The Tesla Gigafactory

download The Tesla Gigafactory

If you can't read please download the document

Transcript of The Tesla Gigafactory

  • 1.Planned 2020 Gigafactory Production Exceeds 2013 Global Production500,000 Vehicles 40!GWh/Year Production 35!Global cell supply growing, but almost entirely in Asia Gigafactory!30!Others! Lishen!25!BYD! BAK!20!ATL! Maxell!15!Sony! Panasonic!35,000 Vehicles 10!LGC! SDI!5!0! 2010!2011!2012!2013!2014!2015!2016!2017!2018!2019!2020!Battery pack cost/kWh reduced >30% by Gen III volume ramp in 2017Source: IIT Takeshita 2013

2. Gigafactory Process Flow PackEnclosure Raw Steel/ Aluminum Anode ManufacturingCopperFoil Battery PackRecycling Separator AnodeElectrode Winding PackModuleModuleModuleModule SeparatorManufacturing ModuleCellCellCellCell Raw Materials Aluminum Foil Can & Cap CathodeElectrode Cell Assembly Cathode Manufacturing Electrolyte Manufacturing Battery Pack Lifetime Usage Vehicle Assembly(Fremont, CA) 3. Tesla Gigafactory Gigafactory Projected Figures 2020 Tesla Vehicle Volume500,000/yr2020 Gigafactory Cell Output35 GWh/yr 2020 Gigafactory Pack OutputNew Local Renewables Solar and Wind 50 GWh/yr Space Requirement Total Land Area (acres) EmployeesUp to 10M ft2w/ 1-2 levels500-1000 6,500Rendering 4. Gigafactory Location Finalists Finished battery packs from the Gigafactory to Fremont, CA for vehicle assembly.Final site selection activities are underway. 5. Gigafactory Projected Timeline Site Selection ACTIVE Initial Project Design Tesla and its partners will invest $4-5 billion in the Gigafactory through 2020. CapEx will be shared by Gigafactory partners. Tesla will directly invest $2 billion. PartnerDiscussionsZoning & Design / BuildFacility Construction Equipment Installation Production Launch and Ramp2020(500k Veh/Yr) TODAY 2014 2015 2016 2017 6. Forward Looking Statements Certain statements in this communication, including statements regarding the Tesla Gigafactory and its development plans, production capacity, cost savings, costs, timeline and vehicle production estimates, are forward-looking statements that are subject to risks and uncertainties. These forward-looking statements are based on managements current expectations, and as a result of certain risks and uncertainties, actual events or results may differ materially from those contained in the forward-looking statements. Various important factors could cause actual results to differ materially from those in the forwardlooking statements, including potential difculties in nding a suitable Tesla Gigafactory site, obtaining required permits, negotiating terms with technology and other partners, maintaining implementation schedules, output and cost estimates and vehicle demand. Please refer to Teslas most recent Annual Report on Form 10-K and its other lings with the Securities and Exchange Commission. These lings contain and identify important factors that could cause actual results to differ materially from those contained in Teslas forward-looking statements. Tesla disclaims any obligation to update information contained in these forward-looking statements.