The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of...

19
The Way To The Technical Limit Case Study: Drilling In Vata Field Bucharest, April 2015

Transcript of The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of...

Page 1: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

The Way To The Technical Limit Case Study: Drilling In Vata Field

Bucharest, April 2015

Page 2: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

The Way To The Technical Limit

2 OMV Petrom S.A. The Way To The Technical Limit presentation

Technical Limit in Drilling is defined as:

“A theoretical limit representing a stretched target of

what is theoretically possible in a perfect world where

both ideal and optimized drilling conditions are fulfilled.”

Page 3: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

The Way To The Technical Limit

3 OMV Petrom S.A. The Way To The Technical Limit presentation

Plan

Implement Monitor & Evaluate

Learn

Improve

Page 4: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Plan

4 OMV Petrom S.A. The Way To The Technical Limit presentation

Establish and develop the baseline

Set the project goal, objective and target

Risk evaluation

Get management support

Communicate and establish Key Performance Indicators (KPI's)

Page 5: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Implement

5

Implement KPI’s Have the best team in charge with the project Have meetings with all the people involved. Communication is the key Implement new technologies in order to deliver sustainable results

OMV Petrom S.A. The Way To The Technical Limit presentation

Page 6: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Monitor & Evaluate

6

Facilitate periodic checks to ensure that the process is a success

Analysis and review actual versus planned performance

Compare with the best in class [well] drilling performance and see if the Technical Limit was achieved

OMV Petrom S.A. The Way To The Technical Limit presentation

Page 7: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Learn

7

Provide feedback regarding the project

Identify NPT & ILT

Manage lessons learned in order to improve the efficiency in the planning phase of the new wells

OMV Petrom S.A. The Way To The Technical Limit presentation

Page 8: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Real metrics show real improvements

8 OMV Petrom S.A. The Way To The Technical Limit presentation

Non productive time (NPT)

Invisible lost time (ILT)

ROP

Flat time

Actual time < Planned time

Cost reduction

Implementation of lessons learned

Others

Page 9: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Case Study: Vata Field

9 OMV Petrom S.A. The Way To The Technical Limit presentation

Page 10: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Case Study: Vata Field

10 OMV Petrom S.A. The Way To The Technical Limit presentation

Page 11: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Case Study: Vata Field

11 OMV Petrom S.A. The Way To The Technical Limit presentation

Page 12: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Case Study: Vata Field

12 OMV Petrom S.A. The Way To The Technical Limit presentation

Page 13: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Case Study: Vata Field

13 OMV Petrom S.A. The Way To The Technical Limit presentation

Page 14: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Case Study: Vata Field

14 OMV Petrom S.A. The Way To The Technical Limit presentation

Flat Time was reduced using the following:

Casing while drilling technology for the first section

“C” Plate for suspending the casing

Minimize time for BOP works

For wells with inclination > 30 deg. used pipe conveyed logging

Reamer shoe for 7’’ casing

Page 15: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Case Study: Vata Field

15 OMV Petrom S.A. The Way To The Technical Limit presentation

“C” Plate

Page 16: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Case Study: Vata Field

16 OMV Petrom S.A. The Way To The Technical Limit presentation

The ROP was increased using the following:

8 ½’’ PDC bit, Type MSi519LHUBPX

PDM motor in BHA

Optimized drilling parameters

Drilling fluid: KCl Polymer Glycol

Page 17: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Case Study: Vata Field

17 OMV Petrom S.A. The Way To The Technical Limit presentation

Average saving for all wells drilled in 2014

Page 18: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical

|

Conclusion

18

Wells drilled in 2014 were included on this analysis

Improving drilling activities is a goal of any operator while the costs increases from year to year

The approach to Technical Limit as a tool of continuous improving needs the involvement of all contractors to achieve the objective

OMV Petrom S.A. The Way To The Technical Limit presentation

Page 19: The Way To The Technical Limit Case Study: Drilling In ...Improving drilling activities is a goal of any operator while the costs increases from year to year The approach to Technical