Third Quarter 2017 Results - golarlng.com/media/Files/G/Golar-Lng/documents/presentation/... ·...
-
Upload
nguyenxuyen -
Category
Documents
-
view
213 -
download
0
Transcript of Third Quarter 2017 Results - golarlng.com/media/Files/G/Golar-Lng/documents/presentation/... ·...
© Golar LNG Limited
Third
Quarter
2017
Results
© Golar LNG Limited
FORWARD
LOOKING
STATEMENT
2
This press release contains forward-looking statements (as defined in Section 21E of the SecuritiesExchange Act of 1934, as amended) which reflects management’s current expectations, estimates andprojections about its operations. All statements, other than statements of historical facts, that addressactivities and events that will, should, could or may occur in the future are forward-looking statements.Words such as “may,” “could,” “should,” “would,” “expect,” “plan,” “anticipate,” “intend,” “forecast,”“believe,” “estimate,” “predict,” “propose,” “potential,” “continue,” or the negative of these terms andsimilar expressions are intended to identify such forward-looking statements. These statements are notguarantees of future performance and are subject to certain risks, uncertainties and other factors, some ofwhich are beyond our control and are difficult to predict. Therefore, actual outcomes and results may differmaterially from what is expressed or forecasted in such forward-looking statements. You should not placeundue reliance on these forward-looking statements, which speak only as of the date of this press release.Unless legally required, Golar undertakes no obligation to update publicly any forward-looking statementswhether as a result of new information, future events or otherwise.
Among the important factors that could cause actual results to differ materially from those in the forward-looking statements are: changes in LNG carriers, FSRU and floating LNG vessel market trends, includingcharter rates, ship values and technological advancements; changes in the supply and demand for LNG;changes in trading patterns that affect the opportunities for the profitable operation of LNG carriers,FSRUs; and floating LNG vessels; changes in Golar’s ability to retrofit vessels as FSRUs and floating LNGvessels and in our ability to obtain financing for such retrofitting; increases in costs; changes in thetimeliness of the Hilli Episeyo (the "Hilli") commissioning; changes in our ability to close the sale of theequity interests in Hilli on a timely basis or at all; our ability to make additional equity funding payments toGolar Power and OneLNG to meet our obligations under each of the respective shareholders' agreements;changes in the availability of vessels to purchase, the time it takes to construct new vessels, or the vessels’useful lives; changes in the ability of Golar to obtain additional financing; changes in Golar’s relationshipswith major chartering parties; changes in Golar’s ability to sell vessels to Golar LNG Partners LP; Golar’sability to integrate and realize the benefits of acquisitions; changes in rules and regulations applicable toLNG carriers, FSRUs and floating LNG vessels; our inability to achieve successful utilization of our expandedfleet or inability to expand beyond the carriage of LNG and provisions of FSRUs particularly through ourinnovative FLNG strategy and our JVs; changes in domestic and international political conditions,particularly where Golar operates; as well as other factors listed from time to time in registrationstatements, reports or other materials that we have filed with or furnished to the Securities and ExchangeCommission, or the Commission, including our most recent annual report on Form 20-F.
As a result, you are cautioned not to rely on any forward-looking statements. Actual results may differmaterially from those expressed or implied by such forward-looking statements. The Company undertakesno obligation to publicly update or revise any forward-looking statements, whether as a result of newinformation, future events or otherwise unless required by law.
© Golar LNG Limited
Financial Highlights
4
Unaudited Audited
(USD millions) Q3 Q2 Q3 12 months to
2017 2017 2016 Dec-16
Total operating revenues 32.4 28.4 22.3 80.3
Voyage, charter-hire and commission expenses
Grand charter and fair value guarantee (1.0) (0.8) (5.8) (22.3)
Other voyage expenses (12.1) (11.0) (5.9) (25.3)
Net operating revenues 19.3 16.6 10.6 32.7
Operating expenses (13.8) (12.1) (12.1) (53.2)
Administration expenses (11.0) (11.1) (9.8) (46.0)
EBITDA (5.5) (6.6) (11.3) (66.4)
Other non-operating (loss) income (0.1) 0.1 (12.2) (8.6)
Net financial (expense) income (7.2) (40.9) 7.6 (59.5)
Equity in net earnings (losses) of affiliates (5.9) 0.7 15.7 47.9
Net loss (43.9) (73.8) (17.4) (186.5)
Vessel numbers 14 14 14 14
Dividend 0.05 0.05 0.05 0.20
© Golar LNG Limited
Balance Sheet
5
(USD thousands)
2017
Sep 30
(Unaudited)
2017
Jun 30
(Unaudited)
2016
Dec 31
(Audited)
Current assets
Cash and cash equivalents
Restricted cash and short-term receivables
Other current assets
Non-current assets
Restricted cash
Investment in affiliates
Cost method investments
Vessels and equipment, net
Asset under development
Other non-current assets
TOTAL ASSETS
Current liabilities
Current portion of long-term debt and short-term debt
Other current liabilities
Non-current liabilities
Long-term debt
Other long-term liabilities
Golar LNG Ltd’s stockholders’ equity
TOTAL LIABILITIES & EQUITY
286,562
270,087
31,925
182,416
684,285
7,347
2,093,515
1,032,116
56,970
4,645,223
1,102,560
329,527
1,199,989
228,718
1,784,429
4,645,223
343,226
205,227
19,781
233,144
668,707
7,347
2,110,537
855,949
54,340
4,498,258
919,918
193,825
1,403,112
158,757
1,822,646
4,498,258
224,190
183,693
18,334
232,335
648,780
7,347
2,153,831
731,993
56,408
4,256,911
451,454
317,673
1,525,744
52,214
1,909,826
4,256,911
© Golar LNG Limited
An Integrated LNG Energy Company
8
Exploration
& DrillingShipping Power Generation
Production &
LiquefactionRegasification
Golar Power
51% 50%
Integrated value created with ability to link well to grid
© Golar LNG Limited
FLNG Update
8
FLNG Hilli Episeyo:
Conversion, pre-commissioning completed.
Vessel left Singapore 12 October ‘17.
Arrived Cameroon 20 November ‘17.
Notice of Readiness will be served.
Full LNG commissioning commences Early December.
First LNG production expected around year end.
Final commissioning on track to complete during 2nd half
of 1Q ’18
Fortuna:
Good progress recently made on financing but year-end
execution looks tight.
Solid project economics support FID during early 2018.
OneLNG:
OneLNG making very good progress with both
development of active projects and funnel of future
opportunities.
Delfin:
Mark II FEED study on track to complete March 2018.
© Golar LNG Limited
Shipping Update
6
LNG Spot earnings (USD/day)
Source: Clarksons Platou
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
De
c 1
4Ja
n 1
5Fe
b 1
5M
ar 1
5A
pr
15
May
15
Jun
15
Jul 1
5A
ug
15
Sep
15
Oct
15
No
v 1
5D
ec
15
Jan
16
Feb
16
Mar
16
Ap
r 1
6M
ay 1
6Ju
n 1
6Ju
l 16
Au
g 1
6Se
p 1
6O
ct 1
6N
ov
16
De
c 1
6Ja
n 1
7Fe
b 1
7M
ar 1
7A
pr
17
May
17
Jun
17
Jul 1
7A
ug
17
Sep
17
Oct
17
No
v 1
7
USD
/day
LNG 160K CBM Spot Rate LNG 145K CBM Spot Rate
Real and positive progress:
Significant new production coming online.
34mtpa of 2016 nameplate capacity
ramping up; A further 33mtpa nameplate
capacity starting up in 2017.
Increasing Chinese demand, more of which
is being supplied by the US resulting in
rising ton miles.
The re-emergence of inter-basin arbitrage
opportunities also contributing additional ton
miles.
Average spot rates for TFDE vessels have
now exceeded $70kpd. ST tonnage rates
have also increased to around $40kpd.
An increase in requirements for long-term
charters has been noted.
© Golar LNG Limited
FSRU and Power Update
7
Sergipe project making good progress:
Construction on schedule and budget.
Currently more than 1,200 workers on site.
Power island modules due to arrive Q1 2018.
Mooring/Pipeline EPCI contractor appointed.
FSRU Nanook 25-year time charter agreed.
Other opportunities:
FSRU newbuild market remains very
competitive.
Market for small-mid sized FSRUs is robust.
Several integrated power opportunities
continue to be progressed.
View of groundworks for Sergipe Power Station
© Golar LNG Limited
Summary and Outlook
11
Golar is currently going through a process that will see it transition from a mid-stream
shipping company into a fully integrated gas to wire energy company.
Key building blocks to this transformation are as follows:
The delivery and start-up of FLNG Hilli Episeyo;
The project development of the Fortuna field;
The development of the power project in Sergipe including deployment of FRSU
Nanook;
The LNG shipping market showing strong signs of improving;
The improved outlook for Golar Partners as a result of its commitment to acquire an
initial interest in FLNG Hilli.
This unique combination provides a differentiated and competitive value proposition in the
gas to wire energy sector. As a result of the above, Golar is a company likely to increase
its earnings significantly over the coming three years. These results will be underpinned
by secured contracts currently in execution, further augmented by a strengthening shipping
market and a solid portfolio of projects that are expected to translate into new contracts.
The company looks forward to providing confirmation of the above over the forthcoming
quarters.
THANK
YOU
© Golar LNG Limited