The Scientific Costing Guide BBuuiillddCCOOSSTTbuildsystem.in/userfiles/SamplepagesBuildCost.pdf ·...
Transcript of The Scientific Costing Guide BBuuiillddCCOOSSTTbuildsystem.in/userfiles/SamplepagesBuildCost.pdf ·...
The Scientific Costing Guide
Building Construction Cost Data
BuildCOSTBuildCOSTBuildCOST
Item of Work Cost Database
2018
Div. No. Title Page Div. No. Title Page
01 GENERAL REQUIREMENTS 1 06 WOOD, PLASTICS, AND COMPOSITES 43
01 45 Quality Control 3 06 17 Shop-Fabricated Structural Wood 45
01 45 23 Testing and Inspecting Services 3 06 17 53 Shop-Fabricated Wood Trusses 45
02 EXISTING CONDITIONS 5 06 22 Millwork 45
02 32 Geotechnical Investigations 7 06 22 13 Standard Pattern Wood Trim 45
02 32 19 Exploratory Excavations 7 06 26 Board Paneling 46
02 41 Demolition 7 06 26 13 Profile Board Paneling 46
02 41 13 Selective Site Demolition 7 06 42 Wood Paneling 46
03 CONCRETE 11 06 42 10 Wood Paneling 46
03 05 Common Work Results for Concrete 13 06 43 Wood Stairs and Railings 47
03 05 13 Basic Concrete Materials 13 06 43 13 Wood Stairs 47
03 11 Concrete Forming 13 06 48 Wood Frames 47
03 11 13 Structural Cast-in-Place Concrete Forming 13 06 48 16 Interior Wood Door Frames 47
03 15 Concrete Accessories 15 07 THERMAL AND MOISTURE PROTECTION 49
03 15 05 Concrete Forming Accessories 16 07 11 Dampproofing 51
03 15 13 Waterstops 16 07 11 17 Damp-Proof Course 51
03 21 Reinforcing Bars 17 07 13 Sheet Waterproofing 51
03 21 10 Uncoated Reinforcing Steel 17 07 13 13 Bituminous Sheet Waterproofing 51
03 22 Welded Wire Fabric Reinforcing 17 07 16 Cementitious And Reactive Waterproofing 52
03 22 05 Uncoated Welded Wire Fabric 17 07 16 16 Crystalline Waterproofing 52
03 31 Structural Concrete 17 07 21 Thermal Insulation 55
03 31 05 Normal Weight Structural Concrete 17 07 21 14 Building Insulation 56
03 35 Concrete Finishing 21 07 22 Roof and Deck Insulation 56
03 35 29 Tooled Concrete Finishing 21 07 22 16 Roof Board Insulation 57
03 41 Precast Structural Concrete 21 07 26 Vapor Retarders 57
03 41 05 Precast Concrete Members 21 07 26 10 Vapor Retarders 57
03 41 16 Precast Concrete Slabs 23 07 32 Roof Tiles 57
03 45 Precast Architectural Concrete 23 07 32 13 Clay Roof Tiles 57
03 45 13 Faced Architectural Precast Concrete 23 07 41 Roof Panels 58
04 MASONRY 25 07 41 13 Metal Roof Panels 58
04 21 Clay Unit Masonry 27 07 41 34 Asbestos Roof Panels 60
04 21 13 Brick Masonry 27 08 OPENINGS 61
04 22 Concrete Unit Masonry 31 08 09 Metal Doors, Windows And Frames 63
04 22 10 Concrete Masonry Units 31 08 09 16 Aluminum Doors, Windows and Frames 63
04 23 Glass Unit Masonry 32 08 09 21 Steel Doors, Windows and Frames 63
04 23 13 Vertical Glass Unit Masonry 32 08 12 Metal Frames 64
04 43 Stone Masonry 33 08 12 21 Steel Frames 64
04 43 10 Stone Masonry 33 08 14 Wood Doors 65
05 METALS 39 08 14 50 Wood Shutters 65
05 05 Common Work Results for Metals 41 08 33 Coiling Doors and Grilles 69
05 05 23 Metal Fastenings 41 08 33 23 Overhead Coiling Doors 69
05 12 Structural Steel Framing 41 08 33 33 Side Coiling Doors 69
05 12 23 Structural Steel for Buildings 41 08 44 Curtain Wall and Glazed Assemblies 69
05 51 Metal Stairs 41 08 44 13 Glazed Aluminum Curtain Walls 69
05 51 16 Metal Floor Plate Stairs 41 08 71 Door Hardware 71
05 55 Metal Stair Treads and Nosings 42 08 71 20 Hardware 71
05 55 13 Metal Stair Treads 42 08 75 Window Hardware 75
05 73 Decorative Metal Railings 42 08 75 10 Windows Hardware 75
05 73 23 Ornamental Railings 42 09 FINISHES 77
06 WOOD, PLASTICS, AND COMPOSITES 43 09 21 Plaster and Gypsum Board Assemblies 79
06 11 Wood Framing 45 09 21 13 Plaster Assemblies 79
06 11 10 Wood Framing 45
Unit Price Section - Table of Contents
Div. No. Title Page Div. No. Title Page
Unit Price Section - Table of Contents
09 FINISHES 77 22 PLUMBING 115
09 22 Supports for Plaster And Gypsum Board79
22 11 Facility Water Distribution120
09 22 26 Suspension Systems 79 22 11 13 Facility Water Distribution Piping 120
09 23 Gypsum Plastering 80 22 11 19 Domestic Water Piping Specialties 126
09 23 20 Gypsum Plaster 80 22 12 Facility Potable-Water Storage Tanks 126
09 24 Portland Cement Plastering80
22 12 23 Facility Indoor Potable-Water Storage Tanks126
09 24 20 Portland Cement Plaster 80 22 13 Facility Sanitary Sewerage 127
09 24 26 Pointing On Walls And Floors 82 22 13 16 Sanitary Waste and Vent Piping 12709 28 Backing Boards and Underlayments 83 22 13 23 Sanitary Waste Interceptors 136
09 28 13 Cementitious Backing Boards 83 22 33 Electric Domestic Water Heaters 136
09 30 TILING 84 22 33 30 Residential, Electric Domestic Water Heaters 136
09 30 10 Precast Pre-polished Tiling 84 22 41 Residential Plumbing Fixtures 136
09 30 13 Ceramic Tiling 84 22 41 13 Residential Water Closets, Urinals, & Bidets 136
09 30 23 Glass Mosaic Tiling 85 22 41 16 Residential Lavatories and Sinks 139
09 30 35 Terrazo Tiling 86 22 41 19 Residential Bathtubs 141
09 51 Acoustical Ceilings 86 22 41 39 Residential Faucets, Supplies, and Trim 141
09 51 23 Acoustical Tile Ceilings 86 22 42 Commercial Plumbing Fixtures 143
09 63 Masonry Flooring87
22 42 13 Commercial Water Closets, Urinals, & Bidets143
09 63 13 Brick Flooring87
23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
145
09 63 30 Marble Flooring 87 23 07 HVAC Insulation 147
09 63 35 Granite Flooring 93 23 07 13 Duct Insulation 147
09 63 40 Stone Flooring 94 23 09 Instrumentation and Control for HVAC 148
09 64 Wood Flooring97
23 09 33 Electric and Electronic Control System for HVAC 148
09 64 16 Wood Block Flooring97
23 09 53 Pneumatic and Electric Control System for HVAC 151
09 65 Resilient Flooring 98 23 21 Hydronic Piping and Pumps 151
09 65 16 Resilient Sheet Flooring 98 23 21 20 Hydronic HVAC Piping Specialties 151
09 66 Terrazzo Flooring 98 23 21 23 Hydronic Pumps 152
09 66 13 Portland Cement Terrazzo Flooring 98 23 21 24 Hydronic Piping 159
09 91 Painting 100 23 31 HVAC Ducts and Casings 161
09 91 13 Exterior Painting 100 23 31 13 Metal Ducts 161
09 91 23 Interior Painting 101 23 33 Air Duct Accessories 161
10 SPECIALTIES 105 23 33 11 Air Duct Accessories 161
10 14 Signage 107 23 34 HVAC Fans 161
10 14 53 Traffic Signage 107 23 34 11 Fans 161
10 28 Toilet, Bath, and Laundry Accessories 107 23 41 Particulate Air Filtration 164
10 28 16 Bath Accessories 107 23 41 13 Panel Air Filters 164
10 44 Fire Protection Specialties 109 23 52 Heating Boilers 165
10 44 13 Fire Extinguisher Cabinets 109 23 52 13 Electric Boilers 165
10 44 16 Fire Extinguishers 109 23 52 23 Cast-Iron Boilers 165
21 FIRE SUPPRESSION 111 23 64 Packaged Water Chillers 166
21 12 Fire-Suppression Standpipes 113 23 64 10 Packaged Water Chillers 166
21 12 13 Fire-Suppression Hoses and Nozzles 113 23 64 13 Absorption Water Chillers 168
21 13 Fire-Suppression Sprinkler Systems 113 23 65 Cooling Towers 170
21 13 13 Wet-Pipe Sprinkler Systems 114 23 65 11 Cooling Towers 170
22 PLUMBING115
23 73 Indoor Central-Station Air-Handling Units171
22 05 Common Work Results for Plumbing 117 23 73 13 Modular Indoor Central-Station Air-Handling 171
22 05 23 General-Duty Valves for Plumbing Piping 117 23 74 Packaged Outdoor HVAC Equipment 172
22 05 76 Facility Drainage Piping Cleanouts 119 23 74 33 Packaged, Outdoor, Heating and Cooling 172
Div. No. Title Page Div. No. Title Page
Unit Price Section - Table of Contents
23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
14531 50 EXCAVATION SUPPORT and
PROTECTION246
23 76 Evaporative Air-Cooling Equipment 172 31 50 13 Excavation Support And Protection 246
23 76 13 Direct Evaporative Air Coolers 172 31 62 Driven Piles 247
23 81 Decentralized Unitary HVAC Equipment 173 31 62 13 Concrete Piles 247
23 81 19 Self-Contained Air-Conditioners 173 31 63 Bored Piles 247
23 81 26 Split-System Air-Conditioners 173 31 63 23 Bored Concrete Piles 247
23 82 Convection Heating and Cooling Units 174 32 EXTERIOR IMPROVEMENTS 249
23 82 16 Air Coils 174 32 11 Base Courses 251
23 82 19 Fan Coil Units 175 32 11 23 Aggregate Base Courses 251
26 ELECTRICAL 177 32 11 26 Asphaltic Base Courses 251
26 05 Common Work Results for Electrical 179 32 12 Flexible Paving 252
26 05 13 Medium -Voltage Cables 179 32 12 16 Asphalt Paving 252
26 05 19 Low-Voltage Electrical Power Conductors and Cables 185
32 13 Rigid Paving253
26 05 26 Grounding & Bonding for Electrical Systems 193 32 13 13 Concrete Paving 253
26 05 29 Hangers & Supports for Electrical Systems 194 32 14 Unit Paving 253
26 05 33 Raceway and Boxes for Electrical Systems194
32 14 13 Precast Concrete Unit Paving253
26 05 36 Cable Trays for Electrical Systems196
32 16 Curbs, Gutters, Sidewalks, And Driveways
254
26 05 90 Residential Wiring 199 32 16 13 Curbs And Gutters 254
26 24 Switchboards and Panelboards 219 32 31 Fences and Gates 254
26 24 13 Switchboards 219 32 31 13 Chain Link Fences and Gates 254
26 27 Low-Voltage Distribution Equipment 220 33 UTILITIES 257
26 27 26 Wiring Devices 220 33 11 Water Utility Distribution Piping 259
26 28 Low-Voltage Circuit Protective Devices 223 33 11 13 Public Water Utility Distribution Piping 259
26 28 16 Enclosed Switches and Circuit Breakers 223 33 36 Utility Septic Tanks 268
26 41 Facility Lightning Protection 230 33 36 13 Utility Septic Tank and Effluent Wet Wells 268
26 41 13 Lightning Protection for Structures 230 33 41 Storm Utility Drainage Piping 269
26 51 Interior Lighting 230 33 41 13 Public Storm Utility Drainage Piping 269
26 51 13 Interior Lighting Fixtures, Lamps, & Ballasts 230 33 44 Storm Utility Water Drains 271
27 COMMUNICATIONS 233 33 44 13 Utility Area Drains 271
27 15 Communications Horizontal Cabling 235
27 15 10 Special Communications Cabling 235
28 ELECTRONIC SAFETY AND SECURITY 237
28 31 Fire Detection and Alarm 239
28 31 23 Fire Detection and Alarm Annunciation Panels and Fire Stations 239
31 EARTHWORK 241
31 11 Clearing and Grubbing 243
31 11 10 Clearing and Grubbing 243
31 14 Earth Stripping and Stockpiling 243
31 14 13 Soil Stripping and Stockpiling 243
31 22 Grading 243
31 22 16 Fine Grading 243
31 23 Excavation and Fill 243
31 23 16 Excavation 243
31 23 19 Dewatering 245
31 23 23 Fill 245
31 31 Soil Treatment 246
31 31 16 Termite Control 246
BuildCOST GENERAL REQUIREMENTS
45 Quality Control01
23 Testing And Inspecting Services UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
4501TOTAL
Pile Test21
Vertical load testing ( INITIAL ) of piles in
accordance with IS 2911 (Part IV) including
installation of loading platform / or reaction piles
and preparation of pile head or construction of
test cap and dismantling of test cap after test
etc. to 150% of designed load, complete, of pile
capacities :
10005 /testupto 50 ton 44840.00 - - 44840.00 51566.00
10010 /testabove 50 ton and upto 100 ton 82600.00 - - 82600.00 94990.00
10015 /test/50 tadd for every additional 50 ton or part thereof 44840.00 - - 44840.00 51566.00
Vertical load testing ( ROUTINE ) of piles in
accordance with IS 2911 (Part IV) including
installation of loading platform / or reaction piles
and preparation of pile head or construction of
test cap and dismantling of test cap after test
etc. to 150% of designed load, complete, of pile
capacities :
10020 /testUpto 50 ton 44840.00 - - 44840.00 51566.00
10025 /testabove 50 ton and upto 100 ton 82600.00 - - 82600.00 94990.00
10030 /test/50 tadd for every additional 50 ton or part thereof 35400.00 - - 35400.00 40710.00
Cyclic vertical load testing of pile in accordance
with IS:2911 (part IV) including preparation of pile
head etc., to 150% of designed load, complete,
of pile capacities :
10035 /testupto 50 ton 44840.00 - - 44840.00 51566.00
10040 /testabove 50 t and upto 100 ton 82600.00 - - 82600.00 94990.00
10045 /test/50 tadd for every additional 50 ton or part thereof 44840.00 - - 44840.00 51566.00
Lateral load testing of single pile in accordance
with IS:2911 (Part IV) to 150% of designed load,
complete, of pile capacities :
10050 /testupto 50 ton 44840.00 - - 44840.00 51566.00
10055 /testAbove 50 ton and upto 100 ton 70800.00 - - 70800.00 81420.00
10060 /test/50 tAdd for every additional 50 ton or part
thereof.
44840.00 - - 44840.00 51566.00
Vertical load testing ( INITIAL ) of piles in
accordance with IS 2911 (Part IV) including
installation of loading plateform / or reaction piles
and preparation of pile head or construction of
test cap and dismantling of test cap after test
etc. to 250% of designed load complete, of pile
capacities :
10065 /testupto 50 ton 44840.00 - - 44840.00 51566.00
10070 /testabove 50 ton and upto 100 ton 82600.00 - - 82600.00 94990.00
10075 /test/50 tadd for every additional 50 ton or part thereof 44840.00 - - 44840.00 51566.00
Vertical load testing ( ROUTINE ) of piles in
accordance with IS 2911 (Part IV) including
installation of loading plateform / or reaction piles
and preparation of pile head or construction of
test cap and dismantling of test cap after test
etc. to 250% of designed load, complete, of pile
capacities :
10080 /testupto 50 ton 44840.00 - - 44840.00 51566.00
10085 /testabove 50 ton and upto 100 ton 67260.00 - - 67260.00 77349.00
10090 /test/50 tadd for every additional 50 ton or part thereof 44840.00 - - 44840.00 51566.00
Testing50
Conducting laboratory tests at approved
laboratory, including preparation and taking of
samples to laboratory, testing of samples and
getting and submitting test results :
3
BuildCOST GENERAL REQUIREMENTS
45 Quality Control01
23 Testing And Inspecting Services UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
4501TOTAL
10005 /testCompressive strength test on rock samples 1888.00 - - 1888.00 2171.20
10010 /testChemical analysis of soil samples 1888.00 - - 1888.00 2171.20
10015 /testChemical analysis of water samples 1770.00 - - 1770.00 2035.50
4
BuildCOST EXISTING CONDITIONS
32 Geotechnical Investigations02
19 Exploratory Excavations UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
3202TOTAL
Test Pit17
Drilling 150 mm diameter bore holes in all type of
soils by manual auguring, conducting standard
penetration tests, collecting disturbed and
undisturbed soil samples, conducting necessary
laboratory tests, recommending suitable type of
foundation and allowable bearing pressure and
submission of report in three copies :
10005 mGround level to 6.0 m or refusal,
whichever is earlier
531.00 - - 531.00 610.65
10010 mOver 6.0 m and upto 10.0 m or refusal,
whichever is earlier
590.00 - - 590.00 678.50
10015 mOver 10.0 m and upto 12.0 m or refusal,
whichever is earlier
649.00 - - 649.00 746.35
Drilling 150 mm diameter bore holes in all type of
soils by Calyx drilling, conducting standard
penetration tests, collecting disturbed and
undisturbed soil samples, conducting necessary
laboratory tests, recommending suitable type of
foundation and allowable bearing pressure and
submission of report in three copies :
10020 mGround level to 6.0 m or refusal, which is
earlier
1121.00 - - 1121.00 1289.15
10025 mOver 6.0 m and upto 10.0 m or refusal,
which is earlier
1180.00 - - 1180.00 1357.00
10030 mOver 10.0 m and upto 12.0 m or refusal,
which is earlier
1298.00 - - 1298.00 1492.70
Drilling 100 mm dia bore hole in rock using
double core barrel Diamond/TC including
recovery of cores, wherever possible and
keeping a log of the same :
10035 mWeathered / disintegrated rock 2478.00 - - 2478.00 2849.70
10040 mHard rock 5428.00 - - 5428.00 6242.20
41 Demolition02
13 Selective Site Demolition UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
4102TOTAL
Concrete / Rcc / Masonry Demolition21
10005 cumDemolishing lime concrete / cement
concrete in all mixes, in foundations, super
structure and basement, at all heights /
depths, including disposal of unserviceable
materials upto a 50 m lead.
- 325.22 - 325.22 374.00
10010 cumDemolishing RCC work in foundations, super
structure and basement, at all heights /
depths, including cutting, straightening
scrapping, cleaning and stacking of
reinforcement bars and disposal of
unserviceable materials upto a 50 m lead.
- 1333.39 - 1333.39 1533.39
10015 cumDemolishing RB work in foundations, super
structure and basement, at all heights /
depths, including cutting, straightening
scrapping, cleaning and stacking of
reinforcement bars and disposal of
unserviceable materials upto a 50 m lead.
- 1212.18 - 1212.18 1394.01
10020 cumDismantling / Demolishing brick work in
cement / lime mortar in foundations, super
structure and basement, at all heights /
depths, including removing of mortar ,
cleaning bricks and stacking of serviceable
materials and disposed of unserviceable
materials upto 50 m lead
- 1481.55 - 1481.55 1703.79
7
BuildCOST EXISTING CONDITIONS
41 Demolition02
13 Selective Site Demolition UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
4102TOTAL
10025 cumDismantling / demolishing stone rubble
masonry in cement / lime mortar in
foundations, super structure and basement
at all heights / depths including stacking of
serviceable materials and disposal of
unserviceable materials upto a 50 m lead.
- 930.29 - 930.29 1069.83
Ceiling Demolition22
Dismantling false ceiling, partitions, wall lining,
etc supported / fixed to wooden / aluminium /
metal frame including dismantling of frame,
stacking of serviceable material and disposal of
unserviceable material upto a 50 m lead, with :
10005 sqmPlaster of Paris /Gypsum / Plywood / Block
board / Particle board / MDF sheets / tiles
- 63.49 - 63.49 73.01
10010 sqmWooden planks - 95.24 - 95.24 109.53
10015 sqmGlass / Mirror / Fabric / Extruded metal - 127.22 - 127.22 146.30
10020 sqmAsbestos cement, celotax or other hard
board
- 63.49 - 63.49 73.01
Flooring Demolition24
Dismantling tile work in floors and roofs in
cement mortar/lime mortar including stacking of
serviceable material and disposal of
unserviceable material upto a lead of 50 m, of
thickness :
10005 sqm10 mm to 25 mm - 31.70 - 31.70 36.45
10010 sqmover 25 mm and upto 40 mm - 48.51 - 48.51 55.78
10015 sqmDismantling dry brick pitching in floors,
drains etc, including stacking of serviceable
materials and disposal of unserviceable
materials within a 50 m lead.
- 57.56 - 57.56 66.20
10020 sqmDismantling stone slab flooring in cement
mortar / lime mortar, including stacking of
serviceable materials and disposal of
unserviceable materials within a 50 m lead.
- 100.77 - 100.77 115.88
Demolition of flooring including stacking of
serviceable materials and disposal of
unserviceable materials upto a 50m lead, with :
10025 sqmParquet flooring - 36.01 - 36.01 41.42
10030 sqmPVC flooring - 8.00 - 8.00 9.20
10035 sqmCarpet flooring - 8.00 - 8.00 9.20
Framing Demolition25
Dismantling woodwork in frames, trusses, purlins
and rafters upto a 10 metres span and 5 metres
height including stacking the material within a 50
m lead, of sectional areas :
10005 mupto 4000 sqmm - 8.01 - 8.01 9.21
10010 cumover 4000 sqmm - 2001.28 - 2001.28 2301.47
10015 QuintalDismantling steel work in built up sections at
all heights and depths, in angles, tees, flats,
channels and tubes including all gusset
plates, bolts, nuts, cutting rivets, welding
etc. including dismembering and stacking
within 50 m lead.
- 235.12 - 235.12 270.38
10020 QuintalDismantling steel work in single sections at
al l heights and depths inc luding
dismembering and stacking within a 50 m
lead.
- 141.07 - 141.07 162.23
Lining Dismantling26
Dismantling and removing wooden boardings in
lining of walls and partitions, excluding
supporting members, but including stacking
8
BuildCOST CONCRETE
05 Common Work Results For Concrete03
13 Basic Concrete Materials UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0503TOTAL
Admixture, Concrete20
Providing and mixing admixtures, conforming to
IS:9103, in recommended proportions, in
concrete :
10005 kgAccelerating admixtures 76.99 8.00 - 84.99 97.74
10010 kgRetarding admixtures 84.92 8.00 - 92.92 106.85
10015 kgAir entraining admixture 73.59 8.00 - 81.59 93.83
10020 kgW a t e r r e d u c i n g a d m i x t u r e s
(Plasticizer/Super Plasticizer)
115.49 8.00 - 123.49 142.01
Concrete Additives21
10005 kgProviding and mixing water proofing
compound, conforming to IS:2645, in cement
concrete/reinforced concrete works.
97.37 8.00 - 105.37 121.18
11 Concrete Forming03
13 Structural Cast-in-place Concrete
Forming
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1103TOTAL
Forms In Place18
Providing and fixing centering and shuttering for
concrete work (plain and reinforced) in following
locations, including strutting, propping, bracing,
bolting tie bolt / spring coil / plastic cone,
wedging, easing, striking, removal etc, complete.
Allow for forming grooves, drips, throats,
chamfers, cut-outs, openings etc. where called
for and for dressing with approved shuttering oil
to prevent adhesion. The works are at all levels .
The floor height is up to 4.00 m :
10005 sqmSides of footings of columns and walls and
sides of base slabs.
70.95 101.52 - 172.47 198.34
10010 sqmFoundation beams, floor channels, kerb
stones and drain walls.
70.95 101.52 - 172.47 198.34
10015 sqmSides of columns, piers and pedestals of any
shape, size and profile.
93.73 322.24 - 415.97 478.36
10020 sqmSides of walls, retaining walls, attached
columns, pilasters.
69.58 291.20 - 360.79 414.90
10025 sqmSoffits and sides of beams, plinth beams,
lintels, ties, ribs, pergolas and such other,
string courses, cornices, corbels.
74.52 232.04 - 306.55 352.54
10030 sqmSides of facias, parapets, railings, planting
boxes and such other vertical elements.
65.61 406.21 - 471.82 542.59
10035 sqmSoffits and sides of suspended slabs, floor
and roof projections, landing slabs ,
canopies, chajjas, slabs of planting boxes
and such other horizontal elements, coffer
ribs and slabs.
72.42 322.24 - 394.66 453.85
10040 sqmSoffits and sides of waist slabs of stairs,
sides of risers and stepped waist slabs,
spiral staircases, etc.
53.48 352.84 - 406.32 467.27
10045 sqmSides of mullions, suspenders, struts, ties,
slings including flarings or taperings of any
shape and profile.
85.48 690.14 - 775.62 891.96
10050 sqmSoffits of inclined slabs and ramps, folded
plates. ( slopes more than 15o and upto 45o)
74.90 406.21 - 481.11 553.28
10055 sqmArches, archribs, domes, shells, vaults, etc. 383.61 732.99 - 1116.60 1284.08
10060 sqmWell Steinings 81.15 1620.88 - 1702.03 1957.33
10065 sqmVertical and horizontal fins individually or
forming boxes
65.61 406.21 - 471.82 542.59
10070 sqmChimney shafts 69.58 291.20 - 360.79 414.90
13
BuildCOST MASONRY
21 Clay Unit Masonry04
13 Brick Masonry UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2104TOTAL
Brick Work, Conventional Bricks46
Providing brick work with bricks of class 75,
joints finished flush/raked to 12 mm depth, cured
including necessary scaffolding complete in
cement mortar 1:6 with coarse sand, in :
10005 cumFoundations and plinths (1.5 m below and
upto 1.2 m above GL)
2523.91 1141.15 44.25 3709.30 4265.70
10010 cumSuperstructures upto 20.0 m above plinth
level.
2523.91 2186.57 120.36 4830.84 5555.47
10015 cumBasement, under ground water tank and the
like, upto 7.0 m below GL
2523.91 1605.07 70.39 4199.37 4829.27
10020 cumArches, vaults, domes, etc., in super
structures/basements and the like in cement
mortar 1:3 with coarse sand including
centering, shuttering, struting, proping ,
wedging, bolting and removal, etc. ,
complete.
3774.20 3367.89 97.00 7239.08 8324.95
10025 cumAdd for every additional 4.0 m height or part
thereof for brick work/exposed brick work
beyond 7.0 m below GL
- 300.78 - 300.78 345.89
10030 cumAdd for every additional 20.0 m height or
part thereof for brick work/exposed brick
work beyond 20.0 m above plinth level
- 597.03 - 597.03 686.58
10035 cumAdd for brick work in cement mortar 1:4 in
place of 1:6
195.00 - - 195.00 224.25
10040 cumAdd for brick work in cement mortar 1:3 in
place of 1:6
390.00 - - 390.00 448.50
10045 cumDeduct for brick work in cement mortar with
fine sand in place of coarse sand
59.94 - - 59.94 68.93
10050 cumAdd for brick work/exposed brick work in
square or rectangular pillars
- 432.76 - 432.76 497.67
10055 cumAdd for brick work, curved in plan/elevation,
upto mean radius not exceeding 6.0 m
136.08 368.61 - 504.69 580.40
10060 mAdd for cutting or chamfering the bricks to
required shape in masonry work
- 17.61 - 17.61 20.26
10065 cumDeduct for using bricks of class 50 in place
of class 75
155.61 - - 155.61 178.95
10070 mProviding 70 mm thick and 57 mm projected
string course/ band with bricks of class 75 in
cement mortar 1:4 with coarse sand
11.00 10.67 0.50 22.16 25.49
10075 100 mm/mProviding and making mouldings, cornices &
corbels with bricks of class 75 in cement
mortar 1:4 with coarse sand (girth to be
measured in mm and length in running
metres)
10.24 12.00 0.49 22.72 26.13
Providing brick work with bricks of class 75 in
half brick thick walls in any shape and profile
including curvilinear, laid in cement mortar 1:4
with coarse sand, joints finished flush/raked to 12
mm depth, cured, including scaffolding and flat
reinforcement (25 x 3 mm) at every fourth course
and embedding the same in adjoining
masonry/columns by drilling holes etc complete :
10080 sqmSuper structure upto 20.0 m above plinth
level.
407.57 255.15 8.73 671.45 772.17
10085 sqmBasements, and the like, upto 7.0 m below
GL
407.57 209.61 9.79 626.97 721.02
10090 sqmArches, domes, vaults at all levels in cement
mortar 1:3 with coarse sand including
centring and shuttering strutting, propping,
bolting and removal complete. (Flat iron
reinforcement 25 x 3 mm not to be provided)
704.64 1001.91 9.79 1716.35 1973.80
10095 sqmAdd for every 4.0 m height or part thereof for - 34.48 - 34.48 39.65
27
BuildCOST METALS
05 Common Work Results For Metals05
23 Metal Fastenings UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0505TOTAL
Bolts & Hex Nuts10
10005 kgProviding and fixing MS bolts upto 300 mm
in length including nuts and washers,
complete.
53.63 38.02 - 91.66 105.40
Welding88
10005 10 mm/mGas welding including mobilization at site,
complete, (for designed structural welding).
295.00 - - 295.00 339.25
10010 10 mmGas welding including mobilization at site,
complete, (for non structural welding).
4.23 - - 4.23 4.87
10015 10 mm/mElectric arc welding including mobilization at
site, complete (for designed structural
welding).
224.20 - - 224.20 257.83
10020 10 mmElectric arc welding including mobilization at
site, complete (for non structural welding).
3.40 - - 3.40 3.91
12 Structural Steel Framing05
23 Structural Steel For Buildings UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1205TOTAL
Structural Steel Built Up Section23
Providing, fabricating and erecting built up steel
tubular trusses, welded and bolted including
special shaped washers, etc. and applying a
primer coat of zinc chromate on duly prepared
surfaces, complete :
10005 kgHot finished, welded tubes 105.66 30.71 - 136.37 156.83
10010 kgHot finished, seamless tubes 105.66 30.71 - 136.37 156.83
10015 kgElectric resistance or induction welded tubes 105.66 30.71 - 136.37 156.83
10020 kgProviding, fabricating and erecting bolted
structural steel built up sections, trusses and
frames and applying a primer coat of zinc
chromate on duly prepared surfaces,
complete.
63.96 21.52 - 85.48 98.31
10025 kgProviding, fabricating and erecting welded
structural steel built up sections in trusses
and frames and applying a primer coat of
zinc chromate on duly prepared surfaces,
complete.
67.09 14.63 - 81.72 93.98
10030 sqmProviding and applying three finish coats of
synthetic enamel paint on steel surfaces,
complete.
2696.47 80.69 - 2777.15 3193.73
Structural Steel Single Section81
10005 kgProviding, fabricating and erecting structural
steel, single sections, and applying a primer
coat of zinc chromate on duly prepared
surfaces, complete.
72.90 12.49 - 85.39 98.20
10010 kgProviding and fixing wind ties of MS section 62.46 10.50 - 72.96 83.91
51 Metal Stairs05
16 Metal Floor Plate Stairs UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
5105TOTAL
Steel Stairs13
Providing, fabricating and erecting MS welded
built up sections/ frames and applying a primer
coat of zinc chromate on duly prepared surfaces ,
complete :
10005 kgIn stringers, treads, landings, etc. of
staircases including chequered plates
wherever required, all complete.
86.45 6.28 - 92.73 106.64
41
BuildCOST METALS
51 Metal Stairs05
16 Metal Floor Plate Stairs UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
5105TOTAL
10010 kgIn guard bars, ladders, railings, and similar
works.
67.55 35.99 - 103.54 119.07
Providing, fabricating and erecting hand rails by
welding to steel ladders/railings, balcony railings,
and staircase railings including primer coat of
zinc chromate on duly prepared surfaces,
complete :
10015 kgMS black tubes 221.32 32.28 - 253.60 291.64
10020 kgERW tubes 221.32 32.28 - 253.60 291.64
10025 kgGalvanised steel pipes 205.07 32.28 - 237.34 272.94
10030 kgStructural steel sections, flats, angles ,
channels, etc.
86.85 30.26 - 117.11 134.67
55 Metal Stair Treads And Nosings05
13 Metal Stair Treads UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
5505TOTAL
Stair Treads And Nosing51
10005 kgProviding and fixing MS angles 50 x 50 x 5
mm nosing with lugs of MS flats 10 x 5 mm,
100 mm long and forked at ends, 600 mm
apart (minimum three lugs to be provided)
including necessary welding and applying a
primer coat on exposed surfaces etc.,
complete.
79.67 28.14 - 107.81 123.98
10010 kgProviding and fixing aluminium angles 35 x
35 x 3 mm nosing with lugs of flats 10 x 3
mm, 100 mm long and forked at ends, 600
mm apart (minimum three lugs to be
provided) including necessary welding, etc.,
complete.
342.29 180.88 - 523.17 601.64
Providing and fixing aluminum strip edge to
staircases including fixing with rawl plugs and
stainless steel screws, with under layer of
cement mortar 1:3 with coarse sand, of strip
edging of size :
10015 m57 x 12 x 3 mm 243.76 104.94 - 348.71 348.71
10020 m38 x 12 x 3 mm 233.75 104.94 - 338.69 389.50
73 Decorative Metal Railings05
23 Ornamental Railings UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
7305TOTAL
Railings, Ornamental50
Providing, fabricating and erecting MS balusters
in stair flight slabs, landing balconies and similar
other railings, anchored to steps, landings etc .,
all fixing accessories including providing pockets
in concrete/brick works and grouting with ironite
or other equivalent, applying three coats of
synthetic enamel paint over a primer coat of zinc
chromate on duly prepared surfaces, complete.
10005 kgSolid sections 207.98 107.44 - 315.42 362.73
10010 kgHollow sections 215.49 107.44 - 322.93 371.37
42
BuildCOST WOOD, PLASTICS, AND COMPOSITES
11 Wood Framing06
10 Wood Framing UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1106TOTAL
Ceiling Framing12
Providing, fabricating and fixing in position
selected quality seasoned and chemically treat
ed wood work in frames of false ceilings,
partitions, etc., complete :
10005 cumIst class Deodar wood. 54083.88 6254.00 - 60337.88 69388.57
10010 cum2nd class Deodar wood. 52582.22 6254.00 - 58836.22 67661.65
10015 cumSal wood 31809.14 6254.00 - 38063.14 43772.61
10020 cum2nd class Kail wood 25301.91 6254.00 - 31555.91 36289.30
10025 cumHollock wood 34061.64 6254.00 - 40315.64 46362.99
Wall Framing40
Providing and fixing wooden frame with 50 mm x
50 mm battens, fixed at 600 mm centre to centre
(both ways). Allow for solignum treatment to the
timber framework :
10005 sqmSal wood 389.85 207.01 - 596.86 686.39
10010 sqm2nd class CP teak Wood 691.23 207.01 - 898.24 1032.97
Providing and fixing wooden framework with 50
mm x 75 mm battens, fixed at 600 mm centre to
centre(both ways). Allow for solignum treatment
to the timber framework :
10015 sqmSal wood 541.58 301.25 - 842.83 969.25
10020 sqm2nd class CP Teak Wood 993.64 301.25 - 1294.89 1489.13
17 Shop-fabricated Structural Wood06
53 Shop-fabricated Wood Trusses UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1706TOTAL
Roof Trusses10
Providing, fabricating and fixing in position
selected quality seasoned & chemically treated
wrought wood work in trusses, rafters, runners
posts, struts, walls plates etc. of size and profile
in inclind roofs including anchoring to concrete
members with holding down bolts, fixing
accessories & all incidental works (Flat, angles,
other steel sections and holding down bolts used
in connections will be paid separately), complete
:
10005 cum2nd class CP teak wood 66252.16 8453.34 - 74705.50 85911.32
10010 cumIst class Deodar wood 50813.58 8453.34 - 59266.92 68156.96
10015 cum2nd class Deodar wood 48625.44 8453.34 - 57078.78 65640.59
10020 cumSal wood 31120.28 8453.34 - 39573.62 45509.66
10025 cumHollock wood 31606.54 8453.34 - 40059.87 46068.85
22 Millwork06
13 Standard Pattern Wood Trim UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2206TOTAL
Mouldings12
Providing and fixing select quality seasoned and
chemically treated wooden moulded beadings to
door and window frames with mild steel
screws/headless nails and a primer coat on
unexposed surface, etc. complete, of beading
sizes :
Burma teak wood :
10005 m30 x 12 mm 35.25 71.13 - 106.38 122.34
45
BuildCOST WOOD, PLASTICS, AND COMPOSITES
22 Millwork06
13 Standard Pattern Wood Trim UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2206TOTAL
10010 m40 x 12 mm 49.62 71.13 - 120.75 138.87
10015 m40 x 20 mm 79.64 71.13 - 150.77 173.38
10020 m50 x 12 mm 61.02 71.13 - 132.15 151.98
10025 m50 x 20 mm 98.41 71.13 - 169.54 194.97
2nd class CP teak wood :
10030 m30 x 12 mm 28.18 71.13 - 99.31 114.20
10035 m40 x 12 mm 39.24 71.13 - 110.37 126.93
10040 m40 x 20 mm 62.33 71.13 - 133.46 153.48
10045 m50 x 12 mm 48.04 71.13 - 119.17 137.05
10050 m50 x 20 mm 88.50 71.13 - 159.63 183.58
Ghana teak wood :
10055 m30 x 12 mm 24.74 71.13 - 95.87 110.25
10060 m40 x 12 mm 34.21 71.13 - 105.34 121.14
10065 m40 x 20 mm 64.29 71.13 - 135.42 155.73
10070 m50 x 12 mm 41.75 71.13 - 112.88 129.81
10075 m50 x 20 mm 66.29 71.13 - 137.42 158.03
2nd class Deodar wood :
10080 m30 x 12 mm 22.73 71.13 - 93.86 107.93
10085 m40 x 12 mm 39.53 71.13 - 110.66 127.25
10090 m40 x 20 mm 48.94 71.13 - 120.07 138.08
10095 m50 x 12 mm 39.00 71.13 - 110.13 126.65
10100 m50 x 20 mm 71.85 71.13 - 142.98 164.43
Rubber wood :
10105 m30 x 12 mm 16.03 71.13 - 87.16 100.24
10110 m40 x 12 mm 21.43 71.13 - 92.56 106.45
10115 m40 x 20 mm 32.65 71.13 - 103.78 119.35
10120 m50 x 12 mm 25.78 71.13 - 96.91 111.45
10125 m50 x 20 mm 39.68 71.13 - 110.81 127.43
26 Board Paneling06
13 Profile Board Paneling UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2606TOTAL
Paneling, Boards10
Providing and fixing in wall lining flat pressed
three layer & graded (medium density) particle
boards, prelaminated, one side decorative
lamination and on other side balancing
lamination, grade I, Type II, conforming to
IS:12823, with necessary fixing arrangements
and screws etc. complete, of thicknesses :
10005 sqm12 mm 2509.28 160.76 - 2670.04 3070.55
10010 sqm18 mm 3240.29 160.76 - 3401.05 3911.20
Pre-finished Paneling11
10005 sqmProviding and fixing 9 mm thick laminated
wall panelling made of melamine
impregnated MDF board having tonge and
groove jointing system, complete with
accessories like wall base skirting and other
profiles complete.
3043.06 232.10 3.54 3278.70 3770.51
42 Wood Paneling06
10 Wood Paneling UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
4206TOTAL
46
BuildCOST THERMAL AND MOISTURE PROTECTION
11 Dampproofing07
17 Damp-proof Course UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1107TOTAL
Damp-proof Course10
Providing and laying damp-proof course with
cement concrete 1:2:4 with graded stone
aggregate 12.5 mm nominal size, including side
shuttering, compacting etc., complete.
10005 sqm40 mm thick 162.51 128.11 19.47 310.09 356.60
10010 sqm50 mm thick 201.56 141.91 21.59 365.06 419.82
10015 kg/50kgProviding and mixing waterproofing material
in cement concrete work @ 1.0 kg per 50 kg
bag of cement used in the mix.
97.37 8.00 - 105.37 121.18
10020 sqmApplying a cost of residual petroleium
bitumen of penetration 80/100 @ 1.70 kg/sq.
on damp-proof course.
83.08 21.55 - 104.63 120.33
13 Sheet Waterproofing07
13 Bituminous Sheet Waterproofing UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1307TOTAL
Built-Up Sheet Waterproofing13
Providing and laying vapour barrier of low density
polythene film (700 microns), laid in blown grade
bitumen at 1 kg. per. sqm, over a coat of primer
at 400 gms per sqm and finished with a coat of
bitumen at 1 kg per sqm as per specifications ,
complete :
10005 sqmOver RCC roof surfaces. 240.54 32.61 - 273.15 314.12
10010 sqmOn external wall surfaces. 240.54 38.04 - 278.58 320.37
Providing and laying vapour barrier of aluminium
foil 0.075 mm thick, laid in blown grade bitumen
at 2 kg per sqm over a coat of primer at 400 gms
per sqm and finished with a coat of bitumen at 1
kg per sqm as per specifications, complete :
10015 sqmOver RCC roof surfaces 151.50 43.66 - 195.16 224.44
10020 sqmOn external wall surfaces 151.50 43.66 - 195.16 224.44
10025 sqmAdd for aluminum foil of thickness 0.1 mm
instead of 0.075 mm
24.09 - - 24.09 27.70
10030 sqmPainting top of roof surface with 80 / 100
penetration bitumen @ 1.7 kg per sqm
impregnated with coarse sand, 6 mm thick,
including cleaning of slab surface with brush
and finally with a cloth soaked in kerosene
oil.
87.97 42.00 - 129.97 149.47
10035 sqmProviding and laying damp-proofing
treatment comprising a primer coat, one
layer of aluminium foil 0.1 mm thick and two
layers of bitumen at the rate of 2 kg per sqm
per layer to ground floor/paving, complete.
186.20 43.66 - 229.86 264.34
10040 sqmProviding and laying waterproofing treatment
to roof slabs comprising of Primer coat, one
layer of fibre glass RP tissue, one layer of
aluminium foil 0.10 mm thickness, three
layers of bitumen at the rate of 2 Kg per sqm
per layer, sealing of edges and corners as
called for, complete.
237.21 65.22 - 302.43 347.79
10045 sqmProviding and laying damp-proofing
treatment comprising a primer coat, one
layer of fibre-glass RP tissue and two layers
of bitumen at the rate 2 kg per sqm per layer
in toilets and other areas including side and
end laps, etc., complete.
115.52 65.22 - 180.74 207.85
10050 sqmAdd for additional layer of aluminium foil ,
(0.10 mm thick) and additional layer of
121.30 21.56 - 142.86 164.29
51
BuildCOST THERMAL AND MOISTURE PROTECTION
13 Sheet Waterproofing07
13 Bituminous Sheet Waterproofing UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1307TOTAL
bitumen at the rate of 2 kg per sqm in roof
surface treatment.
10055 sqmProviding and laying at roof ridges and other
locations, where called for, waterproofing
treatment consisting of one layer of blown
grade bitumen at 1 kg per sqm followed by
one layer of fibreglass tissue laid and
finished with one layer of bitumen at 1 kg per
sqm.
96.01 43.66 - 139.67 160.62
10060 sqmAdd for finishing the waterproofing treatment
with 6 mm pea-size gravel at the rate of 1
cum per 100 sqm (bitumen layer for laying
gravel included in waterproofing item).
8.01 2.76 - 10.77 12.38
10065 sqmAdd for providing polymeric polythene felt
membrane instead of fibre-glass RP tissue.
99.49 - - 99.49 114.41
10070 sqmDeduct for providing hessian based self
finish bitumen felt instead of fibre-glass RP
tissue.
-78.21 - - -78.21 -89.94
10075 sqmAdd for every additional coat of blown /
residual bitumen applied hot @ 2 kg per
sqm.
22.28 22.11 - 44.39 51.05
10080 sqmAdd for every additional layer of fibre-glass
RP tissue and bitumen @ 2 kg per sqm.
50.44 32.61 - 83.05 95.50
16 Cementitious And Reactive Waterproofing07
16 Crystalline Waterproofing UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1607TOTAL
Cementitious Waterproofing20
10005 sqmBrick bat coba waterproofing treatment to
terraces, terrace gardens, roof surfaces and
such other locations where called for, by
providing an even base layer of minimum 20
mm thick cement mortar 1:4 with coarse
sand admixed with acrylic waterproofing
compound, brick bats of size ranging from
40 mm to 100 mm, laid with gaps of 10 to 15
mm between them and grouted with cement
mortar 1:4 with coarse sand and admixed
with acrylic waterproofing compound, laid to
slope of 1:120 or as specified and a
protective coat of 20 mm thick cement
mortar 1:4 with coarse sand admixed with
acrylic waterproofing compound, fixing of
rough Kotah stone of 18-20 mm thickness
over a bed of cement mortar 1:4 with coarse
sand admixed with acrylic waterproofing
compound and joints grouted to full depth of
stone with cement slurry admixed with
acrylic waterproofing compound. Kotah
stone shall be fixed within 48 hours of
completing and laying the protective coat to
brick coba treatment. Treatment to vertical
faces of parapets, walls, beams, etc. will
comprise 20 mm thick cement plaster 1:4
with coarse sand admixed with acrylic
waterproofing compound and finished neet
upto a height of 300 mm (only horizontal
treatment area shall be measured for
payment). The average thickness, excluding
the Kotah stone and its bedding mortar, shall
be 120 mm. The minimum thickness at
khurra, excluding the Kotah stone and its
bedding mortar, shall be 80 mm.
1039.07 1120.11 23.01 2182.19 2509.52
52
BuildCOST OPENINGS
09 Metal Doors, Windows And Frames08
16 Aluminum Doors, Windows And
Frames
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0908TOTAL
Aluminum Doors, Windows And
Frames
10
Providing, fabricating and fixing aluminium doors,
windows and ventilators with sections (IS 733
and IS 1825), 60 microns pure polyster coated,
25 microns colour nutred anodised (IS 1868), of
grade AC 25, fixed with rawl plugs and screws /
fixing clips / expansion hold fasteners and filling
gaps with PVC / Neoprene felt along with
aluminium snap beadings, CP brass/stainless
steel screws for glazing / panelling complete
(cost of glazing / panelling not included)
(payment will be made for weight of aluminium
used in the work).
10005 kgFixed portion 282.02 23.76 - 305.78 351.64
10010 kgShutters of doors, windows and ventilators
including providing and fixing hinges/pivots
and making provision for fixing of fittings
including PVC/neoprene gasket, complete
(cost of fitting not included).
302.17 31.51 - 333.68 383.74
21 Steel Doors, Windows And Frames UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0908TOTAL
Steel Doors, Windows And Frames10
Providing and fixing MS glazed doors, windows
and ventilators of standard heavy rolled steel
sections, conforming to IS 7452-1990, joints
mitred and welded with 15 x 3 mm lugs, 100 mm
long, embedded in cement concrete blocks 150 x
100 x 100 mm of 1:3:6 with coarse sand or with
wooden plugs and screws or rawl plugs and
screws/ with fixing clips/ with bolts and nuts as
required, incluing providing and fixing of 4 mm
thick glass panes with glazing clips and special
metal sash putty including three coats of
synthetic enamel paint over a primer coat of zinc
chromate on duly prepared surfaces excluding
the cost of metal beading and other fittings
except necessary hinges or pivot as required ,
complete :
10005 sqmDoors 6801.76 437.32 1.77 7240.84 8326.97
10010 sqmWindows fixed 6622.99 437.32 1.77 7062.07 8121.38
10015 sqmWindows-side hung 6801.76 437.32 1.77 7240.84 8326.97
10020 sqmVentilators-top hung 6563.40 437.32 1.77 7002.48 8052.85
10025 sqmVentilators-centre hung 6563.40 437.32 1.77 7002.48 8052.85
In composite units of doors, windows and
ventilator :
10030 sqm(For overall portion treated as fixed) 6622.99 437.32 1.77 7062.07 8121.38
Add for side hung portion :
10035 sqmDoors 178.77 - - 178.77 205.59
10040 sqmWindows 178.77 - - 178.77 205.59
10045 sqmAdd for top hung portion. -59.59 - - -59.59 -68.53
10050 sqmAdd for centre hung portion. -59.59 - - -59.59 -68.53
10055 mAdd for providing vertical coupling, mullion
bar, or horizontal coupling mullion bar (when
openable windows are to be coupled above
fixed ones or between two fixed windows) or
horizontal coupling mullion bar (where
windows are not exposed to weather).
124.42 16.20 - 140.63 161.72
10060 mExtra for providing horizontal coupling
mullion bar or weather bar (especially used
158.99 20.70 - 179.69 206.64
63
BuildCOST OPENINGS
09 Metal Doors, Windows And Frames08
21 Steel Doors, Windows And Frames UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0908TOTAL
when the coupled unit is exposed to rain).
10065 mAdd for providing and fixing stainless steel /
aluminium beading of approved shape and
section with SS screws instead of glazing
clips and metal sash putty in steel doors ,
windows, ventilators and composite units.
78.11 10.81 - 88.92 102.26
11 Metal Doors And Frames08
13 Hollow Metal Doors And Frames UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1108TOTAL
Hollow Metal Doors and Frames11
10005 sqmProviding, fabricating and fixing 1 mm thick
MS sheet door with hollow MS section frame
of 40 x 40 x 3 mm and 3 mm gussets at the
junctions and corners with necessary fittings
and three coats of synthetic enamel paint
over a primer coat of zinc chromate on duly
prepared surfaces, complete.
8112.32 1310.21 - 9422.53 10835.91
10010 sqmProviding, fabricating and fixing 1 mm thick
MS sheet door with MS angle 40 x 40 x 6
mm frame, and 3 mm gussets at the
junctions and corners with necessary fittings ,
three coats of synthetic enamel paint over a
primer coat of zinc chromate on duly
prepared surfaces, complete.
8113.70 1310.21 - 9423.91 10837.50
10015 sqmAdd for MS angles 40 x 40 x 6 mm for
diagonal braces.
1212.34 296.15 - 1508.49 1734.76
10020 sqmAdd for MS flats 30 x 6 mm for diagonal
braces and central cross piece.
579.28 285.04 - 864.32 993.96
12 Metal Frames08
21 Steel Frames UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1208TOTAL
Steel Frames13
10005 kgProviding and fixing MS frames for doors,
w i n d o w s a n d v e n t i l a t o r s w i t h
Tee/angle/fabricated-sections, joints mitred
and welded with 15 x 3 mm lugs 100 mm
long embedded in cement concrete blocks
150 x 100 x 100 mm 1:3:6 with coarse sand
or with wooden plugs and screws or rawls
plugs and screws/with fixing clips/with bolts
and nuts as required including fixing of butt
hinges and screws and applying three coats
of synthetic enamel paint over a primer coat
of zinc chromate on duly prepared surfaces,
complete.
222.55 18.92 0.00 241.46 277.68
Providing and fixing pressed steel door frames,
manufactured from commercial mild steel sheet
of 1.25 mm thickness, including hinges jamb,
lock jamb, bead, and required threshold of mild
steel flat of section 30 x 3 mm/8 mm round or
square bar welded or rigidly fixed together by
mechanical means, adjustable lugs with split end
tail to each jamb including steel butt hinges 2.5
mm thick with mortar guards, lock strike - plate
and shock absorbers and applying three coats of
synthetic enamel paint over a primer coat of zinc
chromate on duly prepared surfaces i /c filling
hollows of the frame with CC 1:3:6, complete :
10010 mProfile A 1008.76 72.65 1.42 1082.82 1245.25
64
BuildCOST FINISHES
21 Plaster And Gypsum Board Assemblies09
13 Plaster Assemblies UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2109TOTAL
Expansion Control With Chicken
Mesh
13
10005 sqmProviding and fixing galvanized chicken wire
mesh (24 gauge 12 mm size) to junctions of
concrete and masonry work and other
locations including cutting to required sizes ,
side laps of minimum 75 mm and fixing in
position with galvanized iron wire nails,
complete.
126.15 200.13 2.71 328.99 378.34
22 Supports For Plaster And Gypsum Board09
26 Suspension Systems UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2209TOTAL
Aluminium Frame Work14
Providing and fixing frame work for suspended
ceiling with anodised aluminium 15 microns
coating/Polyester pre-coated (50 microns), main
runner T-sections 35 x 35 x 1.5 mm thick
suspended from ceiling with 6 mm dia MS
adjustable hangers, fixed to ceiling with MS cleat
25 x 25 x 5 mm and 50 mm long, fixed to RCC
surface with expandable fasteners 12.5 x 40 mm,
intermediate T-section 23.5 x 19 x 1.5 mm thick
fixed to main runner and perimeter angle 35 x 15
x 1.5 mm thick fixed to wall/beam with cadmium
plated steel screws with rawl plug @ 450 mm
etc., all complete, for panel sizes (cost of
hangers with cleat to be paid for separately) :
10005 sqm1220 x 610 mm 599.14 236.51 - 835.65 961.00
10010 sqm610 x 610 mm 650.88 236.51 - 887.38 1020.49
10015 sqmAdd for providing and making arrangement
for fixing light, fixture grills and diffusers in
the frame work.
538.16 236.30 - 774.45 890.62
Ms Frame Work15
Providing and fixing frame work for suspended
ceiling, made from 0.55 mm thick GS sheet
section consisting of GS channel main runner
suspended from ceiling with 6 mm dia MS
adjustable hanger fixed to ceiling with MS angle
of 25 x 25 x 5 mm thick and 50 mm long with
expandable fastners 12.5 x 40 mm, intermediate
T - sections fixed to main runner, and perimeter
channel section fixed to wall with cadmium
plated steel screw with rawl plug @ 450 mm
centre to centre, complete, for panel size (cost of
hangers with cleat to be paid for separately).
10005 sqm1220 x 610 mm 691.02 236.51 - 927.53 1066.66
10010 sqm610 x 610 mm 813.24 236.51 - 1049.75 1207.21
10015 sqmAdd for providing and making arrangement
for fixing light fixture grills and diffusers in the
frame work.
813.24 236.30 - 1049.54 1206.97
Ceiling Supports, Suspension16
10005 EachProviding and fixing level adjusting hangers
of 6 mm dia. MS Rods fixed to roof slabs by
means of MSangle ceiling cleats 40 x 40 x 5
mm size, 40 mm long and expansion hold
fastners 12.5 mm dia. 40 mm long including
applying a primer coat of zinc chromate,
complete.
84.37 15.66 - 100.03 115.03
79
BuildCOST SPECIALTIES
14 Signage10
53 Traffic Signage UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1410TOTAL
Traffic Signs20
10005 EachProviding and fixing Cats Eye (Glow studs),
heavy duty integral stem, reflective ,
aluminium dia cast with elegant finish, of
size 100 x 100 mm and 20 mm high, having
a stem of 50 mm screwed / nailed with 12
mm dia 90 mm long nail to fix into the road
surface or at the nosing of the central verge .
The road studs should have reflectors fitted
on one side of the studs, complete.
218.36 33.32 - 251.68 289.43
28 Toilet, Bath, And Laundry Accessories10
16 Bath Accessories UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2810TOTAL
Bath Accessories10
Providing and fixing stainless steel curtain rods
with stainless steel brackets, complete, of size :
10005 m25 mm outer dia 384.18 210.04 - 594.22 683.35
10010 m32 mm outer dia 551.20 210.04 - 761.24 875.42
10015 mProviding and fixing CP brass curtain rod
with CP brass brackets 25 mm outer dia,
complete.
1270.28 210.04 - 1480.32 1702.37
10020 SetProviding and fixing CP brass brackets for
curtain rods 25 mm outer dia, complete.
554.60 157.43 - 712.03 818.83
Providing and fixing angular/bent grab bars
fabricated from 32 mm dia. seamless stainless
steel tubes with peened non-slip gripping
surface, polished flanges firmly fixed, to be fully
safe, with heavy duty anchor fastener having
finish/capping similar to the grab bar, complete,
including cutting and making good the
walls/floors for :
10025 EachWall-mounted /floor-mounted for European
type water closet - 830 mm high
1291.34 315.38 - 1606.71 1847.72
10030 EachBath tub - 1320 mm long 1401.83 315.38 - 1717.20 1974.78
10035 EachWash basin and shower - 610 mm long 1512.32 315.38 - 1827.69 2101.85
10040 EachProviding and fixing fully automatic "NO
TOUCH" hand driers of stainless steel body
suitable to operate on 230 V, single ph 50
Hz, AC power supply including brackets for
fixing on wall including cutting and making
good the walls, etc., complete.
10688.58 315.38 - 11003.96 12654.55
10045 EachProviding and fixing bevelled edge mirrors
5.5 mm thick of float glass, complete with 6
mm thick marine ply board backing, fixed
with CP brass screws and washers,
complete, of size 450 x 600 mm.
2276.80 367.25 - 2644.05 3040.66
Providing and fixing float glass mirror 5.5 mm
thick with plastic moulded frame and 6 mm thick
marine ply board backing, complete, of outer
dimensions :
10050 EachCircular shape 450 mm dia 528.49 367.25 - 895.74 1030.10
10055 EachRectangular shape 453 x 357 mm 445.22 367.25 - 812.47 934.34
10060 EachOval shape 450 x 350 mm 445.82 367.25 - 813.08 935.04
10065 EachRectangular shape 1500 x 450 mm 945.99 473.12 - 1419.10 1631.97
10070 sqmProviding and fixing rectangular float glass
mirror 5.5 mm thick of any size with 6 mm
thick marine ply board backing, supported on
clips fixed with CP brass screws and
washers, complete.
899.05 525.10 - 1424.15 1637.78
107
BuildCOST FIRE SUPPRESSION
12 Fire-suppression Standpipes21
13 Fire-suppression Hoses And Nozzles UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1221TOTAL
Fire Hose And Equipment52
10005 EachProviding and fixing stand post fire hydrants
Type A, conforming to IS:908, with 63 mm
dia. outlet f i t ted with gunmetal
instantaneous type coupling, 80 mm dia.
inlet, one number cast iron double flanged
sluice valve, CI duck foot bends and flanged
riser, painting with one coat of ready mixed
red oxide primer and two coats of synthetic
enamel paint of fire red colour, finished to an
even shade, complete, excluding the cost of
brick chamber.
19430.05 654.04 - 20084.08 23096.70
10010 EachProviding and fixing gun metal, under ground
type fire hydrants, conforming to IS-909, with
control valve and 63 mm dia single outlet
fitted with instantaneous type coupling,
conforming to IS-901 for connection to hose
and 80 mm dia inlet and chained cap,
complete, excluding the cost of brick
chamber.
27754.31 300.49 - 28054.80 32263.02
Providing and fixing gunmetal, hand wheel
operated fire hydrant valves Type A, conforming
to IS:5290, with 63 mm dia outlet fitted with
instantaneous female coupling, conforming to
IS:901, and 80 mm dia inlet, complete, with
blank caps and chains with :
10015 EachSingle outlet 10221.13 100.06 - 10321.20 11869.38
10020 EachDouble outlet 19651.69 120.08 - 19771.77 22737.54
10025 EachProviding and fixing first aid hose reels, of
heavy duty mild steel construction, with CI
brackets, wall mounted, swinging type, fitted
with 19 mm dia., 36.5 m long high pressure
hose, conforming to IS-5132, with 5 mm dia
outlet gunmetal nozzle and shut off valve,
conforming to IS 884-1967, complete.
14753.54 450.17 - 15203.71 17484.27
10030 EachProviding and fixing 63 mm dia, 15 m long
reinforced rubber lined hoses, conforming to
IS:636, including gunmetal male and female
instantaneous type coupling, conforming to
IS: 903, machine wound with galvanised
steel wire, complete.
8481.19 30.03 - 8511.22 9787.91
10035 EachProviding and fixing standard short size
gunmetal branch pipes, conforming to
IS-903, with 16 mm dia. outlet gunmetal
nozzle, suitable to fit with standard
instantaneous type 63 mm coupling along
with nozzle spanner, complete.
3893.30 30.03 - 3923.33 4511.83
10040 EachProviding and fixing standard firemans axes
with heavy insulated rubber handle ,
conforming to IS:926, complete.
835.58 30.03 - 865.62 995.46
Providing and fixing gunmetal fire brigade
connections, conforming to IS-905, with 63 mm
dia. instantaneous type inlet and 150 mm dia
flanged outlet with built in check valves for fire
risers complete in all respects :
10045 EachTwo-way 11749.53 150.00 - 11899.53 13684.46
10050 EachThree-way 17004.42 170.21 - 17174.63 19750.82
10055 EachProviding and fixing 25 mm size single acting
air valves with SCR inlet, conforming to
IS-12992, complete.
1519.50 200.13 - 1719.63 1977.58
13 Fire-suppression Sprinkler Systems21
113
BuildCOST PLUMBING
05 Common Work Results For Plumbing22
23 General-duty Valves For Plumbing
Piping
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0522TOTAL
Valve, Ball23
Providing, fixing and testing brass ball valve,
SCR lever operated, complete, of size:
10005 Each8 mm 206.96 50.03 - 256.99 295.54
10010 Each10 mm 206.96 70.04 - 277.00 318.55
Providing, fixing and testing brass ball valves
with carbon steel lever, complete of size :
10015 Each15 mm 293.32 70.04 - 363.36 417.86
10020 Each20 mm 831.60 70.04 - 901.64 1036.89
10025 Each25 mm 1318.19 80.05 - 1398.25 1607.98
10030 Each32 mm 1818.68 80.05 - 1898.73 2183.54
10035 Each40 mm 1969.99 100.06 - 2070.05 2380.56
10040 Each50 mm 2489.72 100.06 - 2589.79 2978.25
Providing, fixing and testing brass ball valves
with aluminium alloy lever of size :
10045 Each15 mm 503.73 70.04 - 573.77 659.84
10050 Each20 mm 762.71 70.04 - 832.76 957.67
10055 Each25 mm 952.86 80.05 - 1032.91 1187.84
10060 Each32 mm 1852.71 80.05 - 1932.76 2222.68
10065 Each40 mm 2627.36 100.06 - 2727.43 3136.54
10070 Each50 mm 4139.18 100.06 - 4239.25 4875.14
Valve, Balancing24
Providing, fixing and testing CI balancing valve,
body conforming to IS:210, with companion
flanges (IS:6392), complete, of size:
10005 Each80 mm 6840.00 126.79 - 6966.79 8011.80
10010 Each100 mm 9690.00 148.24 - 9838.24 11313.98
10015 Each125 mm 13395.00 185.26 - 13580.26 15617.30
10020 Each150 mm 18192.50 234.10 - 18426.60 21190.60
10025 Each200 mm 39900.00 312.09 - 40212.09 46243.90
10030 Each250 mm 64790.00 390.11 - 65180.11 74957.12
10035 Each300 mm 87590.00 506.60 - 88096.60 101311.08
Providing, fixing and testing G/Met balancing
valve SCR, conforming to IS:778, etc., complete,
of size:
10040 Each25 mm 1784.16 80.05 - 1864.21 2143.84
10045 Each32 mm 2183.74 95.06 - 2278.80 2620.62
10050 Each40 mm 2694.83 110.07 - 2804.90 3225.63
10055 Each50 mm 4553.33 120.08 - 4673.40 5374.41
10060 Each65 mm 8270.33 137.99 - 8408.31 9669.56
10065 Each80 mm 11046.92 160.10 - 11207.03 12888.08
Valve, Check27
Providing, fixing and testing CI check valve with
flanges, conforming to IS:9338 etc., complete, of
size:
10005 Each40 mm 2990.70 50.03 - 3040.73 3496.84
10010 Each50 mm 4516.16 54.03 - 4570.19 5255.72
10015 Each65 mm 5979.17 60.04 - 6039.20 6945.09
10020 Each80 mm 7289.04 65.04 - 7354.08 8457.19
10025 Each100 mm 10125.11 148.24 - 10273.35 11814.35
10030 Each125 mm 13395.32 185.26 - 13580.59 15617.67
10035 Each150 mm 14140.21 234.10 - 14374.32 16530.46
10040 Each200 mm 28901.16 312.09 - 29213.25 33595.24
10045 Each250 mm 37486.33 390.11 - 37876.44 43557.90
117
BuildCOST PLUMBING
05 Common Work Results For Plumbing22
23 General-duty Valves For Plumbing
Piping
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0522TOTAL
Providing, fixing and testing G/Met vertical check
valve, integral seat, flanged female connection,
conforming to IS:778, complete, of size:
10225 Each25 mm 810.13 42.03 - 852.16 979.98
10230 Each32 mm 1187.51 46.03 - 1233.54 1418.57
10235 Each40 mm 1564.16 50.03 - 1614.20 1856.32
10240 Each50 mm 2195.79 54.03 - 2249.83 2587.30
10245 Each65 mm 3804.40 57.04 - 3861.44 4440.65
10250 Each80 mm 6198.35 65.04 - 6263.39 7202.89
10255 Each100 mm 11313.37 147.23 - 11460.60 13179.69
Valve, Gate31
Providing, fixing and testing brass gate valves
with CI Wheel, conforming to IS:778, secrewed
ends, complete, of nominal size :
10005 Each25 mm 792.21 50.03 - 842.25 968.58
10010 Each32 mm 939.46 50.03 - 989.49 1137.91
10015 Each40 mm 1446.94 50.03 - 1496.97 1721.52
10020 Each50 mm 1983.47 50.03 - 2033.50 2338.53
10025 Each65 mm 4918.24 60.04 - 4978.28 5725.02
10030 Each80 mm 6118.63 60.04 - 6178.67 7105.47
Providing, fixing and testing G/Met gate valve,
non-rising stem SCR, conforming to IS:778,
complete, of size:
10035 Each15 mm 803.76 20.01 - 823.78 947.34
10040 Each20 mm 999.47 25.02 - 1024.49 1178.16
10045 Each25 mm 1822.73 28.02 - 1850.75 2128.36
10050 Each32 mm 2536.23 32.02 - 2568.25 2953.48
10055 Each40 mm 2999.13 35.02 - 3034.15 3489.28
10060 Each50 mm 5251.55 39.03 - 5290.57 6084.16
10065 Each65 mm 9610.51 42.03 - 9652.53 11100.41
10070 Each80 mm 13683.49 50.03 - 13733.52 15793.55
10075 Each100 mm 23212.39 50.03 - 23262.42 26751.78
Valve, Plastic60
Providing, fixing and testing PTMT stop cocks,
complete, of nominal size :
10005 Each15 mm 150.24 50.03 - 200.27 230.32
10010 Each20 mm 171.31 50.03 - 221.34 254.54
76 Facility Drainage Piping Cleanouts UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0522TOTAL
Cleanouts10
10005 EachProviding and fixing 100 mm dia. flanged
clean-out plugs with CI flanged tail pieces,
blind flanges conforming to IS-1538 fixed
with necessary neoprene washers ,
galvanised fasteners, complete, (excluding
cost of tail piece and its joints).
518.35 125.08 - 643.43 739.94
Providing and fixing cast brass clean-out plugs
with suitable inset keys for opening, and
galvanised steel bends including fixing to
galvanised steel / sand cast iron/ centrifugally
spun pipes with lead joint, of nominal dia :
10010 Each50 mm 1018.32 195.05 - 1213.38 1395.38
10015 Each75 mm 1695.73 195.05 - 1890.78 2174.40
10020 Each100 mm 2852.82 292.43 - 3145.24 3617.03
10025 Each150 mm 6942.27 292.43 - 7234.70 8319.91
119
BuildCOST HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
07 Hvac Insulation23
13 Duct Insulation UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0723TOTAL
Duct Insulation11
Providing and fixing, fiber-glass insulation ,
bonded by resin conforming to IS:8183, for
ducts, etc., with 0.5 mm thick aluminium sheet
cladding having 50 mm overlap at joints etc .,
complete, of following thickness and density:
10005 sqm25 mm thick 16kg per cum 660.13 272.17 - 932.30 1072.15
10010 sqm25 mm thick 24 kg per cum 709.30 272.17 - 981.48 1128.70
10015 sqm25 mm thick 32 kg per cum 760.82 272.17 - 1033.00 1187.94
10020 sqm50 mm thick 16 kg per cum 787.42 272.17 - 1059.60 1218.54
10025 sqm50 mm thick 24 kg per cum 883.43 272.17 - 1155.61 1328.95
10030 sqm50 mm thick 32 kg per cum 987.64 272.17 - 1259.81 1448.78
Providing and fixing, rigid polyurethane foam
(PUF) slab for thermal insulation, conforming to
IS:12436, paper laminated/ unfaced, complete,
of following thickness and density:
10035 sqm15 mm thick 32 kg per cum 522.82 208.01 - 730.83 840.45
10040 sqm20 mm thick 32 kg per cum 673.73 208.01 - 881.74 1014.00
10045 sqm25 mm thick 32 kg per cum 853.17 208.01 - 1061.19 1220.36
10050 sqm30 mm thick 32 kg per cum 1005.39 208.01 - 1213.40 1395.41
10055 sqm40 mm thick 32 kg per cum 1336.49 208.01 - 1544.50 1776.18
10060 sqm50 mm thick 32 kg per cum 1668.23 208.01 - 1876.24 2157.68
Providing and fixing, polyurethane rigid foam
insulation pipe section, conforming to IS:12436
and density 36 kg per m3 with 0. 5 mm thick
aluminium sheet cladding having 50 mm overlap
on joints and supports, complete, of following
thickness and nominal bo
25 mm thickness :
10065 m20 mm 325.45 32.00 - 357.45 411.07
10070 m25 mm 366.34 32.00 - 398.34 458.09
10075 m32 mm 405.68 32.00 - 437.68 503.33
10080 m40 mm 441.61 32.00 - 473.61 544.65
10085 m50 mm 492.66 32.00 - 524.66 524.66
10090 m65 mm 546.30 32.00 - 578.31 665.05
10095 m80 mm 605.16 48.00 - 653.16 751.13
10100 m100 mm 696.84 48.00 - 744.85 856.57
10105 m125 mm 832.51 48.00 - 880.52 1012.59
10110 m150 mm 937.21 48.00 - 985.21 1132.99
10115 m200 mm 1162.21 48.00 - 1210.21 1391.75
10120 m250 mm 1428.60 48.00 - 1476.60 1698.09
10125 m300 mm 1622.38 64.00 - 1686.38 1939.34
10130 m350 mm 2122.37 64.00 - 2186.38 2514.33
10135 m400 mm 2429.34 64.00 - 2493.34 2867.34
30 mm thickness :
10140 m20 mm 370.56 32.00 - 402.56 462.94
10145 m25 mm 433.20 32.00 - 465.20 534.98
10150 m32 mm 469.13 32.00 - 501.13 576.30
10155 m40 mm 507.42 32.00 - 539.42 620.33
10160 m50 mm 579.28 32.00 - 611.28 702.97
10165 m65 mm 627.72 32.00 - 659.72 758.68
10170 m80 mm 694.38 48.00 - 742.38 853.74
10175 m100 mm 809.24 48.00 - 857.24 985.82
10180 m125 mm 947.51 48.00 - 995.51 1144.84
147
BuildCOST ELECTRICAL
05 Common Work Results For Electrical26
13 Medium-Voltage Cables UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0526TOTAL
Cable End Terminations With
Compression Glands
20
Providing and making end termination with single
compression brass gland and aluminium lugs for
PVC insulated and PVC sheathed / XLPE
aluminium conductor cable of 1.1 kV grade,
complete, of size :
10005 Set1 core 300 sqmm 300.91 250.16 - 551.07 633.73
10010 Set1 core 400 sqmm 511.02 250.16 - 761.18 875.36
10015 Set1 core 500 sqmm 558.13 300.49 - 858.63 987.42
10020 Set1 core 630 sqmm 644.25 300.49 - 944.74 1086.45
10025 Set2 core 6 sqmm 61.91 100.06 - 161.98 186.27
10030 Set2 core 10 sqmm 63.12 120.08 - 183.19 210.67
10035 Set2 core 16 sqmm 85.86 120.08 - 205.94 236.83
10040 Set2 core 25 sqmm 143.47 120.08 - 263.55 303.08
10045 Set2 core 35 sqmm 146.04 120.08 - 266.12 306.04
10050 Set2 core 50 sqmm 151.56 120.08 - 271.63 312.38
10055 Set2 core 70 sqmm 156.56 120.08 - 276.64 318.14
10060 Set3 core 10 sqmm 87.45 120.08 - 207.53 238.66
10065 Set3 core 16 sqmm 145.05 120.08 - 265.12 304.89
10070 Set3 core 25 sqmm 147.50 120.08 - 267.58 307.71
10075 Set3 core 35 sqmm 151.36 120.08 - 271.44 312.16
10080 Set3 core 50 sqmm 159.63 120.08 - 279.71 321.67
10085 Set3 core 70 sqmm 264.64 160.10 - 424.74 488.45
10090 Set3 core 95 sqmm 268.39 160.10 - 428.49 492.77
10095 Set3 core 120 sqmm 462.25 250.16 - 712.41 819.28
10100 Set3 core 150 sqmm 478.76 250.16 - 728.92 838.25
10105 Set3 core 185 sqmm 537.54 250.16 - 787.70 905.85
10110 Set3 core 240 sqmm 777.80 250.16 - 1027.96 1182.16
10115 Set3 core 300 sqmm 840.45 250.16 - 1090.61 1254.20
10120 Set3 core 400 sqmm 1059.16 330.21 - 1389.37 1597.77
10125 Set3½ core 25 sq. mm 150.71 120.08 - 270.79 311.41
10130 Set3½ core 35 sqmm 154.58 160.10 - 314.68 361.88
10135 Set3½ core 50 sqmm 163.67 160.10 - 323.77 372.33
10140 Set3½ core 70 sqmm 269.96 160.10 - 430.06 494.57
10145 Set3½ core 95 sqmm 276.47 250.16 - 526.63 605.62
10150 Set3½ core 120 sqmm 474.34 250.16 - 724.50 833.17
10155 Set3½ core 150 sqmm 531.46 250.16 - 781.62 898.86
10160 Set3½ core 185 sqmm 550.88 250.16 - 801.04 921.19
10165 Set3½ core 240 sqmm 796.48 250.16 - 1046.64 1203.64
10170 Set3½ core 300 sqmm 986.49 330.21 - 1316.71 1514.21
10175 Set3½ core 400 sqmm 1292.50 330.21 - 1622.71 1866.12
10180 Set4 core 10 sq. mm 90.13 120.08 - 210.20 241.73
10185 Set4 core 16 sqmm 148.26 120.08 - 268.34 308.59
10190 Set4 core 25 sqmm 151.53 160.10 - 311.64 358.38
10195 Set4 core 35 sqmm 156.68 160.10 - 316.79 364.31
10200 Set4 core 50 sqmm 260.69 160.10 - 420.79 483.91
10205 Set4 core 70 sqmm 258.97 250.16 - 509.13 585.50
10210 Set4 core 95 sqmm 294.06 250.16 - 544.22 625.86
10215 Set4 core 120 sqmm 538.11 250.16 - 788.27 906.51
Cable End Termination Kit, Cast
Resin Compound
22
179
BuildCOST ELECTRICAL
05 Common Work Results For Electrical26
13 Medium-Voltage Cables UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0526TOTAL
Providing and making indoor/outdoor cable end
termination with heat shrinkage jointing kit, with
all accessories including lugs for XLPE
aluminium conductor cable of 33 kV (E) grade,
complete, of size :
Outdoor,
10005 Each2 core 25 sqmm 1459.01 370.64 - 1829.65 2104.10
10010 Each2 core 35 sqmm 1461.59 370.64 - 1832.22 2107.06
10015 Each2 core 50 sqmm 1467.10 370.64 - 1837.74 2113.40
10020 Each2 core 70 sqmm 1627.37 370.64 - 1998.01 2297.71
10025 Each3 core 25 sqmm 1463.04 370.64 - 1833.68 2108.73
10030 Each3 core 35 sqmm 1466.91 370.64 - 1837.54 2113.18
10035 Each3 core 50 sqmm 1627.43 500.32 - 2127.75 2446.91
10040 Each3 core 70 sqmm 1639.46 500.32 - 2139.78 2460.74
10045 Each3 core 95 sqmm 1873.90 800.51 - 2674.41 3075.58
10050 Each3 core 120 sqmm 1889.93 800.51 - 2690.45 3094.01
10055 Each3 core 150 sqmm 1906.44 800.51 - 2706.95 3112.99
10060 Each3 core 185 sqmm 2835.93 870.16 - 3706.08 4262.00
10065 Each3 core 240 sqmm 3511.20 1000.64 - 4511.84 5188.61
10070 Each3 core 300 sqmm 3573.84 1000.64 - 4574.48 5260.66
10075 Each3 core 400 sqmm 796.09 1124.32 - 1920.41 2208.47
10080 Each3½ core 25 sqmm 1470.47 370.64 - 1841.11 2117.27
10085 Each3½ core 35 sqmm 1622.38 500.32 - 2122.70 2441.10
10090 Each3½ core 50 sqmm 1631.46 658.32 - 2289.79 2633.25
10095 Each3½ core 70 sqmm 1875.47 658.32 - 2533.79 2913.86
10100 Each3½ core 95 sqmm 1881.98 800.51 - 2682.49 3084.86
10105 Each3½ core 120 sqmm 1902.02 800.51 - 2702.53 3107.91
10110 Each3½ core 150 sqmm 2829.85 870.16 - 3700.01 4255.01
10115 Each3½ core 185 sqmm 2849.26 870.16 - 3719.42 4277.33
10120 Each3½ core 240 sqmm 3590.06 1000.64 - 4590.70 5279.30
10125 Each3½ core 300 sqmm 3658.20 1124.32 - 4782.52 5499.90
10130 Each3½ core 400 sqmm 4398.61 1205.57 - 5604.18 6444.81
10135 Each4 core 25 sqmm 2380.61 500.32 - 2880.93 3313.07
10140 Each4 core 35 sqmm 2389.97 658.32 - 3048.29 3505.54
10145 Each4 core 50 sqmm 2401.00 658.32 - 3059.32 3518.22
10150 Each4 core 70 sqmm 2520.14 658.32 - 3178.46 3655.23
10155 Each4 core 95 sqmm 2525.15 800.51 - 3325.66 3824.51
10160 Each4 core 120 sqmm 2546.52 800.51 - 3347.03 3849.09
Indoor,
10165 Each3 core 70 sqmm 5559.21 500.32 - 6059.53 6968.46
10170 Each3 core 95 sqmm 5562.97 500.32 - 6063.29 6972.78
10175 Each3 core 120 sqmm 6419.18 800.51 - 7219.70 8302.65
10180 Each3 core 150 sqmm 6435.69 800.51 - 7236.20 8321.63
10185 Each3 core 185 sqmm 6453.85 800.51 - 7254.36 8342.51
10190 Each3 core 240 sqmm 7625.47 1000.64 - 8626.11 9920.02
10195 Each3 core 300 sqmm 7688.11 1000.64 - 8688.75 9992.07
10200 Each3 core 400 sqmm 9470.42 1124.32 - 10594.74 12183.95
Outdoor,
10205 Each3 core 70 sqmm 13909.97 500.32 - 14410.29 16571.83
10210 Each3 core 95 sqmm 13913.73 500.32 - 14414.05 16576.15
10215 Each3 core 120 sqmm 16923.15 800.51 - 17723.66 20382.21
10220 Each3 core 150 sqmm 16939.65 800.51 - 17740.16 20401.19
180
BuildCOST ELECTRICAL
05 Common Work Results For Electrical26
13 Medium-Voltage Cables UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0526TOTAL
10225 Each3 core 185 sqmm 16957.81 800.51 - 17758.32 20422.07
10230 Each3 core 240 sqmm 20747.02 1000.64 - 21747.66 25009.81
10235 Each3 core 300 sqmm 20809.67 1000.64 - 21810.31 25081.86
10240 Each3 core 400 sqmm 23739.29 1124.32 - 24863.61 28593.15
Cable End Termination Kit, Cold
Shrinkage
24
Providing and making indoor/outdoor cold shrink
termination including aluminium lugs and all
other jointing materials for XLPE aluminium
conductor cable of 11 kV (E) grade, complete, of
size:
Indoor,
10005 Each3 core 70 sqmm 13768.68 400.26 - 14168.93 16294.27
10010 Each3 core 95 sqmm 13772.43 400.26 - 14172.69 16298.59
10015 Each3 core 120 sqmm 14898.70 658.32 - 15557.02 17890.58
10020 Each3 core 150 sqmm 14915.20 658.32 - 15573.52 17909.55
10025 Each3 core 185 sqmm 14933.36 658.32 - 15591.69 17930.44
10030 Each3 core 240 sqmm 17531.78 800.51 - 18332.29 21082.14
10035 Each3 core 300 sqmm 17594.43 800.51 - 18394.94 21154.18
10040 Each3 core 400 sqmm 17691.27 1000.64 - 18691.91 21495.70
Outdoor,
10045 Each3 core 70 sqmm 23748.18 400.26 - 24148.43 27770.70
10050 Each3 core 95 sqmm 23751.93 400.26 - 24152.19 27775.02
10055 Each3 core 120 sqmm 26724.14 658.32 - 27382.46 31489.83
10060 Each3 core 150 sqmm 26740.64 658.32 - 27398.97 31508.81
10065 Each3 core 185 sqmm 26758.81 658.32 - 27417.13 31529.70
10070 Each3 core 240 sqmm 29718.91 800.51 - 30519.42 35097.33
10075 Each3 core 300 sqmm 29781.55 800.51 - 30582.07 35169.38
10080 Each3 core 400 sqmm 29878.40 1000.64 - 30879.04 35510.89
Providing and making indoor/outdoor cold shrink
termination including aluminium lugs and all
other jointing materials for XLPE aluminium
conductor cable of 33 kV (E) grade, complete, of
size:
Indoor,
10085 Each3 core 50 sqmm 36949.57 500.32 - 37449.89 43067.38
10090 Each3 core 70 sqmm 36961.60 658.32 - 37619.92 43262.91
10095 Each3 core 95 sqmm 36965.35 658.32 - 37623.67 43267.23
10100 Each3 core 120 sqmm 36981.39 800.51 - 37781.90 43449.18
10105 Each3 core 150 sqmm 41583.68 800.51 - 42384.19 48741.82
10110 Each3 core 185 sqmm 41601.84 1000.64 - 42602.48 48992.85
10115 Each3 core 240 sqmm 41666.08 1000.64 - 42666.72 49066.73
10120 Each3 core 300 sqmm 45589.99 1124.32 - 46714.31 53721.45
Outdoor,
10125 Each3 core 50 sqmm 49137.28 500.32 - 49637.60 57083.24
10130 Each3 core 70 sqmm 49149.30 658.32 - 49807.63 57278.77
10135 Each3 core 95 sqmm 49334.36 658.32 - 49992.68 57491.58
10140 Each3 core 120 sqmm 49350.39 800.51 - 50150.90 57673.54
10145 Each3 core 150 sqmm 49366.89 800.51 - 50167.40 57692.51
10150 Each3 core 185 sqmm 49385.05 1000.64 - 50385.69 57943.55
10155 Each3 core 240 sqmm 54396.60 1000.64 - 55397.24 63706.83
10160 Each3 core 300 sqmm 54459.25 1124.32 - 55583.57 63921.10
181
BuildCOST COMMUNICATIONS
15 Communications Horizontal Cabling27
10 Special Communications Cabling UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1527TOTAL
Cable, Telephone25
Providing and drawing PVC insulated, PVC
sheathed, tinned copper conductor telephone
cable in the existing surface/recessed, PVC/steel
conduit/PVC casing and capping, of size :
0.51 mm dia,
10005 m1 pair 8.97 38.00 - 46.97 54.01
10010 m2 pair 17.09 38.00 - 55.09 63.35
10015 m3 pair 24.67 38.00 - 62.67 72.07
10020 m5 pair 37.59 38.00 - 75.59 86.93
10025 m10 pair 72.43 38.00 - 110.42 126.99
10030 m20 pair 139.58 38.00 - 177.57 204.21
10035 m50 pair 365.86 42.75 - 408.60 469.89
0.61 mm dia,
10040 m1 pair 11.72 38.00 - 49.72 57.17
10045 m2 pair 22.56 38.00 - 60.55 69.64
10050 m3 pair 33.10 38.00 - 71.10 81.76
10055 m5 pair 51.04 38.00 - 89.03 102.39
10060 m10 pair 98.69 38.00 - 136.69 157.19
10065 m20 pair 191.59 38.00 - 229.59 264.03
10070 m50 pair 519.85 42.75 - 562.60 646.99
0.71 mm dia,
10075 m1 pair 11.28 38.00 - 49.27 56.66
10080 m2 pair 35.39 38.00 - 73.39 84.39
10085 m3 pair 53.74 38.00 - 91.74 105.50
10090 m5 pair 88.41 38.00 - 126.40 145.36
10095 m10 pair 176.52 38.00 - 214.52 246.70
10100 m20 pair 350.62 38.00 - 388.61 446.90
10105 m50 pair 762.58 42.75 - 805.32 926.12
235
BuildCOST ELECTRONIC SAFETY AND SECURITY
31 Fire Detection And Alarm28
23 Fire Detection And Alarm
Annunciation Panels And Fire
Stations
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
3128TOTAL
Fire Detection And Fire Alarm
System
10
P r o v i d i n g , i n s t a l l a t i n g , t e s t i n g a n d
commissioning of standard fire detection and
alarm control panel in 16 SWG sheet steel
enclosure duly painted, consisting of power
supply, automatic control battery charger, control
and zone cards, duplex talk back facility etc (but
without PA system) for operation on 24 V, DC,
complete with 2 numbers 12 V Lead Acid storage
batteries of suitable capacity, for :
10005 Each2 zones 17703.54 1557.97 - 19261.51 22150.73
10010 Each4 zones 21398.12 1604.45 - 23002.57 26452.95
10015 Each6 zones 26284.50 1653.84 - 27938.34 32129.10
10020 Each8 zones 29979.08 1747.97 - 31727.05 36486.10
10025 Each10 zones 33673.66 1791.63 - 35465.29 40785.09
10030 Each12 zones 37368.24 1837.60 - 39205.84 45086.71
Providing and fixing heat detector, conforming to
IS:2175, including making connections, of type :
10035 EachRate of rise (ROR) 2070.63 56.99 - 2127.62 2446.76
10040 EachFixed temperature 1812.07 56.99 - 1869.06 2149.42
10045 EachRate of rise - cum - fixed temperature 2005.99 56.99 - 2062.98 2372.43
Providing and fixing smoke detector, conforming
to IS:11360, including making connections, of
type :
10050 EachIonisation 2147.39 56.99 - 2204.38 2535.04
10055 EachPhoto-electric/optical 2031.37 113.99 - 2145.36 2467.16
10060 EachProviding and fixing spot (response) indicator
including making connection.
141.82 136.03 - 277.85 319.53
Providing and fixing sounder including making
connections, of intensity :
10065 EachLow 958.75 47.50 - 1006.25 1157.18
10070 EachHigh 1614.24 47.50 - 1661.74 1911.00
10075 EachProviding and fixing manual call box,
complete with cover, switch including making
connections.
1254.32 136.03 - 1390.35 1598.90
P r o v i d i n g , i n s t a l l a t i n g , t e s t i n g a n d
commissioning addressable fire detection and
alarm control panel in 16 SWG sheet steel
enclosures, duly painted, consisting of power
supply, automatic control battery charger, loop
cards, fire / fault event recorder, duplex talk back
facility etc. (but without PA system), suitable for
operation on 24V, DC, complete with 2 numbers
12 V Lead Acid storage batteries of suitable
capacity, for :
10080 Each2 loop 283594.12 1791.63 - 285385.75 328193.61
10085 Each4 loop 423511.44 2028.22 - 425539.66 489370.61
10090 Each6 loop 610862.40 2263.15 - 613125.55 705094.39
10095 Each8 loop 751018.08 2529.35 - 753547.43 866579.54
10100 Each10 loop 937773.14 2756.34 - 940529.48 1081608.91
10105 Each12 loop 1124528.20 2986.05 - 1127514.25 1296641.39
Providing and fixing, addressable heat detector ,
conforming to IS:2175, including making
connections, of type :
10110 EachRate of rise (ROR) 4914.79 56.99 - 4971.78 5717.55
10115 EachFixed temperature 4656.23 56.99 - 4713.22 5420.20
239
BuildCOST EARTHWORK
11 Clearing And Grubbing31
10 Clearing And Grubbing UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1131TOTAL
Clear And Grub10
10005 100 sqmClearing jungle including uprooting of rank
vegetation, grass, brush wood, trees and
saplings of girth upto 300 mm (measured at
a height of 1.0 m above GL) and removal of
rubbish up to a distance of 50 m outside the
periphery of the area cleared, complete.
- 666.71 - 666.71 766.72
Felling trees including cutting of trunks and
branches, removing the roots, stacking of
serviceable materials and disposal of
unserviceable materials within a 50 m lead,
complete, of girths (measured at a height of 1.0
m above GL.) :
10010 Eachover 300 mm and upto 600 mm - 200.01 - 200.01 230.01
10015 Eachover 600 mm and upto 1200 mm - 909.13 - 909.13 1045.49
10020 Eachover 1200 mm and upto 2400 mm - 4000.20 - 4000.20 4600.23
10025 Eachover 2400 mm - 8000.40 - 8000.40 9200.46
Clearing11
10005 100 sqmClearing grass and removal of the rubbish
upto a distance of 50 m outside the
periphery of the area cleared, complete.
- 339.02 - 339.02 389.87
14 Earth Stripping And Stockpiling31
13 Soil Stripping And Stockpiling UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1431TOTAL
Soil Stripping13
10005 100 sqmSurface dressing of the ground including
removing vegetation and inequalities not
exceeding 150 mm deep, in all types of soil
and disposal of rubbish upto a lead of 50 m,
complete.
- 1290.38 - 1290.38 1483.94
22 Grading31
16 Fine Grading UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2231TOTAL
Topsoil11
10005 100 sqmEarth work in surface excavation not
exceeding 300 mm in depth but exceeding
1.5 m in width as well as 10 sqm on plan, in
all types of soil including disposal of
excavated earth up to 50 m and lift up to 1.5
m, disposed soil to be leveled and neatly
dressed, complete.
- 5000.25 - 5000.25 5750.29
23 Excavation And Fill31
16 Excavation UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2331TOTAL
Excavating, Trench12
Earth work in excavation in foundation trenches
or drains (not exceeding 1.5 m in width or 10
sqm on plan) including dressing of sides and
ramming of bottoms, lift upto 1.5 m, including
getting out the excavated soil and disposal of
surplus excavated earth as directed, within a
lead of 50 m, complete :
10005 cumAll types of soil - 363.86 - 363.86 418.44
243
BuildCOST EARTHWORK
23 Excavation And Fill31
16 Excavation UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
2331TOTAL
10010 cumOrdinary and disintegrated rock 35.13 563.43 - 598.56 688.35
10015 cumHard rock (requiring blasting) 90.95 727.32 - 818.27 941.01
10020 cumHard rock (blasting prohibited) - 1176.77 - 1176.77 1353.28
Excavating, Utility Trench14
Earth work in excavation, in trenches, in all types
of soil, for pipes, cables, etc. including
excavation for sockets, and dressing of sides ,
ramming of bottoms, depth up to 1.5 m including
getting out the excavated earth and then
returning the soil as required, in layers not
exceeding 200 mm in depth including
consolidating each deposited layer by ramming ,
watering etc. and disposing of surplus excavated
soil as directed, within a lead of 50 m complete,
of pipes, cables of sizes :
10005 mupto 80 mm dia. (minimum width of trench
450 mm)
- 227.32 - 227.32 261.42
10010 mover 80 mm dia. and upto 300 mm dia.
(minimum width of trench 600 mm)
- 371.09 - 371.09 426.76
10015 mover 300 mm dia. (minimum width of trench
850 mm)
- 579.50 - 579.50 666.43
Earth work in excavation in trenches, for pipes ,
cables, etc. including excavation for sockets,
depth up to 1.5 m including getting out the
excavated materials, returning the soil as
required in layers not exceeding 200 mm in
depth including consolidating each deposited
layer by ramming, watering etc., stacking
serviceable material for measurement and
disposal of unserviceable material, within a lead
of 50 m complete, of pipes, cables of sizes,
Ordinary and disintegrated rock :
10020 mupto 80 mm dia. (minimum width of trench
450 mm)
16.60 325.00 - 341.60 392.84
10025 mover 80 mm dia. and upto 300 mm dia.
(minimum width of trench 900 mm)
41.11 804.62 - 845.73 972.59
10030 mover 300 mm dia. (minimum width of trench
900 mm)
47.31 925.45 - 972.76 1118.68
Hard rock (blasting prohibited) :
10035 mupto 80 mm dia. (minimum width of trench
450 mm)
- 617.58 - 617.58 710.22
10040 mover 80 mm dia. and upto 300 mm dia.
(minimum width of trench 900 mm)
- 1528.36 - 1528.36 1757.62
10045 mover 300 mm dia. (minimum width of trench
900 mm)
- 1758.66 - 1758.66 2022.46
Hard rock (requiring blasting) :
10050 mupto 80 mm dia. (minimum width of trench
450 mm)
42.98 402.81 - 445.79 512.66
10055 mover 80 mm dia. and upto 300 mm dia.
(minimum width of trench 900 mm)
106.41 996.76 - 1103.18 1268.65
10060 mover 300 mm dia. (minimum width of trench
900 mm)
122.48 1147.49 - 1269.96 1460.46
Add for excavating trenches for pipes, cable etc .
in ordinary/hard rock :
10065 mFor depth exceeding 1.5 m, but not
exceeding 3.0 m (Rate is over corresponding
basic item for depth upto 1.5 m)
84.66 1034.75 - 1119.41 1287.33
10070 mFor depth exceeding 3.0 m, but not
exceeding 4.5 m (Rate is over corresponding
basic item for depth upto 1.5 m)
185.51 2588.80 - 2774.31 3190.46
Excavating holes up to 0.5 cum including getting
out the excavated material, then returning the
244
BuildCOST EXTERIOR IMPROVEMENTS
11 Base Courses32
23 Aggregate Base Courses UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1132TOTAL
Aggregate Base Courses10
Providing and laying water bound macadam with
stone aggregate, stone screening and blinding
material including screening, sorting, spreading
to template and consolidation with power road
roller of 8 to 10 t capacity etc., complete, of
courses :
10005 cumSub-base with stone aggregate 90 to 45 mm
including stone screening 13.2 mm size
1838.99 404.27 163.14 2406.40 2767.36
10010 cumBase course with 63 to 45 mm size including
stone screening 13.2 mm size
1854.26 337.55 136.29 2328.10 2677.32
10015 cumBase course with 53 to 22.4 mm size
including stone screening 11.2 mm size
1798.50 337.55 136.29 2272.35 2613.20
Laying water bound macadam with stone
aggregate, stone screening and blinding material
including screening, sorting, spreading to
template and consolidation with power road
roller of 8 to 10 t capacity etc. complete
(payment for stone aggregate, screenings,
kankar, moorum and red bajri etc. to be made
separately) of courses:
10020 cumSub-base with stone aggregate 90 to 45 mm
including stone screening 13.2 mm size.
28.78 404.27 163.14 596.19 685.62
10025 cumBase course with 63 to 45 mm size including
stone screening 13.2 mm size.
39.31 337.55 136.29 513.16 590.13
10030 cumBase course with 53 to 22.4 mm size
including stone screening 11.2 mm size.
39.31 337.55 136.29 513.16 590.13
10035 100 sqmScarifying metalled (water-bound) road
surface including disposal of rubbish, lead
upto 50 m and consolidation of the
aggregate received from scarifying with
power road roller of 8 to 10 t capacity,
complete.
15.99 1025.69 529.47 1571.15 1806.82
10040 mProviding and edging with bricks of class 75
in full brick width and half brick depth
including excavation, refilling and disposal of
surplus earth, lead up to 50 m.
60.48 40.38 - 100.86 115.99
10045 mProviding and edging 70 mm wide, 114 mm
deep to plinth protection with bricks of class
75 including excavation, re-filling and
disposal of surplus earth upto lead of 50 m
and grouting with cement mortar 1:4 with fine
sand, complete.
28.40 11.73 0.71 40.84 46.97
Subgrade11
10005 100 sqmPreparation of subgrade by excavating or
filling with available earth to an average of
225 mm depth, dressing to camber, watering
and consolidating with road roller of 8-10 t
capacity including making good the
undulations etc. and disposal of surplus
earth / bringing earthfrom borrow pits within
a lead of 50 m, complete.
64.63 8125.67 221.37 8411.67 9673.42
10010 100 sqmConsolidation of sub-grade with road roller of
8 to 10t capacity including making good the
undulations, etc.with earth or quarry spoils,
etc. and rerolling the sub-grade, complete.
64.63 21.60 223.02 309.25 355.64
10015 100 cmAdd for compaction of earth work in
embankment under optimum moisture
conditions to give at least 95% of the
maximum dry density (Proctor density)
95.95 797.20 334.12 1227.26 1411.35
26 Asphaltic Base Courses UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1132TOTAL
251
BuildCOST EXTERIOR IMPROVEMENTS
11 Base Courses32
26 Asphaltic Base Courses UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1132TOTAL
Paving, Bitumen And Stone Grit15
10005 sqmProviding surface dressing on new surface
with paving bitumen of grade A-90 / S-90,
using 2.25 kg. of bitumen per sqm with 1.65
cum of stone chippings 13.2 mm nominal
size per 100 sqm of road surface including
consolidation with road roller of 6 to 8 t
capacity etc., complete.
116.33 28.54 12.05 156.92 180.46
10010 sqmProviding surface dressing on new surface in
two coats with bitumen of grade A-90/S-90,
using 1.8 kg. of bitumen per sqm with 1.5
cum of stone chippings 13.2 mm nominal
size per 100 sqm of road surface for first
coat and 1.1 kg. of bitumen per sqm. with
1.00 cum of stone chippings 11.2 mm
nominal size per 100 sqm. or road surface
for second coat, including consolidation of
each coat separately with road roller of 6 to 8
t capacity etc., complete.
152.45 41.18 16.81 210.44 242.01
Providing surface dressing one coat on new
surface with bitumen of specified grade at a rate
of 1.95 kg/ sqm.of surface area with 1.5 cum. of
stone chippings 13.2 mm nominal size per 100
sqm. of road surface including consolidation with
road roller of 6 to 8 t capacity etc., complete :
10015 sqmUsing cut back RC 3 (rapid curing) bitumen,
conforming to IS:217
77.68 26.21 11.12 115.01 132.26
12 Flexible Paving32
16 Asphalt Paving UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1232TOTAL
Asphaltic Concrete Pavement15
Providing and applying tack coat, using hot ,
straight run bitumen of grade 80/100 including
heating the bitumen, spraying the same with
mechanically operated spray unit fitted on
bitumen boiler, cleaning and preparing the
existing road surface, complete, on surfaces :
10005 sqmW.B.M, @ 0.75 kg/sqm 28.95 8.75 0.70 38.40 44.16
10010 sqmBituminous surface @ 0.50 kg/sqm 20.61 8.75 0.70 30.06 34.57
Providing and laying premix bituminous
macadam base course with stone aggregate of
20 mm and down gauge and straight run bitumen
of grade 80/100 @ 4% by weight of total mix
including hot mixing of stone aggregate and
bitumen in hot mix plant, transporting mixed
material and laying mixed material with paver
finisher to the required level and grade, rolling
with road roller of 8 to 10 t capacity to achieve
the specified compaction and density, complete,
of compacted thickness :
10015 cum40 mm 6283.66 100.03 1003.68 7387.37 8495.47
10020 cum50 mm 6283.66 100.03 1003.68 7387.37 8495.47
Providing 20 mm thick premix carpet with 1.8
cum and 0.90 cum of stone chippings of 13.2
mm size and 11.2 mm size respectively per 100
sqm. and 52 kg. and 56 kg. of hot bitumen per
cum. of stone chippings of 13.2 mm and 11.2
mm size respectively including a tack coat with
hot straight run bitumen and consolidation with
road roller of 6 to 8 t capacity etc., complete,
(cost of tack coat not included), of paving asphat
252
BuildCOST UTILITIES
11 Water Utility Distribution Piping33
13 Public Water Utility Distribution
Piping
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1133TOTAL
Water Supply Chamber, Brick
Masonry
50
Constructing brick masonry chambers with class
75 bricks in cement mortar 1:5 with fine sand,
RCC top slab 1:2:4 of avg. thickness 150 mm,
including reinforcement, excavation, refilling, 100
mm thick foundation concrete 1:5:10 with coarse
sand, 12 mm thick inside plastering with cement
mortar 1:3 with coarse sand, finished with a
floating coat of neat cement, and 15 mm thick
outside plastering in cement mortar 1:4 with fine
sand, complete with one brick thick wall, of size :
10005 Each600 x 600 x 750 mm deep inside, with CI
surface box 100 mm top dia., 160 mm
bottom dia. and 180 mm deep inside, with
chained lid.
4534.70 2317.52 96.64 6948.86 7991.19
10010 Each900 x 900 x 1000 mm deep inside, with CI
surface box 100 mm. top dia., 160 mm
bottom dia. and 180 mm deep inside, with
chained lid.
7264.34 3706.11 154.70 11125.15 12793.92
10015 Each1200 x 1200 x 1000 mm deep inside, with CI
surface box 100 mm. top dia., 160 mm
bottom dia. and 180 mm deep inside, with
chained lid.
9077.10 5586.16 188.33 14851.59 17079.33
10020 Each600 x 600 x 750 mm deep inside, with CI
surface box 350 x 350 mm and 165 mm
deep inside, with chained lid, for fire hydrant.
4988.29 2294.73 95.58 7378.59 8485.38
10025 Each600 x 450 x 500 mm, deep inside with CI
double flap surface box 400 x 200 x 200 mm.
inside, with locking arrangement, for water
meter.
4465.29 1731.43 76.82 6273.54 7214.57
Piping, Water Distribution Systems60
Providing, laying, jointing and testing double
flanged ductile iron pipes having screwed
flanges, conforming to IS:8329, including
compressed neoprene washers, galvanised steel
fasteners, complete, excluding trenching and
back filling, of nominal dia.:
10005 m80 mm 2461.66 35.51 - 2497.17 2871.75
10010 m100 mm 4084.83 62.14 - 4146.97 4769.01
10015 m150 mm 4100.27 62.14 - 4162.41 4786.77
10020 m200 mm 6068.31 71.01 - 6139.32 7060.22
10025 m250 mm 7184.25 97.64 - 7281.89 8374.17
10030 m300 mm 9361.57 111.01 - 9472.58 10893.47
10035 m350 mm 11621.66 142.02 - 11763.68 13528.24
10040 m400 mm 15306.41 150.90 - 15457.31 17775.91
10045 m450 mm 18593.51 190.94 - 18784.45 21602.12
10050 m600 mm 30781.34 284.05 - 31065.39 35725.19
Providing, laying, jointing and testing S&S ductile
iron pipes, conforming to IS:8329, with
pre-moulded rubber (IS:5382 and dimensions as
per IS:12820) joints complete, excluding
trenching and back filling, of nominal dia.:
10055 m80 mm 1608.01 35.51 - 1643.52 1890.04
10060 m100 mm 2223.65 39.89 - 2263.54 2603.07
10065 m150 mm 3246.11 62.14 - 3308.25 3804.48
10070 m200 mm 4125.94 71.01 - 4196.95 4826.50
10075 m250 mm 5436.66 97.64 - 5534.30 6364.45
10080 m300 mm 6936.35 111.01 - 7047.36 8104.47
259