def: The Investment Worth of all projects are measured at the Minimum Attractive Rate of Return (MARR) of a company.
  • Slide 3
  • MARR MARR is company specific u utilities - MARR = 10 - 15% u mutuals - MARR = 12 - 18% u new venture - MARR = 20 - 30% MARR based on u firms cost of capital u Price Index u Treasury bills
  • Slide 4
  • Investment Worth Alternatives u NPW( MARR ) > 0Good Investment
  • Slide 5
  • Investment Worth Alternatives u NPW( MARR ) > 0Good Investment u EUAW( MARR ) > 0Good Investment
  • Slide 6
  • Investment Worth Alternatives u NPW( MARR ) > 0Good Investment u EUAW( MARR ) > 0Good Investment u IRR > MARRGood Investment
  • Slide 7
  • Present Worth Example: Suppose you buy and sell a piece of equipment. Purchase Price $16,000 Sell Price (5 years) $ 4,000 Annual Maintenance $ 3,000 Net Profit Contribution $ 6,000 MARR 12% Is it worth it to the company to buy the machine?
  • Slide 8
  • Present Worth 16,000 6,000 3,000 5 0 4,000 NPW= -16 + 3(P/A,12,5) + 4(P/F,12,5) 16,000 3,000 5 0 4,000
  • Slide 9
  • Present Worth 16,000 6,000 3,000 5 0 4,000 NPW= -16 + 3(P/A,12,5) + 4(P/F,12,5) = -16 +3(3.6048) + 4(.5674) 16,000 3,000 5 0 4,000
  • Slide 10
  • Present Worth 16,000 6,000 3,000 5 0 4,000 NPW= -16 + 3(P/A,12,5) + 4(P/F,12,5) = -16 +3(3.6048) + 4(.5674) = -2.916 = -$2,916 16,000 3,000 5 0 4,000
  • Slide 11
  • Annual Worth Annual Worth (AW or EUAW) AW(i) = PW(i) (A/P, i%, n) = [ A t (P/F, i%, t)](A/P, i%, n) AW(i) = Annual Worth of Investment AW(i) > 0 **OK Investment**
  • Slide 12
  • Annual Worth; Example Repeating our PW example, we have AW(12)= -16(A/P,12,5) + 3 + 4(A/F,12,5) 3,000 5 0 4,000 16,000
  • Slide 13
  • Annual Worth; Example Repeating our PW example, we have AW(12)= -16(A/P,12,5) + 3 + 4(A/F,12,5) = -16(.2774) + 3 + 4(.1574) 3,000 5 0 4,000 16,000
  • Slide 14
  • Annual Worth; Example Repeating our PW example, we have AW(12)= -16(A/P,12,5) + 3 + 4(A/F,12,5) = -16(.2774) + 3 + 4(.1574) = -.808 = -$808 3,000 5 0 4,000 16,000
  • Slide 15
  • Alternately AW(12) = PW(12) (A/P, 12%, 5) = -2.92 (.2774) = - $810 < 0 NO GOOD 3,000 5 0 4,000 16,000
  • Slide 16
  • Internal Rate of Return Internal Rate-of-Return IRR - internal rate of return is that return for which NPW(i*) = 0 i* = IRR i* > MARR **OK Investment**
  • Slide 17
  • Internal Rate of Return Internal Rate-of-Return IRR - internal rate of return is that return for which NPW(i*) = 0 i* = IRR i* > MARR **OK Investment** Alt: FW(i*) = 0 = A t (1 + i*) n - t
  • Slide 18
  • Internal Rate of Return Internal Rate-of-Return IRR - internal rate of return is that return for which NPW(i*) = 0 i* = IRR i* > MARR **OK Investment** Alt: FW(i*) = 0 = A t (1 + i*) n - t PW revenue (i*) = PW costs (i*)
  • Slide 19
  • Internal Rate of Return Example PW(i) = -16 + 3(P/A, i, 5) + 4(P/F, i, 5) 3,000 5 0 4,000 16,000
  • Slide 20
  • Internal Rate of Return Example PW(i) = -16 + 3(P/A, i, 5) + 4(P/F, i, 5) 3,000 5 0 4,000 16,000
  • Slide 21
  • Internal Rate of Return Example PW(i) = -16 + 3(P/A, i, 5) + 4(P/F, i, 5) i* = 5 1 / 4 % i* < MARR 3,000 5 0 4,000 16,000
  • Slide 22
  • Public School Funding
  • Slide 23
  • 216% 16 yrs
  • Slide 24
  • School Funding 12316 100 216 F = P(F/P,i *,16) (F/P,i *,16) = F/P = 2.16 (1+i * ) 16 = 2.16
  • Slide 25
  • School Funding 12316 100 216 (1+i * ) 16 = 2.16 16 ln(1+i * ) = ln(2.16) =.7701
  • Slide 26
  • School Funding 12316 100 216 (1+i * ) 16 = 2.16 16 ln(1+i * ) = ln(2.16) =.7701 ln(1+i * ) =.0481
  • Slide 27
  • School Funding 12316 100 216 (1+i * ) 16 = 2.16 16 ln(1+i * ) = ln(2.16) =.7701 ln(1+i * ) =.0481 (1+i * ) = e.0481 = 1.0493
  • Slide 28
  • School Funding 12316 100 216 (1+i * ) 16 = 2.16 16 ln(1+i * ) = ln(2.16) =.7701 ln(1+i * ) =.0481 (1+i * ) = e.0481 = 1.0493 i* =.0493 = 4.93%
  • Slide 29
  • School Funding 12316 100 216 We know i = 4.93%, is that significant growth?
  • Slide 30
  • School Funding 12316 100 216 We know i = 4.93%, is that significant growth? Suppose inflation = 3.5% over that same period.
  • Slide 31
  • School Funding 12316 100 216 We know i = 4.93%, is that significant growth? Suppose inflation = 3.5% over that same period. d ij j 1 04930350 1... d= 1.4%
  • Slide 32
  • School Funding 12316 100 216 We know that d, the real increase in school funding after we discount for the effects of inflation is 1.4%. So schools have experienced a real increase in funding?
  • Slide 33
  • School Funding 12316 100 216 We know that d, the real increase in school funding after we discount for the effects of inflation is 1.4%. So schools have experienced a real increase in funding? Rapid City growth rate 3% / yr.
  • Slide 34
  • Summary u NPW > 0 Good Investment
  • Slide 35
  • Summary u NPW > 0 Good Investment u EUAW > 0 Good Investment
  • Slide 36
  • Summary u NPW > 0 Good Investment u EUAW > 0 Good Investment u IRR > MARR Good Investment
  • Slide 37
  • Summary u NPW > 0 Good Investment u EUAW > 0 Good Investment u IRR > MARR Good Investment Note: If NPW > 0 EUAW > 0 IRR > MARR
  • Slide 38
  • Internal Rate of Return Internal Rate-of-Return IRR - internal rate of return is that return for which NPW(i*) = 0 i* = IRR i* > MARR **OK Investment** Alt: FW(i*) = 0 = A t (1 + i*) n - t PW revenue (i*) = PW costs (i*)
  • Slide 39
  • Internal Rate of Return Example PW(i) = -16 + 3(P/A, i, 5) + 4(P/F, i, 5) 3,000 5 0 4,000 16,000
  • Slide 40
  • Internal Rate of Return Example PW(i) = -16 + 3(P/A, i, 5) + 4(P/F, i, 5) i* = 5 1 / 4 % i* < MARR 3,000 5 0 4,000 16,000
  • Slide 41
  • Spreadsheet Example
  • Slide 42
  • Slide 43
  • Slide 44
  • Slide 45
  • Slide 46
  • IRR Problems 1,000 4,100 5,580 2,520 n 0123 Consider the following cash flow diagram. We wish to find the Internal Rate-of-Return (IRR).
  • Slide 47
  • IRR Problems 1,000 4,100 5,580 2,520 n 0123 Consider the following cash flow diagram. We wish to find the Internal Rate-of-Return (IRR). PW R (i * ) = PW C (i * ) 4,100(1+i * ) -1 + 2,520(1+i * ) -3 = 1,000 + 5,580(1+i * ) -2
  • Slide 48
  • IRR Problems NPV vs. Interest ($5) $0 $5 $10 $15 $20 $25 0%10%20%30%40%50%60% Interest Rate Net Present Value
  • Slide 49
  • External Rate of Return Purpose: to get around a problem of multiple roots in IRR method Notation: A t = net cash flow of investment in period t A t, A t > 0 0, else -A t, A t < 0 0, else r t = reinvestment rate (+) cash flows (MARR) i = rate return (-) cash flows R t = C t =
  • Slide 50
  • External Rate of Return Method find i = ERR such that R t (1 + r t ) n - t = C t (1 + i ) n - t Evaluation If i = ERR > MARR Investment is Good
  • Slide 51
  • Example MARR = 15% R t (1 +.15) n - t = C t (1 + i ) n - t 4,100(1.15) 2 + 2,520 = 1,000(1 + i ) 3 + 5,580(1 + i ) 1 i =.1505 External Rate of Return 0 1 2 3 1,000 4,100 5,580 2,520
  • Slide 52
  • Example MARR = 15% R t (1 +.15) n - t = C t (1 + i ) n - t 4,100(1.15) 2 + 2,520 = 1,000(1 + i ) 3 + 5,580(1 + i ) 1 i =.1505 ERR > MARR External Rate of Return 0 1 2 3 1,000 4,100 5,580 2,520
  • Slide 53
  • Example MARR = 15% R t (1 +.15) n - t = C t (1 + i ) n - t 4,100(1.15) 2 + 2,520 = 1,000(1 + i ) 3 + 5,580(1 + i ) 1 i =.1505 ERR > MARR Good Investment External Rate of Return 0 1 2 3 1,000 4,100 5,580 2,520
  • Slide 54
  • Critical Thinking IRR < MARR a.IRR < MARR < ERR b.IRR < ERR < MARR c.ERR < IRR < MARR
  • Slide 55
  • Critical Thinking IRR > MARR a.IRR > MARR > ERR b.IRR > ERR > MARR c.ERR > IRR > MARR
  • Slide 56
  • Savings Investment Ratio Method 1 Let i = MARR SIR(i) = R t (1 + i) -t C t (1 + i) -t = PW (positive flows) - PW (negative flows)
  • Slide 57
  • Savings Investment Ratio Method #2 SIR(i) = A t (1 + i) -t C t (1 + i) -t SIR(i) = PW (all cash flows) PW (negative flows)
  • Slide 58
  • Savings Investment Ratio Method #2 SIR(i) = A t (1 + i) -t C t (1 + i) -t SIR(i) = PW (all cash flows) PW (negitive flows) Evaluation: Method 1: If SIR(t) > 1 Good Investment Method 2: If SIR(t) > 0 Good Investment
  • Slide 59
  • Savings Investment Ratio Example SIR(t) = 3(P/A, 12%, 5) + 4(P/F, 12%, 5) 16 = 3(3.6048) + 4(.5674) 16 =.818 < 1.0 16 0 123 4 5 3 3 33 7
  • Slide 60
  • Savings Investment Ratio Example SIR(t) = 3(P/A, 12%, 5) + 4(P/F, 12%, 5) 16 = 3(3.6048) + 4(.5674) 16 =.818 < 1.0 16 0 123 4 5 3 3 33 7
  • Slide 61
  • Payback Period Method Find smallest value m such that where C o = initial investment m = payback period investment m t = 1 R t C o
  • Slide 62
  • Payback Period Example m = 5 years n c o 1 16 3 3 16 9 4 16 12 5 16 19 2 16 6 16 0 123 4 5 3 3 33 7 R t n 0
  • Slide 63
  • Capitalized Costs Example: $10,000 into an account @ 20% / year A = P(A/P, i, ) P = A / i.. AAA 10,000
  • Slide 64
  • Class Problem u A flood control project has a construction cost of $10 million, an annual maintenance cost of $100,000. If the MARR is 8%, determine the capitalized cost necessary to provide for construction and perpetual upkeep.
  • Slide 65
  • Class Problem 1 2 3 4... 100 100 10,000 P c = 10,000 + A/i = 10,000 + 100/.08 = 11,250 u A flood control project has a construction cost of $10 million, an annual maintenance cost of $100,000. If the MARR is 8%, determine the capitalized cost necessary to provide for construction and perpetual upkeep. Capitalized Cost = $11.25 million
  • Slide 66
  • Class Problem 2 u Suppose that the flood control project has major repairs of $1 million scheduled every 5 years. We now wish to re-compute the capitalized cost.
  • Slide 67
  • Class Problem 2 Compute an annuity for the 1,000 every 5 years: 1 2 3 4 5... 100 100 100 100 100 10,000 1,000
  • Slide 68
  • Class Problem 2 u Compute an annuity for the 1,000 every 5 years: 1 2 3 4 5... 100 100 100 100 100 10,000 1,000 A = 100 + 1,000(A/F,8,5) = 100 + 1,000(.1705) = 270.5
  • Slide 69
  • Class Problem 2 1 2 3 4 5... 170.5 170.5 10,000 P c = 10,000 + 270.5/.08 = 13,381 1 2 3 4 5... 100 100 100 100 100 10,000 1,000
  • Slide 70
  • How Many to Change a Bulb? How does Bill Gates change a light bulb?
  • Slide 71
  • How Many to Change a Bulb? How does Bill Gates change a light bulb? He doesnt, he declares darkness a new industry standard!!!
  • Slide 72
  • How Many to Change a Bulb? How many Industrial Engineers does it take to change a light bulb?
  • Slide 73
  • How Many to Change a Bulb? How many Industrial Engineers does it take to change a light bulb? None, IEs only change dark bulbs!!!!!