THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the...

17
THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT: EXPERIENCES AND CHALLENGES ON THE EXAMPLE OF THE GOTTHARD BASE TUNNEL Samuel Gehrig 8th International Conference “Tunnel Safety & Ventilation”, Graz, 2016 April 25 th 2016

Transcript of THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the...

Page 1: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELSDURING EQUIPMENT: EXPERIENCES AND CHALLENGES ON THE EXAMPLE OF THE GOTTHARD BASE TUNNEL

Samuel Gehrig8th International Conference “Tunnel Safety & Ventilation”, Graz, 2016April 25th 2016

Page 2: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

CONTENT AND INTRODUCTION

Introduction

The tunnel

The boundary conditions

The requirements

The ventilation system

The cooling system

Experiences and challenges

Conclusion

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 2

THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING

EQUIPMENT: EXPERIENCES AND CHALLENGES ON THE EXAMPLE OF THE

GOTTHARD BASE TUNNEL

Page 3: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

THE TUNNEL

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 3

Courtesy of ATG

Page 4: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

THE BOUNDARY CONDITIONS AND INTERFACES (1)

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 4

The equipment work

Courtesy of

Page 5: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

THE BOUNDARY CONDITIONS AND INTERFACES (2)

Diesel engines only, with very strict requirements:

– EU guideline 2004/26, status June 2004, oxidising catalyst for CO and HC, selective

catalytic reduction system for NOx and a particle filter.

General equipment procedure:

1. temporary installations, power and com-munication cables, using tyred vehicles.

2. slab track (the most power consuming process) using a rail train, a sleeper train, 450

m long concrete carrier train, and several smaller diesel driven machines assisting

the trains (e.g. welding machine, concrete shuttles, etc.). Cf. picture.

3. installation of the remaining systems, such as the catenary, using trains driven with

smaller locomotives and rail cars.

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 5

The machines deployed

Courtesy of

Page 6: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

THE BOUNDARY CONDITIONS AND INTERFACES (3)

Heat sources:

– Rock: up to 11.0 MWth per tube

– Machines: up to 1.7 MWth per tube

– Curing concrete: up to 0.4 MWth per tube

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 6

The Heat sources

Page 7: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

THE REQUIREMENTS TO VENTILATION AND COOLING

Fresh air quantities compliant to SIA 196:

– Fresh air for transports: 2 m3/(minute, Diesel kW),

– Fresh air for heavy duty stationary engines: 4 m3/(minute, Diesel kW).

Air velocity in the tubes within a working band of 0.3 m/s to 5 m/s:

– Consequence: Air volume flow in the tubes limited to 200 m3/s.

– Corresponding to 6’000 Diesel kW per ventilation line.

Climatic goal at design: 28°C dry-bulb temperature in the working section

Climatic goal during operation compliant with SUVA guidelines:

– No limit on the type of activity up to 28° WBGT.

– Only light works permitted between 28° to 30° WBGT.

– No work allowed above 30° WBGT.

Other requirements:

– Monitoring of flow, climate and air quality.

– Re-use of ventilation and cooling systems of previous contractors.

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 7

Page 8: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

THE VENTILATION SYSTEM

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 8

MFS SedrunAmstegErstfeld MFS Faido Bodio

120 m3/s 85 m3/s

east

tube

west

tube

air lock

lane change gate, door

( )+

gate

fanexhaust air

incoming air

exhaust airways

PLN_20160128_pictures-paper-LP21_GSA.vsd / LK03a

MFS SedrunAmstegErstfeld MFS Faido Bodio

200 m3/s

200 m3/s

100 m3/s

200 m3/s

100 m3/s

east

tube

west

tube

air lock

lane change gate, door

( )+

gate

fanexhaust air

incoming air

exhaust airways

PLN_20160128_pictures-paper-LP21_GSA.vsd / LK05

Page 9: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

THE COOLING SYSTEM

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 9

Parameter Cooling GBT north Cooling GBT south

Max. requested refrigeration capacity in tunnel, MW 8.4 11.8

Max. requested cooling capacity in tunnel, MW 11.4 16.0

Cooling capacity available at cooling plant, MW 11.4 21.0

Pump capacity available at cooling plant, m3/h 800 1’120

Max. number of MACs includable

(net refrig. capacity 420 MW each)20 28

pump station

pressure exchangesystem

mine air cooler (MAC)

cooling plant

east

tube

west

tube

MFS SedrunAmstegErstfeld MFS Faido Bodio

cooling water pipes (feed and return)

industrial water pipe

cooling GBT north cooling GBT south

PLN_20160128_pictures-paper-LP21_GSA.vsd

southnorth center

heat exchanger

Page 10: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

EXPERIENCES AND CHALLENGES (1)

Integration of permanent equipment into

the temporary ventilation

– Integrate permanent ventilation elements

into the temporary ventilation where

available in order to reduce additional

maintenance and avoid the installation of

parallel temporary systems. E.g. ventilation

of cross connections, cf. picture.

High coordination effort:

– 45 lots within and outside Transtec,

needing at least an interface check to the

lot ventilation / cooling

– 24 lots with interfaces identified.

Coordination in time and space necessary.

– Coordination efforts amount to about ½ of

total planning time.

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 10

High coordination effort

Integration of permanent equipment into temporary ventilation

Page 11: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

EXPERIENCES AND CHALLENGES (2)

Sizing of the ventilation according to SIA 196.

Monitoring of pollutants’ concentrations during operation.

Concentrations far below OEL most of the time.

But: High volume flow rate strongly supports cooling of the tunnel.

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 11

Ventilation supports cooling

Courtesy of

Page 12: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

EXPERIENCES AND CHALLENGES (3)

Sizing of the cooling:

– Designed for 28°C dry-bulb temperature, on the assumption of frequent relative

humidity at 100%.

– Operated following the WBGT-index.

– As tunnel is sealed against water seepage, humidity is low in the central section,

about 30% rH.

– Consequence: Cooling oversized.

Climatic conditions during transition periods

– loss of control on the air flows

or no cooling available

– consequence: unavoidable local overheating

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 12

Sizing of the cooling

Climatic conditions during transition periods

Courtesy of

Page 13: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

EXPERIENCES AND CHALLENGES (4)

Cooling GBT South: open water cycle → high corrosion

Cooling GBT North: closed water cycle → low corrosion

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 13

Design of cooling water cycle

Cooling GBT South

Cooling GBT North

Page 14: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

EXPERIENCES AND CHALLENGES (5)

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 14

Alternative cooling concept

above below

ground

Mine Air Cooler

above below

ground

n times

primary cycle secondary cyclerefrigeration plant

pump station

fan

compressor

throttle

water pipes

(feed and return)

refrigerant cycle

air flow

heat exchanger,

condensor, evaporator

cooling plant, open cooling

tower

Future alternative

Present solution

PLN_20160128_pictures-paper-LP21_GSA.vsd / A lternati ven

1-4 °C

15-20 °C

Page 15: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

CONCLUSION

Past: The systems devised and used fulfilled the requirements and were

capable to adapt to an environment with parallel running processes.

Present: Solid know-how for the ventilation and cooling of long railway tunnels

during equipment by experiences made and challenges encountered.

Future: Brenner Base Tunnel and Lyon-Turin can profit from this know-how.

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 15

Page 16: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

Consulting. Engineering. Projects. Operations. www.poyry.com

Page 17: THE VENTILATION AND COOLING OF LONG RAILWAY ...tunnel2016/images/documents/PDF...Sizing of the ventilation according to SIA 196. Monitoring of pollutants’ concentrations during operation.

COPYRIGHT©PÖYRY

BIBLIOGRAPHY

1) VERT-Filterliste, Geprüfte und erprobte Partikelfilter-Systeme für die

Nachrüstung von Dieselmotoren, Bundesamt für Umwelt, Wald und

Landschaft (BUWAL), Bern, Dezember 2005

2) Schweizerischer Ingenieur- und Architekten-Verein, SIA 196, Baulüftung im

Untertagebau, Zürich, 1998

3) SUVA, Schweizerische Unfallversicherungsanstalt, Abteilung Arbeitsmedizin,

Arbeitsmedizinische Prophylaxe bei Arbeiten im Untertagebau im feucht-

warmen Klima, März 2003, Bestellnr. 2869/26.d

GRAZ, APRIL 25TH 2016THE VENTILATION AND COOLING OF LONG RAILWAY TUNNELS DURING EQUIPMENT 17