The Safety Professionals Guide to Planning and … Safety Professionals Guide to Planning and...
Transcript of The Safety Professionals Guide to Planning and … Safety Professionals Guide to Planning and...
The Safety Professionals Guide to
Planning and Executing Capital
Projects
Steven M. Hochstadt, P.E., CSP
Sr. Environmental, Health & Safety Manager
Bay Area Safety Symposium
American Society of Safety Engineers
March 5, 2014
Introduction
Responsibilities of EHS Managers
Regulatory Compliance
Program Development
Audits & Inspections
Hazard Control
Claims Management
Plan Review - Projects
Safely Planning & Executing Capital Projects 2 March 5, 2014
Definitions
Capital Projects: A long-term investment made in order to build upon, add to or improve on a capital-intensive project. A capital project is any undertaking which requires the use of notable amounts of capital, both financial and labor, to undertake and complete. Capital projects are often defined by their large scale and large cost relative to other investments requiring less planning
and resources. (Investopedia)
Safely Planning & Executing Capital Projects 3 March 5, 2014
Definitions (con’t)
Screening - is the investigation of a great number of something (for instance, potential EHS issues) looking for those with a particular problem or feature.
Capital Projects – Requires investment of >$10M.
Screening Tools – Used to identify
critical EHS aspects or risks
of a project.
Safely Planning & Executing Capital Projects 4 March 5, 2014
Types of Projects
New building construction
Building demolition
Major lab renovations (exhaust,
waste systems, new equipment)
Seismic & safety retrofits (ADA, Code Updates)
Installation, or replacement, of key building systems (fire prevention, alarms, security)
Site improvements (café, fitness, conference)
Safely Planning & Executing Capital Projects 5 March 5, 2014
Project Teams Capital projects are usually delivered using a prescribed process by a project-specific cross functional team of stakeholders, including:
Business unit/end user (Customer) Project Management/Engineering Facilities Planning & Services Risk Management & Compliance Finance Reliability, Validation, QA EHS Consultants & Contractors
Safely Planning & Executing Capital Projects 6 March 5, 2014
Screening Tools EHS screening checklist can vary depending on size
& complexity of project
Small (non-capital) projects may require a quick review of general EHS categories
Capital projects require a more comprehensive review of all EHS aspects & risks
Usually completed by EHS &
Project Manager during Basic
or Conceptual Design Phase.
Safely Planning & Executing Capital Projects 7 March 5, 2014
Use of Screening Checklists
Used to identify various EHS aspects of the project.
Will help Project Manager budget for the EHS items identified.
Will require planning & follow-up by EHS Project Manager to assure proper permits are obtained and compliance achieved.
Used to determine EHS strategy &
plan and for project documentation.
Safely Planning & Executing Capital Projects 8 March 5, 2014
EHS Aspects All projects are evaluated for potential EHS impacts & risks during Conceptual Design including: Fire/Life Safety – fire/gas detection, alarms, egress Physical Safety – electrical, noise, eqpt, ergonomic layout Hazardous Materials – storage & distribution systems Chemical/Industrial Hygiene – lead, asbestos, chemical, bio,
radiation exposures and exhaust ventilation Environmental – hazardous wastes, emissions, soil, GW, SPCC, storm water & wastewater Process Safety – hazard control, eqpt review Sustainability – energy, recycling, refrigerants
Safely Planning & Executing Capital Projects 9 March 5, 2014
You have the List, Now What? Use the aspects identified on the list to:
Determine EHS Strategy – How am I going to mitigate the issues, keep the project on schedule, within budget and obtain all permits?
Are consultants needed? What type? Who?
Is in-house support available (SMEs)?
Which permits are needed? What data is
required?
Which agencies need to be contacted?
Contractor Selection: Skills Required,
Safety Record.
Safely Planning & Executing Capital Projects 10 March 5, 2014
EHS Project Support
Plan Review
Contractor Selection & Audits
Site Inspections
Accident/incident investigations
Site permits & agency inspections
Equipment review & commissioning
Program development & training
Safely Planning & Executing Capital Projects 11 March 5, 2014
Plan Review
Fire code – alarms, pull stations, exits, signage
Gas & fire detection – smoke, O2, NH3, explosion
Safety eqpt – shower/eye wash, first aid, rescue, fire extinguishers, PPE & spill cabinets.
Haz mat & waste storage, classifications
Safety – railings, barriers, signage
Waste collection & treatment
Ergonomics & material handling
Environmental – spill containment
Safely Planning & Executing Capital Projects 12 March 5, 2014
Contractor Selection
Need to do your due diligence
Services available to provide
review criteria……for a fee
IIR, Xmod, OSHA history
Insurance coverage & certificates
IIPP & Written Safety Programs
Organizational Structure, Policies & Staff
Experience on similar projects
Safely Planning & Executing Capital Projects 13 March 5, 2014
Contractor Safety Plan Review
Review their plans & written programs:
Is their IIPP site & project specific?
Are the written programs adequate & applicable to the project?
Does their Emergency Plan address
reasonable contingencies for location?
Do they have proper training & records?
Are inspection records maintained?
Job safety analyses for all hazardous tasks?
Yes, subcontractors must be included!
Safely Planning & Executing Capital Projects 14 March 5, 2014
Written Safety Programs IIPP – project specific, most important
Job Safety Task Analyses & hazard controls
Training Program
Emergency Plan – site specific, first aid, fire, injuries
Hazard Communication with MSDSs on-site
Fall prevention, confined space, PPE,
excavation, ladders/scaffolds, hot work, subs,
LOTO, fire prevention, industrial trucks, injury
reporting, and many more as applicable to project
****Review, and if NOT satisfactory, request revisions, as these written programs are the Contractors “Commitment to Safety”
Safely Planning & Executing Capital Projects 15 March 5, 2014
Inspections Auditing the Contractors “Commitment to Safety”
Review the implementation of their written plans
Check inspection, training, incident & JHA records
Perform site inspection with Contractor’s Safety Rep
Observe behaviors, as well look for hazards
Use checklist for documentation & forward to Safety Rep
Request corrective actions & follow-up
Provide praise as needed, as construction sites
are full of potential hazards & contractors
have key investment in project’s safety.
Safely Planning & Executing Capital Projects 16 March 5, 2014
Inspection Checklist Must meet Construction Safety Orders: 29 CFR 1926 & CCR Title 8, Subchapter 4
Look for the following, indicate S, U or N/A: PPE, what’s required & are they wearing it? Emergency/first aid – eye wash, first aid kits, fire
extinguishers, exits marked & not blocked, postings with emergency phone #s
Hazardous materials – MSDSs, storage, labels, flam liquids, spill eqpt, compressed gases, gas monitoring
Ladders, stairs, scaffolds, floor openings, power tools Permits (site & regulatory) – excavations, hot work, lifts,
industrial trucks, confined spaces Electrical – GCFI, grounding, cords, LOTO, panel labeling Housekeeping – Not a clean room. Clear egress. ID hazards.
Safely Planning & Executing Capital Projects 17 March 5, 2014
Construction Safety Training The OSHA Outreach Training Program:
Training on the recognition, avoidance, abatement, and prevention of safety and health hazards in the construction industry.
Voluntary program, does not meet training requirements for any OSHA standards.
Reviews key sections of CFR. Delivered by OSHA-authorized trainers.
The 10-hour class is intended for entry level workers,
The 30-hour class is more appropriate for supervisors or workers with some safety responsibility.
Classes offered at ASSE PDCs & NSC Congresses http://www.osha.gov/dte/outreach/construction/index.html
Safely Planning & Executing Capital Projects 18 March 5, 2014
Consultants
Why Do you Need Them?
How Do You Select Them?
Preparing RFQ/SOW & Reviewing Quotes .
Who’s Doing the Work?
Do’s & Don’ts.
Checking on Progress.
Deliverables.
YOU ARE Responsible for your Consultants!
Safely Planning & Executing Capital Projects 19 March 5, 2014
The Safety Professionals Guide to Planning and Executing Capital
Projects
Case Study # 1
Construction of a New Research Building
Safely Planning & Executing Capital Projects 20 March 5, 2014
EHS Screening Checklist Project Description
Project Title Location Project Manager Project Team Members Funding Approval Estimated Start & Finish dates Brief Description – Planned use, square
footage, acreage, number of floors, etc.
Safely Planning & Executing Capital Projects 21 March 5, 2014
Project Scope Are contractors needed? Is GC selected? Yes
GC TBD. Several sub contactors to be used.
Is demolition needed for existing structures? NA.
Is building or space to be remodeled? NA.
Will there be soil excavation? Yes. Soil to be tested prior to disposal.
Will fire alarms, suppression system or walls be impaired? NA. New building.
Will new property be purchased or leased?
Yes. Property purchased. Check prior usage. Phase I
ESA? Safely Planning & Executing Capital Projects 22 March 5, 2014
Hazardous Materials Will hazardous materials be used during project? Yes,
as needed for construction. HMBP submitted by GC.
Will hazardous materials be added after project? Yes, as needed for research. HMBP submitted by EHS.
Will hazardous wastes be generated during or after project? Yes. EPA Generator ID# for research wastes.
Will project change hazardous materials used in existing processes? NA.
Safely Planning & Executing Capital Projects 23 March 5, 2014
Equipment
Will existing utility systems (drains, piping, electrical, HVAC) be altered? No. New building.
Will removing existing equipment require hazardous waste disposal? NA.
Is new equipment added for exposure control or haz mat containment? Yes. Exhaust vents, hoods.
Will new eqpt added create hazards? Yes. Evaluate.
Will sewer or storm systems be modified? Yes. New sewer connections to be made.
Will permanent safety equipment be added? Yes. Fire extinguishers, first aid kits, shower/eye wash, AEDs.
Safely Planning & Executing Capital Projects 24 March 5, 2014
Physical Hazards Will new energy sources be involved? Yes. Eqpt &
processes require steam, heat, pressure & electricity. LOTO.
Will there be hot work (welding, brazing, grinding)? Yes. Hot work permit required.
Off hours construction, noise, dust concerns? Yes. As typical in construction. Few neighbors in area. Use controls.
Confined space entry required? Yes. Excavations.
Fall protection needed? Yes. Unprotected elevations.
Overhead work? Yes. Cranes, lifts & ladders.
Will changes be made to exits or egress routes?
NA. New building.
Safely Planning & Executing Capital Projects 25 March 5, 2014
Environmental
Will there be discharge of industrial wastewater? Yes.
Use process knowledge to characterize discharge. Apply for permit.
Will there be air emissions (VOCs, Toxics)? Yes. Review eqpt specs. Hire air consultant. Apply for permits from AQMD.
Will there be generators or boilers? Yes. Special permitting & monitoring requirements. Source testing required per AQMD.
Will there be haz wastes requiring disposal? Yes. Typical lab wastes. Apply for EPA ID #. Hire waste handling & disposal contractor.
Will there be haz mat storage in tanks? Yes. Gases, fuel & treatment chemicals. Add to HMBP, SPCC.
Will haz mats be handled near storm drains? Yes. Need containment, spill control plan (SPCC) & SWPP.
Will lead or asbestos be disturbed? NA. New construction.
Safely Planning & Executing Capital Projects 26 March 5, 2014
EHS Issues
Hazardous Materials & Waste Permits
HMBP filed with County, multiple inspections
Secondary containment required in utilities area
Typical lab quantities & hazard classes (FL, CL, NFG, Corr)
ABTs for fuel and cryogenic liquid storage
Waste storage room with secondary containment, gas detectors, alarms, emergency eqpt
EPA Generators ID# obtained for site
Emergency Response Plan prepared & Team formed
Waste collections & inspections performed by contractor
Safely Planning & Executing Capital Projects 27 March 5, 2014
EHS Issues Waste Water Permit
Strict discharge limits due to Regional GW issue
Concerns with pH, salinity, minerals, temp, flow
Process, sanitary & industrial waters modeled for discharge, using various conditions
Treatability study to select neutralization system
Application submitted, amended, negotiated
Interim permit granted. Flow limitations.
Extended sampling program. Flow meter issues.
Safely Planning & Executing Capital Projects 28 March 5, 2014
EHS Issues Air Permits
Boilers, heaters, generators
Consultant used to file permit applications
Risk Assessment & Air Dispersion Model - contours
Initial & Annual Source Testing (CO, NOX, O2, CO2)
AQMD site inspection – during source testing
Permit issued with conditions
Annual reporting & testing (operating hours, gas use)
Safely Planning & Executing Capital Projects 29 March 5, 2014
EHS Issues SPPC & SWPP
Oil and fuel tanks present (>55 gal)
Spill prevention plan written (CA – APSA)
Site inspection & training programs
Fueling, drainage & spill procedures
Shut off valves & covers for storm drains
Catchment drains at loading docks
Storm water runoff to private basin
No permit reqd. Lease agreement controls (BMPs)
Safely Planning & Executing Capital Projects 30 March 5, 2014
The Safety Professionals Guide to Planning and Executing Capital
Projects Case Study # 2
Demolition of Old Research Building
Safely Planning & Executing Capital Projects 31 March 5, 2014
EHS Screening Checklist Project Scope
Are contractors needed? Is GC selected? Yes. GC TBD. Several sub contractors to be used. Support selection process.
Is demolition needed for existing structures? Yes. Structures & utilities to be demolished. Select demo contactor.
Is building or space to be remodeled? Yes. Site to be used for parking lot.
Will there be soil excavation? Yes. Test soil prior to disposal.
Will fire alarms, suppression system or walls be impaired? Yes. At some point, system to be disconnected.
Will new property be purchased or leased? NA.
Safely Planning & Executing Capital Projects 32 March 5, 2014
Hazardous Materials Will hazardous materials be used during
project? Yes. Labs & eqpt to be decontaminated using various cleaning solutions.
Will hazardous materials be added after project? No.
Will hazardous wastes be generated during or after project? Yes. Decontamination wash waters, lab wastes and surplus chemicals to be collected for off-site hazardous waste disposal.
Will project change hazardous materials used in existing processes? NA.
Safely Planning & Executing Capital Projects 33 March 5, 2014
Equipment
Will existing utility or eqpt systems (drains, piping, electrical, HVAC) altered? Yes. All utilities to be removed.
Will removing existing equipment require hazard waste disposal? Yes. All equipment to be decontaminated.
Is new equipment added for exposure control or hazardous materials containment? NA.
Will new eqpt added create hazards? NA.
Will sewer or storm systems be modified? Yes. Cap.
Will permanent safety equipment be added? NA.
Safely Planning & Executing Capital Projects 34 March 5, 2014
Physical Hazards Will new energy sources be involved? No.
Will there be hot work (welding, brazing, grinding)? Yes. Cutting. Hot work permit required.
Off hours construction, noise, dust concerns? Yes. Adjacent building occupied. Controls to be implemented.
Confined space entry required? Yes. Trenches. Non-permit.
Fall protection needed? Yes. Eqpt required while on roof.
Overhead work? Yes. Cranes, lifts & ladders.
Will changes be made to exits or egress routes? Yes. Changes made during various phases of demolition.
Safely Planning & Executing Capital Projects 35 March 5, 2014
Environmental Will there be discharge of industrial wastewater? No. Terminate
existing discharge permit.
Will there be air emissions (VOCs, Toxics)? No. Asbestos.
Will there be generators or boilers? Yes. Clean, remove & dispose. Terminate air permits.
Will there be hazardous wastes requiring disposal? Yes. Decontamination wastes & lab surplus chemicals to be collected & disposed.
Will there be haz mat storage in tanks? Yes. Drain, clean & remove above ground fuel tanks.
Will haz mats be handled near storm drains? Yes. Cover drains. Prepare storm water plan for construction project.
Will lead or asbestos be disturbed? Yes. Hire licensed contractors to sample and test, and to remove and dispose. File permit.
Safely Planning & Executing Capital Projects 36 March 5, 2014
EHS Issues
Haz Mat Decontamination
SOW. Quotes from qualified contractors. Decontamination and Health & Safety Plans prepared. All eqpt drained & surfaces to be decontaminated. Hoods & ducts cleaned or removed as hazardous waste. Chemical & biological hazards. Surplus chemicals & contaminated supplies collected. Decontamination rinse waters collected for disposal. Wipe samples taken for analysis (pH, CAM 17 metals). Site inspections by CUPA. Closure report sent to CUPA. Permits retired.
Safely Planning & Executing Capital Projects 37 March 5, 2014
EHS Issues Asbestos & Lead
Present in older buildings (pre 1970s). Must be abated prior to demolition permit issued. Survey performed, samples taken by certified sampling
contractor (CAC). Analysis at approved lab. Abatement report with results, locations & estimated
quantities. Bid documents for abatement contractor. Abatement by licensed asbestos removal contractor.
Permit required. Warning signs posted at site. PPE. Containment required.
Disposal at Class 1 or 2 landfill. Approved hauler. Manifest to be included in final report.
Safely Planning & Executing Capital Projects 38 March 5, 2014
EHS Issues Soil Sampling
Soil data needed due to excavation, disposal & worker
exposure needs, and to determine prior spills.
Required for site HMBP closure.
Potential sources – fuel tanks, lab waste discharge.
Contractor with subsurface sampling experience hired.
Borings made around all sides of bldg. Samples at multiple depths. Analyzed for VOCs, metals, etc.
No contamination found. No further action needed.
Report provided to CUPA. Safely Planning & Executing Capital Projects 39 March 5, 2014
EHS Issues
Equipment Disposal
Much eqpt, tools & supplies left as surplus. If contaminated, clean, or dispose as
hazardous waste. Tools & supplies distributed to depts & ee’s. Larger eqpt gets sold to brokers, dealers. Many require certificate of decontamination. Sales contracts reviewed by Legal Dept. Buyer to transport. Assure eqpt is “safe off”.
Safely Planning & Executing Capital Projects 40 March 5, 2014
The Safety Professionals Guide to Planning and Executing Capital
Projects Conclusions
EHS has a key role in Capital Projects. EHS is involved with Project Team early in design. EHS evaluates risks by “screening” project. EHS develops plan to mitigate risks. EHS obtains all permits & works with all agencies
& inspectors. EHS assists with project turnover. EHS works with the Project Team & all contractors
to assure project’s safety & success.
Safely Planning & Executing Capital Projects 41 March 5, 2014