The Total Economic Impact Of Microsoft Windows...
Transcript of The Total Economic Impact Of Microsoft Windows...
A Forrester Total Economic
Impact™ Study
Commissioned By Microsoft
Project Director:
Sean Owens
October 2013
The Total Economic
Impact Of Microsoft
Windows Azure Infrastructure, Data, And App Services Can Help Save IT Costs And Enable New Revenue Opportunities
Table Of Contents
Executive Summary .................................................................................... 3
Disclosures .................................................................................................. 4
TEI Framework And Methodology ............................................................ 5
Analysis ........................................................................................................ 7
Financial Summary ................................................................................... 23
Microsoft Windows Azure: Overview ..................................................... 24
Appendix A: Composite Organization Description .............................. 25
Appendix B: Total Economic Impact™ Overview ................................. 26
Appendix C: Glossary ............................................................................... 27
Appendix D: Endnotes .............................................................................. 27
ABOUT FORRESTER CONSULTING
Forrester Consulting provides independent and objective research-based
consulting to help leaders succeed in their organizations. Ranging in scope from a
short strategy session to custom projects, Forrester’s Consulting services connect
you directly with research analysts who apply expert insight to your specific
business challenges. For more information, visit forrester.com/consulting.
© 2013, Forrester Research, Inc. All rights reserved. Unauthorized reproduction is strictly prohibited.
Information is based on best available resources. Opinions reflect judgment at the time and are subject to
change. Forrester®, Technographics
®, Forrester Wave, RoleView, TechRadar, and Total Economic Impact
are trademarks of Forrester Research, Inc. All other trademarks are the property of their respective
companies. For additional information, go to www.forrester.com.
3
Executive Summary
In August 2013, Microsoft commissioned Forrester
Consulting to conduct a Total Economic Impact™ (TEI)
study and examine the potential return on investment (ROI)
enterprises may realize by deploying Windows Azure. The
purpose of this study is to provide readers with a framework
to evaluate the potential financial impact of Windows Azure
on their organizations.
To better know the benefits, costs, and risks associated with
a Windows Azure implementation, Forrester interviewed
current customers, each with at least a year of experience.
Interviewed organizations have taken advantage of
Windows Azure’s infrastructure, data, and application
offerings, leveraging services such as: Virtual Machines,
Storage, SQL Database, StorSimple, and Service Bus.
Prior to Windows Azure, customers had a variety of on-
premises solutions, perhaps located in a hosted data center
but still fully managed and administered by the organization.
This led to a variety of issues, such as: the existing data
center running out of room, opportunities or sales having
been missed because of slow application development or
delivery, and IT budgets rising at the same time the
company was calling for savings.
With Windows Azure, customers were able to:
› Increase revenue through greater sales and faster time-
to-market, leveraging Windows Azure Infrastructure
Services like Virtual Machines, for fast initiation and
removal of development and test environments, and a
more mature and easier-to-use application delivery
channel.
› Save costs in IT administration and backup processes
with the Virtual Machines, Storage and Backup Services,
with many now being completely handled by Microsoft
and other processes being greatly reduced by the
simplicity of Windows Azure.
› Improve marketing effectiveness and reporting by
leveraging Windows Azure App Services like Service Bus
to communicate with internal systems and retail partners.
WINDOWS AZURE LEADS TO FINANCIAL BENEFITS
Interviews with six existing customers and subsequent
financial analysis found that a composite organization based
on these companies estimated startup costs of about
$70,000, followed by annual service and management costs
of almost $100,000, versus benefits of around $330,000 per
year, plus a one-time first-year benefit of nearly $700,000 in
avoided hardware costs.
These add up to the risk-adjusted results shown in Figure 1
and Figure 2. See Appendix A for a description of the
composite organization.
FIGURE 1
Composite Organization Overview Of Risk-Adjusted ROI And NPV With Key Benefits
97.5% 33%
ROI: 349%
NPV: $1,105,902
Improvement in
development/test environment
setup and configuration
Increase in customers in the first
year with a cloud-based software
distribution system
Source: Forrester Research, Inc.
Windows Azure enabled several key benefits for
many interviewed organizations, such as:
Infrastructure services help increase
revenue with an easier-to-use and more
streamlined application delivery platform.
Infrastructure and data services help
increase revenue with a scalable pay-what-
you-use development and test environment
leading to faster time-to-market.
App Services help connect data and
applications for faster setup and reduced
errors related to business marketing
activities, like a coupon campaign.
4
› Benefits. Some of the most impactful benefits
experienced by the composite organization are listed
here, as identified by interviewed companies:
• Increased service subscription sales of about
$60,000 to $120,000 per year with a more
advanced client application connected with
Windows Azure. The composite organization
previously distributed its application via CD-ROM,
which led to delivery and update difficulties. But
now with a hybrid application model that includes
Windows Azure, it is easier to distribute, share, and
manage the application. This has enabled easier
trial and update processes that have helped lead to
more sales — an increase of 33% in the first year,
with growth at a lower rate in following years.
• By migrating to Windows Azure, one-time costs
estimated at nearly $700,000 for planned new
and upgraded servers, hosting, and other
hardware purchases were avoided. Keeping the
previous solution made up of resources housed on-
premises and at a colocation site would have
required continued investment including new
hardware to meet scale, upgrades to existing
hardware, and continued hosting costs.
• Windows Azure’s App Services help marketing
connect data and applications for faster setup
and reduced errors, leading to $50,000 in
savings per year. Windows Azure Service Bus
helped to more easily and quickly initiate a coupon
marketing campaign, track sales, set coupon valid
dates, and reduce duplicate coupon use.
› Costs. The composite organization experienced the
following risk-adjusted costs:
• Estimated Windows Azure subscription fees
starting of about $80,000 per year over three
years. Fees for Windows Azure, including Windows
Server Virtual Machines, SQL Server, BizTalk
Server-based Service Bus, Storage, Backup, and
Support services, are paid based on usage. Costs
are estimates: Because pay-per-use service
charges are applied only to what is used, light
periods may be less expensive, and heavy periods
may be more expensive. Additionally, the
composite organization signed a 12-month
commitment, which includes a significant discount.
• Annual costs for managing Windows Azure of
about $20,000. This is an annual estimate of
resource costs to administer and manage Windows
Azure. However, as shown in the Benefits column,
it is much less than managing an on-premises
solution, since many management tasks (like
patches, updates, server health monitoring, etc.)
are handled by the Azure platform when used as a
platform-as-a-service (PaaS) offering, and an
infrastructure-as-a-service (IaaS) offering (but to a
lesser extent with the latter).
• Implementation costs of about $70,000. This is
based on time required for planning, migration (or
new development), and implementation of an
existing or new application or service to Windows
Azure.
See Figure 2 for more details on these and other benefits
and costs reviewed in this study.
Disclosures
The reader should be aware of the following:
› The study is commissioned by Microsoft and delivered by Forrester Consulting.
› Forrester makes no assumptions as to the potential ROI that other organizations will receive. Forrester strongly advises
that readers use their own estimates within the framework provided in the report to determine the appropriateness of an
investment in Microsoft Windows Azure.
› Microsoft reviewed and provided feedback to Forrester, but Forrester maintains editorial control over the study and its
findings and does not accept changes to the study that contradict Forrester's findings or obscure the meaning of the study.
› The customer names for the interviews were provided by Microsoft. Microsoft did not participate in customer interviews.
5
TEI Framework And Methodology
INTRODUCTION
From the information provided in the interviews, Forrester
has constructed a Total Economic Impact™ (TEI)
framework for those organizations considering implementing
Microsoft Windows Azure. The objective of the framework is
to identify the cost, benefit, flexibility, and risk factors that
affect the investment decision.
APPROACH AND METHODOLOGY
Forrester took a multistep approach to evaluate the impact
that Microsoft Windows Azure can have on an organization
(see Figure 3). Specifically, we:
› Interviewed Microsoft marketing, sales, and/or consulting
personnel, along with Forrester analysts, to gather data
relative to Windows Azure and the marketplace for
Windows Azure.
FIGURE 2
Summary Of Risk-Adjusted, One-Time, And Annual Costs And Benefits
Source: Forrester Research, Inc.
Note: This is based on three-year risk-adjusted figures. Values of costs and benefits are representative of a composite organization constructed from
aggregated feedback based on interviews with Microsoft Windows Azure customers.
$750,000
$1.25 million $500,000 $250,000 ($250,000)
Initial planning and implementation (one-time)
Present Value
Costs ($317 thousand)
Benefits ($1.42 million)
Improved revenue from increased customers and faster time-to-market
Reduced marketing costs from better business responsiveness
Reduced IT management and software development costs
Annual resource consumption and management costs
Avoided hardware costs (one-time)
($500,000) $1 million $1.5 million
6
› Interviewed six organizations currently using Microsoft
Windows Azure to obtain data with respect to costs,
benefits, and risks.
› Designed a composite organization based on
characteristics of the interviewed organizations (see
Appendix A).
› Constructed a financial model representative of the
interviews using the TEI methodology. The financial
model is populated with the cost and benefit data
obtained from the interviews as applied to the composite
organization.
Forrester employed four fundamental elements of TEI in
modeling Microsoft’s Windows Azure service:
› Costs.
› Benefits to the entire organization.
› Flexibility.
› Risk.
Given the increasing sophistication that enterprises have
regarding ROI analyses related to IT investments,
Forrester’s TEI methodology serves the purpose of
providing a complete picture of the total economic impact of
purchase decisions. Please see Appendix B for additional
information on the TEI methodology.
FIGURE 3
TEI Approach
Source: Forrester Research, Inc.
7
Analysis
COMPOSITE ORGANIZATION
For this study, we conducted a total of six interviews with
representatives from the following companies, which are
Microsoft customers based in the US and Europe:
› A multinational consumer- and business-products
manufacturing company headquartered the US.
› A midsized sporting-goods manufacturing company
based in the US.
› A large retail firm headquartered and primarily located in
the US.
› A global furniture manufacturing company headquartered
in the US.
› A global construction company headquartered in the US.
› A local government school system in Europe.
Based on the interviews, Forrester constructed a TEI
framework, a composite company, and an associated ROI
analysis that illustrates the areas financially affected. The
composite organization that Forrester synthesized from
these results represents an organization with the following
characteristics:
› A US-based firm that develops and sells products sold in
retail stores as well as some software.
› About 50,000 employees.
› About 1,500 customers of the primary software product.
› Twenty to 30 servers supporting development, testing,
and operations for that group.
› On-site storage and tape backup solutions, along with off-
site services such as tape storage.
After an extensive request-for-proposal (RFP) and business
case process evaluating multiple vendors, the composite
organization chose Microsoft Windows Azure and began
deployment:
› Implementation started in early 2013.
› This first phase included subscriptions for IaaS virtual
machine services as well as backup and storage services.
› Further investigation and potential implementation of
additional Windows Azure services are planned.
“We had been spending a lot of time
on server updates, security patches,
and other management tasks, which
are now part of the Windows Azure
services.”
~ Project manager at a European school system
INTERVIEW HIGHLIGHTS
Information was collected from the six interviewed
organizations and summarized as a composite organization.
The following situation, solution, and results are based on
this analysis.
Situation
The composite organization was faced with several key
business issues that it wanted to resolve quickly:
› The organization developed and sold a well-regarded
niche software solution but saw flat (and even decreasing)
subscription sales in what should have been a growing
market. The application was built on old development
technologies that occasionally connected to a simple
database, which led to distribution problems, update
delays, and version issues.
› The organization was projecting significant investment
requirements for a number of in-house server resources,
including dedicated development and test environments.
› The organization had a nightly tape backup system that
was reaching its limits as backup times approached 24
hours — an upgraded or replacement system was
needed soon.
› The organization saw rising costs in areas such as
marketing, IT management, development, and testing, as
resources had to spend more time using older systems
for more and more complex problems.
Solution
The composite organization had used a few cloud-based
point solutions but selected Windows Azure for its full
8
solution set, high-quality services based on worldwide
infrastructure, and the confidence that Microsoft’s name
provides.
While Windows Azure provides a broad variety of services,
the organization started with compute services for
virtualized Windows Server environments, data services for
SQL Server and backup, and application services for
Service Bus.
Results
The interviews revealed that for the composite organization:
› Windows Azure enables a more streamlined and
better-managed application development,
distribution, and licensing platform. Coupled with an
application migration to .NET development, moving the
back-end of the application to a shared application
database to Azure meant that it could ensure a reliable
data store that could scale to larger markets, check and
automatically update client software as needed, and
implement a user account system as a required step to
use the client software. This allowed the organization to
eliminate draconian distribution policies and simply post
the client software on the site — which resulted in near-
instant positive feedback as well as a greater number of
organizations downloading, testing, and purchasing the
software.
“Windows Azure’s geo-redundant
offering is a much better setup than a
company of my size would ever be
able to afford.”
~ Vice president of information technology at a construction
management firm
› Costs associated with the purchase of servers and
other hardware, hosting services, and ongoing
management are avoided by migrating to Windows
Azure services. The composite organization was able to
reduce or avoid a number of IT costs:
• Avoid purchasing a number of new servers and
upgrading existing servers.
• Eliminate costs to colocation hosts for resources
moved to Windows Azure.
• Avoid the purchase of at least one new tape backup
system.
• Greatly reduce the amount of time spent on
management tasks dealing with the above
equipment and services, such as managing a
development/test server farm, backup tasks, and
services costs for off-site storage and retrieval of
tape backups.
› Time-to-market is improved with faster time-to-
implement, more scalable, and more reliable
development and test Windows Azure Compute
services. A new development and test environment can
be set up quickly — and not six or eight weeks after you
request the server from procurement and have it set up by
IT. That means development and testing can start
immediately — and those eight weeks could mean
significant additional revenue for certain applications
(such as a new sales tool that helps reps close more
deals).
“Anytime you have to requisition
hardware, it will take weeks to
coordinate efforts between
procurement, data center
management, IT operations, and
other groups.”
~ Development manager at a sporting goods manufacturer
› Easy setup of environments and the ability to only
pay for what’s used with Windows Azure mean
development and test cost savings. In addition to
increased revenue, faster development or test
environment setup means much less management time
— setup takes just a few clicks. Also, production,
development and test environments are all exactly the
same Windows Azure environment — unforeseen issues
that might arise because the development and test
environments were domain-attached servers (for
example) are eliminated. Finally, the organization only
pays for what it needs — instead of having to buy a new
server to support new development and test
environments needed for a busy period, it simply expands
and then turns down its Windows Azure service needs.
9
› With Windows Azure Service Bus, data transfer
between internal and partner systems leads to
immediate marketing campaign improvements. The
composite organization, with Windows Azure Service
Bus, can more easily share information between internal
systems, partners, and customers; a service bus is a
mechanism for centralizing and optimizing
communications between multiple disparate systems.
Based on the responses from interviewed organizations,
the specific process of distributing and redeeming
coupons was included in the composite organization
model, measuring benefits in areas such as more easily
and quickly initiating a coupon marketing campaign and
more accurately tracking and reporting campaign
effectiveness. With Windows Azure, the composite
organization was able to distribute coupons via email,
track incoming redeemed codes more effectively, and
save significant costs in coupon marketing campaign
upfront initiation and campaign-end reporting.
10
BENEFITS
The composite organization based on the interviewed with
six Windows Azure customers experienced several
quantified benefits enabled by Windows Azure integrated
with other cloud and on-premises business applications,
data, and processes:
› Increased revenue from better software scalability and
distribution.
› Increased revenue from faster time-to-market.
› Improved marketing management and reporting.
› Hardware and hosting costs avoidance.
› Reduced ongoing management costs.
› Higher developer productivity through faster test
environment procurement.
Increased Revenue With Better Software Scalability And
Distribution Enabled By Windows Azure
With Windows Azure, the organization improved its
application platform delivery, support, and distribution
platform, leading to a reported 33% more new customers for
its most popular software offering in the first year, plus an
estimated continued growth in subsequent years.
Previously, the application was distributed like a shrink-
wrapped product. Even though it was for a very specific
market and connected to a central database for data
storage and business logic, it did not include authentication.
So the organization couldn’t just post the application online
and allow subscribers to download it — that would make it
available to virtually anyone and provide access to the full
product. This resulted in a number of organizational and
customer difficulties as illustrated in Figure 4, including:
› The organization spent significant time and money
printing and shipping the client application via CD-ROM.
› It also spent significant time handling customer requests
for new and updated software — each request had to be
verified manually before shipping a CD-ROM.
› The organization would ship updates to all subscribers,
but there was no validation or reminders to ensure that
updates were installed.
› Since it was harder to get updates, remember to install
them, and/or request a replacement CD-ROM, new
customers were starting to choose alternative solutions,
and even existing customers were starting to move.
This, coupled with the fact that the application developed on
an older application platform, meant a flat, and even
shrinking, subscriber base. Windows Azure and a client
application re-development to .NET enabled subscriber
authentication and validation checks for the latest version.
The central application database was deployed on Windows
TABLE 1
Non-Risk-Adjusted Incremental Revenue From Increased Number Of Customers
Ref. Metric Calculation Year 1 Year 2 Year 3
A1 Customers today 1,700
A2 Revenue per customer/subscriber (per year) $775
A3 Expected growth with Windows Azure 33% 10% 10%
A4 Expected customer growth with Windows
Azure A1*A3 2,261 2,487 2,487
A5 Total revenue with Windows Azure (A5-A1)*A2 $434,775 $610,003 $610,003
A6 Profit margin (for revenue from software apps
on Windows Azure) 16%
At Increased revenue from more customers,
enabled by the Azure platform scalability A6*A7 $69,564 $97,600 $128,440
Source: Forrester Research, Inc.
11
Azure for a full hybrid solution built on Windows Azure, the
client application, and back-end systems.
With the updated solution, the organization saw a return to
strong subscription sales (primarily from the reduced
customer barriers to test and subscribe), adding up to nearly
$70,000 in the first year, and expects nearly $100,000 in the
second year and $130,000 in the third year since moving to
Windows Azure.
“Prior to going to Azure, we had to
physically distribute our software,
including printing CDs, stuffing
envelopes, sending them out, and
such. With Windows Azure, we’re able
to put our software on the website
available for download.”
~ Project manager at a European school system
Customers are much more satisfied with the improved
reliability and ease of support (for example, simply
downloading the application to install it on a new or
upgraded PC), and the organization not only has seen
increased revenue but also is able to spend less time and
money on old-fashioned distribution processes, like burning
and shipping CDs.
Increased Revenue From Faster Time-To-Market
In addition to an increase in customers for the primary
consumer product, the composite organization is able to
generate additional revenue from faster development of it
and other consumer and internal applications. With
Windows Azure, the organization found it much quicker and
easier to set up development and test environments,
particularly:
› It avoided the process and logistics of ordering, waiting,
and setting up new hardware to support development and
test environments — which can take as much as eight
weeks or more. Additionally, this delay may also be an
issue for new applications sent to production — even
when planning ahead, there may be no avoiding a release
delay if data center expansions are required, such as
waiting for servers to be shipped, setting up and
integrating with the current infrastructure, and testing the
hardware to make sure it’s ready and correctly configured.
› Development and test environments may not quite match
production servers (e.g., a development environment may
be a virtual or physical server attached to a corporate
domain), which may require extra time or special
handling. So developers can be more efficient by focusing
on core application needs and not infrastructure changes.
› The development and test virtual server farm is used for a
number of application projects, and each project requires
some special setup or configuration. Instead of constantly
making configuration changes, uninstalling past work, and
reinstalling required resources like SQL Server, with
Windows Azure, setting up a new environment is very
FIGURE 4
Application Deployment Is Streamlined And Reduces Potential Customer Barriers To Entry
Source: Forrester Research, Inc.
12
quick, and recreating past environments is complete in
just a few clicks of the mouse.
› Also, virtual development and test environments can be
shut down quickly with Windows Azure, so the
organization is not charged for it when not in use (and the
environment profile can be saved for quick recreation).
“Profits from improved and faster
application sales improve local
services and benefit taxpayers — a
great example of good government!”
~ Project manager at a European school system
The cost savings from quick setup, easier management,
and reduced infrastructure costs are all covered in the
license and management costs savings sections. However,
applications that provide consumers or internal users with
new capabilities can also help generate new direct or
indirect sales — for example, an update to the main
application should lead to more new sales than without the
update, or a new or updated internal sales tool can help
close more deals. In both cases, making those applications
available two months early can mean new revenue for a
significant number of new and updated products and
internal applications. The composite organization develops
an average of one new or upgraded application per year,
which both:
› Can generate new otherwise-unrealized revenue.
› Would have required new hardware for development/test
or production environments or was faster than past
development cycles due to the quick setup of saved
development/test environments with Windows Azure.
On average, the application development time is 7.5 weeks
faster with Windows Azure, leading to the generation of
about $20,000 to $35,000 in additional revenue per year, as
shown in Table 2.
“A lot of companies fail to realize: We
get our pick of the best developers
because they want to work in the
cloud, and turnover is less since
moving to Azure.”
~ Development manager at a sporting goods manufacturer
TABLE 2
Non-Risk-Adjusted Increased Revenue From Faster Time-To-Market
Ref. Metric Calculation Year 1 Year 2 Year 3
B1 Average on-premises server procurement
cycle time (weeks) 8.0
B2 Percent improvement in resource allocation
time with Azure 93.75%
B3 Resource allocation time with Azure (weeks) 0.5
B4 Value of one week faster time-to-market $8,360 $11,730 $15,440
B5 Applications developed per year that could
generate increased revenue 2.0 2.0 2.0
B6 Profit margin (for revenue from software apps
on Windows Azure) 16% 16% 16%
Bt Increased revenue, due to faster
application time-to-market
(B1-B3)*B4*
B5*B6 $20,064 $28,152 $37,056
Source: Forrester Research, Inc.
13
Avoided Costs From Better Marketing And Business
Responsiveness
In addition to software- and IT-related benefits, the
organization, as a global conglomerate with many different
business units, also included Windows Azure Service Bus in
its subscription, specifically for its product marketing teams
to implement a hybrid environment where data and
information among organization, partners, and customers
can be shared across a variety of systems — Windows
Azure, other cloud solutions, or on-premises. Based on the
interviews with users of Windows Azure and discussions of
their experiences, the specific process modeled for the
composite organization is the distribution and redemption of
coupons distributed directly to consumers or through retail
channels.
With a variety of channels and distribution modes, the
organization had problems syncing information and sharing
accurate information with partners. For example, a one-use
coupon available for store or online purchase was not
properly validated, so coupons could be used multiple
times. Also, quick validation of coupons was not possible,
so coupons were distributed live, meaning that even with
specific start and end dates, coupons could be used any
time after distribution, and coupons were very time-
consuming to set up within the disconnected systems.
Furthermore, accurate coupon redemption data was hard to
come by, or come by within a reasonable time.
These and other issues meant that the organization was not
able to accurately measure the results of a coupon-based
marketing campaign. Coupons were redeemed and sales
were made, but it was very hard to tell whether the coupon
helped drive more sales; what days, weeks, or seasons
might be the most effective times for a campaign; and what
markets or consumer types would be the best targets.
“All our coupons had to be
individually activated; even with
some automation, it would take more
than a day, as many groups were
involved. With Service Bus,
information-sharing across groups is
automated, and activating a million
coupons takes less than an hour.”
~ Director of information technology at a large retailer
The organization identified benefits in areas such as: more
easily and quickly initiating a coupon marketing campaign,
more accurately tracking sales during coupon marketing
TABLE 3
Non-Risk-Adjusted Better Marketing And Business Responsiveness Cost Savings
Ref. Metric Calculation Year 1 Year 2 Year 3
C1 Coupon campaigns per year 15
C2
Average number of hours required to set up
and initialize a coupon campaign for
distribution before Windows Azure
80
C3
Average number of hours required to prepare
a marketing campaign report, collecting data
from multiple sources
16
C4 Percent improvement with Windows Azure
Service Bus 75%
C5 Average marketing full-time equivalent salary
(FTE) per hour $50
Ct Avoided costs from better marketing and
business responsiveness
C1*(C2+C3)
*C4*C5 $54,000 $54,000 $54,000
Source: Forrester Research, Inc.
14
campaigns, more accurately setting coupon valid dates, and
reducing duplicate coupon use. In particular, the first two
areas were seen as the most measurably affected by
Windows Azure. The organization implemented Windows
Azure Service Bus, which provides a messaging channel for
connecting cloud applications to on-premises applications
as well as services and systems both inside and outside of
the organization. With Service Bus, the organization was
able to create a central data source where it could share
and receive coupon validation and usage information, with
retail partners able to leverage that information, validate
online coupon use, and more easily integrate coupon data
with other line-of-business systems to assess campaign
performance and drive improvement for future campaigns.
Table 3 shows that the organization estimates that it took 80
hours to set up and initialize the electronic coupon records
for a marketing campaign and 16 hours to pull together the
information and data afterwards for an average of 15
campaigns per year. Since subscribing to and implementing
Service Bus, it estimates saving 75% of the time it takes to
do these tasks, adding up to a savings of nearly $55,000
per year. The organization also expects to see significant
benefits in its return on marketing investment, and
increased revenue from marketing process and targeting
improvements enabled by Service Bus. However, it has not
been in use long enough to track that level of benefit.
“We started Windows Azure with four
instances. If we built our data center
on-premises, I would have requested
10 or 20 servers.”
~ Marketing manager at a multinational consumer- and
business-products manufacturer
Avoided Hardware And Other Costs
The composite organization realized a key benefit from
Windows Azure by avoiding a much greater hardware
investment for a similar on-premises solution. To meet the
scale and reliability needs with an on-premises
implementation, the organization would have had to:
› Purchase 20 additional servers.
› Upgrade 50 others.
This adds up to a total server count of more than the
equivalent size of the Windows Azure subscription, because
the on-premises solution needs to be ready for peak traffic
times. And Windows Azure provides the same or better
security of the organization’s data, which meets industry
standards for security and reliability, provides data
TABLE 4
Non-Risk-Adjusted Avoided Server And Implementation Costs
Ref. Metric Calculation Year 1 Year 2 Year 3
D1 Non-Azure estimated servers to purchase, to meet estimated peak need
20
D2 Estimated average per-server purchase cost $25,000
D3 Non-Azure estimated servers to upgrade, to meet estimated peak need
50
D4 Estimated average per-server upgrade cost $3,000
D5 Estimated average new server setup and configuration time (hours)
16
D6 IT FTE hourly salary $35
D7 Other scheduled or expected hardware, hosting, or other costs
$25,000
Dt Avoided server and implementation costs (D1*D2)+
(D3*D4)+(D1 *D5*D6) +D7
$686,200 $0 $0
Source: Forrester Research, Inc.
15
encryption, and is continually tested and improved.
The organization was also able to avoid the purchase of a
new tape backup system estimated to cost about $25,000.
Total avoided costs added up to a one-time savings of
nearly $690,000 during the initial migration to Windows
Azure, as shown in Table 4.
Reduced Ongoing Management Costs
In addition to hardware and other avoided costs, the
composite organization saw a significant reduction in
ongoing server management costs following the Windows
Azure implementation. With Windows Azure Compute and
virtual machine subscriptions:
› Many server management tasks are included with
Windows Azure subscriptions (especially for PaaS
Compute services), such as operating system updates,
patches, security updates, etc.
› The organization was able to refocus its resources to
managing applications and data.
› Supporting a larger customer base was possible with
Windows Azure (because the application is easier to
distribute now that it is connected to resources installed
on Windows Azure and the SQL Server database on
Windows Azure — along with the updated client
application — is more reliable).
With the retirement or repurposing of nearly all of the 70
servers, the organization estimates that it will save nearly all
of the 80 hours per week previously spent on system
management and backup processes, adding up to more
than $130,000 per year in costs as shown in Table 5.
The organization also implemented Windows Azure Storage
Services and StorSimple, which meant it could retire its
difficult, error-prone, and time-intensive tape backup system
for the data stored in its on-premises SharePoint Server; the
estimates include savings from tape backup process and
management costs (including recovery fees from the third-
party tape storage provider) as well as overall easier
processes with StorSimple and SharePoint integration.
“We selected and implemented
StorSimple because it is integrated
with SharePoint. Everything has
worked great!”
~ Manager of core infrastructure services at a global
furniture manufacturer
Development And Test Environment Setup, Procurement,
And Management Cost Savings
Along with reduced hardware purchases that would have
been necessary, in part, for ongoing development and test
environment needs, the organization is able to save process
time and costs associated with setting up, configuring, and
retiring development/test physical or virtual servers. Also,
any delays in waiting for procurement, shipping, and
configuration are eliminated.
The composite organization, with multiple development
efforts happening throughout the year, was able to almost
completely eliminate the tasks associated with the setup
and management of development and test environments
TABLE 5
Non-Risk-Adjusted Avoided Management And Support Effort
Ref. Metric Calculation Year 1 Year 2 Year 3
E1 Average number of hours per week required to
support the solution before Azure 80
E2 Percent reduction of hours per week required
to support Windows Azure 90%
E3 IT FTE hourly salary $35
Et Avoided management and support effort E1*E2*E3*52 $131,040 $131,040 $131,040
Source: Forrester Research, Inc.
16
with Windows Azure. Before, a new development and
testing process might require new hardware (which added
significant time while waiting for the procurement and data
center teams to complete their tasks) and nearly always
required some setup or configuration from the previous
setup — often back to the same or similar setup from a
previous version of the same application. Additionally, any
networking or configuration issues would have needed to be
handled with the appropriate IT teams.
With Windows Azure, nearly all of those steps are
eliminated, as virtual machine setup requires a few clicks of
the mouse — fewer when using saved configurations. As
few or as many virtual machines can be set up as needed
— to meet the number of environment configurations and/or
scale necessary. Also, these development and test
TABLE 6
Non-Risk-Adjusted Reduced Costs From Improved And Faster Development And Test Processes
Ref. Metric Calculation Year 1 Year 2 Year 3
F1 Time to set up/configure/take down a development/testing environment before Windows Azure (hours)
20.0
F2 Percent improvement in development/testing environment setup (etc.) time, with Windows Azure
97.50%
F3 Time to set up (etc.) development/testing environment with Windows Azure (hours)
F1*F2 0.5
F4 Development/test environments set up per month
2.0
F5 Development/test FTE salary $60
Ft Cost savings from improved dev/test processes
(F1-F2)*F4*F5*12
$28,080 $28,080 $28,080
Source: Forrester Research, Inc.
TABLE 7
Total Benefits (Non-Risk-Adjusted)
Benefit Initial Year 1 Year 2 Year 3 Total
Present
value
Increased revenue from more customers,
enabled by the Azure platform scalability $0 $69,564 $97,600 $128,440 $295,605 $240,401
Increased revenue, due to faster
application time-to-market $0 $20,064 $28,152 $37,056 $85,272 $69,347
Avoided costs from better marketing and
business responsiveness $0 $54,000 $54,000 $54,000 $162,000 $134,290
Avoided server and implementation costs $0 $686,200 $0 $0 $686,200 $623,818
Avoided management and support effort $0 $131,040 $131,040 $131,040 $393,120 $325,877
Cost savings from improved dev/test
processes $0 $28,080 $28,080 $28,080 $84,240 $69,831
Total benefits $0 $988,948 $338,872 $378,616 $1,706,437 $1,463,564
Source: Forrester Research, Inc.
17
environments are the same as the Windows Azure
production environment; an application can be changed or
moved from test to production with a few clicks of the
mouse, and any past issues (though few) that arose from
slightly different development, test, and production
environments are eliminated.
“With every new operating system,
we have to add that environment to
our development and test farm.”
~ Development manager at a sporting goods manufacturer
The organization spent an average of 20 total hours setting
up, configuring, and managing each development/test
virtual server farm. With Windows Azure, that is reduced to
almost nothing — just an hour or so. The organization
develops and tests two new or upgraded applications per
month, on average, which adds up to a total savings of
nearly $30,000 per year as shown in Table 6.
Total Benefits
Table 7 shows the total of all benefits across the areas
listed previously as well as present values discounted at
10%. Over three years, the composite organization expects
total benefits to represent a present value of more than
$1.46 million.
18
COSTS
The composite organization experienced the following costs
associated with the Windows Azure solution:
› Annual Windows Azure subscription fees.
› Annual management costs.
› One-time implementation and migration costs.
These represent the mix of internal and external costs
experienced by the composite organization for initial and
ongoing resources associated with the solution.
“Once we explained Windows Azure’s
comprehensive security, our
executives were onboard.”
~ Manager of core infrastructure services at a global
furniture manufacturer
Windows Azure Implementation Costs
The organization’s implementation of Windows Azure,
shown in Table 8, included setting up the necessary
databases, server resources, and Service Bus; configuring
StorSimple and Windows Azure Storage Services and
migrating data, application pointers, and other necessary
changes. Application updates were not included, as they
were already deemed necessary and planned before the
move to Windows Azure. Training was also not included. As
for the most part, it was not necessary, except to review the
Windows Azure management interfaces for the couple of
people who would manage and monitor it on a regular
basis.
Windows Azure Resource Consumption Fees
Windows Azure fees are billed monthly based on actual
consumption of resources, measured to the nearest minute;
these are estimated as an average monthly cost and then
added up annually for this discussion. Microsoft provides an
online pricing tool that prospective customers can use to
estimate the cost of consuming Azure subscription-based
resources (or the cost of consuming other subscription
options), and that tool was used to calculate costs for the
composite organization.1 For the composite organization,
resource consumption options include:
› Compute:
• Four Windows Server medium virtual machines.
• Two SQL Enterprise Server medium instances.
• One Standard BizTalk Server medium instance.
• Bandwidth of 1,000 GB.
• Standard support.
› Storage/Data Management:
• Geo-redundant storage of 25,000 GB.
• Backup space of 2,000 GB.
• Included support.
Additionally, the composite organization expects a 10%
TABLE 8
Non-Risk-Adjusted Planning And Implementation Costs
Ref. Metric Calculation Initial Year 1 Year 2 Year 3
H1 Planning and implementation time (weeks)
12.0
H2 Planning and implementation FTE 4.0
H3 Estimated FTE hourly salary $35
H4 Other initial costs (e.g., training) $0
Ht Initial planning and implementation costs
H1*40*H2* H3+H4
$67,200 $0 $0 $0
Source: Forrester Research, Inc.
19
annual growth in Windows Azure resource needs.
These add up to around $7,500 to $9,000 per month.
Because the composite organization signed a 12-month
commitment, a 22.5% discount can be applied, and the
updated total is about $6,000 to $7,000 per month.
(Discounts are available to organizations to subscription
commitments, pre-pay estimated subscription costs, and/or
include Windows Azure in their volume licensing agreement
such as an Enterprise Agreement.)2
Over a full three-year analysis, including discounts and
estimated growth, this adds up to about $70,000 to $85,000
per year, as shown in Table 9.
Annual Maintenance Cost
Windows Azure management is expected to be minimal,
given that Microsoft Windows Azure resources handled the
day-to-day management of Azure servers, which is included
in the subscription fees. Any remaining tasks that the
organization will need to continue are mainly related to
reviewing and adjusting scale options, setting up and
shutting off test and development servers, dealing with
backup retrieval support issues, and managing any changes
or updates to the Service Bus. The organization estimates
this to be one-fourth of an FTE’s time (one or more IT
resources with other responsibilities related to other server
and line-of-business systems that have remained on-
TABLE 9
Non-Risk-Adjusted Windows Azure Estimated Annual Consumption Fees
Ref. Metric Calculation Year 1 Year 2 Year 3
I1 Estimated Annual Growth Rate of Windows
Azure implementation 10%
I2 Estimated Azure VM Costs per month
(charged per minute; billed monthly) $5,000 $5,500 $6,050
I3 Other Azure Service Costs per month (charged
per minute; billed monthly) $2,500 $2,750 $3,025
I4 12-Month-Commitment Discount (based on
Azure resource consumption costs) 22.5% 22.5% 22.5%
I5 Other Annual Costs, including system
management $0 $0 $0
It Annual Azure Resource Consumption
Costs
(I2 + I3 + I5) *
12 $69,750 $76,725 $84,398
Source: Forrester Research, Inc.
TABLE 10
Non-Risk-Adjusted Annual Organization Resource Maintenance Costs For Windows Azure
Ref. Metric Calculation Year 1 Year 2 Year 3
J1 Average management time per week (hours) 10 10 10
J2 Estimated Windows Azure Management FTE
hourly salary $35 $35 $35
Jt Annual organization resource costs for
Windows Azure management J1*52*J2 $18,200 $18,200 $18,200
Source: Forrester Research, Inc.
20
premises). As shown in Table 10, resource time is
estimated to cost about $20,000 per year.
“Long-term, because we’ve been very
happy with Azure, we want to move
all our stuff over.”
~ Vice president of information technology at a construction
management firm
Total Costs
Table 11 shows the total of all costs as well as associated
present values, discounted at 10%. Over three years, the
composite organization expects costs to total a net present
value of a little more than $315,000.
TABLE 11
Total Costs (Non-Risk-Adjusted)
Benefit Initial Year 1 Year 2 Year 3 Total
Present
value
Initial planning and implementation costs ($67,200) $0 $0 $0 ($67,200) ($67,200)
Annual Azure resource consumption
costs $0 ($69,750) ($76,725) ($84,398) ($230,873) ($190,227)
Annual organization resource costs for
Windows Azure management $0 ($18,200) ($18,200) ($18,200) ($54,600) ($45,261)
Total costs ($67,200) ($87,950) ($94,925) ($102,598) ($352,673) ($302,688)
Source: Forrester Research, Inc.
21
FLEXIBILITY
Flexibility, as defined by TEI, represents an investment in
additional capacity or capability that could be turned into
business benefit for some future additional investment. This
provides an organization with the right or the ability to
engage in future initiatives but not the obligation to do so.
There are multiple scenarios in which a customer might
choose to implement Windows Azure and later realize
additional uses and business opportunities. Flexibility would
also be quantified when evaluated as part of a specific
project (described in more detail in Appendix B).
Windows Azure provides a variety of options for future
expansion of cloud strategies and delivery of new cloud-
based services to employees, partners, and/or customers.
Two areas identified during customer interviews are
highlighted here:
› First, the two revenue-generating benefits, increased
software sales and improved time-to-market, are
examples of specific benefits that, with broader adoption,
could become new revenue and profit opportunities.
• If all costs were doubled to meet new resource
consumption and management task needs, it would
add up to about $300,000 (three-year cumulative
costs, undiscounted and not risk-adjusted).
Migrating one or more applications could generate
new revenue plus additional management cost
savings. Doubling all associated benefits (as costs
were doubled) could add up to nearly $1 million in
added benefits over three years (again
undiscounted and cumulative over three years).
› Second, Windows Azure provides a platform that could
completely or nearly completely replace an organization’s
internal data center requirements. Daily management,
support, patching, security, and other primary tasks would
all be handled by Microsoft, and the organization could
reduce more costs related to hardware, support, help
desk, data center hosting, on-premises office rental,
HVAC and power, resources, and a variety of other costs.
Firms that use technology to enable their business can
focus on their core business.
RISK
Forrester defines two types of risk associated with this
analysis: implementation risk and impact risk.
Implementation risk is the risk that a proposed investment in
Windows Azure may deviate from the original or expected
requirements, resulting in higher costs than anticipated.
Impact risk refers to the risk that the business or technology
needs of the organization may not be met by the investment
in Windows Azure, resulting in lower overall total benefits.
The greater the uncertainty, the wider the potential range of
outcomes for cost and benefit estimates.
The TEI includes a focus on risk to quantitatively capture
potential investment and impact uncertainties by directly
adjusting the financial estimates to provide a more accurate
projection of the ROI analysis. In general, risks affect costs
by raising the original estimates, and they affect benefits by
reducing the original estimates. The risk-adjusted numbers
should be taken as realistic expectations since they
represent the expected values considering risk.
The following implementation risks that affect costs are
identified as part of this analysis:
› Windows Azure resource consumption costs. Since
these estimates are based on charges calculated to the
minute of future, actual consumption of services, any
TABLE 12
Cost And Benefit Risk Adjustments
Costs Risk adjustment
Windows Azure resource
consumption costs 5%
Windows Azure organization
management resource costs 10%
Benefits Risk adjustment
Increased revenue with better
software scalability and
distribution
10%
Increased revenue from faster
time-to-market 5%
Avoided costs from better
marketing and business
responsiveness
10%
Source: Forrester Research, Inc.
22
increase or decrease in actual use could mean changes
to these estimates. To be conservative, a low risk
adjustment of 5% was added to these costs
› Composite organization resource costs in the event
of Windows Azure outages. While Windows Azure
provides a service-level agreement (SLA) that includes
reimbursement of the subscription costs for unplanned
outage time, that does not include resource costs of
scrambling to implement a mitigation plan. Outages are
rare — there have been three significant outages of 8 or
more hours over the past three years (as of August 2013)
— but possible and would require significant organization
resource time in remediating issues, setting up alternative
processes, etc. While the likelihood of a major outage is
low, the IT and resource costs could be quite high. To
provide a conservative estimate, 10% was added to
Windows Azure management costs to cover the business
and resource costs of possible Windows Azure outages.
The following impact risks that affect benefits are identified
as part of the analysis:
› Increased revenue with better software scalability and
distribution enabled by Windows Azure. As highlighted
previously, Windows Azure provides an SLA, but any
compensation in the event of a longer outage won’t cover
lost revenue. While an outage of that length is unlikely,
the impact is high, so this benefit has been adjusted
(reduced) by 10%.
› Increased revenue from faster time-to-market. An
Azure outage could affect revenue if it happens during a
period of extra application revenue. Since that is not all of
the time, the risk adjustment (reduction) is just 5%.
› Avoided costs from better marketing and business
responsiveness. Marketing and coupon campaigns rely
on a lot of people, partners, consumers, systems, etc. A
breakdown in any area, even one completely unrelated to
Windows Azure, would likely mean extra time dealing with
coupon administration and data management. A 10% risk
reduction has been applied to this benefit.
Table 12 shows the values used to adjust for risk and
uncertainty in the cost and benefit estimate, but readers are
urged to apply their own risk estimates based the degree of
confidence in their own cost and benefit estimates.
23
Financial Summary
The financial results calculated in the Costs and Benefits
sections can be used to determine the ROI and net present
value (NPV) for the organization’s investment in Windows
Azure. These are shown in Table 13.
Table 14 and Figure 2 show the risk-adjusted ROI, NPV,
and cumulative values. These are determined by applying
the risk-adjustments from Table 12 in the Risk section to the
benefit and cost totals in Tables 7 and 11.
For the composite organization, the move to Windows
Azure enabled a variety of cost savings and revenue
opportunities and transitioned nearly all costs related to the
application development and marketing outlined previously
from capital to operational expenses, which can now be
planned as a regular monthly expenses, like a utility.
TABLE 13
Cash Flow: Non-Risk-Adjusted
Initial Year 1 Year 2 Year 3 Total Present value
Costs ($67,200) ($87,950) ($94,925) ($102,598) ($352,673) ($302,688)
Benefits $0 $988,948 $338,872 $378,616 $1,706,437 $1,463,564
Net benefits ($67,200) $900,998 $243,947 $276,019 $1,353,764 $1,160,876
ROI 384%
Source: Forrester Research, Inc.
TABLE 14
Cash Flow: Risk-Adjusted
Initial Year 1 Year 2 Year 3 Total Present value
Costs ($67,200) ($93,258) ($100,581) ($108,637) ($369,676) ($316,725)
Benefits $0 $975,588 $322,305 $358,520 $1,656,413 $1,422,627
Net benefits ($67,200) $882,331 $221,724 $249,882 $1,286,737 $1,105,902
ROI 349%
Source: Forrester Research, Inc.
FIGURE 5
Risk-Adjusted Annual And Cumulative Costs And Benefits (In Thousands)
Source: Forrester Research, Inc.
($67) ($93) ($101) ($109)
$976
$322 $359
Initial Year 1 Year 2 Year 3
TotalCosts
TotalBenefits
RunningTotal
24
Microsoft Windows Azure: Overview
Windows Azure is an open and flexible cloud platform that
enables organizations to quickly build, deploy, and manage
applications across a global network of Microsoft-managed
data centers, which can be integrated with an existing IT
environment.
Windows Azure enables organizations to build and run
applications without focusing on the infrastructure. It
provides automatic OS and service patching, built-in
network load balancing, and resiliency regarding hardware
failure. It supports a deployment model that enables you to
upgrade applications without downtime.
Windows Azure supports many languages, frameworks, and
tools to build applications. Features and services are
exposed using open REST protocols. The Windows Azure
client libraries are available for multiple programming
languages and are released under an open source license.
Windows Azure enables application scaling to any size. It is
an automated self-service platform that allows for fast
resource provisioning, with a billing model that charges for
resources used. Windows Azure is available in multiple data
centers around the world, enabling deployment of
applications close to customers and users.
Windows Azure delivers a flexible cloud platform that can
satisfy many application needs. It enables organizations to
reliably host and scale out application code; store data
using relational SQL databases, NoSQL table stores, and
unstructured blob stores; as well as leverage Hadoop and
business intelligence services for data-mining. When
deployed with the StorSimple solution on-premises,
Windows Azure helps provide a more complete hybrid cloud
storage solution.
Windows Azure’s messaging capabilities enable scalable
distributed applications and deliver hybrid solutions that run
across a cloud and on-premises enterprise environment.
For more information visit www.windowsazure.com.
25
Appendix A: Composite Organization Description
For this TEI study, Forrester has created a composite
organization to illustrate the quantifiable costs and benefits
of implementing Windows Azure. The composite company
is intended to represent a US-based firm focused on
developing and selling consumer products but has
branched out into software development and services.
In purchasing Windows Azure, the composite company has
the following objectives:
› Reduced operations costs.
› Created new revenue opportunities for software products.
› Moved capex expenses to opex.
Based on the interviews, Forrester constructed a TEI
framework, a composite company, and an associated ROI
analysis that illustrates the areas financially affected. The
composite organization that Forrester synthesized from
these results represents an organization with the following
characteristics:
› A US-based firm that develops and sells products sold in
retail stores as well as some software.
› About 50,000 employees.
› About 1,700 customers of the primary software product
before Windows Azure implementation.
› Twenty to 30 servers supporting development, testing,
and operations for that group.
› On-site storage and tape backup solutions, along with off-
site services such as tape storage.
After an extensive RFP and business case process
evaluating multiple vendors, the composite organization
chose Microsoft Windows Azure and began deployment:
› Implementation started in Q3 of 2012.
› This phase included subscriptions for IaaS virtual
machine services as well as StorSimple and Service Bus.
› Further investigation and potential implementation of
additional Windows Azure services is planned.
FRAMEWORK ASSUMPTIONS
Table 15 provides the model assumptions that Forrester
used in this analysis.
The discount rate used in the present value (PV) and NPV
calculations is 10%, and the time horizon used for the
financial modeling is three years. Organizations typically
use discount rates between 8% and 16% based on their
current environment. Readers are urged to consult with their
respective company’s finance department to determine the
most appropriate discount rate to use within their own
organizations.
TABLE 15
Model Assumptions
Ref. Metric Value
A1 Hours per week 40
A2 Weeks per year 52
A3 Work hours per year (M-F, 9-5) 2,080
A4 Average IT hourly salary $35
A5 Average developer/tester hourly salary $60
A6 Average marketing professional hourly salary $50
Source: Forrester Research, Inc.
26
Appendix B: Total Economic Impact™ Overview
Total Economic Impact is a methodology developed by
Forrester Research that enhances a company’s technology
decision-making processes and assists vendors in
communicating the value proposition of their products and
services to clients. The TEI methodology helps companies
demonstrate, justify, and realize the tangible value of IT
initiatives to both senior management and other key
business stakeholders.
The TEI methodology consists of four components to
evaluate investment value: benefits, costs, risks, and
flexibility.
BENEFITS
Benefits represent the value delivered to the user
organization — IT and/or business units — by the proposed
product or project. Often product or project justification
exercises focus just on IT cost and cost reduction, leaving
little room to analyze the effect of the technology on the
entire organization. The TEI methodology and the resulting
financial model place equal weight on the measure of
benefits and the measure of costs, allowing for a full
examination of the effect of the technology on the entire
organization. Calculation of benefit estimates involves a
clear dialogue with the user organization to understand the
specific value that is created. In addition, Forrester also
requires that there be a clear line of accountability
established between the measurement and justification of
benefit estimates after the project has been completed. This
ensures that benefit estimates tie back directly to the bottom
line.
COSTS
Costs represent the investment necessary to capture the
value, or benefits, of the proposed project. IT or the
business units may incur costs in the form of fully burdened
labor, subcontractors, or materials. Costs consider all the
investments and expenses necessary to deliver the
proposed value. In addition, the cost category within TEI
captures any incremental costs over the existing
environment for ongoing costs associated with the solution.
All costs must be tied to the benefits that are created.
RISK
Risk measures the uncertainty of benefit and cost estimates
contained within the investment. Uncertainty is measured in
two ways: 1) the likelihood that the cost and benefit
estimates will meet the original projections, and 2) the
likelihood that the estimates will be measured and tracked
over time. TEI applies a probability density function known
as “triangular distribution” to the values entered. At a
minimum, three values are calculated to estimate the
underlying range around each cost and benefit.
FLEXIBILITY
Within the TEI methodology, direct benefits represent one
part of the investment value. While direct benefits can
typically be the primary way to justify a project, Forrester
believes that organizations should be able to measure the
strategic value of an investment. Flexibility represents the
value that can be obtained for some future additional
investment building on top of the initial investment already
made. For instance, an investment in an enterprisewide
upgrade of an office productivity suite can potentially
increase standardization (to increase efficiency) and reduce
licensing costs. However, an embedded collaboration
feature may translate to greater worker productivity if
activated. The collaboration can only be used with additional
investment in training at some future point in time. However,
having the ability to capture that benefit has a PV that can
be estimated. The flexibility component of TEI captures that
value.
27
Appendix C: Glossary
Discount rate: The interest rate used in cash flow analysis
to take into account the time value of money. Although the
Federal Reserve Bank sets a discount rate, companies
often set a discount rate based on their business and
investment environment. Forrester assumes a yearly
discount rate of 10% for this analysis. Organizations
typically use discount rates between 8% and 16% based on
their current environment. Readers are urged to consult
their respective organization to determine the most
appropriate discount rate to use in their own environment.
Net present value (NPV): The present or current value of
(discounted) future net cash flows given an interest rate (the
discount rate). A positive project NPV normally indicates
that the investment should be made, unless other projects
have higher NPVs.
Present value (PV): The present or current value of
(discounted) cost and benefit estimates given at an interest
rate (the discount rate). The PV of costs and benefits feed
into the total NPV of cash flows.
Payback period: The breakeven point for an investment.
This is the point in time at which net benefits (benefits minus
costs) equal initial investment or cost.
Return on investment (ROI): A measure of a project’s
expected return in percentage terms. ROI is calculated by
dividing net benefits (benefits minus costs) by costs.
A NOTE ON CASH FLOW TABLES
The following is a note on the cash flow tables used in this
study (see the example table below). The initial investment
column contains costs incurred at “time 0” or at the
beginning of Year 1. Those costs are not discounted. All
other cash flows in Years 1 through 3 are discounted using
the discount rate (shown in Framework Assumptions
section) at the end of the year. PV calculations are
calculated for each total cost and benefit estimate. NPV
calculations are not calculated until the summary tables and
are the sum of the initial investment and the discounted
cash flows in each year.
Appendix D: Endnotes
1 Source: Microsoft Windows Azure Pricing Calculator
(http://www.windowsazure.com/en-us/pricing/calculator/).
2 Link to win azure discount page
TABLE [EXAMPLE]
Example Table
Ref. Metric Calculation Year 1 Year 2 Year 3
Source: Forrester Research, Inc.