Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of...

12
Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the EU funds for 2007-2013 Krakow, Poland, November 25-26, 2005

Transcript of Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of...

Page 1: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

Threats to Danube river 2007 – 2013 ?

Ákos Éger, National Society of Conservationists

Friends of the Earth Hungary/CEE Bankwatch Network

Programming the EU funds for 2007-2013 Krakow, Poland, November 25-26, 2005

Page 2: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

Threats to Danube river 2007 – 2013 ?

Background

Danube and programming

„Beszédes” plan

Danube-Tisza Channel

What to do..

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

Page 3: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

Background

Danube: sensitive issue.

Political changes linked with the Danube river.

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

Page 4: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

Danube and programming

Danube river in the draft National Development Concept:

„..on the Hungarian section of Danube river .. aim is a homogeneous transport corridor.”

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

Page 5: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

„Beszédes” plan

Aim of the plan is to develope the Danube Valley

József Beszédes: big channel builder in the XIX. Century.

Made by local experts and Academic of Science with the support of the local politicians to influence programming.

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

Page 6: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

„Beszédes” plan

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

4 pillars of the plan

Dunabe-Tisza Interfluve Region

Ráckeve-Soroksár Region

Budapest

Danube Bend

Page 7: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

The Danube-Tisza Channel

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

History of the channel

Plans to connect the rivers since 1774.

Starting the construction several times.

1948: 10-15 km was built.

Page 8: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

The Danube-Tisza Channel

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

Channel as planned in 1948:

- 11 water-gate

- Water level:

Danube: 98,2 m

Maximim water gate: 212,76 m

Tisza: 80 m

- 32-33 m wide

- Suitable for 1000-1200 tonnes barges

Page 9: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

The Danube-Tisza Channel

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

WHY?

Desertification of the Region

Shipping

Competitiveness (yacht ports)

Agriculture / irrigation

Page 10: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

The Danube-Tisza Channel

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

Situation now:

Strong lobby with the „Beszédes” Plan.

Possible funding from the EU (estimated cost in 2004: 360 million € / 50 km motorway).

Developing Danube-Tisza Interfuve Region as an accepted major project for 2007-2013.

Content of the project?

Page 11: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

The Danube-Tisza Channel

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005

What we can do:

Strong lobby against the channel on all level, in time.

Greening the program „Developing Danube-Tisza Interfuve Region”.

Greening Danube part of NSRF and OPs of affected regions.

Cooperation just started between MoE and ENGOs on major projects.

Page 12: Threats to Danube river 2007 – 2013 ? Ákos Éger, National Society of Conservationists Friends of the Earth Hungary/CEE Bankwatch Network Programming the.

Thank you for your [email protected]

Programming the EU funds for 2007-2013 Krakow, Poland,November 25-26, 2005