Time at Large
Transcript of Time at Large
![Page 1: Time at Large](https://reader031.fdocuments.us/reader031/viewer/2022021213/577d263e1a28ab4e1ea0a2e1/html5/thumbnails/1.jpg)
8/4/2019 Time at Large
http://slidepdf.com/reader/full/time-at-large 1/2
X Network Access Message: The page cannot be displayed
Explanation: There is a problem with the page you are trying to reach
and it cannot be displayed.
Tr the follow in :
You are here:
Related Articles
ConstructionLaw
All Answers
Answers by Expert:
Ask Experts
Volunteer
Alina Valentina Oprea
Expertise
I can answer to questions
regarding FIDIC 1999
contracts, including practical
use of these conditions of
contract, as well as to
questions regarding dispute
boards, both from theoretical
and practical point of view. I
cannot answer to questions
related to procurement
process, except to some
(limited) extent.
Experience
implementation of works
contracts (FIDIC 1999)
financed by different financial
institutions, including
European Union; dispute
boards
Publications
see
http://alina.oprea.v.googlepag
es.com/publications ; DRBF
Forum Newsletter; Drumuri si
Poduri; Revista Constructiilor;
SIDiR Newsletter
Education/ Credentials
Graduated the University of
Civil Engineering Bucharest,
Faculty of Railways, Roads
and Bridges (1985-1990);
Trained under Mr. Gwyn
Owen’s pupilage scheme for
arbitrators/adjudicators under
Home Industry Construct ion Industry Construct ion Law Time at large
Advertisement
Construction Law /Time at large
Expert: Alina Valentina Oprea - 7/9/2010
Question
Dear,
1. Please explain me the basic concept of "Time at large"?
2. Secondly, if the contractual time of completion or Time of
completion after giving Extension of time has passed. Also
maximum Liquidated Damages has been levied. Than what to do,
if Employer donot want to terminate the contractor as work left is
less?
Answer
Dear Zafar,
Here are the answer to your questions, sent previously, as well.
1. “Time at large” concept deals with waiving the obligation of the
Contractor to comply with the Time for Completion when the
Employer prevented the Contractor to finalize the works within the
Time for Completion. It was used first in the Common Law area, when the mechanism of contract did not al low for
extension of time when the Employer did not fulfil l its obligations.
“Time at large” allows the Contractor to finalize the works within reasonable time, instead within the Time for
Completion time, when the actions or inactions of the Employer prevented the Contractor to finalize in time the works
For example, if the Employer did not grant the access to the site at the time foreseen in the contract, but later, and
the works were delayed because of this, and in the contract there is no mechanism which allows the Contractor toobtain extension of time for completion because of this late possession of site, then the time for completion, in case
the Contractor demonstrates the incurred delay and that no mechanism for granting extension of time because of the
Employer’s failure, becomes “time at large”, and the Contractor is allowed to finalize the works within a reasonable
time.
2. So, what to do when the works are not finalized, the time for completion has passed and the maximum amount of
Liquidated Damages has been levied… Many Employers ask themselves this question, when they do not want to
terminate the Contract, especially when there is not much works to be done. The answer is in the negotiating abilities
of the Employer and Engineer mainly, and in the wisdom of the Contractor, all of them being interested in keeping
their good name and reputation by finalizing a good piece of work. Another method, which could be complementary to
the first one, could be to find the actual reason of not finalizing the works by the Contractor – could be claims not
resolved, lack of resources or financial means from the Contractor. Discussions between the Parties, with the help of a
mediator or other neutral person, or even with the help of the Engineer – if the Parties do not have bad feelings
against him – could lead to agreed solutions to finalize the works in agreed conditions.
Best regards,
Alina
XNetwork Access Message: Thepage cannot be displayed
Explanation: There is a problem with the page you
and it cannot be displayed.
Try the following:
Refresh page: Search for the page again by clbutton. The timeout may have occurred due to
Check spelling: Check that you typed the Webcorrectly. The address may have been mistyped
Access from a link: If there is a link to the pafor, try accessing the page from that link.
If you are still not able to view the requested page, try cadministrator or Helpdesk.
Add to this Answ er Ask a Question
Excuses for Not Going to Work - Excuses for Missing Work for a Job Interview•
Facing Discrimination - Migraines•
Surgery Questions Work - Questions to Ask at Work Before Surgery•
Work Leaves and Career Changes - Pregnancy Over 35•
Job Interview Answers: Questions About Co-Workers and Supervisors•
kifle semu
Alina Valentina Oprea
Daniel Kazado
Florin NICULESCU
Shan Greer
John Dowse
Nasir Gilani Syed
Senthil Kumar
Sellamuthu
Bogdan Oprea
Liaqat Hayat
Peter M. Elliott
Page 1 oConstruction Law: Time at large, concept of time, zafar
3/16/20http://en.allexperts.com/q/Construction-Law-914/2010/7/Time-large-5.htm
![Page 2: Time at Large](https://reader031.fdocuments.us/reader031/viewer/2022021213/577d263e1a28ab4e1ea0a2e1/html5/thumbnails/2.jpg)
8/4/2019 Time at Large
http://slidepdf.com/reader/full/time-at-large 2/2
FIDIC mentoring scheme
(2006 – 2007)
©2011 About.com, a part of The New York Times Company. All rights reserved.
User Agreement Privacy Policy Encyclopedia
Browse Answers:
About Us Tell Friends How to Ask How to Volunteer FAQ Tech Support Top Experts Expert Login
By Category Alphabetically
Page 2 oConstruction Law: Time at large, concept of time, zafar
3/16/20http://en.allexperts.com/q/Construction-Law-914/2010/7/Time-large-5.htm