The World Bankdocuments.worldbank.org/curated/en/948351486393505731/pdf/ICR... · AKNOP Real demand...
Transcript of The World Bankdocuments.worldbank.org/curated/en/948351486393505731/pdf/ICR... · AKNOP Real demand...
1
Document of
The World Bank
Report No: ICR00003347
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IBRD-76690)
ON A
LOAN
IN THE AMOUNT OF US$50 MILLION
TO THE
REPUBLIC OF INDONESIA
FOR A
DAM OPERATIONAL IMPROVEMENT AND SAFETY PROJECT
(DOISP) P096532
January 29, 2017
Water Global Practice East Asia and the Pacific Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
CURRENCY EQUIVALENTS
(Exchange Rate Effective 06/08/2009)
Currency Unit = Indonesian Rupiah
1.00 = US$ 0.0001 US$ 1.00 = 10,041.415
(Exchange Rate of January 10, 2017 used)
Currency Unit = Indonesian Rupiah
1.00 = US$ 0.0001 US$ 1.00 = 13,276.242
FISCAL YEAR January 1 – December 31
ABBREVIATIONS AND ACRONYMS
AF Additional Financing IRR Internal Rate of Return
AKNOP Real demand for O&M ISR Implementation Status Report
APL Adaptable Program Loan IWRM Integrated Water Resources
Management Balai
BBWS
River Basin Agency (under
MPW)
MEAV Modern Equivalent Asset
Value to estimate O&M budget
BDSF Basic Dam Safety Facilities M&E Monitoring & Evaluation
CDMU Central Dam Monitoring Unit MDG Millennium Development Goals
CP Community Program MPW Ministry of Public Works and Housing
CPF Country Partnership Framework NPV Net Present Value
CPIU Central Project Implementation
Unit
NSCWR National Steering Committee
for Water Resources
CPMU Central Project Management Unit O&M Operation & Maintenance
CPS Country Partnership Strategy PDO Project Development Objective
DBOP Directorate for Operation and
Maintenance in DGWR
PIP Project Implementation Plan
DGWR Directorate General for Water
Resources of the Ministry of Public Works and Housing
(MPW)
PIU Project Implementation Unit
DMU Dam Monitoring Unit PJT State-owned company for the operation of water resources
assets
DOISP Dam Operational Improvement and Safety Project
RBO River Basin Organizations (BBWS)
DSP Dam Safety Project RKM Community Work Plan
DSU Dam Safety Unit RPJM(N) (National) Mid-term
Development Plan
3
EAP Emergency Action Plan RPJP Long-term Development Plan
ESMF Environmental and Social
Management Framework
SEOP Spillway Emergency Operating
Procedure GOI Government of Indonesia SID Surveys Investigations, Designs
ICB International Competitive
Bidding
SOP Standard Operating Procedures
ICOLD International Commission on Large Dams
TOR Terms of Reference
ICR Implementation Completion and
Results Report
UKL/UPL Environmental Management
and Monitoring Plan
IDR Indonesian Rupiah USD United States Dollars
INACOLD Indonesian ICOLD Chapter WATSAL Water Resources Sector Adjustment Loan
INT Institutional Integrity WISMP Water and Irrigation Sector
Management Project
Senior Global Practice Director: Guang Zhe Chen
Country Director: Rodrigo Chaves
Practice Manager: Sudipto Sakar
Project Team Leader: Marcus Wishart / Ximing Zhang
ICR Team Leader: Martin Albrecht
4
INDONESIA
Dam Operational Improvement and Safety Project (DOISP)
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Project Performance in ISRs
H. Restructuring
I. Disbursement Graph
1. Project Context, Development Objectives and Design ....................................................... 12 2. Key Factors Affecting Implementation and Outcomes ....................................................... 16 3. Assessment of Outcomes ................................................................................................... 23 4. Assessment of Risk to Development Outcome ................................................................... 29 5. Assessment of Bank and Borrower Performance................................................................ 30 6. Lessons Learned ............................................................................................................... 32 7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners ....................... 33 Annex 1. Project Costs and Financing ................................................................................... 34 Annex 2. Outputs by Component .......................................................................................... 35 Annex 3. Economic and Financial Analysis ........................................................................... 43 Annex 4. Bank Lending and Implementation Support/Supervision Processes ......................... 46 Annex 5. Summary of Borrower's ICR and/or Comments on Draft ICR ................................. 48 Annex 6. List of Supporting Documents ................................................................................ 49
MAP
5
Data Sheet
A. Basic Information
Country: Indonesia Project Name:
Dam Operational
Improvement and
Safety
Project ID: P096532 L/C/TF Number(s): IBRD-76690
ICR Date: 01/29/2017 ICR Type: Core ICR
Lending Instrument: SIL Borrower: REPUBLIC OF
INDONESIA
Original Total
Commitment: USD 50.00M Disbursed Amount: USD 47.02M
Revised Amount: USD 50.00M
Environmental Category:
Implementing Agencies:
Ministry of Public Works and Housing
Cofinanciers and Other External Partners:
B. Key Dates
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 03/28/2006 Effectiveness: 06/08/2009
Appraisal: 10/15/2008 Restructuring(s):
09/19/2013
06/29/2015
10/23/2016
Approval: 03/19/2009 Mid-term Review: 12/15/2011 03/21/2012
Closing: 12/31/2013 06/30/2017
C. Ratings Summary
C.1 Performance Rating by ICR
Outcomes: Moderately Satisfactory
Risk to Development Outcome: Moderate
Bank Performance: Moderately Satisfactory
Borrower Performance: Moderately Satisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Moderately Satisfactory Government: Satisfactory
Quality of Supervision: Moderately Satisfactory Implementing
Agency/Agencies: Moderately Satisfactory
6
Overall Bank
Performance: Moderately Satisfactory
Overall Borrower
Performance: Moderately Satisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments
(if any) Rating
Potential Problem Project
at any time (Yes/No): No
Quality at Entry
(QEA): None
Problem Project at any time (Yes/No):
Yes Quality of
Supervision (QSA): None
DO rating before
Closing/Inactive status: Satisfactory
D. Sector and Theme Codes
Original Actual
Major Sector/Sector
Public Administration
Public administration - Water, sanitation and flood
protection 12 12
Water, Sanitation and Waste Management
Other Water Supply, Sanitation and Waste Management 88 88
Major Theme/Theme/Sub Theme
Environment and Natural Resource Management
Water Resource Management 100 100
Water Institutions, Policies and Reform 100 100
E. Bank Staff
Positions At ICR At Approval
Vice President: Laura Tuck James W. Adams
Country Director: Rodrigo A. Chaves Joachim von Amsberg
Practice
Manager/Manager: Sudipto Sarkar Sonia Hammam
Project Team Leader: Marcus J. Wishart Guy J. Alaerts
ICR Team Leader: Martin B. Albrecht
ICR Primary Author: Martin B. Albrecht
7
F. Results Framework Analysis
Project Development Objectives (from Project Appraisal Document) The objectives of the Project are to (i) increase the safety and the functionality with respect to bulk
water supply of large Ministry of Public Works-owned reservoirs; and (ii) strengthen the safety and
operational management policies, regulations and administrative capacity of Ministry of Public Works.
Revised Project Development Objectives (as approved by original approving authority)
(a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Dam portfolio risk assessment (Number, Custom)
Value quantitative or
Qualitative)
0 22 36 36
Date achieved 05/01/2009 12/31/2013 10/23/2016 09/30/2016
Comments
(incl. % achievement)
Target 100% achieved.
Indicator 2 : DGWR Dam Portfolio Management Program established (Number, Custom)
Value
quantitative or Qualitative)
0 63 63
Date achieved 05/01/2009 12/31/2013 09/30/2016
Comments (incl. %
achievement)
Target 100% achieved. The dam portfolio management program comprises all 63
dams under the project, including an increase in O&M budget, training for staff,
hydrological maps, as well as the establishment of a
Indicator 3 :
DOISP Referable Dam Works and Field Inspection and Certification per DSU
Priority Plan (Percentage, Custom)
Value quantitative or
Qualitative)
0 % 75 % 94 %
Date achieved 05/01/2009 12/31/2013 09/30/2016
Comments
(incl. % achievement)
Target over achieved (125%).
8
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Number of dams rehabilitated (Number, Custom)
Value
(quantitative
or Qualitative)
0
34
33
34
Date achieved 05/01/2009 12/31/2013 12/31/2015 09/30/2016
Comments (incl. %
achievement)
Target overachieved (103%).
Indicator 2 : Number of 34 priority dams with SEOP operational (Percentage, Custom)
Value (quantitative
or Qualitative)
0
>90%
165%
Date achieved 05/01/2009 12/31/2013 09/30/2016
Comments
(incl. % achievement)
Target overachieved (183%). Originally, SEOPs for 34 dams were targeted. Under
the project, SEOPs were prepared for 56 dams as part of the EAPs.
Indicator 3 : Operating staff training took place for 63 dam. (Number, Custom)
Value
(quantitative or Qualitative)
0
63
64
Date achieved 05/01/2009 12/31/2013 09/30/2016
Comments
(incl. %
achievement)
Target overachieved (102%).
Indicator 4 : Special studies for dams completed (Number, Custom)
Value
(quantitative
or Qualitative)
0
21
23
23
Date achieved 05/01/2009 12/31/2013 12/31/2015 09/30/2016
Comments (incl. %
achievement)
Target achieved 100%. The dams for which the special studies were prepared will be included under the AF
Indicator 5 : O&M Manuals (including related training) for Dams completed. (Number,
Custom)
Value (quantitative
or Qualitative)
0
56
51
Date achieved 05/01/2009 12/31/2013 09/30/2016
9
Comments
(incl. %
achievement)
Target 91% achieved.
Indicator 6 : Community-Dam Operator MOUs signed on Greenbelt Management (Number, Custom)
Value
(quantitative
or Qualitative)
0
16
18
Date achieved 05/01/2009 12/31/2013 09/30/2016
Comments (incl. %
achievement)
Target overachieved (113%).
Indicator 7 : Household joining catchment management activities (Percentage, Custom)
Value (quantitative
or Qualitative)
0
25
37
Date achieved 05/01/2009 12/31/2013 09/30/2016
Comments
(incl. % achievement)
Target overachieved (148%).
Indicator 8 : DOISP Reservoir Survey completed (Number, Custom)
Value
(quantitative or Qualitative)
0
30
31
Date achieved 05/01/2009 12/31/2013 09/30/2016
Comments
(incl. %
achievement)
Target overachieved (103%).
Indicator 9 : DSU staff recruited and trained (Percentage, Custom)
Value
(quantitative
or Qualitative)
0
100
100
Date achieved 05/01/2009 12/31/2013 09/30/2016
Comments (incl. %
achievement)
Target 100% achieved.
Indicator 10 : INACOLD certification of Dam Professional (Percentage, Custom)
Value (quantitative
or Qualitative)
0
80
100
Date achieved 05/01/2009 12/31/2013 09/30/2016
Comments
(incl. % achievement)
Target overachieved (125%).
10
G. Ratings of Project Performance in ISRs
No. Date ISR
Archived DO IP
Actual
Disbursements
(USD millions)
1 12/24/2009 Satisfactory Moderately Satisfactory 0.00
2 06/17/2011 Moderately Satisfactory Moderately
Unsatisfactory 7.09
3 12/14/2011 Moderately Satisfactory Moderately
Unsatisfactory 8.08
4 05/29/2012 Moderately
Unsatisfactory Unsatisfactory 8.08
5 11/03/2012 Moderately Satisfactory Moderately Satisfactory 11.48
6 07/20/2013 Moderately Satisfactory Moderately Satisfactory 18.68
7 02/06/2014 Moderately Satisfactory Moderately Satisfactory 25.47
8 08/29/2014 Moderately Satisfactory Moderately Satisfactory 33.63
9 02/26/2015 Moderately Satisfactory Moderately Satisfactory 37.16
10 06/15/2015 Moderately Satisfactory Moderately Satisfactory 39.94
11 12/13/2015 Moderately Satisfactory Moderately Satisfactory 44.62
12 06/24/2016 Moderately Satisfactory Moderately Satisfactory 46.86
13 12/22/2016 Satisfactory Satisfactory 47.02
H. Restructuring (if any)
Restructuring
Date(s)
Board
Approved
PDO Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in USD
millions
Reason for Restructuring &
Key Changes Made DO IP
09/19/2013 MS MS 21.76
Extend closing date, improve project organization, reallocate
loan proceeds, slight change
in intermediate outcome indicators.
06/29/2015 MS MS 42.41
Extend closing date to allow for
completion of contracts.
10/23/2016 MS MS 46.86
Extend closing date to allow for
preparation of Additional
Financing (DOISP2, P161514)
11
I. Disbursement Profile
12
1. Project Context, Development Objectives and Design
1.1 Context at Appraisal 1. Country Context. Indonesia’s geography as a tropical archipelago with more than 17,000
islands and high seasonal rainfall variability was reflected in the complexity of and requirement for sound water resources management. Despite more than 280 dams across the country, around 170
of which classified as large, Indonesia’s storage capacity remained low compared with other
countries1, which was constraining long term development goals of food security, energy security and water security. A large number of the existing assets such as dams, barrages or canals had been
built before 1990, bringing them to the end of their economic lifetime and thus making them a
safety hazard unless rehabilitated. While there had been rapid infrastructure development over the
past decades, operation and maintenance (O&M) of these dams have not been adequately addressed. This increases the safety risk, the loss of effectiveness due to sedimentation, and high expense if
they need to be replaced or rehabilitated.
2. Government Strategy. The Government of Indonesia recognized and outlined in development plans2 the importance of providing water for its growing population. At the time of
appraisal, urban water demand was growing together with economic development, population
growth and urbanization while much of the country’s staple food rice was grown on irrigated areas that consumed about 85% of the bulk water supply. With the high seasonal variability of rainfall,
Indonesia relied heavily on reservoirs and barrages on rivers for water supply3. In the dry season,
reservoirs ensured a second and third annual harvest through irrigation of around 4.7 million
hectares, raising rural incomes and stabilizing food prices. About 18% of the total installed power generating capacity in Indonesia was generated from hydropower. Large dams also functioned as
key infrastructure for flood prevention, which otherwise were a common cause for natural disasters.
3. Considering future impacts of climate change4, reservoirs would play a pivotal role in the management of Indonesia’s water resources. The Government was responding with the intention
of building 15 new reservoirs in the coming decade5 as well as with strengthening the capacity and
resources for operation and maintenance and timely remedial repairs. In the 1990s, with World
Bank support, Indonesia had introduced a dam safety framework6. Linked with the political move towards decentralization, the Government had initiated sector-wide legal, regulatory and
administrative reform for water resources, which had been concluded by a water resources law7.
1 Storage capacity in Indonesia was about 100 m3 per capita in 2005, compared with around 416 m3 per capita in China, 3,600 m3 per capita in Brazil, or 190 m3 per capita in India at that time. 2 Long-term Development Plan (RPJP) 2005 – 2025, and in several mid-term development plans (RPJM)
with the RPJMN 2004 – 2009 at the time of appraisal. 3 Most large cities such as Jakarta, Surabaya, Makassar and Semarang depend largely on reservoirs and
barrages for their water supply - greater Jakarta depends on one large reservoir for about 80% of its tap water; 4 Most studies and observations predict seasons to be more extreme in either sense: the wet season will
become shorter with rainfall coming in fewer, more intense events, while the dry season will be longer with
more pronounced periods of drought. 5 The plan of 15 new dams was the status at appraisal. In 2014, the current Government published their plan
to build 65 new dams until 2019. 6 Through the Dam Safety Project DSP (1994 – 2003). 7 Law No. 7/2004, introducing Integrated Water Resources Management (IWRM), better governance as well
as improved financial sustainability of hydraulic infrastructure. This law was cancelled by the Constitutional
13
4. Rationale for Bank Involvement. Given Indonesia’s demonstrated political will –
including the establishment of dam safety institutions, the passing of a water resources law, and the recognition for the importance of reservoirs with regards to the future development of the country
– Bank support could contribute to further development and implementation of comprehensive
regulatory and administrative framework for dam management, ultimately increasing dam safety
and functionality. Following a long-standing relationship between the Bank and Indonesia in the water resources sector and a focus on dam safety8, the project intended to consolidate the first
institutional and policy achievements of the Dam Safety Project (DSP) and sector reform
achievements.
5. The Bank built on broad experience in technically demanding tasks and institutional
development in the sector with a track record in dam safety in India, China, Sri Lanka and other
countries. Further, the Bank had broad experience in several regions on the linkage between loss of reservoir functionality and sediment import from the upper watershed – a predominant issue in
reservoir management in Indonesia.
6. Higher Level Objectives to Which the Project Contributed. The project intended to
contribute towards meeting the Millennium Development Goals (MDGs) to increase access to water supply9 both for human consumption and for productive use – a core goal for the Government
of Indonesia as well as the Bank. Further, the project intended to contribute to the Government’s
strategy to mitigate climate change and adapt to the changes by reducing its vulnerability of water related disasters. Finally, the project was key to maintain the momentum for sector-wide
engagement and coherent policy and institutional support, which aimed at improving the
performance and the sustainability of this sector, specifically on river basin management, irrigation and flood protection. The Country Partnership Strategy (CPS) at the beginning of the project in
2008 focused on strengthening Indonesia’s institutions and investments in (water) infrastructure,
climate change and disaster mitigation, amongst others. The Project Development Objective (PDO)
was consistent with these priorities.
1.2 Original Project Development Objectives (PDO) and Key Indicators 7. The objectives at the time of approval were to (i) increase the safety and the functionality
with respect to bulk water supply of large Ministry of Public Works-owned reservoirs; and (ii)
strengthen the safety and operational management policies, regulations and administrative capacity of Ministry of Public Works. Implicitly, the aim of the PDO is the extension of the lifetime of
reservoirs and dams, delaying the urgency to build new costly reservoirs.
8. Key indicators at approval were linked to the two parts of the PDO (i and ii) were:
9. PDO part (i): Increase the safety and the functionality with respect to bulk water supply of large MPW-owned reservoirs;
Court in 2015. Impacts on the institutional set-up have been avoided through the issuance of a Ministerial
Decree while the Law is being revised and updated. 8 Notably in form of the Dam Safety Project DSP (1994 – 2003), sector-wide policy reforms (such as the 1999 – 2004 reforms associated with the Water Resources Sector Adjustment Loan WATSAL), and
investments such as irrigation loans in the 1990s as well as the Water Resources and Irrigation Sector
Management Project WISMP 2005-2009). 9 Millennium Development Goal 7c stated: Halve, by 2015, the proportion of the population without
sustainable access to safe drinking water and basic sanitation.
14
Key indicators:
a) Reduction in dam failure risk of about 34 rehabilitated dams using an appropriate Risk Assessment Method & achieving operational Spillway Emergency Operation Plans for
these dams. ‘Extreme’ Hazard dams reduced from 3% to 0%; ‘High’ Hazard dams reduce
from 81 to <5%; ‘Moderate’ Hazard dams increased from 0% to >95%. Overall Hazard of
the 34 dams reduced by > 30% on Risk Score. b) Directorate General for Water Resources (DGWR) Dam Portfolio management improved
by established: Annual Dam O&M Funding Program, Dam Human Resources
Development Program, Dam Hydrology Program, Dam Quality Assurance system and a functional Central Dam Monitoring Unit (CDMU).
c) DSU has completed > 75% of its priority dam inspection & certification load (including 2-
3 large mine tailings dams).
10. PDO part (ii): Strengthen the safety and operational management policies, regulations and
administrative capacity of MPW;
Key indicators: a) Government Regulation on Dams and Ministerial Decrees issued.
b) Administrative procedures and capacity enhanced.
1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and
reasons/justification 11. The PDO was not revised during the project.
12. The targets of the intermediate outcome indicators were modified to be achievable by the
initial closing date of 31 December 2013. The modification included the reduction of the targeted
number of rehabilitated dams from 34 to 33.
1.4 Main Beneficiaries 13. The direct beneficiaries were to be the urban communities and over 2.5 million farm
households who depended on the 63 dams and reservoirs that were altogether covered under the
project for their water supply and livelihood (for 34 of these 63 dams physical works were included). Beneficiaries also included downstream communities who could be placed at physical and/or
environmental risk if the safety of these dams was compromised. Communities in the direct vicinity
of the dams and reservoirs were directly involved in project activities through the community participation program under Component 2, collaborating on watershed management and being
familiarized with appropriate safety measures under the Emergency Action Plans.
1.5 Original Components 14. The project was composed of five components:
15. Component 1: Dam Operational Improvement and Safety Works and Studies (Project Cost: US$ 31.48m). The objective of the Dam Operational Improvement and Safety Works and
Studies Component was to restore dam performance and safety. This was to be achieved through
minor rehabilitation and remedial works10 , developing surveys, investigations and designs (SID)
10 Minor rehabilitation and remedial works refers to works on existing dam structures that are acceptable under the project’s designated safeguards framework. Examples include physical works (repair dam crest,
access road, drains, stabilizing slopes, etc.) and cleaning the dam of weeds, scrubs and trees. If more complex
15
for medium to major works, providing Basic Dam Safety Facility (BDSF) repair and/or upgrading
for improved safety monitoring and preparedness systems, establishing a river inflow and sediment monitoring system, and an assessment of spillway capacity and downstream flooding risks. A total
34 prioritized large dam/ reservoir sites were to be targeted for physical works, out of which four
were ready for implementation in year one, the others were to be undertaken in phases during the
following years. SIDs for medium and major works to restore and/or improve operational performance and safety of approximately other 22 dams/reservoirs were to be prepared for
implementation in a successor project. Both the BDSF repair and/or upgrading as well as the
spillway capacity and downstream flooding risk assessment were to be prepared for 34 dams. The river inflow and sediment monitoring system was to be set up for about 63 dams.
16. Component 2: Operations & Maintenance Improvement and Capacity Building (Project Cost: US$ 13.24m). The objective of this component was to support improved operations and maintenance and to strengthen capacity building of the dam agency. This was to be achieved
through preparing O&M plans, Standard Operating Procedures (SOP) and manuals, as well as
undertaking needs-based budgeting and O&M activities. Further through preparing dam and
reservoir management plans and emergency spillway operation plans, staff training participatory programs with local communities on reservoir and dam management, and providing incremental
operating costs for O&M, to be borne by GOI. Most of these activities were to be conducted in the
aforementioned 34 dams, only the community participation program was to be conducted in 20 reservoirs.
17. Component 3: Reservoir Sedimentation Mitigation (Project Cost: US$ 13.12m). The
objective of this component was to provide for measures to mitigate the risk of sedimentation of selected reservoirs and for sustained performance and safety. This was to be achieved through
bathymetric 11 surveys to determine the total available water storage in reservoirs affected by
sedimentation; through feasibility studies, designs and the Environmental and Social Management
Framework (ESMF) for medium-term interventions within the reservoir, such as dredging, hydro-suction, flushing, etc.; preparations for a sample study for decommissioning of severely silted
reservoirs, to be financed under the successor project; and through piloting of institutional models
and plans to construct sediment retention and river bank protection structures of upstream rivers and (sub-)catchments.
18. Component 4: Dam Safety Institutional Improvement (Project Cost: US$ 2.14m). The
objective of the Dam Safety Institutional Improvement component was to further strengthen and
consolidate the regulatory framework and national dam safety institution and strengthen MPW’s capacity for portfolio management and regulation in order to sustain rehabilitation works and
reservoir life. This was to be achieved through preparing needed Government and Ministerial
regulatory documents and concept/academic papers, a public awareness campaign about dams and reservoirs, through strengthening and developing the Dam Safety Unit (DSU), providing it with a
fully furnished and equipped office and updated guidelines, through establishing a dam engineer
and technician training and certification system, and through supporting incremental costs of the Central Dam Management Unit within the ministry.
19. Component 5: Project Management (Project Cost: US$ 4.36m). The objective of this
component was to provide overall project management and to support the Central Project
safety issues existed, detailed SID were conducted, which included studies on cracks, seepage, intakes,
stability, etc. BDSF includes repair and installation of instrumentation such as piezometers, gauges, etc. 11 ‘Bathymetric survey’ describes a measurement to determine the depth profile of a water body.
16
Management Unit (CPMU), the Central Project Implementation Unit (CPIU) and each Project
Implementation Unit (PIU).
1.6 Revised Components 20. The project components were not revised during the project.
1.7 Other significant changes 21. Reorganization of the implementing agency. The project’s implementing agency, the
Directorate General for Water Resources (DGWR), Ministry of Public Works, was reorganized
during implementation. This led to new implementation units and procedures with subsequent delays in disbursement. The reorganization also led to the establishment of a new Directorate for
Operation and Maintenance (DBOP) within DGWR, in which the CPIU was re-established after
the first restructuring.
22. A change in Government in October 2014 introduced new policies that, amongst other,
focused on water related projects to achieve food, water and energy security12. This involved the
construction of 65 new dams and the rehabilitation of existing dams to increase the share of
reservoir-dependent irrigation schemes from 11% to 20%, or 1.5 million hectares. While the project’s relevance increased with the Government’s new policy, the new focus also rapidly
increased the local demand for dam related expertise. As a consequence, quality national dam
experts were limited on the market, with implications on the quality of work produced, such as designs and special studies for selected dams.
23. Project restructuring. The closing date of the project was extended three times, first from
31 December 2013 to 31 December 2015, and then to 31 December 2016, and again to 30 June 2017. These extensions were needed to complete ongoing contracts that were delayed due to
changes in the original design, a slow procurement process, delays in implementation of civil
works13, as well as complete preparations for the Additional Financing for DOISP 2 (P161514).
Further, the target of the Project Outcome Indicator (i)(a), as well as Intermediate Outcome Indicator (a)(i) on dams to be rehabilitated was changed from 34 to 33 given one of the originally
included dams experienced damage during implementation and required emergency repairs
financed by Government budget. Finally, Outcome Indicator target (a)(ii) describing the number of Spillway Emergency Operation Plans publically accepted was changed from 34 to 56.
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry 24. Establishing a long-term, programmatic approach to dam safety. The Government had
embarked on a programmatic approach to develop a portfolio management approach across its
dams and reservoirs. Building on DSP, DOISP was envisaged as the first project to support this agenda. Unlike DSP, which focused solely on dam safety, DOISP was designed to also include
12 The vision and mission of the new Government Administration is described in the Nawa Cita, which translates into “nine priorities”. 13 See second and third restructuring paper, June 2015.
17
effective operation and management of dams. More extensive preliminary surveys, investigations
and designs (SID) were started under DOISP to allow implementation in a successor project14.
25. Lessons of former projects incorporated into preparation. Several lessons from dam
safety projects in Indonesia and other countries, as well as from other preceding projects in the
sector 15 have been incorporated into the design of this project. The experience showed the
importance of three aspects: (i) proper documentation of pre-project status of dam safety; this had already been undertaken by the national Research Center for Water Resources for all large dams
on Java; (ii) attention to both structural and non-structural remedial measures to ensure dam and
reservoir sustainability; this is part of the project’s design to also focus on institutional development; and (iii) putting in place effective mechanisms for budgeting and maintaining the
level of O&M allocation and dam safety achieved at the end of the project.
26. Adjusting absorption capacity. The project was originally conceived as six-year Specific Investment Loan (SIL) with total loan financing of about USD 130 million. At appraisal, doubts
emerged about the absorption capacity of the Ministry of Public Works for such an amount within
the timeframe of one project. Hence the decision was taken to apply a programmatic approach with
a more modest financial commitment of the first project of around USD 50 million, bringing the total project cost to around USD 70 million. The programmatic approach would then allow more
flexibility to prepare the second phase through a successor project. A two-tranche Adaptable
Program Loan (APL) was also considered at this stage but not pursued further given mixed experience in project performance due to political or logistical constraints that often prevented
meeting the triggers necessary to advance the project to the next phase.
27. Risk score rating and projections of score reductions. The PDO indicator includes a reduction in the risk score for 34 dams (33 after restructuring), most notably aiming to reduce the
number of ‘high’ risk dams from 81% to <5%, and to achieve a reduction of the Overall Risk Index
of >30%16. The ICR team found several uncertainties and inconsistencies with this indicator.
28. First, based on discussions and documents reviewed for this ICR, this targeted level of reduction was found to be high, making it difficult for the project to achieve this target. For some
dams, the necessary reduction in the risk score to achieve targets outlined in project preparation
documents such as the Project Implementation Plan (PIP) or the Project Appraisal Document (PAD) was almost impossible to achieve. The modified ICOLD method used to calculate the score
assesses certain types of hazards and weighs them accordingly17. A certain risk exists due to the
structure of the dam (volume of the reservoir, height of the dam), which cannot be changed through
measures proposed under the project. Other risks originate from the size of downstream population to be evacuated (which in many locations is increasing due to population growth) or are associated
with new or future downstream developments. Moreover, the risk cannot become zero, and the
possible reduction is not proportional18. Considering this, it can be concluded that the target of the
14 Discussion reported in several Aide Memoires of preparation missions. The preparations for possible future
implementation were undertaken as ‘Special Studies’ under Component 1. 15 E.g. the First Water Resources and Irrigation Sector Management Program (WISMP) 16 The ICOLD risk categories are: low (<15), moderate (16 – 45), high (46 – 75) and extreme (>75). 17 The 12 risk types considered in the modified ICOLD method are described in Annex 2. 18 There is a limit of how much each dam can reduce its risk score. E.g. a dam rated as ‘extreme hazard’ (i.e.
a score of >75) can only reduce the risk score by e.g. maximal 20 points, reducing its overall risk rating by only 20-30%. A dam rated as ‘moderate hazard’ (i.e. a score of <46) may also be able to reduce the risk score
by maximal 20 points, reducing its overall risk rating by 40-50%.
18
project outcome indicator 1 (a), which aimed at reducing the percentage of dams rated as ‘high
hazard’ from 81% to less than 5%, was overly ambitious and could not realistically be achieved under the project.
29. Second, the Project Outcome Indicator in the PAD did not clearly define the list of dams
to which the percentages applied. The indicator suggests amongst others that the proportion of high
risk dams should be reduced from 81% to <5%; but the method for establishing the baseline figure of 81% or the target figure of <5% were not clearly defined. Based on the information provided in
the PAD and PIP19, the 34 dams mentioned in the indicator description comprised of two extreme
risk dams (6%), 31 high risk dams (91%) and one moderate risk dam (3%). The modelled reduction in risk score to be achieved under the project further projects that out of the 34 dams, 7 (20%)
would be classified as ‘high risk’ after the project intervention – significantly more than the targeted
5%, which translates into 1.7 dams (i.e. 1 dam in absolute numbers), and not considering the point raised above that some of the projected reduction in risk score was unrealistic to be achieved.
30. Considering this uncertainty about the intended target percentages, the outcomes are
assessed by disregarding the absolute numbers and only considering the difference in risk score
intended to be achieved. For example, 81% minus 5% is a net reduction of 76 percentage points, or 26 dams. Comparing this target with the actual number of dams for which the risk score was
reduced to ‘moderate’ (18 dams) the project outcome can be rated as reasonably successful.
31. Third, another factor influencing the achievement of the Outcome Indicator (i) (a) targets were changes in baseline values for the PDO targets that were established during appraisal. Risk
scores for dams are generally prone to fluctuations due to changing circumstances and conditions
of the dam and its surroundings, such as a change in downstream population, damages to the structure of the dam, etc. This applies even more for the number of old dams in the portfolio,
constructed several decades ago. Given that the physical remedial works at dams under the project
were carried out in phases, works for some dams were carried out several years after the baseline
scores were calculated. By then, the condition of several dams had changed and scores were found to be different than the baseline outlined in the PAD. This impacted the possibility of the project to
achieve its PDO indicator targets of reducing hazard categories.
32. Commitment from client. The experience of the Dam Safety Project (DSP) confirmed that works on existing dam structures for safety and operational improvement are technically
complex, new to the Indonesian Government and national contractors and thus require dedicated
support for capacity building. This lesson has been incorporated into the project design, with better
alignment of institutional development and execution of works to attune better to the absorptive capacity of government agencies.
33. Further, recognizing the linkage between the loss reservoir functionality and sedimentation
import from upper watersheds, a catchment-based activity based on the principles of Integrated Water Resources Management (IWRM) are needed. The experience of projects like the Water
Resources and Irrigation Sector Management Projects 1 and 2 (WISMP), as well as a variety of
Trust Funds on applying IWRM principles in Indonesia have been incorporated into the design of this project. However, implementation of these programs are often complicated by institutional
arrangements involving a range of different stakeholders, strict Government regulations on budget
allocations and execution and the delineation of roles and responsibilities.
19 See Figure 1 in Annex 2, Risk Score for Indonesian Dams to be rehabilitated under DOISP 1.
19
34. Assessment of risks. The PAD identified a series of risks to a successful implementation
of the project, the most critical of which were (i) Government commitment to reform and budget allocation for O&M requirements; (ii) limited capacity to assure quality of surveys, designs and
implementation, as well as limited capacity of financial management staff; (iii) a lack of community
participation; (iv) improperly done environmental and social assessments; (v) unfamiliarity with
Bank guidelines and procedures. The overall project risk was rated “moderate” after mitigation. The risks assessment and mitigation measures were generally on target, and while some were more
successfully mitigated than others, there were no unanticipated risks or missed opportunities for
mitigation that seriously limited achievement of project outcomes. The quality of some achievements, however, was adversely affected by delays in contract management.
2.2 Implementation 35. Decentralized implementation. Based on the lessons from the previous Dam Safety
Project (DSP), the design for rehabilitation and special studies was to be decentralized to the river basins instead of a centralized CPIU. However, this decision did not take into account the number
of dam related experts on the market in Indonesia. So for approximately 8 – 10 design or study
contracts each year, the number of highly-qualified national experts available either as individuals
or through the firms turned out to be limited, leading to the selection of less qualified experts and ultimately impacting the quality of the work produced. Decentralized implementation also
impacted the community related activities, which were supposed to be implemented by the
provincial basin organizations, as per design. Given that only one or two dams per province were being included into the community program, it did not make sense from an administrative and
financial efficiency point of view, to have each provincial basin organization conduct these
activities themselves. Hence in all provinces except for Central Java, the community related
activities were conducted by the PIU of the central level basin organizations.
36. Other issues that were not taken into consideration when decentralizing implementation to
the basin-level were the complex implementation structure and the division of roles and
responsibilities between the different levels of Government operating in one basin. O&M is the responsibility of either central or provincial level government, depending on the location, although
maintenance works are often carried out by provincial or district agencies, through various forms
of delegated arrangements. In the case of Indonesia’s largest and most important dam, the Juanda dam in Jatiluhur, the division of roles and responsibilities is even more complex. As part of a
cascade of three dams, different line ministries are involved. The National Electricity Agency PLN
is in charge of two of the dams (Cirata and Saguling, not part of DOISP), the Ministry of Public
Works (MPW) of Juanda / Jatiluhur. A state-owned enterprise (PJT) was created under the Ministry of State-owned Enterprises to be in charge of the profitable operations, while the maintenance
works are the responsibility of the basin agency responsible (BBWS) under MPW. At the same
time, the BBWS and the PJT arranged cross-support between each other to help with O&M activities, against an agreed fee. Since many of these arrangements are a mix between formal
responsibilities of the agencies and non-formalized arrangements, it is complicated to initiate
changes to these arrangements. Only recently, a joint coordination committee was established to coordinate the upstream hydropower operations and downstream flood control and bulk water
supply operations.
37. A risk index for assessing dam safety. For the Risk Assessment, the project was required
to use ‘an appropriate Risk Assessment Method’, as stated in the Results Framework. The scoring was done using the modified ICOLD Condition Rating Method. The modified ICOLD Method
provided the project with an internationally recognized methodology, but it also tied the risk
assessment into the constraints and shortcomings of that methodology (further described in Chapter 2.1 above). Especially the fluctuations of the risk scores between baseline in 2008 and a
20
reassessment of the score before the project works began (which has happened between 2011 and
2014) caused the score of about half of the dams under the project to start out with a higher risk score than envisaged in the baseline. This had an impact on the project’s ability to achieve the
targets. This issue may have been resolved early on if it had been addressed during the mid-term
review.
38. Procurement and contract management. During implementation, delays occurred in the procurement process and contract management of large procurement packages for Basic Dam
Safety Facilities20 (BDSF) and for several dredgers. BDSF have a significant influence on dam
safety and as such on the dam risk rating. However, a delay in bulk procurement of the facilities directly resulted in a delay in achieving the risk index targets. Similarly, the contract management
for the supply of several dredgers experienced issues causing a delay in provision and installation.
39. The initial procurement arrangement for the BDSF was to divide it into five packages with an estimated value per package between USD 608,000 and USD 642,000. Based on this package
value, National Competitive Bidding was agreed as preferred procurement method. Two packages
were awarded in 2013 and installed at the sites while other packages were delayed. At the time of
finalizing this report, the procurement of the remaining 23 BDSF was still in process. Following the delay, the Government changed the procurement method to International Competitive Bidding
(ICB) and combined dams into regional packages in order to attract more foreign firms to the tender.
It is expected that proper installation of the facilities can be completed in time, ensuring their functionality and training of Government staff for proper operation, as well as including standard
guidance to ensure the compatibility among the different systems.
40. The contract management for the procurement of the dredgers encountered financial difficulties that caused a delay in the process. Despite provisions allowing for demonization of the
contract in multiple currencies, the contract between the CPMU and the Indonesian supplier for
delivery of the dredgers was signed in IDR. This imposed a heavy financial burden on the supplier
after the Indonesian Rupiah (IDR) suffered from an estimated 30% depreciation against the US Dollar after contract signing. Rather than cancelling the contract and rebidding the contract was
extended and the dredgers finally delivered to site in December 2016.
41. The implications of these delays on the outcome indicator Reduction of Failure Risk are such that several of the dams will only actually drop to the lower risk category as targeted once the
BDSF are installed and operationalized.
42. Mid-term review restructuring. The project experienced delays in the early stages of
implementation and disbursement in 2009-10, which caused physical works to fall behind schedule. The main reasons for the delays were the slow adjustment of implementation units to Bank
procurement rules and a reorganization of the main implementing agency DGWR into new
Directorates, and in connection with this, the transfer of the CPIU from the Directorate of River and Coastal to the new Directorate of O&M. Further, an ongoing internal investigation by the
Institutional Integrity team (INT) for another project in Indonesia involved a company that was
also the lead firm in an existing joint venture contract under DOISP. As a result of the investigation, that company was barred from new tenders, which impacted the representation of the international
20 Basic Dam Safety Facilities include measuring tools and gauges that measure structural changes of the
dam, such as seepage, water height, embankment settlement, seismic intensity or reservoir water level.
21
partner in the joint venture and had implications on the performance of this contract due to the
absence of key consultants, including the team leader, for an extended period of time.
43. From 2011, overall project performance improved significantly and it was decided during
the mid-term review that the project would undergo a restructuring that included a revision of the
intermediate outcome targets, the reallocation of loan proceeds and the extension of the closing
date from December 2013 to November 201521. The restructuring was deemed a Level 2 given that the PDO did not change, and there were no changes to the safeguards or other arrangements.
44. Dam Portfolio Management. The newly established Directorate for Operation and
Maintenance under the DGWR attributed more attention towards a dam portfolio management approach, underscoring the Government’s commitment to the management of infrastructure and
the importance of O&M for the sustainability of their assets. This commitment was reflected in an
increase in O&M budget for dams over the following years: While in 2009, the government expenditures on O&M amounted to IDR 21 billion, by 2014 it had doubled to almost IDR 48
billion22 – an improvement compared to before, but still below actual O&M requirements.
45. Aside from the new Directorate, Dam Monitoring Units (DMU) were established in each
river basin, tasked with systematically monitoring and reporting on the situation of each dam to the also newly established Central Dam Monitoring Unit (CDMU) at national government level.
Following this overall increase in commitment to dam safety, support to the project CPIU also
improved and project progress improved significantly after the restructuring. Disbursement increased, and overall Implementation Progress improved from Unsatisfactory (May 2012) to
Moderately Satisfactory (February 2014), and to Satisfactory in December 2016.
46. Dam Safety Panel. A Dam Safety Panel was constituted at the beginning of the project, but mobilization turned out difficult due to the large number of dams to be covered over a
geographically dispersed area. Experts of various specializations23 have visited a number of dams
during the project, including an international expert specifically focusing on the installation of the
Hollow Cone Valve at the Juanda dam in Jatiluhur. The panels’ tasks included checking the quality of remedial works, monitoring seepage and providing recommendations for guidelines and
procedures that were in draft. Recommendations focusing on Standard Operating Procedures (SOP)
for cascade dams under emergency operations procedures included institutional mechanisms for coordinated operations procedures, hydro-met monitoring and flood forecasting & early warning
procedures as well as downstream protection and emergency preparedness plans.
47. Emergency Action Plans. With the passage of Government Regulation No. 37 on Dams
in 2010, the development of emergency action plans (EAPs) to reduce potential impacts caused by dam failure became mandatory for large dams. With support of the project, DGWR has developed
comprehensive guidelines which provide a basic structure for the development of EAPs. To date,
DGWR and the river basin organizations have developed EAPs for about 80 dams, of which 56 have been financed by the project. A review of a selected number of plans indicates that the level
of detail and the quality of EAPs varies widely, particularly in terms of the downstream inundation
mapping and modeling, as well as in sensitization of downstream communities. In terms of operationalization of the EAPs, Indonesia has experienced one event (Way Ela dam in 2013) that
21 Project Restructuring Paper, August 2013. See also Chapter 1.7 Other Significant Changes. 22 Project Progress Report, CPMU 2015. 23 Specialization of experts included hydro-mechanics, dam safety, hydrology, instrumentation, construction
and management.
22
provides insights into the effectiveness of the EAPs. With lessons from that event, it will be
beneficial to further strengthen coordination and implementation capacity of the involved stakeholders. This would require continuous coordination between the RBOs, local governments,
and emergency management authorities to ensure that the EAPs are updated regularly, as well
conducting simulation exercises to reinforce and test the EAPs to benefit the execution of the EAPs
in the event of dam failure.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization 48. M&E design: The objective and indicators were well designed to measure the project
activities. Both PDO and intermediate indicators are reflecting the main objective stated in the PDO,
i.e. increasing the safety of reservoirs and the strengthening the safety and O&M policies, regulation and capacity of the Government. The objective and indicators that were set-up at the
design stage remained valid until ICR reporting, with the exception of the overly ambitious risk
score targets. The means and method to measure the project achievements were well set-up. As part of the work of the preparation team, the baseline data of the risk score for 34 dams/ reservoirs was
collected during appraisal and become a benchmark to measure the project’s achievements. This
baseline score, however, proved to be inaccurate for some dams some years later when physical
works started and the score was re-assessed due to damages that had occurred in the meantime. These possible changes in the baseline were not taken into account for M&E design.
49. M&E implementation. M&E system was implemented as designed. The M&E system
was put in place at the startup of the project. CPMU supported by TA consultants undertook internal monitoring quarterly. External monitoring was done independently by consultants at the mid-term
and completion stages. At mid-term, a team of individual experts conducted independent
monitoring on water resources, economic, and environment including cost and benefit analysis of
the dams. Interim completion evaluation has been also prepared by individual consultants hired by CPMU. There is a minor discrepancy in the internal reporting (ISR) of the project achievements.
The ISR result section only reports the number of dam portfolio risk assessments without
highlighting the number of dam with failure risk reduction. Although it was not fully tracked in the ISR, the project’s M&E continuously monitor the number of dam with failure risks reduction in
line with the indicators set up in the loan agreement.
50. M&E Utilization. The data collected and the monitoring of progress and quality of project rehabilitation have assisted the project to: (i) Identify and remedy construction quality problems
and to incorporate better controls. Up to 2011, the O&M budget was calculated using the Modern
Equivalent Asset Value (MEAV) method, which resulted in insufficient O&M funds being
allocated to each dam. After an independent monitoring study provided recommendations to MPW on how to calculate O&M demands, real needs of the planning figures were used to calculate the
provision of O&M funds (AKNOP); and (ii) Identify the bottleneck in project management.
2.4 Safeguard and Fiduciary Compliance 51. Safeguards. Overall, the project did not create any significant environmental and social issues during its implementation. The project is a Category B project that triggered OP 4.01 on
Environmental Assessment and OP 4.37 on Safety of Dams. In the Environmental and Social
Management Framework (ESMF), the works under DOISP have been scoped so as not to include
any works with major environmental or social impacts. While the project is in compliance, reporting on the safeguard implementation including reporting of Environmental Management and
Monitoring Plan (UKL/UPL) for a number of subprojects was lacking. This is largely due to the
absence of a safeguard focal point assigned in the CPMU. For the successor project, capacity building and more training on safeguard is required for implementing units in any levels.
23
52. Fiduciary. The project has complied with the World Bank’s Procurement Guidelines and
remained moderately satisfactory throughout project implementation. This is mainly due to replacement of key experts after contract signing and delay in the procurement process of major
contracts: particularly the procurement of the Hollow Jet Valve replacement (CT-CW-2), as well
as significant delay in the contract implementation for the supply of dredgers (BOP-GD-02). These
resulted in delays in the project implementation schedule.
53. Overall, the project had an adequate financial management system with a moderately
satisfactory performance rating. The project encountered some problems at the beginning of the
implementation; disclaimer opinion on FY2010 project’s financial statement, delay on IFR submission, delay of budget effectiveness, and weaknesses on payment verification. But the CPMU
took follow-up actions as recommended by the auditors and the World Bank missions to improve
the project’s financial management performance. After 2010, the project consistently received unqualified audit opinions on its financial statements. At the time of closing, the project was able
to submit its financial report timely and complete the follow-up of all audit findings, including
completing the refund of ineligible expenditures to the designated account. One issue that remained
until the end of the project is the continuous delay of budget effectiveness, delaying project implementation. Close coordination between CPMU, PIUs, and the planning bureau of the ministry,
and having a financial management consultant within the CPMU who fully understands the
budgeting processes, are pre-requisites for a timely availability of the budget for this type of project.
2.5 Post-completion Operation/Next Phase 54. Additional Financing under preparation. To ensure the safety of all existing dams and
all newly constructed dams, the Government is continuing its programmatic approach to dam safety.
Given the success of DOISP, the Government as next step requested to scale up the project to
include support to the completion of the original dams and to further extend support in preparation for the expanded portfolio, resulting from the Government’s ambitious development program of 65
new dams until 2019. Hence Additional Financing (AF) is currently under preparation to support
this second phase (DOISP 2) scale up. The original components of DOISP will be retained under the AF. The DOISP2 AF will also scale up the portfolio approach developed under this project to
further enhance the regulatory and administrative arrangements for dam management and safety. It
will build on a rapid, simplified screening to be carried out under this project before the closing date of June 2017. This screening aims at defining the risk profile and identifying prioritized
interventions under DOISP2. A range of analytical work is being carried out in parallel to the
preparation of the AF, including a Public Expenditure Review on Public Spending for O&M, a
study on benchmarking of dam safety within river basin organizations, amongst others.
55. Special Studies. During the preparation of DOISP, the 34 dams to be included for remedial
works were part of a list of 63 priority dams as curated by the Government. A number of other
dams on that list required works that could not be carried out without more in-depth ‘special studies’ to determine the root causes for their reduced safety and inform detailed design of risk-reducing
remedial works as well as necessary environmental and social safeguards requirements. 22 of these
remaining special studies were included in this project to be carried out as preparation for the successor project (DOISP2). These 22 dams would then be the first number of dams to be addressed
under the portfolio approach, while the remaining 115 major dams owned by the Ministry would
undergo more in-depth analysis and prioritization before they are selected for remedial works.
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
24
Relevance of Objectives Rating: High
56. The PDO of increasing the safety and the functionality with respect to bulk water supply
of large Ministry of Public Works-owned reservoirs; and strengthen the safety and operational
management policies, regulations and administrative capacity of Ministry of Public Works remained relevant throughout implementation. It was rooted both in the Government’s Long-term
Development Plan, of which several programs are related to water resources, including
infrastructure development, food security, energy, climate change, environmental protection, health, and employment creation, among others. The Long-term Development Plan is segmented into five-
year medium-term development plans (RPJMN), which translate the long-term goals into specific
development priorities during that period. The first RPJMN 2004-2009 placed emphasis on infrastructure development, sustainable development of natural resources and food security, among
others; all of which are reliant on the effective and sustainable use of water resources. The
Government has subsequently launched an ambitious program to develop 65 new dams, with
around 13 already under construction. This program will improve storage capacity and overall resilience but will also increase the burden on Government capacity, making DOISP highly relevant.
57. The PDO is also aligned with the World Bank’s Country Partnership Frameworks, both at
the time of appraisal as well as at the time of the ICR. During appraisal in 2008, the PDO aligned with the CPS24 focus areas of strengthening Indonesia’s institutions and investments in (water)
infrastructure, climate change and disaster mitigation. At the time of the ICR, the PDO aligned with
the current CPF’s focus areas Infrastructure Platforms at National Level and Collecting More and Spending Better25. The project objective is especially relevant as the current Government further
developed its vision of water and food security and translated it into an ambitious program of
constructing 65 new dams within its legislative period 2014-2019. In this context, support is
becoming more relevant now than at time of appraisal given the rapidly increasing portfolio, competition over water resources, need for multi-purpose management and challenges of national
capacity. Climate change scenarios are predicting more intensity of extreme weather, putting
additional constraints on safe, secure supply of water.
Relevance of Design Rating: Substantial
58. Following the first Dam Safety Project (DSP) in the 1990s, Indonesia embarked on a sector
wide, programmatic reform of its water resources and irrigation sector. This project is thereby following a series of projects, laws and regulations in the broad water resources sector, with the
aim of addressing its strategic dams and reservoirs at a portfolio level. This project was designed
as the first of a series of projects to increase dam safety, functionality and prolong the life span of the asset. The design of DOISP aimed to be an evolution of the DSP, establishing a basic framework
for dam safety at central and provincial levels and carry out remedial works. DOISP as the follow
up project intended to consolidate the achievements of DSP and develop a portfolio approach for dam safety, as well as carry out minor remedial works as well as prepare more extensive surveys
for more complex works to be done under a successor project. The DOISP design thereby aimed at
advancing the Government’s reform agenda and strengthen the performance of institutions
responsible for maintaining dam safety.
24 Country Partnership Strategy FY09 – FY 12, The World Bank Group, 2008. 25 Country Partnership Framework FY16 – FY20, The World Bank Group, 2015.
25
59. As described in chapter 2.1, the project’s components were well designed to advance the
PDO, and implementation arrangements were built on the lessons learned from DSP, emphasizing the need for a decentralized model of implementation in the course of Indonesia’s decentralization
laws that were passed in 2001. About 60% of the total project cost consisted of investments in
infrastructure, studies, investigations and designs (SID) or dam safety instrumentation. The results
indicators adequately measured the progress towards achieving the PDO with the exception of one of the indicators as already described in section 2.1 where the target was set unrealistically high.
3.2 Achievement of Project Development Objectives (Efficacy) 60. The Project Development Objective consists of two parts: (i) increase the safety and the
functionality with respect to bulk water supply of large MPW-owned reservoirs; and (ii) strengthen the safety and operational management policies, regulations and administrative capacity of MPW.
Overall, the Project Development Objective was largely achieved as described below.
PDO part (i) Increase the safety and the functionality with respect to bulk water supply of
large MPW-owned reservoirs.
Rating: Substantial
61. The first part of the PDO was to be achieved by reducing the risk of dam failure for 33
dams 26 through physical remedial works, by preparing Spillway Emergency Operation Plans (SEOP) for 56 dams and by improving the Government’s dam portfolio management program.
Overall, the failure risks of all dams in the project have been successfully reduced (see Table 1
below as well as the information provided in Annex 2). The Outcome Indicator results show that the project has successfully reduced the failure risk of all ‘extreme’ hazard dams to ‘high’; the
failure risk of 20 out of 31 dams from ‘high’ to ‘moderate’; and the overall hazard of dams under
the project by 25%.The number of ‘extreme’ hazard dams in the portfolio has been successfully
reduced to 0%, as set out in the indicator target. The number of ‘high’ hazard dams in the portfolio has been reduced from 31 to 13 (38%), thereby falling short of achieving the target of reducing 27
‘high’ hazard dams to ‘moderate’ hazard set out in the PDO indicator27. The overall hazard of the
33 dams has been reduced by 25%, falling slightly short of the target of >30% set out in the PDO indicator. The other targets of part (i) of the PDO indicator, namely improved DGWR Dam Portfolio
management and the Dam Safety Unit (DSU) completing >75% of its priority dam inspection and
certification load has been achieved.
62. The reasons for the shortcoming of the reduction of ‘high’ hazard dams from 81% to <5%
has been described in Chapter 2.1 above: The original indicator targets were unrealistic.
Considering the type of works done in the time and with the resources available, the overall hazard
reduction of 25% can be considered a significant achievement of the project. At the time of this report, implementation was still ongoing, and with finalization of several outstanding works
26 The target number of dams in the outcome indicators was changed from 34 to 33 with the first restructuring
due to damage that occurred to one dam (slope sliding) of the initial list of 34, causing it to be rehabilitated
urgently using Government budget. Later, another dam was rehabilitated instead under the project, leading
to a total number of 34 rehabilitated dams despite the revised target of 33. 27 As shown in Table 1 below, the baseline of 34 dams at appraisal included two extreme risk dams, 31 high
risk dams and one moderate risk dam. Out of the 31 high risk dams, 20 were reduced to moderate risk leaving 11 dams in the high risk category; two dams, however, were added to the high risk category after their extreme
risk was reduced to high risk, reaching a total of 13 high risk dams.
26
(specifically the installation of the Basic Dam Safety Facilities BDSF), the risk score is expected
to be reduced further for several dams by a few points.
63. The Spillway Emergency Operation Plans were prepared as part of Emergency Action
Plans for 56 dams28 under the project. Dam portfolio management improved as can be seen by an
increase in O&M budget between 60% - 120% compared to 2009, ongoing training of more than
650 staff and dam operators, hydrological maps on probable maximum floods for different regions and quality assurance systems as well as by the establishment of a functional Central Dam
Management Unit and Dam Monitoring Units in the river basin organizations.29
Table 1: Detailed results of Project Outcome Indicator number (i) and its sub-indicators a-c.
No. as
per RF
Project Outcome Indicator and
sub-indicators.
At
appraisal
Re-calculated
baseline
At ICR Target
(i)(a) Number of dams for which dam
failure risk should be reduced
34 34 34 33
(i)(a)a. Number of ‘extreme hazard’ dams
2 (6%) 2 (6%) 0 (0%) 0%
(i)(a)b. Number of dams at ‘high
hazard’
31 31
11+2 = 13
(38%)
From 81%
to <5%
Number of ‘moderate hazard’
dams
1 1 1+20 = 21
(62%)
From 0%
to >95%
(i)(a)c. Overall hazard reduction 25% >30%
Note: The number of high hazard dams at ICR consists of 11 originally high hazard dams plus 2 originally
extreme hazard dams. The overall number of dams reduced from high hazard to moderate hazard is 20.
This Project Outcome Indicator corresponds to the Project Outcome Indicators described in the Results
Framework for PDO Part (i) (See Table A2 - 1 in Annex 2) and is also listed as Intermediate Outcome
Indicator No. 1 in Chapter F of the Data Sheet.
PDO part (ii) Strengthen safety and operational management policies, regulations and
administrative capacity.
Rating: Substantial
64. The second part of the PDO was to be achieved through issuing Government Regulations,
Ministerial Decrees and enhancing administrative procedures and capacity. Overall, this has been achieved. A Government regulation on dams was issued during the implementation of the project,
regulating overall management of dams and its safety procedures. Further, 33 guidelines and
manuals were prepared and staff were trained accordingly. The number of guidelines and manuals
and its status prepared under the project is listed below:
Table 2: Overview of Guidelines and Manuals drafted and issued.
Guidelines and Manual Number Remarks
Ministerial level 4 4 approved
Directorate General Level 31 15 approved
16 in deliberation
Others (Risk Assessment} 5 5 approved Note: Deliberation refers to ongoing internal Government consultations among different departments.
28 Originally, it was envisaged to prepare 33 Spillway Emergency Operation Plans. This number was
increased to 56 during restructuring realizing SEOPs could be prepared under the Emergency Action Plans. 29 Annex 2 provides more detailed information on the results achieved.
27
65. Administrative procedures and capacity was enhanced by training key staff as well as establishing a Dam Monitoring Unit (DMU) in each of the Balais as well as a Central Dam
Monitoring Unit (CDMU) in DGWR. The DMUs monitor dam safety and regularly report on it to
the CDMU. Their reports are the basis for priority maintenance activities as well as maintenance
budget planning.
Table 3: Overview over achievements disaggregated by PDO and PO Indicators.
PDO Project Outcome Indicator Achievem
ent
Remarks
Part (i): increase the
safety and the
functionality with
respect to bulk water
supply of large
MPW-owned
reservoirs;
Indicator (i) (a):
Reduction in dam failure risk of 33
rehabilitated dams using an
appropriate Risk Assessment Method
and Achieving operational Spillway
Emergency Operation Plans for these
dams. “Extreme hazard” dams reduced
from 3% to 0%; “High hazard” dams
reduced from 81% to 5%; Overall
hazard of 33 dams reduced by >30% of Risk Score
Largely
achieved.
34 out of 33 dams
rehabilitated; Extreme
hazard dams reduced to
0%, high hazard dams
reduced to 38% (target:
5%), overall hazard of
34 dams reduced by
25.3% (target >30%)
SEOP achieved for 56
dams (target: 34) See also Table 1
Indicator (i) (b):
DGWR dam portfolio management
improved by established: Annual dam
O&M funding program; Dam human
resources development program; Dam
hydrology program; Dam quality
assurance program; Functional CDMU
Achieved.
Indicator (i) (c): DSU has completed
>75% of its priority dam inspections
and certification load (including 2-3
large mine tailing dams)
Over-
achieved.
94% of dams inspected
out of a target of >75%
Part (ii) strengthen
the safety and
operational
management policies,
regulations and
administrative
capacity of MPW.
Indicator (ii) (a): Government
Regulation on Dams and Ministerial
Decrees issued
Achieved.
Indicator (ii) (b): Administrative procedures and capacity enhanced
Achieved.
3.3 Efficiency Rating: Moderate
66. The economic rationale of dam rehabilitation and safety improvement is to ensure safety and reduce risks of dam failure and consequently prevent or minimize damages to downstream
property and environment, loss of life, loss of reservoir supply and replacement costs of the dam
or construction cost of alternative water supply. An economic and financial analysis was prepared at the time of appraisal, taking into account certain assumptions on dam failure probabilities,
financial data on public expenditures and currency exchange rates at that time. For this report, an
economic analysis was also prepared, following the methodological approach of the appraisal stage.
More detailed information including assumptions used for the analysis can be found in Annex 3.
28
67. The results of the economic analysis indicate a positive Net-Present Value of US$ 56.3
million as well as Internal Rate of Return of 28.7% at 6% discount rate. This is less than assumed at appraisal (NPV US$108.2 million, IRR 32.8%), due to a smaller overall reduced risk score
achieved than originally targeted.
68. It is noteworthy that dam safety is unique in that it represent an extreme situation
characteristic of a low probability event, but with high consequences or hazard. Thus, conventional rules of economic analysis are difficult to extrapolate and extend to such events. For instance,
human life is generally accepted as the most important consequence and often dominates dam
safety decisions. Unfortunately, the confidence with which life loss can be estimated is low, which is a hindrance to credibility and value of dam safety risk assessment results30. However, application
of cost benefit analysis is still relevant as there are insufficient disposable financial resources to
improve the safety of every dam without limit. The analysis is particularly useful for setting priority or determining the order in which dam safety rehabilitation projects should be approached within
a portfolio of dams. The extremely low probabilities of dam failure masks the risks. However,
when the failure actually happens due to neglect or lack of necessary measures, the consequences
are usually very costly, as evidenced by the recent two dam failure events in Indonesia itself31.
69. The project was extended three times to a total of 3.5 years beyond initial closing date. The
reason for these extensions was due in part to: (i) initial delays in implementation, (ii)
reorganization of the implementing agency, (iii) issues around procurement and contract management, and (iv) safety concerns with regards to weather conditions32.
70. Given that the economic indicators remain below the value calculated at appraisal, and
given the time extension of altogether 3.5 years, efficiency has been rated as ‘moderate’.
3.4 Justification of Overall Outcome Rating
Rating: Moderately Satisfactory 71. Given the high relevance of the PDO, the substantial relevance of the design and
implementation, the substantial achievement of the PDO to date and the planned activities
throughout the final year of implementation33, and given the moderate efficiency, the project has been rated as “moderately satisfactory”.
3.5 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
72. The implementation of Community Participation (CP) piloted in 20 schemes for reservoir greenbelt and 4 schemes for watershed management program was running during 2011 to 2014.
30 Loss of life was not used in the quantitative calculations for the economic analysis. 31 In 2009, the Situ Gintung dam collapsed due to a failure to implement appropriate structural and non-
structural dam safety measures (98 casualties). In 2013, the Way Ela dam collapsed due to a hill landslide;
but after the experience of Situ Gintung four years prior, government agencies were better prepared with
early warning systems and awareness among communities. As a consequence, no human life was lost, only
three people went missing and structural damage could be reduced – although the storage volume of the Way
Ela dam is more than 40 times bigger than that of Situ Gintung. 32 The third extension of 6 months was mainly caused by weather related delays in installation of two Hollow-Cone Valves in Indonesia’s largest dam. Due to the El-Niño phenomenon the dry season of 2016 experienced
unusually high rainfall, thereby causing higher water levels in the reservoirs than planned. This impacted the
installation of the valves, which had to be delayed due to safety concerns. 33 At the time of submission of the ICR, negotiations for the proposed Additional Financing of DOISP2 had
been successfully concluded.
29
Though still limited in scale, there are positive impacts achieved by the program in terms of
community awareness to maintain dam safety and conserve the watershed area, as well as impacts on social and economic life of the community both directly and indirectly. The economic impact
of the program on communities has been less visible, mainly because income generating activities
proposed through the community work plans (RKM) were limited in scope, and have not yet been
implemented in some areas. With some improvements, in particular strengthening community institutions, recruiting capable facilitators and support from relevant stakeholders, the CP program
initiated by DOISP is worth continuing in the successor phase of the project.
73. The project did not have a specific poverty or gender focus.
(b) Institutional Change/Strengthening
74. The long-term program of support to dam safety, from the Dam Safety Project, over several
water resources projects to the current programmatic approach to dam safety, has helped the Government establish a comprehensive institutional framework that positions well in advance of
large increase in the dam portfolio through the planned and ongoing construction of 65 new dams
until 2019. The project had a clear focus on strengthening institutions with regards to the overall
dam safety portfolio in Indonesia. Achievements included issuing a Regulation on Dams34. It further included establishing Dam Management Units in each river basin organization, in charge
of systematically monitoring on the condition of dams in the respective Balais. For the most part,
these DMUs have become important and well-functioning entities in the Balais. Further indicators of successfully strengthening institutions are the increase in O&M budget, as mentioned above, the
capacity building of Government officials, and the establishment of a Central Dam Management
Unit, overseeing the overall dam safety situation in the country35.
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
No beneficiary survey or stakeholder workshop has been conducted for this report.
4. Assessment of Risk to Development Outcome Rating: Moderate
75. A number of risks to the development outcome exist, none of which rank as Significant or
High. The main risks include:
76. The biggest long term risk remains the lack of a dedicated revenue stream to support O&M
due to insufficient water user fees. Although farmers are the biggest user of bulk water from
reservoirs, they do not pay user fees for water provided through irrigation systems, as per the Indonesian constitution. Revenue streams for dam operators are therefore limited to fees from other
water users, such as water utilities or hydropower operators. The revenues generated through these
streams are limited so that the budget for O&M of dams relies heavily on Government transfers. This increases the risk of continuous provision of sufficient funds to ensure dam safety and
functionality. The project provided assistance to the overall management of O&M in a
programmatic way, and while the O&M budget for dams has increased during the course of the
project it continues to remain vulnerable to shifting priorities. Further mitigation measures to this risk provided by the project included preparing O&M plans, new regulations, establishing an own
Directorate for O&M within the Ministry of Public Works and Housing, establishing a Dam
34 Government Regulation No. 37/2014 on Dams was issued as an umbrella for national dam safety policy
and management 35 This was still in progress at the closing date for this report.
30
Monitoring Units at the river basin and central level, and providing training on O&M to dam
operators. The Additional Financing will further ensure the continuation of Government commitment to improving the adequacy and appropriateness of O&M in the sector.
77. Coupled with the financial risk of O&M is the risk associated with incentives for new dam
construction rather than for sustainable rehabilitation or O&M of dams. Especially the Government
program of constructing 65 new dams until 2019 has implications on the availability of funds, experts on the market and priorities within the Government agencies to deliver this ambitious
agenda and at the same time provide sufficient support to dam safety measures and regular O&M
activities. Along with the construction of new dams comes the commitment for continuous recurring expenditure requirements for O&M, which have to be taken into account for future
planning and budgeting. The institutional results achieved under the project will be key to ensuring
dam safety and functionality. The expected results under the AF will further support this aim.
78. Aside from the financial constraints, a risk to development outcome is also caused by a
shortage of skilled human resources available for dam safety overall. Following a zero-growth
policy for the civil service over the past few decades, limitations in qualified personnel continue.
More frequent rotations throughout the civil servants’ career paths translate into longer time to gain relevant experience for the small number of new staff designated to dam safety in the ministry. The
decentralization reform of 2001 has furthermore shifted responsibility for dam related works to
central government, creating a gap between mostly older, experienced local-government staff in the field, most close to retirement, and junior to mid-career professionals with only limited
experience to fill the existing positions. With the large portfolio of new dams, the growing need for
skilled personnel to carry out O&M, and with additional positions created by establishing new institutions under this project (CDMU, DMU or Directorate for O&M), the risk pertains that
sufficiently qualified persons can not be found to ensure dam safety for all dams in the future.
79. Uncertainties further exist with regards to the continuous support of communities in the
vicinity of the dams and reservoirs to the safety of the dam. The support of the communities depends on many factors, including the economic hardship forcing them into income-generating activities
with negative impact on the dam/reservoir, or a lack of understanding of direct and indirect impacts
of their actions on dam safety. This risk could be exacerbated by an inadequate proactivity from the Government agencies tasked with community engagement. Within the project, the Community
Participation program was undertaken with good results, achieving positive impact for both the
dams as well as well as the communities. It is proposed to be continued in the AF project DOISP2.
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry Rating: Moderately Satisfactory
80. The Bank team was well experienced and knowledgeable drawing on a long standing
relationship with GOI on water resources in general, and on the development of dam safety policies and institutional capacity in particular. The Government agencies responsible for dam safety were
very motivated in improving the functionality and safety of its dam portfolio, and the Bank
provided sound advice and assistance in this process. Good preparation using lessons from national and international experience was fundamental for the successful implementation of the project and
the acquired knowledge proved to be a worthy asset during its execution. The complexity of the
implementation arrangements were, however, slightly underestimated, leading to delays in
implementation after project effectiveness.
31
81. The Results Framework was well designed in capturing the PDO and well aligned with the
components. Issues appeared with regards to the high targets to be achieved under the PDO indicator (i)(a). Further, the extension of 3.5 years indicates an underestimation of the initially
designed project duration of 4.5 years.
(b) Quality of Supervision Rating: Moderately Satisfactory
82. Bank supervision took place on a regular basis, providing appropriate and well-targeted
advice and observations. The aide memoires provided evidence of regular supervision and professional advice given by the Bank’s experts throughout the project. Timely response to client
request was regularly provided, and adjustments were successfully made to reorganization of the
client’s implementation agency DGWR. Despite a frequent turnover of Task Team Leadership, expert advice was provided regularly to support the client in a range of upcoming issues.
Nonetheless, substantial delays in the procurement and installation of some works packages
occurred.
(c) Justification of Rating for Overall Bank Performance Rating: Moderately Satisfactory
83. The quality at entry and the quality of supervision are rated Moderately Satisfactory, thus, the overall Bank Performance is rated Moderately Satisfactory.
5.2 Borrower Performance
(a) Government Performance Rating: Satisfactory
84. The Government visibly supported the Project given that it is in line with a long-term
commitment in the sector, and the first of several projects in a programmatic approach to dam
safety. The project was implemented as a “national government project”, involving only national-government budget. The overall policy guidance was provided by the National Steering Committee
for Water Resources (NSCWR) in Bappenas, which has been providing the same useful oversight
to other World Bank financed projects in the sector. Implementing agency was the Directorate General for Water Resources (DGWR) in the Ministry of Public Works.
85. Reorganization of the DGWR led to the establishment of a special Directorate for
Operation and Maintenance, to which the Implementation Unit for this project was moved. This
reflects an increased commitment from the Government towards allocating resources to maintaining water resources infrastructure assets – the basis for a dam safety program. With the
achievements of the majority of the project’s targets, the increased commitment to O&M and the
good progress in the Community Program, the Government has shown its commitment to the project. Cooperation between DGWR and the Bank was satisfactory throughout the Project’s
execution.
(b) Implementing Agency or Agencies Performance Rating: Moderately Satisfactory
86. As mentioned, the implementing agency DGWR was well committed to the programmatic
dam safety approach. The advice given and the actions agreed upon in the aide memoires were mostly followed up in due time. Along with creating a Directorate for O&M, the Government also
increased allocated funding to O&M in the sector, issued Dam Regulations and associated manuals
32
and guidelines, and followed through with numerous capacity building and training opportunities
under the project.
87. Shortcomings include insufficient safeguards management due to the absence of a
safeguards focal point, lack of sufficient attention to management of contracts as well as fiduciary
performance.
(c) Justification of Rating for Overall Borrower Performance Rating: Moderately Satisfactory
88. Given the satisfactory performance of the Government, and the Moderately Satisfactory Performance of the Implementing Agency, the overall Borrower Performance is rated Moderately
Satisfactory.
6. Lessons Learned
89. Mechanisms of measuring achievements should include only factors/variables that can be influenced by the project. The modified ICOLD method was used to measure risks to dam
failure. While this method is an internationally accepted methodology, it includes several items that
are not imposing an increased hazard, still add to the overall risk score, but are difficult or impossible to influence under the scope of a project. Examples are the business risk to the dam
owner in case of a failure, the potential damage to downstream population in case of a failure,
downstream asset development or structural specifications such as dam height or reservoir volume.
This can be problematic if the results indicator is requiring the score to pass a certain threshold into a lower overall risk score as success measure. It is recommended to carefully consider PDO
indicator targets that take into account which factors the project can influence and utilize more
disaggregated scoring targets that are not aiming at a lower risk category but a certain reduction in the total score for each dam.
90. The identification of and participation by the local government agencies in the
Community Participation Program (CP) is essential to the effectiveness and sustainability of
the initiative. CP activities were to be implemented by the river basin organizations (Balai) through local facilitators in selected pilot locations to prevent and mitigate the impact of sedimentation on
reservoirs. While the facilitators effectively fulfilled their contract requirements, they received little
tangible guidance from the Balais, who did not have community engagement as part of their basic tasks and functions. The limitation to certain selected sites further limited the scale up of the
program for those Balais eager to do so. While the CP program under the project was successful in
engaging communities with maintenance, dam safety and watershed management, leadership of Balais remains crucial for effectiveness and sustainability of the initiatives. To improve the CP
program in the successor project, it should be ensured that the local government agency responsible
for CP has the resources and skills required, and also receives appropriate training to provide
effective guidance to the facilitators carrying out the activities; that it includes dam maintenance through the sedimentation management aspects, involving communities in land care education and
using market-based mechanisms for ecosystem services by local people.
91. The benefits of decentralizing management responsibilities to the subnational level can be eroded if there is insufficient capacity to meet the increased demand. The decision to
decentralize several of the activities under the project to sub-national Balais was aimed at avoiding
some of the lessons from the predecessor project DSP. However, it did encounter several constraints during implementation, such as a lack of resources and experts on the market to carry
out a number of designs and studies within a short period of time; or to provide resources towards
33
small scale pilot activities in geographically dispersed locations. In order to attribute activities to
implementing agencies at the right levels of government, their capacity to carry out the tasks should be well examined, and support should be provided from central level in case there are constraints
or shortages.
92. The weakness in the design of contracts can cause significant delays, with negative
implications on meeting overall project targets. Significant delays occurred in the procurement of some packages and contracts under the project, especially the procurement of the dredgers, the
hollow cone valve as well as the BDSF. The reasons include financial difficulties due to the
depreciation of the Indonesian Rupiah, exacting management of ongoing contracts or the design of procurement packages. A limitation of specialized expertise on the local market exacerbated these
constraints. Overall, it can be concluded that weaknesses in the design of the contracts as well as
overall contract management can cause significant delays with implications on meeting overall project targets. It is recommended that especially factors such as currency exchange rate
developments, or the size of procurement packages for similar goods and services be examined
carefully and the task team provide thorough assistance on the process to the PIUs. Going forward
into scaling up the overall project approach to the larger dam portfolio in Indonesia, it is further recommended to carry out a market analysis of available experts to ensure the procurement plan
can be carried out in a realistic time frame. This is especially important as the Government is
currently constructing 65 new dams throughout Indonesia, which does require a large number of specialized experts and imposes even further constraints on the availability of these.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/implementing agencies 93. Comments were received by the borrower during several discussions. In principle, the
borrowers agreed with main observations conducted and lessons learned suggested by the Bank
team. Further, initial lessons of the ICR have been used to inform the preparation of the Additional
Financing of the successor project DOISP 2.
94. A summary of the borrower’s comments can be found in Annex 5.
34
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in USD Million equivalent)
Components
Appraisal Estimate
(Bank Finance +
Counterpart fund)
(USD millions)
Actual/Latest Estimate
(Bank Finance +
Counterpart fund)
(USD millions)
Percentage of
Appraisal
Component 1 34.17 31.79 93%
Component 2 14.56 9.57 66%
Component 3 15.06 5.50 37%
Component 4 2.25 3.99 177%
Component 5 4.38 4.65 106%
Total 70.43 55.50 79%
(b) Financing
Source of Funds Type of Co-
financing
Appraisal
Estimate
(USD
millions)
Actual/Latest
Estimate
(USD
millions)
Percentage of
Appraisal
Borrower 20.43 10.45 51%
International Bank for Reconstruction
and Development 50.00 45.03* 85%
*Note: This amount reflects the actual expenditures made under the project as of January 2017. The amount differs from the disbursed amount indicated in the Data Sheet (Section A: Basic
Information: USD 47.02M), which reflects the amount disbursed by the IBRD into the GOI’s
Special Account.
35
Annex 2. Outputs by Component
Results Framework Table A2 - 1 below provides the Results Framework as it was outlined in the Loan Agreement.
Table A2 - 1: Results per Outcome Indicator
Project Development
Objectives
Project Outcome Indicators
(as per loan agreement, including
amendments)
Progress as of December 2016
Part (i): To increase the
safety and functionality
with respect to bulk
water supply of large
MPW-owned reservoirs;
Indicator (i) (a): Reduction in dam failure
risk of 33 rehabilitated dams using an
appropriate Risk Assessment Method and
Achieving operational Spillway
Emergency Operation Plans for these
dams.
a. “Extreme hazard” dams reduced from
3% to 0%;
b. “High hazard” dams reduced from
81% to 5%;
c. Overall hazard of 33 dams reduced
by >30% of Risk Score
a. 2 dams (6%) reduced from
‘extreme hazard’ to ‘high hazard’.
b. 20 dams reduced from ‘high
hazard’ to ‘moderate hazard’,
reducing the ‘high hazard’ risk
from 81% to 38%
c. 25.3 %
Indicator (i) (b): DGWR dam portfolio
management improved by established:
a. Annual dam O&M funding program
b. Dam human resources development
program
c. Dam hydrology program
d. Dam quality assurance program
e. Functional CDMU
a. Ongoing for 58 dams
b. Trained staff by DSU in 28 dams,
by TA CPIU in 64 dams,
international training in 2 batches
c. Ongoing for 33 dams
d. Available and ongoing
e. Established.
Indicator (i) (c): DSU has completed >75%
of its priority dam inspections and
certification load (including 2-3 large mine
tailing dams)
- 37 dams inspected by TA CPIU;
- Priority dams (special study) not yet
certified
- 25 dams non-DOISP have been
certified
- 47 dams under safety review
Part (ii): Strengthen the
safety and operational
management policies,
regulation and
administrative capacity
of MPW
Indicator (ii) (a): Government Regulation
on Dams and Ministerial Decrees issued
PP 37/20103 on Dams Issued:
10 ministerial regulations to be issued
Indicator (ii) (b): Administrative
procedures and capacity enhanced
On-going in 4 PIU Directorates of
DGWR and 10 PIU-Balais / B(B)WS
36
Table A2 - 2: Results by Intermediate Outcome Indicators
Intermediate Outcomes Intermediate Outcome
Indicators
Progress as of October 2016
Outcome (a)
The functionality, safety and
economic life of restored large
MPW-owned dams is improved
and sustainable, while basic
operational safety of un-repaired
dams has been kept at a
manageable level during the
Project.
Outcome (a)
(i) Dam Portfolio Risk
Assessment indicates that
functionality of about 33 MPW-
owned dams is restored, safety
risks of at least 22 dams greatly
reduced and that the risks of 23
un-restored dams (under
successor project) are still
manageable; (ii) Spillway
Emergency Operation Plans
(SEOPs) publicly accepted and
warning system communications
functional for 34 dams. (iii)
Economic Lifetime expectation
increased by 5%. (iv) Bulk water
supply capability restored for
>25 dams.
(i) 34 dams rehabilitated under
the project.
23 Special Studies prepared.
(ii) 56 SEOPs prepared
(iii) Economic lifetime has been
extended through repairs and
improved functionality, but the
exact percentage was not
available in time for this report.
Based on discussions with the
teams, it is estimated that
expected economic lifetime has
been increased by more than 5%.
(iv) Bulk water supply capability
was restored through restoration
of spillway functionality,
remedial works and improved
emergency operating plans,
altogether for more than 25
dams
Outcome (b)
(i) DGWR aware of the level of
serious sedimentation of
important large dams and can
formulate a mitigation program
to prolong economic life &
ensure dam safety (inclusive of
decommissioning planning if
necessary).
(ii) (Sub-)catchment
management and improvement
carried out reducing erosion on
community participation
Outcome (b)
(i) Reservoir Survey of 30 or
more severely sediment-
impacted large dams completed
and structural and non-structural
sedimentation mitigation
program for these dams is ready
for execution.
(ii) At least 25% of the
households in the pilot areas join
and participate. Fifty percent of
erosion-prone sites in and along
rivers in the (sub-) catchment
identified and improved.
(i) Done for 31 dams.
(ii) 37% of households
participated.
Outcome (c)
DSU adequately staffed as per
its DOISP Priority
Implementation Plan and,
national consulting firms and
contractors certified by
INACOLD as eligible for dam
design and works.
Outcome (c)
Fifteen structural and/or
functional certified DSU staff,
and a total of 15 private
engineering firms and
contractors certified.
15 staff recruited and trained,
but none certified as certification
regulations changed during
implementation to no longer be
under Government
responsibility. Preparations have
been conducted to facilitate
certification.
37
The tables and figures in Annex 2 below provide additional information about the outputs,
achievements and results of the project. The information provided in the tables and figures may partially be overlapping with indicators described in the Results Framework above as well as the
Data Sheet, but are not intended to be of identical format. The information below is rather intended
to provide an additional, more detailed understanding of the project’s overall achievements and
results in form of. Information is taken from project documents, such as the PAD, the PIP or project progress reports, as well as depict the author’s own design.
Results by Component Table A2 - 3: Results by Component
Progress of Outcome Indicators (as of October 2016)
Project Component and
Outcome Indicators
Units Target Target
(after
restruc-
turing)
Achieved Remarks
Component 1
Dams Rehabilitated Dam 34 33 34 Achieved.
Basic Dam Safety
Facilities (BDSF)
installed
Dams 34 33 10 Delays in procurement process.
Remaining BDSF currently re-
tendered in different package format.
Special Studies Dam 22 23 23 Prepared and submitted for review and
clearance.
Improve operational
hydrology, review
flood frequency,
assess spillway
capacity and
downstream risk and
preparation
Dam 56 56 56 Included in the scope of work of the
Emergency Action Plans (EAP) and
Special Studies.
Component 2
Preparation of O&M
plans (O&M manuals,
instrument monitoring
& data processing,
SOP, NBB)
Dam 56 51 Submitted for review.
Emergency Action
Plan (EAP)
Dam 56 56 56 Finalized and included in special
studies where applicable.
Staff Training for
O&M and Safety
Monitoring
Dam 63 64 Training has been conducted.
Community Participation (CP)
Dam 20 18 18 Community MOUs signed, 2 dams under PJT I not pursued further
Component 3
DOISP Reservoir
Survey
Dam 30 30 31 Included in scope of work of EAP and
Special Studies
Study for
decommissioning of
Pack 1 1 0 Cancelled as no dam was to be
decommissioned
38
severely sedimented
reservoir
MOU between
community group and
dam management in
pilot area
Catch-
ment
4 4 4 4 MOUs signed, action plans partly
completed.
Percentage of HH
Joined the CP
% 25 25 37 37% of households have joined in
watershed management.
Component 4
Preparation of
regulatory documents
(guidelines and
manuals) on dam
safety
% 100 100 100 4 Ministerial Regulations related with
dam safety and management were
finalized, another 29 related guidelines
and manuals were also prepared, 24 of
which are already completed.
Awareness campaign
and training on
regulation and
guidelines
% 100 100 100 8 trainings on dam safety management
conducted and attended by 651 staff
from River Basin Organizations
(Balais). Various seminars on better
dam management were carried out.
Strengthening and
equipping DSU and CDMU
% 100 100 100 Completed
Establish and support
Dam Safety Panel
Pax 3 6 6 1 international and 5 national panel
members
DSU staff recruited
and training
Pax 15 15 15 Completed, although rotation caused
some of the staff to move.
INACOLD
Certification of
Consultant Firms and
Contractors
Nos. 15 15 0 During implementation, regulations
changed that certification is now
awarded by the Association of
Consultants; INACOLD helped
preparing TOR
INACOLD
Certification of Dam
professionals
Pax 220 275 245
Dams under DOISP
Figure A2 - 1: Overview of dams included in DOISP and selected results achieved.
Number of Dams under DOISP: 63
Emergency Action Plans (EAP) finalized: 56
Dams with Physical Works: 34
•Basic Dam Safety Facilities (BDSF) installed: 10 (23 ongoing)
•Dams with risk reduced from extreme to high: 2
•Dam with risk reduced from high to moderate: 20
•Special studies: 23
Reservoir Survey: 31
39
Table A2 - 4: Risk score per dam. For calculation of scores see Table A2 - 5. Score classes: Low risk 0
– 15; moderate risk 16 – 45; high risk 46 – 75; extreme risk 76 – 90.
No. Name of Dam Risk Score (modified ICOLD method) Targeted
reduction
of risk
score in
PAD (%)
Achieved
reduction
in risk
score (%)
Achieved
risk
category Baseline
score
corrected
baseline
score
before
works
Target
(expected
in PAD)
Latest
available
score
(Oct
2016)
1 Way Jepara 57 55 36 41 36.8 28.1 Moderate
2 Batutegi 64 70 49 53 23.4 17.2 High
3 Merancang 54 54 31 49 42.6 9.3 High
4 Tiu Kulit 49 49 26 37 46.9 24.5 Moderate
5 Pengga 56 45 34 39 39.3 30.4 Moderate
6 Batujai 47 53 40 35 14.9 25.5 Moderate
7 Kalola 57 59 44 43 22.8 24.6 Moderate
8 Salomeko 57 55 36 44 36.8 22.8 Moderate
9 Nglangon 57 53 30 34 47.4 40.4 Moderate
10 Simo 55 49 26 33 52.7 40.0 Moderate
11 Sanggeh 53 53 26 30 50.9 43.4 Moderate
12 Cacaban 64 70 47 40 26.6 37.5 Moderate
13 Penjalin 69 71 43 60 37.7 13.0 High
14 Gembong 45 53 38 33 15.6 26.7 Moderate
15 Tempuran 59 65 36 56 39.0 5.1 High
16 Greneng 55 55 22 35 60.0 36.4 Moderate
17 Kedung Ulin 56 51 20 50 64.3 10.7 High
18 Pacal 54 60 41 58 24.1 -7.4 High
19 Ketro 65 67 36 56 44.6 13.8 High
20 Cengklik 70 70 41 45 41.4 35.7 Moderate
21 Krisak 54 54 37 42 31.5 22.2 Moderate
22 Plumbon 55 51 26 35 52.7 36.4 Moderate
23 Gondang 47 47 36 42 23.4 10.6 Moderate
24 Wonorejo 61 63 47 40 23.0 34.4 Moderate
25 Wlingi 60 64 47 42 21.7 30.0 Moderate
26 Karang Kates 68 68 49 60 27.9 11.8 High
27 Sengguruh 58 56 43 32 25.9 44.8 Moderate
28 Selorejo 70 70 43 44 38.6 37.1 Moderate
29 Sampean Baru 55 53 43 44 21.8 20.0 Moderate
30 Jatiluhur 78 78 - 63 - 19.2 High
31 Darma 64 65 42 47 34.4 26.6 High
32 Malahayu 72 74 45 55 37.5 23.6 High
33 Wadaslintang 76 76 53 48 30.3 36.8 High
34 Sempor 68 70 47 49 30.9 27.9 High
TOTAL 35.4 % 25.3 %
40
Table A2 - 5: Guidance to determine risk scores of Indonesian dams based on modified ICOLD method.
(Taken from Project Implementation Plan, 2008).
Risk Class Extreme High Moderate Low Example
Contribution to Risk (Appropriate weighting is given in brackets)
Reservoir Capacity (ML x 103) Extreme
> 120 (6)
High
120 to 1 (4)
Moderate
1 to 0.1 (2)
Low
< 0.1 (0)
30 x 103 ML
(4)
Dam Height (m) Extreme
> 45 (6)
High
45 to 30 (4)
Moderate
30 to 15 (2)
Low
< 15 (0)
20 m
(2)
Evacuation Requirements (No.
of Persons) (Amended as per
Reference 3)
Extreme
>250,000
(12)
High
250,000 to
10,000 (8)
Moderate
10,000 to 1
(4)
Low
None (0)
Moderate
(4)
Potential Downstream Damage
(to existing structures)
High
(12)
Moderate
(8)
Low
(4)
None
(0)
Low
(4)
Business Risk to Owner arising
from Dam Failure (Additional
Consequence to ICOLD)
High
(6)
Moderate
(4)
Low
(2)
None
(0)
High
(6)
Addition
al
Availability of
construction and None Low Moderate High Low
Factors
for
Maintenance
records. (3) (2) (1) (0) (2)
Existing
Availability of
processed instrumentation
None Low Moderate High None
Dams And surveillance
records. (3) (2) (1) (0) (3)
Level of effort
extended in
previous safety
None Low Moderate High None
Evaluations. (3) (2) (1) (0) (3)
New or future
downstream
development.
High Moderate Low None Moderate
(3) (2) (1) (0) (2)
Addition
al
Impact of
Deficiency on
Failure of the
Dam
Extreme High Moderate Low
Factors Flood capacity
related deficiencies (6) (4) (2) (0)
Moderate
(2)
for
Addressing
Static stability related deficiencies
(18) (12) (6) (0) High (12)
Structure
Earthquake
resistance related
deficiencies
(12) (8) (4) (0) Moderate
(4)
Deficien
cies
Risk Score for the Dam Under Consideration. 48
Risk Class (I, II, III, IV) - Ref. pp.41 of ICOLD Bulletin No. 72. III (High)
Risk Class I (Low) II (Moderate) III (High) IV (Extreme)
Risk Score 0 – 15 16 – 45 46 – 75 76 – 90
41
Figure A2 - 2: Risk Score for 63 dams under DOISP1 as of preparation. The 34 rehabilitated dams are on the left side, between Krisak and Tiu Kulit.
Source: Project Implementation Plan (2008).
42
Development of O&M budget
Figure A2 - 3: Budget disbursed for Operation and Maintenance (O&M) under the Directorate for
O&M in DGWR, Ministry of Public Works and Housing. Figures for 2016 reflect allocated budget.
0
5
10
15
20
25
30
35
40
45
50
2009 2010 2011 2012 2013 2014 2015 2016
Bill
ion
Ind
on
esi
an R
up
iah
Annual budget for Operation and Maintenance
43
Annex 3. Economic and Financial Analysis
Background
In Indonesia, many dams suffer from operational deficiencies, while some dams have structural
and mechanical problems that could become a safety hazard. Some dams are prematurely nearing
the end of their economic life; others have lost a large proportion of their reservoir capacity. As a
result, the volume of water storage in many reservoirs is decreasing as well as the irrigated areas.
The project:
supported operational and physical improvements of 33 dams;
promoted structured O&M program by ensuring adequate dam O&M budget funding;
initiated a program to address watershed erosion and sedimentation
established sustainable institutional arrangements and program for community
participation in reservoir management; and
strengthened national dam safety assurance institutions
The economic rationale of dam rehabilitation and safety project is to ensure safety and reduce risks
of dam failure and consequently prevent or minimize damages to downstream property and
environment, loss of life, loss of reservoir supply and replacement costs of the dam or construction cost of alternative water supply. The primary beneficiaries of DOISP are both urban and rural
communities of 8 million people (about 2 Million households dependent on reservoirs for their
water supply and livelihood as well as all downstream communities, who could be placed at
physical and/or environmental risk if dam safety is compromised.
Methodology
The ICR stage economic analysis followed the appraisal stage methodological approach. Dam
failure probability weighted benefit losses were estimated for without project and with project scenarios to generate incremental benefits. The assumptions used in the economic analysis are
summarized in table A3.1. The sensitivity of the results to key uncertain or relevant variables (such
as dam failure probability reduction assumption) was analyzed. It was difficult to estimate the
probability of failure of any given dam unless extensive and detailed historical data exists on a dam portfolio, which is commonly not the case in developing countries. At both appraisal and ICR stage,
the dam failure probability is assumed to be 13% over a period of 20 years. In the base case, this
failure probability was assumed to decline by 90% at appraisal stage and by 35% at ICR stage (targeted) following project interventions. The ICR stage dam failure probability reduction
assumption is set at 25.3%. This is the mean reduction in Risk Score of 34 dams assessed by SMEC
during project preparation in 2008 and by the CPIU TA in October 2016 for with and without DOISP scenarios.
Table A3.1: Assumptions for economic analysis
No Items At appraisal At ICR
1 Dam failure probability without the project 13% 13%
2 Dam failure probability reduction with the project 90% 25.3%
3 Total Irrigation service area (ha) 601,113 601,113
4 Cropping Intensity 1.5 1.7
5 Annual cropped area (ha) 901,668 1,021,892.1
44
6 Gross margin (US$/ha) 790 790
7 Total Annual Net Production Value (US$) 712,317,720 807,294,759
8 Proportion of Total Annual Net production
protected
30% 30%
9 Averted farm income loss (US$) 213,695,316 242,188,428
10 Number of houses 1,997,500 1,997,000
11 Value of house per unit (US$) 1800 1800
12 Total Value of Houses (US$) 3,595,500,000 3,594,600,000
13 Proportion of the value of houses protected 10% 10%
14 Averted loss of value of houses (US$) 359,550,000 359,460,000
15 Total potential losses avoided (US$) 573,245,316 601,648,428
16 Discount rate 12% 6%
Costs
The actual and estimated cost build-up of the project is displayed in table A3.2. It shows that the project encountered significant delays in implementation. The project has disbursed so far about
93.8% of the total eligible financial resources. Delays in implementation and inability to utilize the
full funds allocated lowers the returns to the project. For the cost calculations, Government
contributions to the project have been considered, as well as O&M spending amounting to approximately US$ 1.1 million per year.
Table A3.2 Estimated and actual disbursement schedule
Year Disbursement at Appraisal (US$ Million) Disbursement at ICR (US$ Million)
2009 9.74 0
2010 13.14 2.01
2011 14.24 6.1
2012 13.28 3.4
2013 6.17 14.0
2014 0 10.9
2015 0 8.23
2016 0 2.24
Total 50 46.90
Benefits
The primary benefits included: (i) reduced risks of dam failure; (ii) prolonged life of dams and reservoirs and restored performance, and strengthened institutional capacity for asset management;
and (iii) mitigated watershed erosion and sedimentation. The improvements – both of
institutional/operational and physical nature – that reduce the risk of dam failure will consequently prevent or minimize damages to downstream property and environment, loss of life, loss of bulk
water supply, and eventual (expensive) replacement of a dam or for construction cost of alternative
water supply. The analysis quantified only benefits from avoided farm income and household asset
losses. Other real benefits such as avoidable loss of hydropower, expenditures for replacing or rehabilitating the dams, and emergency response costs in case the dams fail were not included,
mainly because these were not considered at the appraisal stage. For instance, the 32 dams produce
516,216 MWh of hydropower energy.
45
Results of the economic analysis The results of the economic analysis for the ICR and appraisal stage is summarized in table A3.3.
The analysis confirms that the project is economically viable as predicted at the appraisal stage.
However, the absolute magnitude of the returns at ICR stage is lower than that assessed at appraisal
stage. The major reasons for the discrepancy are:
The substantial difference in assumption regarding reductions in the dam failure probability
with the project interventions, and
Delays in implementation that affected disbursement schedule and the resulting cost and
benefit build-up.
Table A3.3: Summary Results of Economic Analysis for DOISP
Indicator Value at Appraisal Value at ICR
12% Discount rate 6% discount rate
NPV (US$ Million) 108.2 22.0 56.3
IRR (%) 32.8 28.7 28.7
Sensitivity Analysis
Analysis of the sensitivity of the economic viability of the project indicate that the results are robust.
The project would not be viable, if only potential losses of farm income is considered as benefit.
Table A3.4 Summary Results of the Sensitivity Analysis for DOISP
No
Variables At Appraisal At ICR
NPV
(US$ Million)
IRR (%) NPV
(US$ Million)
IRR (%)
1 Counting potential losses of
farm income and household
assets (base case)
108.2 32.8 56.3 28.7
2 Counting only potential losses
of farm income
12.0 15.4 -1.5 5.3
3 Counting only potential losses
of household assets
NA NA 17.3 13.1
4 50% reduction in dam failure
probability
41.0 22.0 150.6 112.8
5 25% reduction in dam failure
probability
- 12.0 55.1 28.2
6 20% reduction in dam failure
probability
-11.0 8.5 36.0 20.4
46
Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members Names Title Unit Responsibility
Lending
Guy J. Alaerts Lead Water Resources Specialist EASRE Task Teak Leader
Ilham Abla Senior Operations Officer EASIS
Alessandro Palmieri Lead Dam Adviser GWADR
Bisma Husen Procurement Specialist
Vivianti Rambe Environmental Specialist
Trithep Lohavisavapanich Economist
Theodore Herman Consultant (Dam, Institutional)
Amien Sunaryadi Senior Governance Specialist
Lis Nainggolan Consultant (Social Safeguards)
Unggul Suprayitno Senior Financial Management
Specialist
GGODR
Farida Zaituni Consultant EASIS
Supervision/ICR
Marcus Wishart Senior Water Resources Specialist GWADR Task Team Leader
Paulus van Hofwegen Senior Water Resources Specialist GWADR Task Team Leader
Ilham Abla Senior Operations Officer EASIS Task Team Leader
Guy J. Alaerts Lead Water Resources Specialist EASRE Task Team Leader
Xiaokai Li Senior Water Resources Specialist Task Team Leader
Cuong Hung Pham Senior Water Resources Specialist GWADR
Martin Albrecht Water and Sanitation Specialist GWADR
Satoru Ueda Lead Dam Specialist
Bisma Husen Senior Procurement Specialist EASRP
Enggar Prasetyaningsih Procurement Specialist
Andrew Daniel Sembel Environmental Specialist EASIS
I Gusti Ngurah Wijaya
Kusuma
Financial Management Specialist
Unggul Suprayitno Senior Financial Management
Specialist
GGODR
Budi Permana Procurement Specialist
Angelia Budi Nurwihapsari Procurement Specialist
Flavio Chaves Consultant (Environmental
Safeguards)
Ninin K. Dewi Consultant (Social Safeguards) GSURR
Tatong Permana Anggrimulja Consultant (Financial Management)
Krisnan P. Isomartana Environmental Specialist
Theodore Herman Consultant (Dam Institutional)
Irama Aboesoemono Consultant (Community
Participation)
Achmad Affandi Nasution Consultant (Good Governance)
Regassa Ensermu Namara Senior Water Resources Economist GWADR
47
(b) Staff Time and Cost
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
No. of staff weeks USD Thousands (including
travel and consultant costs)
Lending
FY06 16.21 84.19
FY07 19.68 94.48
FY08 36.47 207.00
FY09 33.81 172.07
Total: 106.17 557.73
Supervision/ICR
FY09 - 0.30
FY10 16.19 95.98
FY11 15.52 67.65
FY12 29.30 146.92
FY13 27.89 102.77
FY14 20.44 112.25
FY15 15.01 111.30
FY16 10.00 55.81
FY17 9.65 43.67
Total: 144.00 736.66
48
Annex 5. Summary of Borrower's ICR and/or Comments on Draft ICR
The borrower prepared a completion report in April 2015 and submitted a draft to the Bank team for information. It included an overview of the activities and achievements of each component as
well as the results of a survey among the project’s PIUs on issues and challenges they encountered
during implementation. The recommendations provided in the borrower’s ICR can be summarized as follows:
The procurement process of the project partly inhibited timely implementation. Given the
sometimes lengthy processing of loan proceedings and the procurement process, as well as a lack of familiarity and capacity of some PIUs with the Bank’s procedures and regulations, some PIUs
decided to utilize their own budget for remedial and rehabilitation works instead of the loan money
available. This was the especially the case for urgent rehabilitation works that needed to be carried out due to damage that had occurred or an imminent risk the structure was posing. It is
recommended to provide assistance to participating sub-national government PIUs to familiarize
themselves better with Bank procedures and guidelines, and enable them to access loan proceedings in line with their planning and budgeting cycle.
Procurement plans should take into account limitations and constraints imposed by simultaneous
activities carried out under the project. Specifically with regards to limitations in the number of experts available in the market in one area at a time puts constraints on the possibility to follow a
diligent procurement process and implement works in time. If a series of works have to be
undertaken in a short period of time within a geographic location, these constraints should be taken into account and implementation periods should be adjusted accordingly. This is especially valid
considering the amount of specialized dam-related works carried out outside of the project’s scope,
within the Government’s program of constructing 65 new dams until 2019.
Implementation arrangements should be designed to take into account skills, capacity and
resources as well as the designated roles and responsibilities within the decentralized environment
in Indonesia. Especially activities community participation program in individual locations, turned out to have high transaction costs for local agencies to conduct, and were therefore done by central
government agencies, who in turn lacked experience and access to the community level. Sub-
national agencies such as provincial river basin organizations (Balais) do have more experience and more direct access to local communities, but have limited resources for engagement in
dispersed locations that involve high transaction costs to access. Further, they would benefit from
more thorough technical guidance from central level to conduct their activities.
Community Participation Activities should take into account boundaries within which
implementing agencies can operate. This involves specifically those activities, which have the
potential to cause controversies when carried out by agencies that have no clear mandate for it. Despite memoranda of understanding or similar forms of agreements, government agencies with a
technical mandate voiced their hesitation to spend time and resources on activities or purchase
goods provided under the community participation program, which go beyond their description of responsibilities and duties. Examples for this is the provision of roads or assets for local businesses
in return for the communities’ role in monitoring dam safety. The agencies involved mainly report
a fear of consequences from auditors. This should be taken into account when designing the future
community participation program.
49
Annex 6. List of Supporting Documents
Project Appraisal Document Indonesia, Dam Operational Improvement and Safety Project (DOISP) (2009)
Loan Agreement and amendments (2009 - 2016)
Borrower’s Project Implementation Plan and annexes (2008)
Annual Work Plans (2009 – 2016)
Monitoring and Evaluation Reports
Project Annual Progress Reports
Borrower’s Project Completion Report (2016)
Aides Memoire (various, 2008 – 2016)
Implementation Status Reports (various, 2009 – 2016)
Mid-term Review (2012)
World Bank Indonesia Country Partnership Strategy / Framework, various, 2008 - 2016
Indonesia National Long-term Development Plan 2005 - 2025 and Mid-term Development Plans
2004 – 2009, 2009 – 2014, 2014 – 2019
50
MAP