The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

19
The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group

Transcript of The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Page 1: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

The STAR MRPC TOF Project

BNL

December 1, 2005

Geary Eppley, with

Jo Schambach,

for the TOF Group

Page 2: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Design considerations

• The integration space available for TOF in STAR is that currently occupied by the CTB.

• The space is about 2.2m from the beam line: requires precision time measurement.

• The clearance between the TPC and EMC is about 10 cm.

• The space has a uniform 0.5T magnetic field parallel to the beam.

• There is limited space for “nearby” electronics outside the magnet steel.

ZCal

SiliconVertexTracker

CentralTriggerBarrel orTOF

FTPCs

TimeProjectionChamber

Barrel EMCalorimeter

VertexPositionDetectors

EndcapCalorimeter

Magnet

Coils

TPCEndcap &MWPC

ZCal

RICH

Page 3: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

MRPC development

• Multigap glass RPCs developed in the late 1990s at CERN, C. Williams, et.al.

• STAR TOF group designed STAR-specific MRPC modules that would fit existing CTB trays and tested them at CERN in 2000 & 2001.

Page 4: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

MRPC prototypes in STAR

• One tray of MRPC modules has been installed in STAR for Runs 3, 4, & 5.

• An improved tray design each year but some modules have been installed for all 3 years.

• Runs 3 & 4 used CAMAC electronics.

• Prototype HPTDC based electronics used in Run 5

• NINO/HPTDC based electronics for Run 6/7.

Page 5: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Electronics integral to tray

• 95% of the electronics resides on the tray inside the cover

• 4 external electronics boxes located on the magnet steel connect the 23k-channel system to STAR trigger and DAQ

Page 6: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Tray specifications

• There are 32, 6-channel modules per tray.

• The active area covers about 87% of -0.9<eta<0.9

• Occupancy in central AuAu is ~12%.

• HV provides +-7 kV.

• Gas mixture: 95% r134a, 5% isobutane.

• Average noise rates are ~15 Hz/channel with greater than 100% correlation.

• Detection efficiency is ~95%.

Page 7: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Time measuring

• Absolute times are recorded and buffered by the HPTDC for all hits above threshold.

• A single 40 MHz oscillator provides the clock for the 2882 HPTDCs in the system.

• Both start and stop detectors use the HPTDC to record times eliminating systematic uncertainty from the choice of counter.

• Each HPTDC has a 21 bit clock counter providing a 51 us clock period. The HPTDCs are reset by a signal with a common origin at the beginning of each run giving each HPTDC a different phase that may be learned from the data.

• Since this phase is always the same, the phase becomes a powerful tool to monitor the integrity of the data through buffering, trigger matching, event building, transmission to DAQ, and global event building.

Page 8: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Total time resolution from Run 5:

200GeV CuCu, 105ps 62GeV CuCu, 124ps

Page 9: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Time resolution by channel

Page 10: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Timing results, Runs 3, 4, &5:

~80~82~20HF

~89~105~ 55200GeV Cu Cu (ToT)Run V

~92~125~ 8562GeV Cu Cu (ToT)

~82~86~27FF/RFF

~86~96~40FF/RFF, w/o E pVPD

200GeV (Au+Au)

~89~105~5562GeV (Au+Au)

Run IV

~80~160~140200GeV p+p

~85~120~85200GeV d+AuRun III

TOFr

(stop-side)

TOFr

(total)pVPD

Time Resolution (ps)

Operation conditions

~80~82~20HF

~89~105~ 55200GeV Cu Cu (ToT)Run V

~92~125~ 8562GeV Cu Cu (ToT)

~82~86~27FF/RFF

~86~96~40FF/RFF, w/o E pVPD

200GeV (Au+Au)

~89~105~5562GeV (Au+Au)

Run IV

~80~160~140200GeV p+p

~85~120~85200GeV d+AuRun III

TOFr

(stop-side)

TOFr

(total)pVPD

Time Resolution (ps)

Operation conditions

Page 11: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Manufacturing overview

• Module production and test, electronics production and test, and tray assembly and test each have a duration of ~2.2 years.

• Module production begins ~3 months before the start of tray assembly and electronics production ~1.5 months before the start of tray assembly.

• Modules are thoroughly tested in China with integral HV wire and signal cables.

• Electronics cards are tested in groups of 17, 1 tray, with their integral cables and sent to the tray assembly site as a set.

• Modules are assembled into trays, the electronics added, and tested for 2-4 weeks as a complete detector unit.

• Tested trays are shipped to BNL as complete detector units ready for insertion into STAR.

• Trays are re-tested at BNL: HV current, noise rates, gas leak test

• Test beam at BNL for selected trays?

Page 12: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

STAR TOF publications:

• Physics– Open charm yields in d+Au collisions: STAR Collaboration, Phys.Rev.Lett. 94

(2005) 062301.– Cronin effect of identified particle at RHIC: STAR Collaboration, Phys.Lett.B 616

(2005) 8.

• Technical– B. Bonner et al., Nucl.Instr.Meth.A 478 (2002) 176.– M. Shao et al., Nucl.Instr.Meth.A 492 (2002) 344.– W.J. Llope et al., Nucl.Instr.Meth.A 522 (2004) 252.– F. Geurts et al., Nucl.Instr.Meth.A 533 (2004) 60.– J. Wu et al., Nucl.Instr.Meth.A 538 (2005) 243.– Y. Wang et al., Nucl.Instr.Meth.A 538 (2005) 425.– Y.E. Zhao et al., Nucl.Instr.Meth.A 547 (2005) 334.

Page 13: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

TOF electronics schematic

Page 14: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Electronic board status

Board Current Status Future Plans Timeline

TPMT Used in Run 5 Rev design: add discriminators

Ready for production by Q4 FY06.

TINO Prototype designed and built. Testing with cosmics.

Test in test beam. Decision milestone by Q2 FY06. Production by Q4, FY06

TDIG Used in Run 5. Rev design by Q3 FY06: delete comparators & 1 TDC, add L0-mult.

Production by Q4 FY06

TCPU Used in Run 5 Rev design: add TCPU-THUB I/F, delete SIU, TCD I/Fs

Production by Q4 FY06

THUB Prototype currently in preliminary design stage

Prototype with 3 I/F channels, redesign after bench test

Production Q1 FY07

Page 15: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Interface to L0 trigger

• Provides multiplicity at 9.4 MHz with <~700 ns latency.

• The multiplicity range is 0-12 for each half-tray, where a bit is added to the sum if any of the 8 TOF channels in a NINO chip is above threshold.

• The multiplicity sum is formed asynchronously and sent to L0 where it is gated and readout either by the current CDB or by the DSMI directly.

• The point of this is that the RHIC clock is not used anywhere by the TOF electronics (other than to readout trigger commands).

• It is not clear that the noise rates will be low enough for the TOF system to be a useful trigger for UPC. If it does work well enough for UPC, it will still take an enormous amount of manpower to calibrate and commission such a trigger.

• The barrel EMC is already in L0 and has a granularity of 300 compared to 240 for the CTB. It could serve as the complement to the ZDC for centrality triggers.

Page 16: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Interface to L2 trigger

• The intent is to provide a 23K bit map of the TOF hits to L2 for each “L0 accept” command

• At the STAR review of TOF in April 2004, the L2 connection was to be implemented by sending this information to the TOF DAQ receiver which would pass the information to L2 over a network connection. This plan has since been dropped by STAR DAQ.

• The trigger group is now implementing a custom-designed fiber connection (STP) from L0 to L2, and TOF could send its information to L2 over the same type of connection.

• There is no budget in the TOF project to implement this connection, however, the THUB card has not yet been prototyped and it might be relatively straightforward and low-cost to add the necessary components to THUB for an STP fiber connection

Page 17: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

L2, continued.

• STAR Trigger could use the CERN/ALICE DDL link that will be the fiber interface between all STAR detector subsystems and DAQ in the upgraded STAR detector to receive L2 trigger data from detector subsystems. A similar scheme will be implemented in ALICE and just requires splitting the fiber. The software to receive data using the DDL protocol is already implemented in STAR DAQ and could easily be implemented in trigger as well.

• The existing trigger STP fiber concentrator is already full just from L0 so a second custom concentrator would need to be installed to accommodate TOF, and any other subsystems.

Page 18: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Interface to DAQ

• The TOF system needs to be faster than the upgraded TPC so as not to introduce any additional dead time. The TOF information is only useful in a STAR event if the TPC is also readout in that event.

• The system will handle L0 accept commands at >10 kHz.

• The system will handle L2 accept commands at >2 kHz.

• A design issue with a large expense consequence is the required size of the pre-L2 buffer. Or, how many tokens are allowed in the system for events with TPC/TOF readout? The ALICE/CERN ALTRO has buffering for 3 events. Is STAR DAQ planning extra buffer space for TPC events somewhere to allow for asynchronous L2 trigger processing? TOF is currently thinking of allowing for a 256-event buffer and this costs ~$10k for memory.

• Is there a minimum dead time between L0 accept commands because of TPC readout limitations?

Page 19: The STAR MRPC TOF Project BNL December 1, 2005 Geary Eppley, with Jo Schambach, for the TOF Group.

Current project status:

• The official closeout report from the DOE review of the TOF project in August has been received and all the issues dealt with.

• A revised management plan has been accepted by the DOE.

• Cosmic ray testing of the TINO front-end board is ongoing.

• Automated TINO board production has not been achieved. Trying a new vendor.

• Upgraded 38-channel start detector under construction.

• Based on a recommendation from the review, the China TOF project built a few new modules with highly resistive electrodes. Cosmic testing is underway.

• Layout of the first prototype THUB is underway.

• Waiting for the DOE go-ahead to start the project.