The Stockholm bypass - Trafikverket

32
The Stockholm bypass Johan Brantmark, Project Director Lars Malthe, Head of Procurement

Transcript of The Stockholm bypass - Trafikverket

Page 1: The Stockholm bypass - Trafikverket

The Stockholm bypass

Johan Brantmark,

Project Director

Lars Malthe,

Head of Procurement

Page 2: The Stockholm bypass - Trafikverket

2 2013-11-26

Stockholm

Page 3: The Stockholm bypass - Trafikverket

3 2013-11-26

A city on water in a growing metropolitan area

2 million today

2,5 million in 2030

The County of Stockholm grows

by approx 100 inhabitants a day

Page 4: The Stockholm bypass - Trafikverket

4 2013-11-26

Regional development plan

The Stockholm Bypass:

• Forms an outer ring road together

with Norrortsleden and

Södertörnsleden

• Llinks north and south and many

of the regional urban cores

• Creates a single market for jobs,

homes and services

• Reduces the vulnerability of the

road system in Stockholm

• Creates new opportunities for

public transport

• Makes every-day life easier

Page 5: The Stockholm bypass - Trafikverket

5 2013-11-26

Plans since the 1960´s for a north-south connection

Kungshattsleden Västerleden Förbifart Stockholm

Page 6: The Stockholm bypass - Trafikverket

6 2013-11-26

Page 7: The Stockholm bypass - Trafikverket

7 2013-11-26

The Stockholm bypass

Length: just over 21 km

Tunnel: just over 18 km

Travel time: approximately 15 minutes

No. of lanes: three in each direction

Junctions: six

Traffic 2035: 140,000 vehicles/day

Completion: about 10 years

Cost: SEK 27.6 billion

EUR 3.1 billion

(2009 prices)

Page 8: The Stockholm bypass - Trafikverket

8 2013-11-26

Just over 18 out of 21 km in tunnels

Stockholm bypass cross-section with slopes up to junctions at Lovö and Vinsta. Note that the drawing is not to scale

C Current E18 C Current E4

Graphics: Tomas Öhrling 2010

Page 9: The Stockholm bypass - Trafikverket

9 2013-11-26

Main tunnel

• 2 parallel main tunnels

• 3 lanes in each direction

• Emergency exits every 100 m

• 17+1 km in length

• Normal section approx.135 m²

• Ramp tunnels approx. 20 km

Page 10: The Stockholm bypass - Trafikverket

10 2013-11-26

The security concept is being

elaborated in collaboration

with other relevant authorities

• Safe design

• Parallel tunnels without

oncoming traffic

• Round the clock CCTV

• Frequent emergency exits

• Permanent fire fighting

system

• Detectors

A safe journey

Page 11: The Stockholm bypass - Trafikverket

11 2013-11-26

Start of construction works

• Preparatory works

• Moving power lines, piping

etc

• Start of construction

• Seven access tunnels

• Three temporary harbours

• Kungens kurva, Hjulsta,

Johannelund, … Work in

many places

simultaneously

Page 12: The Stockholm bypass - Trafikverket

12 2013-11-26

Det

The Stockholm bypass 2013 and onwards

Time

LAND AQUISITION PLAN

MUNICIPALITIES’ DETAILED

DEVELOPMENT PLANS

OTHER ASSESSMENTS

(Natura 2000)

(Nature and culture reserves)

GO

VE

RN

ME

NT

’S P

ER

MIS

SIB

ILIT

Y A

SS

ES

SM

EN

T

EIA

, 2

00

9

(Ga

ine

d le

gal fo

rce

20

11

)

PROJECT PLANNING

CONSTRUCTION DOCUMENTS

CONSTRUCTION

EIA = Environmental Impact Assessment

ENVIRONMENTAL

RULINGS

APPROVED

Page 13: The Stockholm bypass - Trafikverket

Contractual demand on Swedish F-skatt

• Undeclared work is a major problem in Europe – Undeclared work is work which is in itself legal but is not declared to

the authorities for tax, social security and/or labour law purposes.

• Agreement Stockholm Bypass and Skatteverket – Cooperate to prevent undeclared work – the shadow

economy • Protect responsible business from unfair competition

• Protect labour

• Contractual demand on Swedish F-skatt – In all contracts

– All entreprenours, no matter level

• Protect Trafikverket and the Entreprenours from the effect from other contractors tax and/or social security fraud

• Non discriminating clause

• Contact Skatteverket! – How to apply for a Swedish tax registration – Swedish

F-skatt

– Further information

Page 14: The Stockholm bypass - Trafikverket

The Stockholm bypass Health & Safety

Trafikverket is responsible for long-term

planning of the transport system for road

traffic, rail traffic, and transport by sea

and air. Trafikverket is also responsible

for building, operating and maintaining

national roads and railways.

Work Environment

Page 15: The Stockholm bypass - Trafikverket

15 2013-11-26

Together towards zero accidents

Page 16: The Stockholm bypass - Trafikverket

16 2013-11-26

Attention and priority to Health and Safety

• Health & Safety considered in all

phases of the project

• A common approach and shared values

• Forceful action when rules are not

complied with

Page 17: The Stockholm bypass - Trafikverket

17 2013-11-26

A systematic Health & Safety

Management

A proactive safety culture that

promotes sharing and learning

Excellent coordination between

Installation contractors

Page 18: The Stockholm bypass - Trafikverket

18 2013-11-26

Procurement of contracts in

Page 19: The Stockholm bypass - Trafikverket

19 2013-11-26

Carrying out The Stockholm bypass

• 50 contracts of varying sizes

• 15-20 main civil contracts

• Construction of rock tunnels, civil engineering,

bridges, roads and installations.

• The size of the main civil contracts varies

between 500 and 3000 million SEK.

Page 20: The Stockholm bypass - Trafikverket

20 2013-11-26

When we are going to do it

Page 21: The Stockholm bypass - Trafikverket

21 2013-11-26

Time 2013 2014 2015 2016 2017 2018

Procurement of

installation contracts

The first tender

request

Prequalification

Requests for main

contracts

Procurements of infrastructure operations

Time schedule for procurements

Page 22: The Stockholm bypass - Trafikverket

22 2013-11-26

How we are going to do it

Page 23: The Stockholm bypass - Trafikverket

23 2013-11-26

Strategy for procurements

• Create conditions to produce increased

innovation and productivity

• Provide the conditions for fair

competitiveness in the construction industry

Page 24: The Stockholm bypass - Trafikverket

24 2013-11-26

• To establish a good collaborative

relationship.

• A clear division of roles between client and

contractor.

• The contractor plans, leads and performs

the contract work.

• Collaboration is based on trust and the

contractor's self-checking

• Respect, openness and accessibility between

the parties.

• Co-operation regardless of contract form and

compensation form.

Our view of The Stockholm bypass

project in the role of client

Page 25: The Stockholm bypass - Trafikverket

25 2013-11-26

• Aim to select business forms that stimulate competition.

• Encourage an effective and sustainable use of resources.

• Reward innovation.

• Procurements should be carried out in such a way that the

best possible adaption to current market conditions is

achieved.

• Tender request documents should be clear and accessible

• Responsibility and risk allocation should be unambiguously

defined.

Our procurement strategy in

The Stockholm bypass Project

Page 26: The Stockholm bypass - Trafikverket

26 2013-11-26

• In accordance with the Swedish Public

Procurement Act (LOU).

• The majority of our contract procurements are

above the threshold value.

• All procurements are published in the EU

database Tenders Electronic Daily (TED).

• Open procurements.

• Selective procurement - prequalification

Procurement forms

Page 27: The Stockholm bypass - Trafikverket

27 2013-11-26

• All technical qualifications and contract documents

are drawn up in Swedish.

• If a need is demonstrated, individual documents as

well as complete acts can be translated into English.

• We follow the industry's common standard

agreements for contracts.

Our tender request documents

Page 28: The Stockholm bypass - Trafikverket

28 2013-11-26

Kungens Kurva in brief

Page 29: The Stockholm bypass - Trafikverket

29 2013-11-26

Lovö, Vinsta, Hjulsta in brief

• 3 Interchanges, Lovö,

Vinsta and Hjulsta

Page 30: The Stockholm bypass - Trafikverket

30 2013-11-26

Akalla-Häggvik in brief

• 2 Interchanges, Akalla and

Häggvik

• Concrete - 75 000 m3

• Excavated rock - 500 000 m3

• Coating- 160 000 m2

Page 31: The Stockholm bypass - Trafikverket

31 2013-11-26

• Length main tunnels: 2x18 km

• Length ramp tunnels: approx. 14 km

• 3 temporary harbours

• Total rock: 19 million tonnes

• Boring method: Drill & blast

• 6 main contracts

Rock tunnels in brief

Page 32: The Stockholm bypass - Trafikverket

32 2013-11-26