The Project Workplan and Budget

9
The Project Workplan and Budget Inception Workshop and the First Steering Committee Meeting of the UNEP/GEF Project Piloting Integrated Processes and Approaches to Facilitate National Reporting to Rio Conventions(FNR_Rio) 9-11 February 2010 , UNEP-WCMC, Cambridge, UK Asghar M. FAZEL Global Project Coordinator

description

Inception Workshop and the First Steering Committee Meeting of the UNEP/GEF Project “ Piloting Integrated Processes and Approaches to Facilitate National Reporting to Rio Conventions ” ( FNR_Rio ) 9-11 February 2010 , UNEP-WCMC, Cambridge, UK. The Project Workplan and Budget. Asghar M. FAZEL - PowerPoint PPT Presentation

Transcript of The Project Workplan and Budget

Page 1: The Project Workplan and Budget

The Project Workplan and

Budget

Inception Workshop and the First Steering Committee Meeting of the UNEP/GEF

Project “Piloting Integrated Processes and Approaches to Facilitate National Reporting to

Rio Conventions” (FNR_Rio)

9-11 February 2010 , UNEP-WCMC, Cambridge, UK

Asghar M. FAZELGlobal Project Coordinator

Page 2: The Project Workplan and Budget

Component 1Component 1 Situational Analysis and Reporting Process Design 

Output 1.1: Inventory and analysis report of reporting requirements

Situation analysis, report design Project technical and administrative support at nationa and International levels IC support for situation analysis, report design

  

Output 1.2: National-level analyses and recommendations for data management

6 national studies, incl. country-specific recommendations  6 NCs for national studies, incl. country-specific recommendations

 

National Project Inception meetings and Stakeholder input meeting Project Inception meeting/workshop and Stakeholder input meeting (budgeted with the 1st TWG)  

Output 1.3: Manual produced on piloting integrated reporting

Synthesis of outputs and development of global recommendations   IC input for Synthesis of outputs and development of global recommendationsIC supporting national manual development 

Develop pilot manual on integrated reporting  6 NCs to Develop 6 national manuals on integrated reporting in pilot countriesPreparation and dissemination of the 6 National Manuals

2

Page 3: The Project Workplan and Budget

Component 2

Component 2 Implementation of Integrated Reporting Processes and Experimenting Options for reports design

Output 2.1: Strengthened institutional frameworks for reporting  

Develop and implement country-specific implementations of global recommendations

 6 NCs to support country-specific implementations of global recommendations

Compile feedback and evaluate for each country  IC input for Compiling feedback and evaluate for each country

Output 2.2: Strengthened national systems for monitoring, reporting   

Develop and implement country-specific implementations of global recommendations

 6 NCs to support country-specific implementations

Compile feedback and evaluate for each country   IC input for Compiling feedback and evaluate for each country

Output 2.3: Enhanced capacity for data collection and analysis   

Needs analysis & approach developed for each country (technology and training)    IC support to 6 NCs to develop Needs analysis & approach developed for each country (training and technology)

Technology website registration and launching  

Purchasing the technology needs

Training developed and delivered  Delivering trainings

                       

Output 2.4: Reporting quality assessed

Reports for each country on the quality of reporting to each convention 6 NCs to draft Reports for each country on the quality of reporting to each convention Preparation and dissemination of the 6 national reports

Global synthesis of pilot country experience  IC input for Global synthesis of pilot country experience3

Page 4: The Project Workplan and Budget

Component 3

Component 3 Sharing of Experience and Up scaling Opportunities

 

Output 3.1: Technical Working Group meetings  

1st workshop (3-4 days)  6 national workshops as the Inception workshops (one days each) + National Steerin Committee meetings

IC support to the 1st TWG workshop + 1st PSC meeting (max. 2 days) 

2nd workshop (2-3 days) 6 national review workshops (one days each) + National Steerin Committee meetings IC support to the 2nd TWG workshop +PSC meeting (max. 2 days)

3rd workshop (2-3 days)  6 national workshops (one days each) + National Steerin Committee meetings IC support to the 3rd TWG workshop + final PSC meeting (max. 2 days)

Output 3.2: International events to share experience

Publications

Preparation, facilitation and report Preparation and dissemination of the project reports 

Preparation and dissemination of the project reports

IC support to the preparation of the project reports3 COP side-events

1st Rio Convention side-event (CBD?) 

1st Rio Convention side-events (CCD) 

1st Rio Convention side-event (UNFCCC)

4

Page 5: The Project Workplan and Budget

Component 4 (admin)

M&E (see Appendix 7) Secretariat set-up formation of 6 National teams Appontmaint of 6 NCs and 6 NPAs Recruitment of IC Financial planning and management Drafting and submitting workplans and reports Organising meetings, workshops and side events Travels/missions website (maintenance and updating )

5

Page 6: The Project Workplan and Budget

2010 Annual Work Plan

Next presentation

6

Page 7: The Project Workplan and Budget

Project Budget (US$)

ComponentComponent GEF 2010GEF 2010 GEF 2011GEF 2011 GEF 2012GEF 2012 GEF total

Co-Co-financingfinancing

Total Total

C1 45,000 22,500 28,600 96,100 117,600 213,700

C2 99,400 222,000 164,000 485,400 415,000 900,400

C3 97,500 60,000 66,000 223,500 268,280 491,780

M&E 0 12,000 23,000 35,000 0 35,000

Total 241,900 316,500 281,600 840,000840,000 800,880 1,640,881,640,8800

7

Page 8: The Project Workplan and Budget

Key questions

Special national circumstances? Verification of the need for any changes?

Activities Timeline Budget

8

Page 9: The Project Workplan and Budget

Thank You

Inception Workshop and the First Steering Committee Meeting of the UNEP/GEF

Project “Piloting Integrated Processes and Approaches to Facilitate National Reporting to

Rio Conventions” (FNR_Rio)

9-11 February 2010 , UNEP-WCMC, Cambridge, UK

[email protected]