Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat...
-
Upload
aiyana-grindley -
Category
Documents
-
view
217 -
download
1
Transcript of Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat...
Thierry RENAGLIA / Ramon FOLCH
FP420 Manchester WorkshopDecember 2006
FP420 Connection Cryostat Mechanical Design & Construction
Key capabilities of CERN TS/MME
FP420 Manchester Workshop - December 2006 2 / 23
FP420 Connection Cryostat
CONTENTMechanical design & constructionKey capabilities of CERN TS/MME
2. CONSTRUCTION1. DESIGN
3. CONCLUSION
FP420 versus DFB ATM Pre-design Version #1 Pre-design Version #2 Mechanical analysis Pre-design Version #3 Open issues
Advantages with CERN TS/MME Required framework conditions
Main processes involved Schedule and possible lead times Cost drivers DFB ATM assembly experience
FP420 Manchester Workshop - December 2006 3 / 23
FP420 Connection Cryostat
FP420 versus DFB ATM
Continuity of the X and C lines Higher contraction of the busbar lines Fixed point to be relocated Longer interconnection bellow length Detector constraints (accessibility, precision) Radiation shielding
ArcTerminationModule
DistributionFeedBox
FP420Cryostat
FP420 Manchester Workshop - December 2006 4 / 23
FP420 Connection Cryostat
Pre-design Version #1
Dipole cold foot to replace compensation system Couple two DFB ATM Allow contraction of the BB line
FP420 Manchester Workshop - December 2006 5 / 23
FP420 Connection Cryostat
Pre-design Version #2
Redesigned supporting beam Double cold feet to free space for line X
FP420 Manchester Workshop - December 2006 6 / 23
FP420 Connection Cryostat
Version #2 – Displacement analysis
VACUUM CONDITION
FP420 Manchester Workshop - December 2006 7 / 23
FP420 Connection Cryostat
Version #2 – Displacement analysis
VACUUM CONDITION + INTERCONNECTION at cold (operation conditions)
FP420 Manchester Workshop - December 2006 8 / 23
FP420 Connection Cryostat
Version #2 – Reaction analysis
Bellow force
- 10’000 N
Reaction z- 32’500 N
Reaction y55’000 N
Reaction z70’000 N
Cold condition(vacuum, bellow force)
FP420 Manchester Workshop - December 2006 9 / 23
FP420 Connection Cryostat
Pre-design Version #3
Two lowered supporting beams One single piece
FP420 Manchester Workshop - December 2006 10 / 23
FP420 Connection Cryostat
Version #3 – Open issues & next steps
Detector supported by the cryostat: need to deal with movements during cooling down and operation
Need of additional central fixed point and supporting jack
Use the transport buggies and the lifting beams of the DFBAs
Pre-design v#3 approval awaited
FP420 Manchester Workshop - December 2006 11 / 23
FP420 Connection Cryostat
Construction – Processes involved
Machining (both heavy and accurate) Sheet metal forming (vacuum tanks, piping) MIG/TIG welding Thermal treatments / Surface treatments Mechanical fitting (Beam screen integration) Metrology / Alignment Vacuum test / x-Ray inspection Thermal super-insulation Electrical insulation assembly and test
FP420 Manchester Workshop - December 2006 12 / 23
FP420 Connection Cryostat
J F M A M J J A S O N D J F M A M J J A S O N D J F MProject Approval
Design
Engineering
Construction
Installation
2007 2008 2009
Schedule projection attempt
Green light needed on time to allow the design work to start
The production cannot start before the design is fully
approved
FP420 Manchester Workshop - December 2006 13 / 23
FP420 Connection Cryostat
Cost drivers – What helps cutting them
Re-use existent designed parts (cold feet, jacks, dished heads, etc)
Experienced and multi-skilled workforce Avoid specific tooling Optimize the logistics between operations
FP420 Manchester Workshop - December 2006 14 / 23
FP420 Connection Cryostat
CERN TS/MME experience on DFB ATM
Design and mechanical analysis Full production and assembly of 16 ATM Budget and time constraints sealed in a
interdepartmental workpackage agreement
J F M A M J J A S O N D
1
2
3
4
5
6
7
8
9
10
11
12
14
13
Units
ATM delivery
DFBA schedule
2006
P
H I
G J
M B
C D
E
L
K
F
A
Results:Early deliveries and costs below
expectations after the 3 first units
Results:Early deliveries and costs below
expectations after the 3 first units
ArcTerminationModule
DistributionFeedBox
FP420 Manchester Workshop - December 2006 15 / 23
FP420 Connection Cryostat
Shuffling Box assembly
FP420 Manchester Workshop - December 2006 16 / 23
FP420 Connection Cryostat
Welding of the dished heads
FP420 Manchester Workshop - December 2006 17 / 23
FP420 Connection Cryostat
Cryostating of the Shuffling Module
FP420 Manchester Workshop - December 2006 18 / 23
FP420 Connection Cryostat
Thermal Super-insulation
FP420 Manchester Workshop - December 2006 19 / 23
FP420 Connection Cryostat
Final assembly
FP420 Manchester Workshop - December 2006 20 / 23
FP420 Connection Cryostat
DFBA (ATM & HCM) Transport
FP420 Manchester Workshop - December 2006 21 / 23
FP420 Connection Cryostat
Conclusions
Advantages with CERN/TS/MME– Design and construction synergy benefits– Shortened learning curve (skilled resources and appropriate
equipment available)– Highly responsive multi-technological environment– Reduction of the logistics time and cost– Design and construction traceability (CDD/ EDMS / MTF)
Required framework conditions– Obtain the formal approval of the pre-design– Obtain the final version of the technical specification– Adopt a workpackage oriented approach combining the
mechanical design and the construction
FP420 Manchester Workshop - December 2006 22 / 23
FP420 Connection Cryostat
The CERN TS/MMEMechanical and Materials
Engineering group received the
Golden Hadron Award(LHC best suppliers)
Fair and efficient partnership with CERN Member States
(here: Bulgaria)
FP420 Manchester Workshop - December 2006 23 / 23
FP420 Connection Cryostat
Thanks for their contribution …
Utilisation des ATM pour le projet FP420 - EDMS 771549 – Thierry Renaglia
Use of the ATM for the FP420 Project EDMS 743628 – Thierry Colombet
General information from the TS/MME ATM assembly team (Said Atieh, Laurent Préver-Loiri, Didier Lombard, and al.)
…and thanks for your attention.