Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat...

23
Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN TS/MME

Transcript of Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat...

Page 1: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

Thierry RENAGLIA / Ramon FOLCH

FP420 Manchester WorkshopDecember 2006

FP420 Connection Cryostat Mechanical Design & Construction

Key capabilities of CERN TS/MME

Page 2: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 2 / 23

FP420 Connection Cryostat

CONTENTMechanical design & constructionKey capabilities of CERN TS/MME

2. CONSTRUCTION1. DESIGN

3. CONCLUSION

FP420 versus DFB ATM Pre-design Version #1 Pre-design Version #2 Mechanical analysis Pre-design Version #3 Open issues

Advantages with CERN TS/MME Required framework conditions

Main processes involved Schedule and possible lead times Cost drivers DFB ATM assembly experience

Page 3: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 3 / 23

FP420 Connection Cryostat

FP420 versus DFB ATM

Continuity of the X and C lines Higher contraction of the busbar lines Fixed point to be relocated Longer interconnection bellow length Detector constraints (accessibility, precision) Radiation shielding

ArcTerminationModule

DistributionFeedBox

FP420Cryostat

Page 4: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 4 / 23

FP420 Connection Cryostat

Pre-design Version #1

Dipole cold foot to replace compensation system Couple two DFB ATM Allow contraction of the BB line

Page 5: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 5 / 23

FP420 Connection Cryostat

Pre-design Version #2

Redesigned supporting beam Double cold feet to free space for line X

Page 6: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 6 / 23

FP420 Connection Cryostat

Version #2 – Displacement analysis

VACUUM CONDITION

Page 7: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 7 / 23

FP420 Connection Cryostat

Version #2 – Displacement analysis

VACUUM CONDITION + INTERCONNECTION at cold (operation conditions)

Page 8: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 8 / 23

FP420 Connection Cryostat

Version #2 – Reaction analysis

Bellow force

- 10’000 N

Reaction z- 32’500 N

Reaction y55’000 N

Reaction z70’000 N

Cold condition(vacuum, bellow force)

Page 9: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 9 / 23

FP420 Connection Cryostat

Pre-design Version #3

Two lowered supporting beams One single piece

Page 10: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 10 / 23

FP420 Connection Cryostat

Version #3 – Open issues & next steps

Detector supported by the cryostat: need to deal with movements during cooling down and operation

Need of additional central fixed point and supporting jack

Use the transport buggies and the lifting beams of the DFBAs

Pre-design v#3 approval awaited

Page 11: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 11 / 23

FP420 Connection Cryostat

Construction – Processes involved

Machining (both heavy and accurate) Sheet metal forming (vacuum tanks, piping) MIG/TIG welding Thermal treatments / Surface treatments Mechanical fitting (Beam screen integration) Metrology / Alignment Vacuum test / x-Ray inspection Thermal super-insulation Electrical insulation assembly and test

Page 12: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 12 / 23

FP420 Connection Cryostat

J F M A M J J A S O N D J F M A M J J A S O N D J F MProject Approval

Design

Engineering

Construction

Installation

2007 2008 2009

Schedule projection attempt

Green light needed on time to allow the design work to start

The production cannot start before the design is fully

approved

Page 13: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 13 / 23

FP420 Connection Cryostat

Cost drivers – What helps cutting them

Re-use existent designed parts (cold feet, jacks, dished heads, etc)

Experienced and multi-skilled workforce Avoid specific tooling Optimize the logistics between operations

Page 14: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 14 / 23

FP420 Connection Cryostat

CERN TS/MME experience on DFB ATM

Design and mechanical analysis Full production and assembly of 16 ATM Budget and time constraints sealed in a

interdepartmental workpackage agreement

J F M A M J J A S O N D

1

2

3

4

5

6

7

8

9

10

11

12

14

13

Units

ATM delivery

DFBA schedule

2006

P

H I

G J

M B

C D

E

L

K

F

A

Results:Early deliveries and costs below

expectations after the 3 first units

Results:Early deliveries and costs below

expectations after the 3 first units

ArcTerminationModule

DistributionFeedBox

Page 15: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 15 / 23

FP420 Connection Cryostat

Shuffling Box assembly

Page 16: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 16 / 23

FP420 Connection Cryostat

Welding of the dished heads

Page 17: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 17 / 23

FP420 Connection Cryostat

Cryostating of the Shuffling Module

Page 18: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 18 / 23

FP420 Connection Cryostat

Thermal Super-insulation

Page 19: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 19 / 23

FP420 Connection Cryostat

Final assembly

Page 20: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 20 / 23

FP420 Connection Cryostat

DFBA (ATM & HCM) Transport

Page 21: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 21 / 23

FP420 Connection Cryostat

Conclusions

Advantages with CERN/TS/MME– Design and construction synergy benefits– Shortened learning curve (skilled resources and appropriate

equipment available)– Highly responsive multi-technological environment– Reduction of the logistics time and cost– Design and construction traceability (CDD/ EDMS / MTF)

Required framework conditions– Obtain the formal approval of the pre-design– Obtain the final version of the technical specification– Adopt a workpackage oriented approach combining the

mechanical design and the construction

Page 22: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 22 / 23

FP420 Connection Cryostat

The CERN TS/MMEMechanical and Materials

Engineering group received the

Golden Hadron Award(LHC best suppliers)

Fair and efficient partnership with CERN Member States

(here: Bulgaria)

Page 23: Thierry RENAGLIA / Ramon FOLCH FP420 Manchester Workshop December 2006 FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN.

FP420 Manchester Workshop - December 2006 23 / 23

FP420 Connection Cryostat

Thanks for their contribution …

Utilisation des ATM pour le projet FP420 - EDMS 771549 – Thierry Renaglia

Use of the ATM for the FP420 Project EDMS 743628 – Thierry Colombet

General information from the TS/MME ATM assembly team (Said Atieh, Laurent Préver-Loiri, Didier Lombard, and al.)

…and thanks for your attention.