THE ULTIMATE - Amazon S3...THE ULTIMATE HELPING YOU ON YOUR JOURNEY TO BECOMING A PROFESSIONAL...
Transcript of THE ULTIMATE - Amazon S3...THE ULTIMATE HELPING YOU ON YOUR JOURNEY TO BECOMING A PROFESSIONAL...
CIVIL PE BREADTH EXAM
Isaac Oakeson, P.E.Volume 2
THE ULTIMATE
HELPING YOU ON YOUR JOURNEY TO BECOMING A PROFESSIONAL ENGINEER.
VO
LUM
E 2
Isaac Oakeson, P.E. is a professional engineer working in the great state of Utah. Having passed the PE Exam in the fall of 2012, he is driven to help others
do the same.
His passion has led him to create CivilEngineeringAcademy.com, CivilPEReviewCourse.com and CivilFEReviewCourse.com.
Each website provides the tools necessary to ace the FE and PE exams. Many have used the resources he has created and now he wants to help you too!
www.civilengineeringacademy.com | [email protected]|
TABLE OF CONTENTS
WELCOME…………………………………………….
EXAM SPECIFICATION……………………
START TEST ………………………………...
SOLUTIONS………………………………………
LAST SECOND TIPS AND ADVICE…..
Page 3
Page 6
Page 9
Page 47
Page 88
Page 3
www.civilengineeringacademy.com | [email protected]|
WELCOME!!
Welcome to The Ultimate Civil PE Breadth Practice Exam Volume 2!
Thank you so much for purchasing this book!
This book includes a full 40-question/solution breadth exam. This
exam has been updated to meet the latest NCEES specifications (2015
as of this writing). Each problem is designed to have a similar look
and feel to the real exam.
The key to passing the PE exam is to absolutely crush the breadth
portion of it. If you can get 90 percent or more in the morning section
then the afternoon section will be that much easier on you. All in all,
this is to help you gain more practice, more experience, and ultimately
more confidence in passing.
This test is not endorsed by the NCEES organization. These are
problems that my team and I have written to help you succeed in
passing the PE exam. I would encourage you to take this timed to see
how long it takes you. Afterward, you can take note of the areas that
you might need to work on. I have spent some time getting all of the
information here for you so that it is easy to use. Each problem is
labeled, so you know what problem and area you are dealing with.
There are multiple ways of taking practice exams – you can work
problems like homework, you can take it like the real exam - it’s really
up to you! I would make sure to do at least one practice exam as if it
were the real deal though so you gain that experience.
Page 4
www.civilengineeringacademy.com | [email protected]|
As always, I value your feedback and any constructive criticism you
might have on this exam or anything else we produce to help others
pass. You can also get many more resources on the sites we run at
www.civilengineeringacademy and www.civilpereviewcourse.com,
including step by step video practice problems.
I know that with a lot of practice you will become much more
proficient at working problems and doing them with less and less
assistance. Keep at it and you will be prepared to pass the PE.
I don’t need to tell you about the benefits of obtaining your PE license
because I’m sure you already know them. You must get it to have a
great career in civil engineering (and a lot of other fields!).
As always, I wish you the best of luck!
Sincerely,
Isaac Oakeson, P.E.
(You’re going to have that by your name too!)
P.S. Errata for this or any other exam we created can be found at
www.civilengineeringacademy.com.
Page 5
www.civilengineeringacademy.com | [email protected]|
LEGAL INFORMATION
Civil Engineering Academy’s
The Ultimate Civil PE Breadth Exam Vol. 2
Isaac Oakeson, P.E.
Rights and Liability:
All rights reserved. No part of this book may be reproduced or
transmitted by photocopy, electronic, recording, or any other method
without first obtaining permission from the author. The information in
this book is in no way endorsed by the NCEES organization and the
author shall not have any liability to any person with respect to any
loss or damage caused by the problems in this book.
In other words, please don’t go copying this thing willy-nilly without
giving credit where it should be given by actually purchasing a copy.
Also, don’t go designing real things based on these problems.
If you find errors in this book (I am human of course), or just want to
comment on things, then please let me know! I can be reached
through the website at www.civilengineeringacademy.com or by email
ABOUT THE AUTHOR
Isaac Oakeson, P.E. is a registered professional civil engineer in the
great state of Utah. Shortly after passing the PE exam in the fall of
2012 he started www.civilengineeringacademy.com and
www.civilpereviewcourse.com to help future students pass. He has
authored and helped author various exams with his entire goal of
providing the best resources for engineers to study and pass the PE.
Page 6
|www.civilengineeringacademy.com|[email protected]|
CIVIL – BREADTH EXAM SPECIFICATION
I. Project Planning (4)
A. Quantity take-off methods
B. Cost estimating
C. Project schedules
D. Activity identification and sequencing
II. Means and Methods (3)
A. Construction loads
B. Construction methods
C. Temporary structures and facilities
III. Soil Mechanics (6)
A. Lateral earth pressure
B. Soil consolidation
C. Effective and total stresses
D. Bearing capacity
E. Foundation settlement
F. Slope stability
IV. Structural Mechanics (6)
A. Dead and live loads
B. Trusses
C. Bending (e.g., moments and stresses)
D. Shear (e.g., forces and stresses)
Page 7
|www.civilengineeringacademy.com|[email protected]|
E. Axial (e.g., forces and stresses)
F. Combined stresses
G. Deflection
H. Beams
I. Columns
J. Slabs
K. Footings
L. Retaining walls
V. Hydraulics and Hydrology (7)
A. Open-channel flow
B. Stormwater collection and drainage (e.g., culvert, stormwater
inlets, gutter flow, street flow, storm sewer pipes)
C. Storm characteristics (e.g., storm frequency, rainfall measurement
and distribution)
D. Runoff analysis (e.g., Rational and SCS/NRCS methods,
hydrographic application, runoff time of concentration)
E. Detention/retention ponds
F. Pressure conduit (e.g., single pipe, force mains, Hazen-Williams,
Darcy-Weisbach, major and minor losses)
G. Energy and/or continuity equation (e.g., Bernoulli)
VI. Geometrics (3)
A. Basic circular curve elements (e.g., middle ordinate, length, chord,
radius)
B. Basic vertical curve elements
C. Traffic volume (e.g., vehicle mix, flow, and speed)
Page 8
|www.civilengineeringacademy.com|[email protected]|
VII. Materials (6)
A. Soil classification and boring log interpretation
B. Soil properties (e.g., strength, permeability, compressibility, phase
relationships)
C. Concrete (e.g., nonreinforced, reinforced)
D. Structural steel
E. Material test methods and specification conformance
F. Compaction
VIII. Site Development (5)
A. Excavation and embankment (e.g., cut and fill)
B. Construction site layout and control
C. Temporary and permanent soil erosion and sediment control (e.g.,
construction erosion control and permits, sediment transport,
channel/outlet protection)
D. Impact of construction on adjacent facilities
E. Safety (e.g., construction, roadside, work zone)
Page 10
|www.civilengineeringacademy.com|[email protected]|
1. Suppose that 2000 ft3 of concrete is required to pour 40% of the
slabs of the third floor of the Black Crown Hotel. To construct a
3500 psi concrete, the batching plant produced a 1:2:4 by volume
mixture. Compute the bulk volume of the cement required for the
40% of the third floor slabs.
a) 10.6 yd3
b) 74.1 yd3
c) 29.6 yd3
d) 37.0 yd3
Page 11
|www.civilengineeringacademy.com|[email protected]|
2. Specifications on a job required a fill using borrow soil to be
compacted at 95% of its standard proctor maximum dry density.
Tests indicate that the maximum dry density is 124 pcf with 12%
moisture content. The borrow material has a void ratio of 0.6 and
a solid specific gravity of 2.65. Compute the minimum volume of
borrow soil required per 1 ft3 of fill.
a) 2.25 ft3
b) 1.00 ft3
c) 3.05 ft3
d) 1.14 ft3
Page 12
|www.civilengineeringacademy.com|[email protected]|
3. The following table tabulates the activities for a new project’s
network diagram. Based on the data provided below, determine
the duration of the project?
a) 14 weeks
b) 20 weeks
c) 10 weeks
d) 12 weeks
Path Duration
(weeks)
0-1 (A) 3
0-2 (B) 4
0-3 (D) 2
1-2 (C) 5
2-3 (E) 3
3-4 (F) 3
Page 13
|www.civilengineeringacademy.com|[email protected]|
4. A road is to be constructed and the cut is shown in the following
figure. Determine the cost of the excavation process if it is worth
$2.5/ft3. Use the end area method.
a) $187,500
b) $185,800
c) $178,500
d) $185,700
A2 = 700 ft2
A1 = 800 ft2
100 ft
Page 14
|www.civilengineeringacademy.com|[email protected]|
5. A 28 ft deep braced cut in a sandy soil is shown. The struts are
placed 5 ft center-to-center. Compute the reaction at strut C using
Peck’s empirical pressure diagram.
a) 37,160 lbs
b) 38,990 lbs
c) 35,660 lbs
d) 31,590 lbs
Page 15
|www.civilengineeringacademy.com|[email protected]|
6. A sling system can carry 2000 lbs using 90° basket hitch. What is
the maximum load the sling system can carry using 60° basket
hitch as shown below?
a) 1,155 lb
b) 2,310 lb
c) 2,000 lb
d) 1,732 lb
60° 60°
Page 16
|www.civilengineeringacademy.com|[email protected]|
7. A crane is caring a crate weighing 1000 lb. It is held by four cables
attached to the corners. The attachment point is located directly
above the center of the load. What, most nearly, is the tension in
each cable?
a) 250 lb
b) 300 lb
c) 340 lb
d) 410 lb
15 ft 5 ft
1000 lb
6 ft
Page 17
|www.civilengineeringacademy.com|[email protected]|
8. A vertical retaining wall has a height of 20 ft that supports a
horizontal backfill. Its dry unit weight is 100 lb/ft3 and a saturated
unit weight of 140 lb/ft3. Ground water was found at 8 ft below
the ground surface. Compute the total Rankine active force per
unit length of wall.
a) 9,005 lb/ft
b) 8,544 lb/ft
c) 7,920 lb/ft
d) 6,785 lb/ft
Page 18
|www.civilengineeringacademy.com|[email protected]|
9. From the soil layer shown, determine the closest effective stress
at point C. Layer A is dry, layer B and C are saturated.
a) 1,087 lb/ft2
b) 1,095 lb/ft2
c) 1,054 lb/ft2
d) 1,025 lb/ft2
Page 19
|www.civilengineeringacademy.com|[email protected]|
10. A normally consolidated clay layer is 15 ft (one way drainage).
From the application of a given pressure, the total anticipated
primary consolidation settlement will be 3 inches. Given that the
coefficient of consolidation is 0.00323x10-3 ft2/s, how many days
will it take for 50% settlement to occur if the time factor from a
table is 0.197?
a) 159 days
b) 124 days
c) 170 days
d) 205 days
11. Settling on a structure has three distinct periods. Which of the
following statements is not true about settling?
a) Elastic settling occurs immediately after a structure is constructed.
b) Secondary consolidation occurs in clay soil and happens at a much
slower rate after primary consolidation has finished.
c) Primary consolidation occurs gradually in clay because water is
being extruded from the voids.
d) An influence chart can be used to determine the primary
consolidation rate.
Page 20
|www.civilengineeringacademy.com|[email protected]|
12. What is the factor of safety for the following slope stability
analysis? The unsaturated clay soil has the following properties:
120 pcf , 600 psfc .
a) 1.1
b) 1.8
c) 2.0
d) 2.5
Page 21
|www.civilengineeringacademy.com|[email protected]|
13. A 5 ft x 5 ft foundation is embedded 3 ft into sand. The sand has a
density of 120 pcf and bearing capacity factors of 51c
N , 38q
N
, 44N . Determine the maximum allowable column load, P (in
lbs), to maintain a factor of safety of 3. Ignore shape factors.
a) 8,860 lb
b) 8,960 lb
c) 221,500 lb
d) 224,000 lb
Page 22
|www.civilengineeringacademy.com|[email protected]|
14. A square footing with a depth of 20 inches carries a dead load of
100 kips and a live load of 80 kips. From the figure shown,
determine the approximate dimension of the footing given the
allowable soil bearing capacity of 4000 psf. Use a concrete unit
weight of 150 pcf.
a) 8 ft x 8 ft
b) 7 ft x 7 ft
c) 7.5 ft x 7.5 ft
d) 8.5 ft x 8.5 ft
20”
12”x12” Column
5’ gsoil = 110 pcf
Page 23
|www.civilengineeringacademy.com|[email protected]|
15. In the figure shown, the beam is simply supported at point A and
5 ft from point C. Determine the maximum positive moment.
a) 550 lb-ft
b) 650 lb-ft
c) 750 lb-ft
d) 1500 lb-ft
800 lbs 500 lbs
5 ft 5 ft 5 ft
A C B
Page 24
|www.civilengineeringacademy.com|[email protected]|
16. After analyzing a beam, its moment diagram is shown below.
Given the diagram, determine the maximum positive bending
stress. The section modulus of the beam, S = 8.14 in3.
a) 16.58 ksi
b) 15.36 ksi
c) 12.89 ksi
d) 29.84 ksi
135 kips-in
-125 kips-in
105 kips-in
4 ft 4 ft 3 ft Moment
diagram
Page 25
|www.civilengineeringacademy.com|[email protected]|
17. A column carries a concrete flat plate with a 5 inch thickness. The
slab carries a dead load of 80 psf. Determine the compressive
stress of the column. Use a concrete unite weight of 150 pcf
(tributary area 13 ft x 15 ft).
a) 21.16 psi
b) 48.24 psi
c) 35.21 psi
d) 27.40 psi
13 ft
15 ft
5 in
Column
4 ft
1 ft
Page 26
|www.civilengineeringacademy.com|[email protected]|
18. A 20 ft beam, loaded as shown, is fixed at both ends. Given the
properties of the beam, determine the deflection at the midpoint.
a) 0.87 in
b) 1.5 in
c) 1.3 in
d) 0.12 in
A B
Beam Properties E = 29000 ksi I = 118 in⁴
W=250lbs/ft
3000 lbs
Page 27
|www.civilengineeringacademy.com|[email protected]|
19. Determine the moment diagram of the loaded beam given.
a)
b)
c)
d)
4 ft 8 ft
A B
Page 28
|www.civilengineeringacademy.com|[email protected]|
20. In the figure shown below, design the diameter of pipe CD given a
headloss of 14.5 ft using Manning’s Equation (n=0.013).
a) 20 in
b) 45 in
c) 30 in
d) 60 in
Page 29
|www.civilengineeringacademy.com|[email protected]|
21. Water flows from point B to A. In the system shown, the pressure
from A to B is 1200 psf when the gate valve is closed, and when
the valve is opened, the pressure from B to A is measured 1000
psf. Determine the headloss from point B to A.
a) 19.2 ft
b) 35.2 ft
c) 20.2 ft
d) 10.2 ft
Page 30
|www.civilengineeringacademy.com|[email protected]|
22. Determine the hydraulic radius from the channel section shown.
a) 2.87 ft
b) 3.00 ft
c) 2.50 ft
d) 2.75 ft
Page 31
|www.civilengineeringacademy.com|[email protected]|
23. Given the pipe network with flow rates shown, determine the flow
rate at pipe BE.
a) 2.771 ft3/s
b) 2.935 ft3/s
c) 2.823 ft3/s
d) 2.698 ft3/s
B
3.528 ft3/s QBE = ?
CC
0.176 ft3/s
0.529 ft3/s
E
E
A B
D
C
E
Page 32
|www.civilengineeringacademy.com|[email protected]|
24. An oil with density = 1.7 slugs/ ft3 flows through a cast iron
pipe at a velocity of 3 ft/s. The pipe is 150 ft long and has a
diameter of 6 in. Given an absolute viscosity = 0.0017 lbs - s /
ft2. Determine the head loss due to the friction factor. Use
Reynold’s number.
a) 1.897 ft
b) 1.542 ft
c) 1.675 ft
d) 1.786 ft
Page 33
|www.civilengineeringacademy.com|[email protected]|
25. In a non-uniform flow, water has a discharge of 705 ft3/s through
a rectangular channel measuring 13 ft wide. The water runs from
a steep slope to a mid-slope creating a hydraulic jump. The
upstream depth of flow is 3.94 ft. Determine the downstream
depth of flow.
a) 4.98 ft
b) 5.23 ft
c) 4.81 ft
d) 5.12 ft
Page 34
|www.civilengineeringacademy.com|[email protected]|
26. A simplified water supply system is shown in the figure. The
pressure supplied to the townhomes is 10,000 psf and the
discharge of the system is 4 ft3/s. Determine the head that the
pump will need for the given situation. Use f=0.012. The water
tower is open to the atmosphere.
a) 40 ft
b) 45 ft
c) 50 ft
d) 55 ft
El. 150 ft
El. 20 ft
Length = 3000 ft Diameter = 12”
P
Page 35
|www.civilengineeringacademy.com|[email protected]|
27. A back tangent of a simple curve intersects the forward tangent at
station 67+62 which is 345 ft from the PC. Compute the external
distance of the curve when the radius of the curve is 300 ft.
a) 146 ft
b) 187 ft
c) 157 ft
d) 45 ft
Page 36
|www.civilengineeringacademy.com|[email protected]|
28. A train passing point A at a speed of 65 fps accelerates at 2.46
fps2 for one minute along a straight path, and then decelerates at
3.3 fps2. How far from point A will it be 2 minutes after passing
point A?
a) 15,144 ft
b) 13,879 ft
c) 13,855 ft
d) 13,760 ft
29. A vertical parabolic curve has a back tangent of -5% and a
forward tangent of 3%. If the stationing of PC is at 80+50, locate
the stationing of the lowest point of the curve. The length of the
curve is 820 ft.
a) 86+62
b) 81+62
c) 85+62
d) 88+62
Page 37
|www.civilengineeringacademy.com|[email protected]|
30. Solve the porosity, n, knowing that the sample has a SG=2.55,
weighs 32 lbs total, a total volume of 0.4 ft3, and a water content
of 17%.
a) 0.43
b) 0.47
c) 0.50
d) 0.57
Soil
Water
Air
Page 38
|www.civilengineeringacademy.com|[email protected]|
31. Given a concrete beam that has a dimension of 12”x25” (with 3”
cover) and a tension steel area of 3.33 in2. Determine the depth of
the equivalent stress block. Assume that the steel yields.
a) 4.35 in
b) 6.73 in
c) 5.41 in
d) 11.0 in
a
22 in
3.33 in²
12 in
fc’ = 3 ksi fy = 40 ksi
Page 39
|www.civilengineeringacademy.com|[email protected]|
32. The angle of friction of a cohesive soil which was tested using a
tri-axial shear test is equal to 29°. Failure occurred when the
shear stress reached 45 psi and the normal stress reached 65 psi.
Determine the cohesion of soil.
a) 10 psi
b) 16 psi
c) 9 psi
d) 20 psi
Page 40
|www.civilengineeringacademy.com|[email protected]|
33. The laboratory compaction test of a certain type of soil gives a
maximum dry density of 120 pcf with an optimum moisture
content of 14%. Sand Cone Method was used to determine the
field unit weight and the results are shown below. Determine the
relative compaction.
a) 90.2
b) 92.5
c) 94.6
d) 95.4
V
Soil Properties
Volume of soil excavated from the hole = 0.017 ft³
Mass of moist soil removed
from the hole = 2.2lbs Field moisture content = 13%
Sand Cone Method
Page 41
|www.civilengineeringacademy.com|[email protected]|
34. A given soil has the following particle size distribution: 8% sand,
20% gravel, 48% silt, and 24% clay. Classify the type of soil using
the USDA method below.
a) Silt Loam
b) Loamy Sand
c) Sandy Clay Loam
d) Silty Clay Loam
Page 42
|www.civilengineeringacademy.com|[email protected]|
35. Given the location of the neutral axis of the structural steel tee
section shown, determine the maximum bending stress if the
moment is 150 kips-ft.
a) 11 ksi
b) 40 ksi
c) 26 ksi
d) 51 ksi
Neutral
axis
WT 13.5 x 108.5 properties: d = 14.215 in
y = 3.11 in
Ix = 502 in4
Page 43
|www.civilengineeringacademy.com|[email protected]|
36. A square lot is divided into 60 ft2 and the corners are numbered I-
IV vertically and A-D horizontally. The heights removed after
excavation are tabulated below for a borrow pit. Compute the
volume of earthwork excavated.
AI = 20.3 BI = 19.0 CI = 20.5 DI = 15.1
AII = 18.4 BII = 14.1 CII = 17.1 DII = 12.5
AIII = 12.5 BIII = 8.4 CIII = 14.1 DIII = 8.8
AIV = 6.9 BIV = 6.23 CIV = 12.8 DIV = 5.9
a) 395,460 ft3
b) 459,366 ft3
c) 436,014 ft3
d) 345,690 ft3
B C D A
I
II
III
IV
60 ft
60 ft
60 ft
60 ft 60 ft 60 ft
Page 44
|www.civilengineeringacademy.com|[email protected]|
37. A surveyor measures the elevation on a construction site. Based
on the data below, find the difference in elevation between BM1
and BM2.
a) 4.23 ft
b) 6.30 ft
c) 10.63 ft
d) 4.10 ft
Station BS FS Elev
BM1 8.56 540.51
TP1 9.45 4.23
BM2 3.15 ?
BM1
BM2
TP 1
Page 45
|www.civilengineeringacademy.com|[email protected]|
38. Two levelling rods placed at a distance of 160 ft and 320 ft from
the instrument gives an intercept of 1.6 ft and 3.2 ft respectively.
Determine the stadia interval factor, K.
a) 150
b) 120
c) 100
d) 160
Page 46
|www.civilengineeringacademy.com|[email protected]|
39. Hearing safety is of high importance on a construction site.
According to OSHA, what is the maximum “all-day” 8 hour noise
level limit?
a) 90 dBa
b) 92 dBa
c) 100 dBa
d) 115 dBa
40. A surveyor is setting up new control points for a building layout.
The tangents have a bearing of N40°E and S65°E respectively.
Determine the angle of intersection.
a) 105°
b) 115°
c) 65°
d) 75°
Page 48
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 1 SOLUTION:
QUANTITY TAKE OFF METHODS
Use the proportions to compute the bulk volume. The ratios are given
in this sequence cement:fine aggregate:coarse aggregate. Write the
ratios down and multiply by the volume required to see what you need
of each type.
The cement required is 285.7 ft3 or 10.6 yd3.
(Answer A)
Material Computation Bulk Volume
Gravel
(coarse aggregate)
42000
7 1142.9 ft3
Sand
(fine aggregate)
22000
7 571.4 ft3
Cement 1
20007
285.7 ft3
Page 49
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 2 SOLUTION:
QUANTITY TAKE-OFF
First, for the borrow soil, solve for the dry unit weight of the soil:
2.65 62.4103.35 pcf
1 1 0.6s w
dry
G
e
Then, solve for the compacted soil at 95% compaction:
0.95 124 117.8 pcfdry
The weight of the compacted soil = the weight of soil needed as borrow:
3
117.8 1 103.35
1.14 ft
borrow
borrow
V
V
(Answer D)
Page 50
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 3 SOLUTION:
ACTIVITY IDENTIFICATION AND SEQUENCING
First, draw the paths given and then find the critical path (longest
duration, blue arrows).
Path DF = 2 + 3 = 5 weeks
Path ACEF = 3 + 5 + 3 + 3 = 14 weeks (Answer A)
Path BEF = 4 + 3 + 3 = 10 weeks
In order to finish a project we should complete all activities from the
starting node to the finishing node (0 to 4). But all activities should be
done to complete a project.
Example: In order for node 2 to be completed, activities at path AC
should be accomplished since it has the longest duration of activity
inside node 2.
Path Duration (weeks)
0-1 (A) 3
0-2 (B) 4
0-3 (D) 2
1-2 (C) 5
2-3 (E) 3
3-4 (F) 3
0
1
2
3
4
D (2 weeks)
B (4 weeks)
A (3 weeks) C (5 weeks)
F (3 weeks)
Page 51
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 4 SOLUTION:
COST ESTIMATING
First, compute the volume of soil excavated (cut) using the end area
method:
1 2 3800 700 100
Volume 75000 ft2 2
A A L
Now solve for the cost of the excavation:
Cost 75000 2.5 $187,500
(Answer A)
Page 52
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 5 SOLUTION:
TEMPORARY STRUCTURES
First, solve for the active earth pressure coefficient:
1 sin30 1
1 sin30 3a
K
Find the maximum lateral pressure for braced cuts in sand (Peck’s):
1
0.65 0.65 100 28 5 3033.3 lb/ft3
a aP K H
Then isolate BC to solve for the reaction at point C:
0
3033.3 14 7 8 0
37158 37160 lb
B
C
C
M
R
R
(Answer A)
Page 53
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 6 SOLUTION:
CONSTRUCTION LOADS
This problem can be resolved into a simple statics problem. A sling
system can carry 2000 lbs using a 90° basket hitch, so the capacity of
one leg is half of 2000 lbs, which is 1000 lbs.
So, we need to calculate the vertical component of each leg, then sum
the total capacity of both legs using this 90° basket hitch at 60°.
Draw a force triangle and solve for X:
Vertical component of one leg 1000 lbs sin60 866 lbs
Vertical component of two legs 2 866 lbs 1732 lbs
1732 lbs is the max load this sling system can carry using a 60° angle.
(Answer D)
1000 lbs 1000 lbs
60° 60°
1732 lbs
90° 90°
2000 lbs
1000 lbs 1000 lbs
90° basket hitch goes all
the way around the load.
Page 54
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 7 SOLUTION:
CONSTRUCTION LOADS
Because the problem is 3 dimensional we are dealing with a X, Y, and
Z coordinate. In order to get the length of each cable we must do the
following:
Remember that the pickup point is half of 15 ft and that the pickup
point is half of 5 ft in width too. Solve for the magnitude of L:
2 2 27.5 2.5 6 9.92 ftL
Next you need to solve for the vertical
component in each cable. It can be written
as the following:
6 / 9.92 0.605y
F F F
Next, take the sum of forces in the y direction and solve for the force
in the cable:
4 1000 0
4 0.605 1000
413.2 410 lbs
yF
F
F
(Answer D)
You can see that each cable sees a much larger load that you would
think based on the angle you are pulling up at.
6 ft
L
7.5 ft
2.5 ft
Page 55
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 8 SOLUTION:
SOIL MECHANICS
LATERAL EARTH PRESSURE
First, solve for the active earth pressure coefficient:
1 sin32
0.3071 sin32
aK
Then draw the pressure diagram using the given unit weight and
pressure coefficient:
1st soil layer 12 100 0.307 368.4 psf
2nd soil layer 8 140 62.4 0.307 190.6 psf
Pore water pressure 8 62.4 1 499.2 psf
Note: P1, P2, and P3 are all from the effective pressure of the soil,
while P4 is from pore water pressure.
Page 56
|www.civilengineeringacademy.com|[email protected]|
Then solve for the forces by parts from the diagram and add for the
total force:
1
1368.4 12 2210.4 lb
2P
2368.4 8 2947.2 lbP
3
1559 368.4 8 762.4 lb
2P
4
1500 8 2000 lb
2P
1 2 3 47920 lb per ft
totalP P P P P
(Answer C)
Page 57
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 9 SOLUTION:
EFFECTIVE AND TOTAL STRESS
First, solve for the dry unit weight and saturated unit weight of the
soil:
2.7 62.4
104.65 pcf1 1 0.61
s wdry
G
e
2.7 0.61 62.4
128.3 pcf1 1 0.61
s w
sat
G e
e
Then solve for the effective stress at point C:
' 104.65 6 128.3 62.4 6 1023.3 psf
(Answer D)
Page 58
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 10 SOLUTION:
SOIL CONSOLIDATION
Solve for the time to consolidate:
2 2
3
0.197 1513722910 sec 159 days
0.00323 10v
v
T Ht
C
(Answer A)
PROBLEM 11 SOLUTION:
FOUNDATION SETTLEMENT
All of the answers to this are true about settlement, except option D.
The influence chart (Newmark) is used to find the vertical pressure
underneath a foundation. It is not used to determine the primary
consolidation rate. See Settling in the CERM.
(Answer D)
Page 59
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 12 SOLUTION:
SLOPE STABILITY
To solve this, use the Taylor slope stability chart (CERM Fig. 40.6):
Soil Mechanics, NAVFAC Design Manual DM-7.1
To find d, you solve 85 ft
3.27 326 ft
Dd
H and the slope was given
as 40°. See where these two intersect to find the slope stability
number, oN . Say 5.6
oN .
Solve for the safety factor:
6005.6 1.07 1.10
120 26o
cF N
H
This is an unacceptable safety factor. You want between 1.3-1.5 for
design.
(Answer A)
Page 60
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 13 SOLUTION:
BEARING CAPACITY
Solve for the ultimate bearing capacity of the soil:
0.5ult c q
Q cN DN BN
0c for sands
D depth into sand layer
B width of footing
Groundwater is neglected because it is greater than footing
D B
0 120 3 38 0.5 120 5 44 26880 psfult
Q
Solve for allowable load given the safety factor of 3:
268808960 psf
3ult
allow
FS
8960 psf 5 ft 5 ft 224000 lballow allow
P Q A
(Answer D)
Page 61
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 14 SOLUTION:
FOOTINGS
Solve for the total Unfactored Load:
100 80 180 kipsunfactored D L
P P P
Effective stress:
20 20' 4000 110 5 150 3383.3 psf
12 12
2
'
1800003383.3
53.2 ft
unfactoredP
A
A
A
Since the footing is square, the dimension of length and width should be equal.
Length width 53.2 7.29 7.5 ftA
Dimension = 7.5 ft x 7.5 ft
(Answer C)
Page 62
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 15 SOLUTION:
BEAMS
First, use the equilibrium equations to solve for the reactions:
0
800 5 10 500 15 0
1150 lb
A
B
B
M
R
R
0
1300 1150 0
150 lb
y
A
A
F
R
R
Draw the shear and moment diagrams; the maximum positive
moment is 750 lb-ft.
(Answer C)
Note:
To determine the maximum positive
moment, draw the shear force
diagram and the moment diagram.
1150 lbs
Shear Diagram:
Moving along the beam you start at +150 until you hit 800 lbs,
-650 is next (150-800 = -650) followed by a positive 500 lbs
(-650+1150 = 500).
Moment Diagram:
Because the moment is the integral of the shear, every time the
shear crosses 0 you should have a max or a min point. To find
the max and min’s find the area under the shear curve: 150
lb*5 ft = 750, and linear because shear slope is 0, then 650
lb*5 ft = 3250, so take 750-3250 = -2500 and then up to 0.
800 lbs 500 lbs
150 lbs
-650 lbs
500 lbs
750 lbs-ft
-2500 lbs-ft
150 lbs
5 ft 5 ft 5 ft
Page 63
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 16 SOLUTION:
BENDING
The maximum positive bending moment is 135 kips-in. The maximum
negative bending moment is -125 kips-in. Therefore, we use the larger
of the two values: 135 kips-in.
Solve for the bending stress:
135
or 16.58 ksi8.14
b
Mc Mf
I S
(Answer A)
135 kips-in
-125 kips-in
105 kips-in
4 ft 4 ft 3 ft Moment diagram
Page 64
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 17 SOLUTION:
COLUMNS
First, convert all pressure loads to concentrated loads:
Dead load 80 13 15 15600 lb
Slab weight 5
150 13 1512
12187.5 lb
TOTAL 27787.5 lb
Then use the formula for compressive stress:
27787.56946.9 psf 48.24 psi
4 1a
Pf
A
(Answer B)
80 psf
Dead load + Slab weight
4 ft 1 ft
15 ft
13 ft
5 in
Column
Page 65
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 18 SOLUTION:
DEFLECTION
+
=
3
192p
PL
EI
4
384w
wL
EI
total p w
First, solve for the deflection of the
concentrated load and uniform
load.
3
3
192
300020 12
1000 0.063 in192 29000 118
p
PL
EI
4
4
384
250 120 12
1000 12 0.053 in
384 29000 118
w
wL
EI
Then use superposition to solve for
the total deformation.
0.063 0.053 0.12 in
total p w
(Answer D)
Page 66
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 19 SOLUTION:
BENDING MOMENT DIAGRAM
From the information given,
we can now draw the shear and
moment diagram without any
given values.
The reaction at A starts the shear
up and then carries on until the
reaction at B. Because the shear
has a zero slope the moment is
linear until you hit the internal
moment at 4 ft. This drops the
moment to some value and then it
increases linearly until you hit zero
because the shear still has a zero
slope. Remember that the shear is
the derivative of the moment.
(Answer D)
The reactions from the supports at A
and B should create a resisting
moment in order to maintain the
equilibrium. Since the given load is
counterclockwise, the resisting
moment from the reactions should be
clockwise.
V
M
Page 67
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 20 SOLUTION:
PRESSURE CONDUIT
Parallel
First, solve for the flow rate along the pipe:
330 20 50 ft /s
A B CDQ Q Q
Then solve for diameter of pipe using the head loss
(use Manning’s equation, CERM Eq. 39.30b):
2 2
43
2
2
2
43
2 2
163
2.208
0.25
2.208 0.25
4.66
f
Ln vh
R
QLn
D
D
n LQ
D
2 2
163
2 2
163
4.66
4.66 0.013 950 5014.5
2.487 ft 29.85 in 30 in
f
n LQh
D
D
D
(Answer C)
Note: When pipes are parallel,
flow rates should be added.
Page 68
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 21 SOLUTION:
PRESSURE CONDUIT
Solve using Bernoulli’s equation: 2 2
1 1 2 21 2
2 2
P V P Vz HL z
g g
Solve for elevation Z at point B. Solve by using the Bernoulli equation
given when the gate valve was closed. Notice that velocity head is
cancelled out on both sides when it is closed because the flow is not
moving. There is also no head loss so we don’t need to account for
that. You are left with the following:
1200
62.5
19.2 ft
B AP P
z
z
z
Now solve for head loss. Use the Bernoulli equation given when the
gate valve is now open. Now that we have the elevation at B it should
be easy:
100019.23
62.4
35.26 ft
B A
B A
P PHL z
P PHL z
HL
HL
(Answer B)
Page 69
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 22 SOLUTION:
OPEN CHANNEL FLOW
First, solve for the area and the wetted perimeter of the channel:
Area:
2
1 2
13 4 15 4 66 ft
2A A A
Wetted Perimeter:
1 2 3
5 15 4 24 ftP L L L
Then solve for the Hydraulic Radius:
66
2.75 ft24
AR
P
(Answer D)
Page 70
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 23 SOLUTION:
PRESSURE CONDUIT
B
3.528 ft3/s QBE = ?
C
0.176 ft3/s
0.529 ft3/s
E
E
A B
D
C
E
QAB
First, solve for the flow rates depending on the given discharges in each
pipe before it:
33.528 0.812 0.777 1.939 ft /s
AB A AC ADQ Q Q Q
30.812 0.529 0.283 ft /s
CB AC CQ Q Q
30.777 0.176 0.601 ft /s
DB AD DQ Q Q
Then solve for QBE by adding all flow rates towards point B:
32.823 ft /s
BE CB AB DBQ Q Q Q
(Answer C)
Page 71
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 24 SOLUTION:
PRESSURE CONDUIT
First, solve for the Reynolds number and check to see if the flow is
laminar or turbulent:
61.7 3
12 15000.0017
r
DVN
2000r
N the flow is laminar
Then solve for the friction factor:
64 64
0.04261500
r
fN
Lastly, solve for the head loss using the Darcy Weisbach formula:
2 20.0426 150 3
1.786 ft62
2 32.212
fLVHL
gD
(Answer D)
Nr > 2000 → Laminar Flow
Nr < 2000 → Turbulent Flow
Note: The formula used if the flow
is laminar →
Page 72
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 25 SOLUTION:
OPEN CHANNEL FLOW
First, solve for the flow rate per foot of the jump:
3705 ft /s
54.231 13 ft
b
Then solve for the downstream depth of flow:
2
1 2 1 2
2
2 2
2
1
2
54.231 13.94 3.94
32.2 2
5.12 ft
qd d d d
g
d d
d
(Answer D)
Page 73
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 26 SOLUTION:
CONTINUITY EQUATION
El. 150 ft
El. 20 ft
Length = 3000 ft Diameter = 12”
P
Note: Since the tank is open to the
atmosphere, initial pressure head is
zero and because of the large area of
the reservoir its velocity head is
neglected (zero).
First, solve for the velocity and head loss of the system using the given.
2
45.09 ft/s
14
QV
A
2 20.012 3000 5.09
14.48 ft122
2 32.212
fLVHL
gD
Then use Bernoulli’s theorem from the Elev. 150 ft to Elev. 20 ft point:
2 2
1 1 2 21 2
2
2 21 2
2
2 2
2
10000 5.09150 14.48 20
62.4 2 32.2
45.1 ft
P V P Vz HL HP z
g g
P Vz HL HP z
g
HP
HP
(Answer B)
Page 74
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 27 SOLUTION:
BASIC CIRCULAR CURVE ELEMENTS
First, solve for the angle of the simple curve:
tan / 2
345 300 tan / 2
98
T R I
I
I
Then, solve for the external distance, E:
cos / 2
300cos 98 / 2
300
157.28 157 ft
RI
R E
E
E
(Answer C)
Page 75
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 28 SOLUTION:
TRAFFIC VOLUME
First, instead of constructing a v-t graph and s-t graph, you can
employ this approach (see graph). o
v t is zero if the vehicle starts from
rest. In this problem 65 fpso
v .
D area under the a-t graph
area distance from the a-t graph
65 120 2.46 60 90 3.3 60 30
15144 ft
oD v t Q Q
(Answer A)
a (ft/s²)
t (s²)
2.46
-3.3
120 secs
Acceleration – Time graph (a-t graph)
90
30
60 secs
Page 76
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 29 SOLUTION:
HORIZONTAL CURVE
First, solve for the location of the lowest point in the curve:
1
1 2
0.05820 512.5 ft
0.05 0.03
gx L
g g
Solve for the station of the lowest point:
Sta 80+50 512.5 or 8050 512.5
Sta 85+62.5 or 8562.5
(Answer C)
-5% +3%
820 ft
S
STA 80 + 50
Page 77
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 30 SOLUTION:
SOIL PROPERTIES
From CERM Table 35.7, find the mass of solids first, then solve for the
porosity:
3227.35 lbs
1 1 0.17t
s
mm
w
27.351 1 0.57
2.55 0.4 62.4s
t w
mn
SG V
(Answer D)
Page 78
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 31 SOLUTION:
CONCRETE
In concrete, the resisting force from the steel and effective concrete
block should be in equilibrium. Therefore, C T .
C internal force from the effective compression block of concrete
T internal force from the tension of the steel rebar
'0.85
0.85 3 12 3.33 40
4.35 in
c s y
C T
f ab A f
a
a
(Answer A)
a
22 in
3.33 in²
12 in
C
T
Resisting moment
a
0.85fc’
Asfy
Given:
fc’ = 3 ksi
fy = 40 ksi
Page 79
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 32 SOLUTION:
MATERIAL TEST METHODS
Mohr’s Circle
65 psi
45 psi
X
First, draw the Mohr’s circle of the problem then solve for x:
tan
45tan29
65
16.18 psi
x
x
x
Then solve for the cohesion:
tan
tan2916.18
8.97 9 psi
c
x
c
c
(Answer C)
Y
Normal stress (σ)
Shear stress (τ)
C 29°
Page 80
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 33 SOLUTION:
COMPACTION
First, we solve for the field dry unit weight:
2.2
129.41 pcf0.017
moist
W
V
129.41
114.52 pcf1 1 0.13
moistdry
w
Then we solve for the relative compaction:
,max
114.520.9543 95.43%
120d
c
d
R
(Answer D)
Page 81
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 34 SOLUTION:
SOIL CLASSIFICATION
In classifying the soil using USDA, we need to exclude the percentage
of gravel.
New sand 8%
10%100% 20%
New silt 48%
60%100% 20%
New clay 24%
30%100% 20%
Then draw the lines along the USDA chart. The soil falls in the SILTY
CLAY LOAM area.
(Answer D)
Page 82
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 35 SOLUTION:
STRUCTURAL STEEL
WT 13.5 x 108.5:
d = 14.215 in
y = 3.11 in Ix = 502 in4
Bottom fiber
Top fiber
Solve using the bending stress formula:
b
Mcf
I
Bending stress on top fiber:
150 12 3.11
11.15 ksi502
b
Myf
I
Bending stress on bottom fiber:
150 12 14.215 3.11
39.82 40 ksi502
b
M d yf
I
The maximum bending stress is taken as the larger of the two
values. Therefore, the bending stress on bottom fiber is the
maximum one.
(Answer B)
Neutral axis
Page 83
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 36 SOLUTION:
EXCAVATION
Use the formula for excavations:
1 2 3 42 3 4
4
AV h h h h
Where:
1
2
3
4
20.3 15.1 6.9 5.9 48.2 ft
18.4 12.5 19 20.5 12.5 8.8 6.23 12.8 110.73 ft
0 ft
14.1 17.1 8.4 14.1 53.7 ft
h
h
h
h
Solve for the volume:
1 2 3 4
3
2 3 44
60 60 48.2 2 110.73 3 0 4 53.7
4
436,014 ft
AV h h h h
(Answer C)
B C D A
I
II
III
IV
60 ft
60 ft
60 ft
60 ft 60 ft 60 ft
4 2 4
4 2
2
2 4
1 2 2 1
1 2 1 2
Page 84
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 37 SOLUTION:
CONSTRUCTION SITE LAYOUT
First, plug all the data given into the appropriate field. You can do this
using the figure or by making a table. I’ve solved this using the figure:
Station BS FS Elev
BM1 8.56 540.51
TP1 9.45 4.23
BM2 3.15 ?
8.56 ft 4.23 ft
Elevation= 540.51 ft
BM1
BM2
TP 1
3.15 ft 9.45 ft
HI1=8.56+549.07
HI2=9.45+544.84=554.29
Elevation = 549.07 - 4.23 = 544.84 ft
Elevation = 554.29 - 3.15 = 551.14 ft
After figuring out the elevations at each location, take the elevation
at BM2 and subtract it from BM1’s elevation to find the difference:
551.14 540.51 10.63 ft
(Answer C)
Page 85
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 38 SOLUTION:
CONSTRUCTION SITE CONTROL
160 ft 160 ft
R2-R1=1.6 ft R2-R1=3.2 ft
Use the equation for stadia reading to find the interval factor, K:
x K R c
160 1.6 Eq. 1
320 3.2 Eq. 2
K c
K c
Where:
X = distance from telescope
K = interval factor
R = reading on rod (between top and bottom reading)
C = instrument factor
Substitute the first equation into the second and solve for K:
100K
(Answer C)
Page 86
|www.civilengineeringacademy.com|[email protected]|
PROBLEM 39 SOLUTION:
SAFETY
Typical permissible noise exposure levels range, but according to
OSHA, sec 1910.95, for 8 hours it is 90 dBa. Chapter 82 of the CERM
covers some construction and jobsite safety issues with OSHA
standards included.
(Answer A)
PROBLEM 40 SOLUTION:
CONSTRUCTION SITE LAYOUT AND CONTROL
From the figure below, the angle of intersection is:
180 40 65 75
(Answer D)
N
E
S
W
40°
65°
65°
θ
40°
Page 87
|www.civilengineeringacademy.com|[email protected]|
SCORE SHEET
Correct Answers: ___________
Percentage: (correct answers)/40 = ____/40 = ______
Again, shoot for above 90% and you’ve got it. You’ve now finished 2
test and you’re more prepared to pass the real thing! Keep practice as
much as possible to get more exposure to all kinds of problems.
That’s the secret sauce. Good luck on the real deal and in your career
as a civil engineer. If you need more tips, tricks, and even a review
course then check out www.civilpereviewcourse.com and
www.civilengineeringacademy. We would also love to hear about your
successes, failures, or any way we can improve things to help future
students. Good luck on your exam and in your career as a
professional civil engineer!
Page 88
|www.civilengineeringacademy.com|[email protected]|
LAST SECOND ADVICE AND TIPS
I wanted to wrap up this exam with some tips that I found helpful
when I took the exam. Hopefully, they will help you:
1) Make sure you fully understand what your state board and the
NCEES requires of you to take the PE exam and to receive your
PE. Comply with all rules.
2) You typically need about 3-4 months to really study for the PE.
Map out a schedule and study your depth section first. This will
allow you to make any adjustments as you get closer to test
time. I personally broke down the specification into the 5 major
categories of: water resources, transportation, geotechnical,
structural, and construction, and spent a couple weeks on each
topic with more time devoted to my depth section.
3) Practice everything with the calculator you are going to use on
the real exam. You need to become intimately familiar with it.
4) Know where your exam is, where to park, and where you will get
food (if you don’t plan on bringing your own). Don’t be stuck
trying to figure this out on test day. You’ll regret it.
5) Review courses help. If you can’t get motivated, or need the
extra help and accountability they offer, then consider taking
one. It’s worth it to get your PE and get that boost to your
career. If you’re wondering which one, refer to our helpful tools
below.
Helpful Tools:
We have built www.civilengineeringacademy.com to help any civil
engineer become a PE. We have tons of free video practice problems
there to get you going. We also have plenty of tips, must have
resources, advice on courses, and more practice exams that cover
your depth section. In addition to this, we have created a civil PE
review course that can guide you step-by-step through the entire
exam. You can check that out at www.civilpereviewcourse.com.
Page 89
|www.civilengineeringacademy.com|[email protected]|