[Title will be auto-generated]
-
Upload
tina-williams -
Category
Documents
-
view
213 -
download
1
description
Transcript of [Title will be auto-generated]
Capital Project Solutions – June 2011
1
Conducting a Transition Readiness Assessment to
Ensure a Successful Facility Transition
Ray Walker
Principal Consultant
One of the biggest traps healthcare organizations fall into is the
belief that planning for a new facility is complete once the
structural design is finalized. In fact, the opposite is true. A new
facility provides an organization the ideal opportunity to
reevaluate and update their operational strategies and processes.
However, to truly capitalize on this opportunity, this must be
taken into account during design – prior to the start of
construction.
Given today’s economy, when planning a new facility, there is
tremendous pressure to quickly complete the design process and
start construction. Unfortunately, more often than not,
construction begins before the design is completed. Following
this path makes it virtually impossible to carefully and thoughtfully
map out the operational impacts of the new environment. Many
of the more complex operational issues to be implemented in the
new facility are only discussed at a high level during this initial
phase. Particulars are not discussed and it is merely assumed that
operational process flow changes will mesh with how the new
facility is constructed. Without careful planning and coordination,
the results can be a significant disconnect between what is built
and what is necessary to support operational strategies. In an
effort to manage the coordination between operational planning
and the physical environment, we encourage healthcare
organizations to begin Transition Planning as early in the project
schedule as possible, preferably beginning as soon as the design is
complete.
Transition Readiness Assessment
Per Webster’s Dictionary, Transition is defined as: “passage
from one state, PLACE, stage or subject to another”. A
successful transition from one facility to another is realized when
the completed facility and operational readiness merge, optimizing
Capital Project Solutions – June 2011
2
functional patient care activities. So how does a healthcare
organization know that they are ready to transition from one
building to another? What assurances do the executive leaders of
a hospital have that the plans to date are still in sync with how
the building is actually being constructed? These questions are
often answered during the Transition Planning process. To
initiate this phase, we recommend that healthcare organizations
conduct a Transition Readiness Assessment (TRA). TRA is
a gap analysis of the transition planning completed to date. It also
identifies items that remain to be completed and ultimately
results in a comprehensive plan to address all elements. The
phases of the assessment are quite similar to a physician treating a
patient. They are:
Discovery (History and Physical) – What information
is currently available relative to the proposed transition?
This involves initial data and information gathering along with
pre-session interviews.
Gap Analysis (Diagnosis) – Where are the gaps in what
is known and not known? What has already been done?
What still needs to be done?
Implementation Plan (Treatment Plan) – How can
we bridge the gaps in order to ensure everyone’s
expectations are aligned and we’re heading down the same
path together?
Five Steps to Complete TRA
1. Conduct Stakeholder/Staff Interviews: Key
stakeholders should be interviewed to gauge their current
understanding of the transition process, i.e.:
Will the location of the ancillary services change
how service is provided?
Conduct Stakeholder/
Staff Interviews
Evaluate Data,
Tools & Systems
Develop Team
Structure
Develop Budget & Schedule
Transition Implementation
Plan
Capital Project Solutions – June 2011
3
What model of care changes will take place in the
new space? Is the staff prepared for these
changes?
How will supplies be distributed in the new space?
Is this different from the current model?
2. Evaluate Data, Tools & Systems
Review contracts for services, furniture,
equipment, signage, etc.
Review inventory tracking logs.
Conduct way finding analysis and map traffic
patterns.
Review regulatory information and approvals.
Review Communication and Public Relations Plan.
3. Develop Transition Team Structure
Create the Transition Steering Committee.
Create the Operational Readiness Assessment
Team.
Create the Facility Readiness Assessment Team.
Ensure multi-disciplinary participation.
Establish clear expectations, roles and
responsibilities.
Ensure Integration of the transition teams with the
project delivery teams.
4. Develop Transition Budget & Schedule
The transition budget should include - move
company expenses, warehousing charges, training
expenses, marketing expenses, public relations
expenses, etc.
The transition schedule should be integrated with
the Project Delivery Team’s Construction
Schedule.
The transition schedule should include staff
training, furniture and equipment coordination,
stocking of supplies, programming and testing of
technology systems, final cleaning, etc.
5. Transition Implementation Plan
Based on the information gathered in the previous
steps, a Transition Implementation Plan can be
prepared that addresses the identified gaps.
Capital Project Solutions – June 2011
4
Will clearly state goals and objectives for the
project.
Will clearly state team member responsibilities.
Conclusion
Again, the first step in a successful transition plan is to recognize
that planning does not end with a complete design. If the
Transition Readiness Assessment process is followed,
chances for a successful transition will be significantly increased.
In addition to streamlining the move, the functionality of the new
space will be greatly improved which will provide substantial long-
term benefits and enable the leadership team to achieve the staff
and patient satisfaction that they originally sought at the onset of
the project.
Capital Project Solutions – July 2011
The Components of Transition Planning- Operational
Readiness
Stevie McFadden – Associate Consultant
Patrick E. Duke – Vice President
Last month we centered our discussion on the starting point for the
transition planning process – Transition Readiness Assessment
(TRA). The TRA sets the tone for the successful relocation of
staff, assets, supplies and patients from an existing space to a new
space. This month, and for the next two months, we will focus on
the three components of the transition planning effort after
completion of a TRA – Operational Readiness, Facility Readiness,
and Move Management.
What is Operational Readiness?
Operational Readiness involves planning for new processes and
practices that define the way an organization will conduct business
in a new facility. It requires an emphasis on review and design of
clinical and business operations to allow their future state to be in
harmony with the changed physical environment, thereby enabling
the organization to achieve desired outcomes. The effort to
achieve true Operational Readiness will involve education, training,
and orientation that must be effectively coordinated and balanced
with the Facility Readiness and Move Management components of
the overall transition planning work. If the future state of
operations was well defined and integrated into the design effort
from the onset of the project, achieving Operational Readiness will
be the result of more implementation planning and less process
redesign work later on.
There is often a perception that patient satisfaction and outcomes
will improve by virtue of facility improvements and the eventual
relocation into a new space. The reality is that without integrating
desired process improvement into the design and then educating
staff members on the benefits of adopting it, the new facility
becomes no more than an empty suit. While you may conduct a
successful move, you will not achieve true Operational Readiness
Capital Project Solutions – July 2011
and defeat the most likely primary driver for the new space – to
deliver more efficient patient care and improve outcomes.
When Should We Start Preparing for Operational
Readiness?
It is important that leaders in healthcare organizations and project
delivery teams understand the perspective of all staff members as
they are challenged to “think outside of the box” when developing
improved workflows in a new space. Staff members are prone to
becoming overwhelmed on projects because of the amount of
changes that must occur to their daily workflows in addition to the
changes in how they do everything from park to clock in and out
each day. The looming question is - How will I function in the new
facility given the changes it will bring? To answer this question and
reduce anxiety that can be associated with any change, we advocate
launching your transition planning effort after the Architect
completes their Design Development phase.
Traditionally, user groups made up of staff members are heavily
involved in the planning of the new facility from project inception
and through the Design Development phase. It is during this time
that interest and engagement is extremely high. Team members are
actively involved in discussions and meetings to plan what the new
facility will look like, identify how they can best move through the
space, and develop strategies to improve patient care. However,
typically a one to two year lull occurs after Design Development
ends and when transition planning begins where there is no follow-
up with the user groups. During this lull everyone returns to their
day jobs, and valuable knowledge of the why and how is lost.
Therefore, the previous alignment and buy-in around design and
workflow decisions is at risk. The typical result is a reeducation
process that results in decreased morale and changes on the project
that were not anticipated in the budget or schedule. Changes later
in the project are more costly and the schedule impacts much
harder to mitigate, as depicted in the figure.
How Do I Organize and Facilitate the Effort to Achieve
Operational Readiness?
Capital Project Solutions – July 2011
As you launch the transition planning process, it is important to first
establish an organizational structure that will support the critical
balance of the Facility Readiness, Operational Readiness and Move
Management components. While the user groups that were integral
to the design process can remain intact, they will need to do so
within the framework of an organizational structure that promotes
cross collaboration necessary to complete preparations for
relocating and operating in the new space.
Once an organizational structure is set-up the following steps are
necessary to begin the journey towards achieving and sustaining
Operational Readiness:
Determine Resource Loading Required to Complete
Planning Priorities – Healthcare organizations often struggle to
manage the day to day requirements and must maintain a lean
staffing model to be profitable. In order to prepare for relocation
and operation in a new facility, there will be many resources that
must go above and beyond their day to day duties. To avoid a
strain on resources and impact on current operations, it is
important to properly resource the transition planning effort.
Team Alignment Session – Initial alignment meetings with the
Team’s should be scheduled and facilitated. These sessions allow
for shared goals to be developed for the planning effort as a whole.
There also is consensus developed around expectations, roles, and
methods of planning effort. The decision making process and how
those decisions are communicated will also be agreed upon.
Development of a Baseline Activity Schedule – It is important
to develop a schedule of activities with each Team in coordination
with the overall Master Program Schedule for the facility’s design,
construction and installation of all furniture, fixtures, equipment and
technology systems. We believe sessions that feature interactive
and collaborative thought from key stakeholders and members of
focused teams are the most productive. It is imperative that the
“silo effect” is avoided during the entire planning process and all
events encourage collaboration and group thought. Development
of a baseline activity schedule will set a timeline for key activities
and tasks that must occur prior to the targeted move sequence.
The development of this work product will also highlight key
synergies between different teams.
Develop and Analyze Constraints – The development of a
baseline activity schedule will provide a more detailed path for each
focus team, but we find it necessary to go a step further and
Capital Project Solutions – July 2011
evaluate all constraints to meeting the milestone dates that were
agreed upon. There is a distinct difference in being organized for
presentation versus being organized for implementation. You must
utilize communication and tracking tools that allow for ease of
identifying and analyzing constraints and track where commitments
are being met by each team member being held accountable.
Complete Implementation Plans for Each Focus Team –
Each focus team should use the information from the Alignment
Session and Baseline Schedule Development Sessions to develop a
detailed Implementation Plan for their effort. The Implementation
Plan should feature a detailed team activity schedule, constraints
analysis, resource allocation and budget. Considering there are
typically a multitude of synergies between each transition team, it is
essential to have a process in place to update key milestones.
Present an Integrated Implementation Plan to Leadership
for Approval – We suggest that each Team Leader present their
Implementation Plan to Leadership for final approval. It is important
to do this work as early as possible to identify one-time operational
costs associated with the planning and implementation work in
addition to the year one operating budgets for the new facility.
Execute, Communicate, Adapt and Achieve – Each Team
should execute its plan and the Team Leader’s should ensure that
there is cross collaboration and communication as required. The
Transition Steering Committee meetings will provide an excellent
forum to identify any points of connectivity and clarification
required. The teams should be prepared to adapt to changes in the
field and stick to the structured process in place so they can
eventually achieve Operational Readiness.
Understand the Move is Not the End – Early in the planning
process it is important to not only plan to achieve Operational
Readiness for opening day, but have a process in place to help
sustain the positive changes you have made and identify areas for
improvement as well. Many organizations shut down their
transition planning organization after opening day, when in fact
there are still elements of transition going. We believe the
transition planning structure should remain in effect six (6) months
to a year after opening day. This provides a means to continuously
assess and evaluate the effectiveness of implementation and provide
support to all staff that are working to acclimate to their new
physical environment.
Capital Project Solutions – July 2011
Critical Success Factors in Achieving Operational
Readiness
Operational Readiness is a critical component to the overall success
of the transition planning process. It must be achieved in balance
with Facility Readiness and Move Management to ensure a smooth
transition. The following are critical success factors in achieving
Operational Readiness:
Begin the Project with the End in Mind – From the onset of
the project integrate operational planning into the design effort to
avoid more work later.
Avoid the Dangerous “Lull Period” – We recommend
beginning your transition planning effort after Design Development.
This will avoid a lull in action and participation by staff that
oftentimes plagues projects through cost overruns, schedule delays
and decreasing morale.
Set a Structured Process and Stick to It – A structured
process for transition planning and Operational Readiness needs to
be set early and you need to have alignment achieved around that
prior to developing implementation plans and continuing with your
planning efforts.
Plan for Beyond the Move – The move does not signify the end
of transition. This is often an enterprise wide event that affects all
systems, structures and staff members. Oftentimes, they need
more support in the days and months following the move than prior
to and during the move, keeping a structure in place to address
issues and communicate decisions and changes throughout the
organization.
Conclusion
We believe focusing on the factors above is an excellent start from
a macro level as you launch your transition planning effort and work
towards achieving true Operational Readiness. Next month, we will
discuss Facility Readiness.
Capital Project Solutions – August 2011
1
Facility Readiness- Is Your Team Ready For The
Move?
Gary P. Wilkinson
Senior Consultant
The “Three Legged Stool”
It is not a hyperbole to say that a well defined and executed
Relocation Plan resembles that of a three legged stool. Last
month, we discussed that Operational Readiness
involves planning for new processes and practices
that define the way an organization will conduct
business in a new facility. It requires an emphasis on
review and design of clinical and business operations
to allow their future state to be in harmony with the
changed physical environment, thereby enabling the
organization to achieve desired outcomes. The
effort to achieve true Operational Readiness will
involve education, training, and orientation that must
be effectively coordinated and balanced with the
Facility Readiness and Move Management
components of the overall relocation planning work.
If the future state of operations was well defined and
integrated into the design effort from the onset of
the project, achieving Operational Readiness will be
the result of more implementation planning and less process
redesign work later on in the project delivery process.
Running parallel to planning and coordinating the operational
components of the relocation strategy is the Facility Readiness
piece. There is an abundant amount of preparation that must be
done in order for the facility to be completed in time for the
patient move. The absence of a well defined Facility Readiness
Plan will pose the biggest risk of any activity associated with
relocating into a new facility.
Facility Readiness Plan
The development of a Facility Readiness Plan centers on
preparing the building and/or facility to accept patients and
Capital Project Solutions – August 2011
2
hospital operations. It is well understood at the most basic level
that in order to begin operations, construction will be complete
and all building systems will be installed. To make that happen it
is important to understand many of the more detailed
components that must be completed to ensure a successful
transition.
Equipment Procurement Process: Throughout the course of
the design and into construction, numerous planning and
coordination meetings will be held with almost every stake holder
in the hospital to review needs and requirements for medical
equipment. Careful planning as to architectural parameters as well
as mechanical, electrical, and plumbing details is needed to ensure
that the equipment will be installed correctly and prevent costly
change orders later down the road. One planning element that
cannot be avoided is the detailed coordination of the
procurement process associated with equipment. To guarantee
the successful distribution of the medical equipment there are
many key decisions that must be made:
Equipment Delivery Model - Will the medical
equipment be shipped “Just in Time” (JIT) or will an
offsite warehouse be used? Often times with larger
projects, the JIT method is extremely difficult due to
loading dock constraints, the size of the equipment and
number of pieces being delivered.
Hospital Receiving Methods - Once the medical
equipment is received at the facility there are numerous
hospital protocols that must be followed. How will the
following be coordinated?
o Asset tagging
o Biomedical checks
o Delivery of equipment to end point location
o Assembly of equipment
o Hanging and placement of equipment
A definitive equipment procurement process must be developed
to ensure that these questions do not become problems during
this chaotic phase of the project. It is recommended that a
mover/logistics firm be engaged after you complete the Design
Development phase to coordinate these activities. By hiring a
firm of this nature prior to the issuance of the purchase orders, a
Capital Project Solutions – August 2011
3
streamlined procurement and delivery process can be established;
thus eliminating chaos when the equipment is delivered.
IT Systems: Often in capital healthcare projects, the
Information and Technology budget is second only to that of
construction. For many healthcare facilities, the race to keep up
with the ever changing and advancing technologies is almost
unwinnable. With the vast amount of systems and applications
that are being installed and constructed in facilities today, it is
crucial to coordinate the following to prepare the facility for a
timely move.
Training, Training, and More Training - Prior
to moving into any facility and “Going Live”, the most
difficult and cumbersome aspect is getting all of the
end users trained and indoctrinated on all of the new
IT applications and systems. These systems not only
affect the clinicians; but registration, accounting, and
medical records applications as well. The most
critical element concerning training is to allow
enough time between the issuance of the Certificate
of Occupancy to the actual “Go Live” date. Far too
often, healthcare organization do not allow sufficient
time to properly train staff on new systems which
results in total chaos and confusion in the new facility.
Proper training is achieved when specific systems
training is combined with a comprehensive macro
level education on how each system works together
to influence workflows and operations. It is not
enough just to have the vendors come and train on
each system independently.
Develop and IT Implementation Team - The
best way to keep your project on schedule and
prepared for Move Day is to make sure that there is
a dedicated team to lead and coordinate all of the IT
related items. In most cases, there is a “Technology
Consultant” or “Low Voltage” planner that assists in
the design of the IT systems. However, to assume
that they will be there to follow through on the
installation, certification, testing, and training of the
systems is a mistake made by too many hospital
Capital Project Solutions – August 2011
4
leaders. The IT Team should be responsible for
identifying gaps in this process as well providing
solutions for the gaps. We recommend that you look
at options for contracting all technology systems
through a Technology Integrator rather than having
multiple systems installed by multiple parties that are
managed by multiple individuals.
Schedule and Accountability: There is no doubt that by the
time the project is coming to a close and the Facility Readiness
planning is in full swing, the owner has seen his/her fair share of
schedules. Information such as Overall Project Schedules, Near
Term Schedules, and Milestone Schedules
have all made their way across his/her
desk more than a time or two. However,
in the case of planning the “Go Live” date
and preparing the facility for the event, it
is necessary to develop the Relocation
Schedule so that dates and durations that
are critical can be successfully managed.
One helpful way to track the Relocation
Schedule is to form a Facility Relocation
Committee. This Committee should be
composed of key stakeholders from the
hospital Facility and Operational Team, IT
and Medical Equipment Representatives,
Construction Team, and hospital
administration. This Committee will hold teams accountable as
well as monitor and track the Relocation Schedule to ensure that
deadlines are being met.
Conclusion
There are many moving parts associated with preparing for
Facility Readiness. Success in this phase of the project is
dependent upon the attention given to detail in the
implementation of the building plan. Streamlining all medical
equipment and IT functions is just one step in the right direction
for a smooth relocation. Combined with oversight by the Facility
Relocation Committee of key stake holders and one can begin to
build a Facility Readiness Plan that is achievable and easily
implemented.
Capital Project Solutions – September 2011
1
Move Management - The "Big Move Day" Is Here
Patrick E. Duke, Senior Vice President
Gary Wilkinson, Senior Consultant
It All Comes Down to "The Big Move"
The day-to-day activities that are associated with delivering a
major healthcare capital project can be overwhelming. During
construction, it is easy to lose site of the goals that were
established at the onset of the project. Often times, these goals
are replaced with the single minded notion of “just finishing” and
“getting it complete”. The pressure to stay on schedule and
within budget, combined with change orders and patient and staff
disruptions often overshadow the need to properly plan the
physical move into the new facility. The cliché that “people only
remember the last three months of the project” is only too true.
All of the praise for proper programming, design, and
construction can be lost in an instance if the team fails to
properly plan the move.
Over the past three months, we have discussed the importance
of conducting a Transition Readiness Assessment as well as
Operational Readiness and Facility Readiness. These three critical
planning elements can ensure a smooth transition into the new
building. The time for planning will inevitably come to an end and
you must make "The Big Move" into your new facility. In this
edition of Capital Project Solutions, we will focus on:
Setting the date for the "The Big Move"
Setting up a command and communication structure
Recommended support after "The Big Move"
Setting a Date for "The Big Move"
Setting the date for “The Big Move” can often times become one
of the most discussed, debated and misunderstood issues during
Transition Planning efforts. The primary reasons are as follows:
Capital Project Solutions – September 2011
2
Lack of Clarity Around the Definition of
Contractor Completion - The Owner's project
management team should clearly define “Contractor
Completion” in the Construction Management
Agreement. We often see confusion because contracts
can use the terms Substantial Completion and Certificate
of Occupancy separately. It is preferred to link the two
and define Contractor Completion as the date that the
Owner can legally take control of the building after
receiving a Certificate of Occupancy (CO). A Contractor
that achieves Substantial Completion typically has
punchlist work and commissioning activities remaining
before CO can be achieved. Therefore, Owner
activation activities such as stocking and training cannot
begin until after CO and this should be the date defined
as Contractor Completion.
Lack of Clarity Around Inspection Process to
Determine Clinical Readiness - You are probably
well versed in routine or surprise inspections that occur
from your local, state and sometimes national health
officials and accrediting bodies. While some elements of
these inspections are similar to the inspection process to
determine clinical readiness, there are also some
differences. Because of the variability from state to state
and inspector to inspector, we recommend that
communication between the project delivery team and
inspection agency occur prior to project launch. This
communication should continue throughout the life of the
project in order to thoroughly understand all of the
requirements for clinical readiness inspections. The date
of "The Big Move" cannot be set with any accuracy until
you fully understand all of the requirements of clinical
readiness inspections.
Lack of Understanding of Time Required for
Activation Activities – By their very nature, healthcare
organizations are flexible and quite skilled at quickly
adapting to their environment so as to remain focused on
delivering quality patient care. As expected, they are well
versed in emergency preparedness. This trait, while
extremely positive when related to patient care, can
actually work against the need to provide adequate time
Capital Project Solutions – September 2011
3
to complete all activation activities. There is no doubt,
that given a deadline, the staff in a healthcare organization
will meet it and ensure that proper patient care is
delivered. Unfortunately, the amount of time that is
required for appropriate staff training and process
retooling is typically way underestimated. The result is
often an increase in cost and a decrease in efficient early
in the new facility's life cycle.
In our experience, there cannot be too much time
allotted for activation activities. While construction is
never an exact science it behooves the Owner to set a
date for "The Big Move" as early as possible. Once this
date has been established, a cascade of decisions can be
made. For example, if new services that require
additional FTE's will be added, recruiting must be factored
into the schedule. In addition, procuring a Relocation
Specialist (the physical mover) should happen sooner
rather than later. There are only a handful of companies
that specialize in large hospital moves and their calendars
are booked well in advance.
Considering all these factors and based on our experience over
the years, we recommend that a date be set for the "The Big
Move" that is no less than 60-90 days from Certificate of
Occupancy for smaller projects or those that are in ambulatory
settings. For larger and more complex projects, we recommend
that the date be a minimum of 90-120 days from Certificate of
Occupancy.
Setting Up a Command and Communication Structure
Given the complexities and risks surrounding the move to a new
facility, it is recommended that this task be approached in a
manner similar to an Emergency Preparedness situation. Many
hospitals utilize principles of the Hospital Emergency Incident
Command System (HEICS) and set up the requisite Incident
Command Center (ICC). Since healthcare staff is familiar with
these terms and procedures, it will be beneficial to closely mimic
this set-up for the command and communication structure to
Capital Project Solutions – September 2011
4
support "The Big Move". Some considerations in your plan
should be as follows:
Timing of Command Center Activation - The
physical move of contents may take place the weekend
prior to first clinical visit or for larger facilities it could
begin two to four weeks ahead. Typically, patient moves
occur in one day over a weekend. However, depending
on your volume, it may be best for your organization to
phase your patient moves. Regardless, we recommend
activating the Command Center to support the beginning
of the physical move. Obviously, there is a ramp up
period from the early days of your Command Center
operations to when you complete the move.
Keeping The Clutter Out - Especially on patient move
days, it is vital to include only essential Command Center
personnel who have a defined role in the process. Setting
a "Contractor & Vendor Support Room" that is linked by
communications with the Command Center is critical to
coordinate all activities. Should staff require systems
support during the patient move, contractors and
vendors can easily be dispatched from this area to the
trouble spot. Also, separate rooms for media, volunteers
and patient's families should be set up in a similar fashion.
Leverage Technology - The best Command Centers
we have encountered have been those that utilize the
facility technology to allow for enhanced monitoring and
communication. With proper planning, temporary
measures can allow for effective use of the facility
communication and monitoring systems even if the
Command Structure location is not part of a permanent
Central Command in the hospital. The Command
Center should be able to access all camera locations to
view activity, view bed management and have its own
unique phone number with an extension that is easy to
remember such as x6683 or "MOVE".
The Command Center is the epicenter of "The Big Move" and
should be activated when the physical move begins. Roles and
Capital Project Solutions – September 2011
5
responsibilities for all staff supporting "The Big Move" should be
well defined and only those essential to the Command Center
operations should occupy it. Other separate areas for groups
like contractors, vendors, media, volunteers and patient's families
should be designated and linked through the communications
systems to the Command Center to maintain a stable
environment during the patient move. A Command Center that
leverages technology systems in the new facility most effectively
allows for closer monitoring and better response time to any
issues that may arise.
Recommended Support After "The Big Move"
A common mistake in approach to transition planning is to close
the planning window at the conclusion of "The Big Move". The
reality is that transition does not stop at that point. It continues
past "The Big Move" and depending on the scope of the project,
can last months, even years longer. Failure to plan and support
staff post "The Big Move" can lead to low morale, low patient
satisfaction scores, increased operating costs and lower margins.
In looking beyond "The Big Move" you should consider the
following:
Command Center Operations Post Move – A
proven best practice is to keep the Command Center
open at least one week post "The Big Move". The hours
and staffing model should be discussed and adjusted based
on agreed need. Using the Command Center in this time
period to address issues provides a safety net to staff and
allows the organization to respond quickly to any issues
that may arise.
Maintain Transition Planning Structure Post Move
- The Transition Planning structure should be maintained
up to a year post "The Big Move". For the first 3 months
following the move, the Transition Steering Committee
should meet on a bi-monthly basis and address ongoing
issues related to the transition. Allowing these issues to
filter through existing management processes and systems
can lead to delays in response times and may strain
relationships with staff, patients and visitors.
Capital Project Solutions – September 2011
6
Gear Up Your Lean Team - Lean or Performance
Improvement teams, inside healthcare organizations,
should be integrally involved in the transition planning
effort and should be maintained post "The Big Move".
Modeling and development of processes and workflows
that aligned with your facility design prior to transition
need close evaluation and optimization in the near term
after the move. This level of support and monitoring will
address any bottlenecks that occur and provide yet
another critical support element to the staff.
It is easy to quickly return to operations as usual once "The Big
Move" is completed. Avoiding this scenario is highly
recommended. Staff, patients and visitors need time to adjust to
the new environment and new processes. Despite their unique
ability to adapt and adjust to new environments while maintaining
focus on patient care, staff involved in the transition are
experiencing change in a way that most have never experienced
before. This change needs to be recognized and a bridging
process should be developed post "The Big Move" to provide
critical support before returning to normal operating procedures.
Conclusion
The last thing anyone remembers about the project is "The Big
Move". In order to finish strong, it is imperative that adequate
time for all of the Owner's activation tasks be built into the
schedule initially. While you may begin with more time than you
think is necessary between Certificate of Occupancy and "The Big
Move", construction is never an exact science and contingency
time should be allocated. Given the dramatic change that many
staff will experience for the first time in their careers, providing a
support network dedicated to the move, and more importantly
post move, will be welcomed. Proper planning, flexibility and
team work will ensure that your new facility achieves your goals
and fulfills your vision.
CORPORATE OFFICE100 W. Franklin Street, Suite 200, Richmond, VA 23220 • 804.343.0161 • fax 804.343.0170
REGIONAL OFFICES2090 Columbiana Road, Suite 3500, Birmingham, AL 35216 • 205.259.1940 • fax 205.259.1941
8117 Preston Road, Suite 300, Dallas, TX 75225 • 214.706.9339 • fax 214.706.9341
401 Westpark Court, Suite 200, Peachtree City, GA 30269 • 678.783.1077 • fax 678.783.0120
1400 Broadfield Blvd, Suite 200, Houston, Texas 77084 • 281.994.7822 • fax 281.994.7801www.klmkgroup.com