THECB Project Application

16
THECB Project Application Texas Higher Education Coordinating Board Finance and Resource Planning Roland Gilmore, Program Director

Transcript of THECB Project Application

THECB Project Application

Texas Higher Education

Coordinating Board

Finance and Resource Planning

Roland Gilmore, Program Director

Integrated Campus Planning System (ICPS)

2

Project Approvals

Exempt Projects

Application Procedures

Tracking Report

Reapprovals

The THECB Project Approval ProcessProject Approvals

3

• New Construction (Addition) - $4 million or more

• Repair and Renovation - $4 million or more

• Auxiliary Enterprise - $4 million or more

• Intercollegiate Athletic - $4 million or more

• E&G Improved & Unimproved

Real Property Purchases - all

• E&G improved Real Property Gifts - over $300,000

• Energy Savings Performance Contracts - all

• Tuition Revenue Bond Projects (evaluation only) - all

The THECB Project Approval ProcessProjects Exempt from Approvals

4

• New Construction (Addition) -Less than $4 million

• Repair and Renovation -Less than $4 million

• Projects financed with more than 50 percent PUF or AUF

• Construction of privately owned buildings on land leased from an institution.

• Lease of property or facilities.

• Gifts, Grants, lease purchase agreements for clinical or research facilities.

• Projects pursuant to specific legislative authority.

• Gifts or lease-purchase of unimproved real property.

• Gifts or lease-purchase of improved real property with no E&G space and the value is $300,000 or less.

The THECB Project Approval Process Application Procedures

5

• ICPS Application

• Signed Board of Regents Certification

Committee on Strategic Planning and Policy or the Board Level Projects

• 80 days prior to Committee meeting

• All information and clarifications provided

• Incomplete applications or applications with unresolved issues move to the next Board meeting

The THECB Project Approval Process Application Procedures

6

Project Description Items

• Full narrative

• Name, location, and types of space

• GSF, NASF and E&G NASF amounts

• Outline of phases

• Explain cost categories that exceed thresholds

• Contingency costs over 10%

• Other costs over 5%

• Shelled Space

• Anticipated completion date

• Anticipated NASF, E&G NASF, and types of space

Integrated Campus Planning System (ICPS)Application Procedures - Project Specifics

7

Integrated Campus Planning System (ICPS)Application Procedures - Project Space

GSF, NASF and E&G NASF space (as available at submission)

Demolished or permanently removed from inventory

Total space to be added or removed from inventory

8

Room Inventory CBM011 Edits

9

• Room Inventory report (CBM011) with a total room area exceeding the building GSF or NASF will produce a hard error, that will require error correction and resubmission of the report.

• Room Inventory report with total room area exceeding divided by the building GSF and exceeds a building efficiency of 90 percent will produce review soft error.

Integrated Campus Planning System (ICPS)Application Procedures - Project Costs

10

Integrated Campus Planning System (ICPS)Application Procedures - Project Costs

11

Integrated Campus Planning System (ICPS)Application Procedures - Project Costs

12

Integrated Campus Planning System (ICPS)Application Procedures - Project Costs

13

Tracking Report Update Project Tracking

14

Uses:

• Space Projection Model – Surplus/Deficit

• Approved Not-Online E&G NASF added to actual space

• Construction Cost Standard

• New Construction Costs

• Renovation Costs

• GSF

Tracking Report Update Project Reapproval

15

Reapproval Required if:

• 10 % increase between approved and expended Total Project Cost

• 10 % change between approved and expended Gross Square Feet (plus or minus)

• Project not contracted within 18 months of approval

• Property not purchased within 24 months of approval

• Any change in Funding Source