Turkish Railways
TARGET 2023
MoT
Cengiz SİRİNOGLUTurkish State Railways (TCDD)
Content
Railway Investments in Turkey
First HSLs in Turkey
Socio-cultural effects of HSLs in Turkey
Some figures and new Projects
TCDD’s target for 2023
2
İSTANBUL
ESKİŞEHİRPolatlI
ANKARA
533 km
HSLs being constructed
HSLs already constructed
BİLECİK
ANKARA-İSTANBUL HIGH SPEED RAILWAY LINE PROJECT
WORKS OF ART: 755 IN TOTAL
Underpass : 112 Overpasses : 56
Bridges : 43 Culverts : 480
Viaducts : 21 Tunnels : 43
Excavation : 32 million m3 Filling : 19 million m3
Ankara-Eskişehir Section of Ankara-Istanbul HSL was inaugurated in 2009. Construction studiesbetween Eskişehir and İstanbul are going on.
Physical progress between Ankara and İstanbul is about 60 % .
Construction Studies started in 2004
3
20 reciprocal runs daily. 6 thousand pax at weekdays; 8 thousand pax travel at weekends.
5 million 867 thosand pax have been transported between March 13, 2009 and June 22, 2012.
ANKARA-İSTANBUL YÜKSEK HIZLI DEMİRYOLU PROJESİOPERATIONS ON ANKARA-ESKİŞEHİR HSL STARTED ON MARCH 13, 2009.
4
İSTANBUL
ESKİŞEHİRPolatlI
ANKARA
533 km
HSLs being constructed
HSLs already constructed
BİLECİK
From Ankara to İstanbul (YHT+Convnt. Train) 5,5 h
From Ankara to Bursa (YHT+Coaches) 4 h
From Ankara to Kütahya (YHT+Convnt. Train) 3 h
From Ankara to Eskişehir (YHT) 1,5 h 3,5 hours
7,5 hours
6,5 hours
4,5 hours
CONNECTIONS TO İSTANBUL, BURSA AND KÜTAHYA WERE SET WITH
CONVENTIONAL TRAINS AND COACHES
Habits of travelling changed after YHT and the cities have become the suburbs of the others.
A 16 % increase was observed in the total travelling demand.
In the distribution of the reasons for travelling; travels for tours, health and touristic aims have
increased from 15 % to 40 % with YHT.
5
ANKARA-İSTANBUL HIGH SPEED RAILWAY LINE PROJECT
ANKARA-ESKİŞEHİR SECTION
6
0
50.000
100.000
150.000
200.000
250.000
Ma
rt 0
9
Nis
an
09
Ma
yıs
09
Hazira
n 0
9
Te
mm
uz 0
9
Ağu
sto
s 0
9
Eylü
l 0
9
Ekim
09
Ka
sım
09
Ara
lık 0
9
Oca
k 1
0
Şu
ba
t 1
0
Ma
rt 1
0
Nis
an
10
Ma
yıs
10
Hazira
n 1
0
Te
mm
uz 1
0
Ağu
sto
s 1
0
Eylü
l 1
0
Ekim
10
Ka
sım
10
Ara
lık 1
0
Oca
k 1
1
Şu
ba
t 11
Ma
rt 1
1
Nis
an
11
Ma
yıs
11
Ha
zira
n 1
1
Te
mm
uz 1
1
Ağu
sto
s 1
1
Eylü
l 11
Number Of Pax transported on Ankara-Eskişehir HSL (March2009 – October 2011)
Number of YHT Passengers – Ankara-Eskişehir HSL
7
Share of TCDD which was 8% before was increased to 72%.
8
0
20.000
40.000
60.000
80.000
100.000
120.000
140.000
160.000
180.000
january february March April May June
2012 Eskişehir YHT Yolcu Sayısı
Number of pax transported on Ankara-Eskişehir HSL
in the last 6 months
Share of Means of transport before and after Ankara-Eskişehir HSL
Private
cars
37%
Conventi
onal
Train 8%
Coaches
% 55
BEFORE YHT (Before 13 March 2009 )
9
YHT -
HSL 70%
Coaches %
10
Convent.
train % 2
Private
Cars % 18
AFTER YHT (HSL)
FIGURES ABOUT ESKİŞEHİR-İSTANBUL HSL:
Physical progress in Eskişehir Station Pass: 57 %.
Physical Progress in Eskişehir-İnönü section: 92 %.
Physical progress in İnönü-Vezirhan section: 65 %.
Physical Progress in Vezirhan-Köseköy section: % 51 %.
ANKARA-İSTANBUL HIGH SPEED RAILWAY LINE PROJECT
ESKİŞEHİR-İSTANBUL HSL WILL BE TAKEN INTO OPERATION
AT THE END OF 2013
10
ANKARA-İSTANBUL HIGH SPEED RAILWAY LINE PROJECT
11
ANKARA-İSTANBUL HIGH SPEED RAILWAY LINE PROJECT
12
•The passenger share on Ankara-İstanbul, the most intense pas-senger and freight axel in Turkey will increase from 10 % to 78 %.1
• Travel time between Ankara and İstanbul will decrease to approximately 3 hours. 2
• With Marmaray entegration, seamless passenger transportation from Asia to Europe and vice versa will be realized. 3
• Social, economical and cultural interaction between Ankara, Eskişehir and İstanbul will increase.4
AFTER THE START OF OPERATIONS ON ANKARA-İSTANBUL HSL;
13
Polatlı
ANKARA
KONYA
212 km
HSLs being constructed
HSLs already constructed
HS Operations started on 24 August 2011 between Ankara and Konya.
Daily 16 Reciprocal runs.
975 thousand pax have been transported between 24 August 2011 and 22 June 2012.
WORKS OF ART: 264 in total
Underpasses: 83 Overpasses : 30
Bridges : 7 Culverts : 143
Viaducts : - Tunnels : 1
Excavation : 33 million m3 Filling : 13 milion m3
THE CONSTRUCTION STARTED ON ANKARA-KONYA HSL IN 2006
14
CONSTRUCTION STUDIES ON ANKARA-KONYA HSL
15
ANKARA-KONYA HSL
16
ANKARA-KONYA HSL, DOUBLE TRACK AND HIGH STANDARDS
17
• The distance was decreased from 612 km to 309 kms and Travelling time was decreased from 10,5 hours to 1h 4o min. 1
• Konya has become the suburb of Ankara; the capital city. 2
•Economical, social and cultural interaction increased between Ankara, Konya, Eskişehir and İstanbul.
3
• The number of the domestic tourists has increased in the these cities. Daily tours are organized between the said cities.. 4
• Contribution to the prevention of air pollution (especially byincreasing its market share by getting passengers from private carsand coaches).
5
• Avarage number of pax transported: weekdays; 4000, weekends5000. 6
AFTER THE START OF THE OPERATIONS ON ANKARA-KONYA HSL…
18
19
0
20.000
40.000
60.000
80.000
100.000
120.000
140.000
january february March April May June
107.782
84.90290.152
116.966 118.886124.254
Number of pax transported on Ankara-Konya HSL in
the last 6 months
Share of Means of transport before and after Ankara-Konya HSL
20
YHT0%
Coaches70%
Private Cars29%
Airway1%
Before YHT (HSL)
YHT (HSL)54%
Coaches
35%
Private Cars11%
Airways 0%
After YHT (HSL)
ANKARA
405 km
YOZGATYerköy
HSLs being constructed
HSLs already constructed
SİVAS
Physical progress of infrastructure works on Yerköy-Sivas section : 88 %.
CONSTRUCTION STUDIES ON ANKARA-SİVAS HSL STARTED ON 13 MARCH 2009
WORKS OF ART: 876 in total
Underpasses: 139 Overpasses : 67
Bridges : 16 Culverts : 551
Viaducts : 53 Tunnels : 50
Excavation : 68,5 million m3 Filling : 20 million m3
21
• It will constitute the east-west HS axle.1
• The existing Ankara-Sivas Railway line will be shortened from 602km to 405 km.2
• The existing travelling time between ankara and Sivas will be decreased from 12 hours to 2 hours..3
• The travelling time between İstanbul and Sivas will be decreasedfrom 21 hours to 5 hours. 4
• The number of the domestic tourists will be increased and thesocio-cultural and economical interaction between the said cities wilgrow.
5
AFTER THE START OF THE OPERATIONS ON ANKARA-SİVAS HSL…
22
CONSTRUCTION STUDIES ON ANKARA-SİVAS HSL
23
CONSTRUCTION STUDIES ON ANKARA-SİVAS HSL
24
SİVASERZİNCAN
235 km
HSLs to be constructed
HSLs already constructed
SİVAS-ERZİNCAN HSL PROJECT
Project works of Sivas-Erzincan HSL, the continuation project of Ankara-Sivas HSL, have been completed.
25
Polatlı
ANKARA
AFYONİZMİR
MANİSA624 km
HSLs to be constructed
HSLs already constructed
ANKARA-İZMİR HSL PROJECT
The tender for Polatlı-Afyon section have been finalized.
Project works for Afyon-Uşak-İzmir sections are going on.
26
ESKİŞEHİR
ANKARA
BURSABİLECİK
124 km
Polatlı
HSLs being constructed
HSLs already constructed
The site for Bursa-Yenişehir section was delivered and land acquisition has been started.
Project works for Yenişehir-Bilecik section are going on.
ANKARA-BURSA HSL PROJECT
27
ANKARA HIGH SPEED LINE STATION
TO BE TENDERED UNDER BOT SCHEME
28
PROJECTSAnkara High Speed Train Station
The tender procedures are completed
Area of usage : 180.000 m2 Hotel, shopping center, restaurants,indoor and outdoor parking lots, metro and suburban connection
MARMARAY PROJECT
Asian
Side
European
Side
GEBZE
ÜSKÜDAR
HALKALI
SİRKECİ
ISTANBUL STRAIT CROSSING
1. The Bosphorus Crossing (BC1)
– Immersed tube tunnel (1,4 km),
– Immersed tube depth is 60 m,
– 12 km bored tunnels & cut-cover tunnels,
– 4 new stations.
2. The Upgrading of the Commuter Rail (CR1/CR3)
– New high standard triple track line (~ 65 km),
– 37 new stations.
3. Procurement of new Rolling Stocks (CR2)
– 440 new train sets.
Total length : Approx. 77 km
– At grade, European side 19.6 km
– At grade, Asian side 43.4 km
– Bored tunnels 12.2 km
– Immersed tube tunnel 1.4 km
75.000 pax per hour in one direction / Total travel time: ~ 105 min.
A DREAM of 151 YEARS is becoming a REALITY !...
MARMARAY PROJECT
The Bosphorus Crossing (BC1)
HSLs will be increased to10.000 kms.
Total HSLs will be 3500 kms.
Total HSLs will be 6500 kms.
Total HSLs will be 10000 kms.
4.000 kms of newconventional
railway line will be constructed..
1.300 kms of newconventional line
will be constructed.
A total of 2600 kmsof new
conventional linewill be constructed.
A total of 4000 kmsof new
conventional linewill be constructed.
8.000 kms of linewill be electrified
and signalled.
4.000 kms of linewill be electrified
and signalled.
A total of 6800 kmsof line will be
electrified andsignalled.
A total of 8000 kmsof line will be
electrified andsignalled.
20122015
20162019
20202023
2023 RAILWAY TARGETS
32
K A R A D E N İ Z
MEVCUT YHT HATLARI
MEVCUT KONVANSİYONEL HATLAR
2011- 2015 YHT HATLARI
2011- 2015 KONVANSİYONEL HATLAR
2016- 2023 KONVANSİYONEL HATLAR
2016- 2023 YHAT HATLARI
HALEP
Güllük
Sincan Yerköy
Karasu
Ereğli
KartalSapancaHalkalı
Turgutlu
Torbalı
Manavgat
Alanya
Aliağa
Karkamış
HaburUlukışla
Yenice
Boğazköprü
Polatlı
Gemlik
Nusaybin
Cizre
Narlı
Hanlı
Mürşitpınar
ANKARAESKİŞEHİR
KAYSERİ
KONYA
SİVAS
ERZİNCAN
İSTANBUL
İZMİR
BALIKESİR BURSA
AFYON
UŞAKMANİSA
KARAMANANTALYA
BARTIN
TRABZON
KARS
MALATYA
ELAZIĞ
DİYARBAKIR
MARDİN
GAZİANTEP
AYDIN
ADANA
MERSİN
ADAPAZARI
EDİRNE
ŞANLIURFA
SAMSUN
ERZURUM
BİLECİK
Kurtalan
2023 RAILWAY TARGETS
Black sea
Medditerenean
Sea
The total rail network will be increased to 2023 a total of 25.940 kms by constructing
10.000 km of HS lines and 4000 kms of conventional lines.
Existing HSL
Conventional Lines in 2023
HSL to be constructed till 2023
ALEPPO
Güllük
Sincan Yerköy
Karasu
Ereğli
KartalSapancaHalkalı
Turgutlu
Torbalı
Manavgat
Alanya
Aliağa
Karkamış
HaburUlukışla
Yenice
Boğazköprü
Polatlı
Gemlik
Nusaybin
Cizre
Narlı
Hanlı
Mürşitpınar
ANKARAESKİŞEHİR
KAYSERİ
KONYA
SİVAS
ERZİNCAN
İSTANBUL
İZMİR
BALIKESİR BURSA
AFYON
UŞAKMANİSA
KARAMANANTALYA
BARTIN
TRABZON
KARS
MALATYA
ELAZIĞ
DİYARBAKIR
MARDİN
GAZİANTEP
AYDIN
ADANA
MERSİN
ADAPAZARI
EDİRNE
ŞANLIURFA
SAMSUN
ERZURUM
BİLECİK
Kurtalan
Black Sea
Mediterranean
Sea
Aeg
ea
nS
ea
33
It is aimed to increase the total length of the network to 25.940 km by constructing
approximately 10.000 km HSL and 4.000 km conventional lines untill 2023 the 100th
anniversery of the foundation of the Republic of Turkey.
THANK YOU
FOR YOUR ATTENTION
CENGİZ SİRİNOGLU
TCDD