PRIMROSE EAST BRIDGE
Implementation of Folded Plate Technology & Geosynthetic Reinforced Soil-Integrated
Bridge System
2016 Concrete Paving WorkshopJason Volz
NDOR Construction
![Page 2: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/2.jpg)
Primrose BridgePrimrose East Bridge:
• Constructed Fall 2014
• On a county road east of Primrose
• Contractor: Simon Contractors
• Designer: NDOR Bridge Division
![Page 3: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/3.jpg)
Primrose BridgeNew Technologies:
• GRS Abutment• Folded Plate
Girder• Ultra-High
Performance Concrete
![Page 4: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/4.jpg)
Geosynthetic Reinforced Soil (GRS) Integrated Abutment:
• Accelerated Construction
• No Crane/Pile Hammer
• No Specialized Labor
![Page 5: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/5.jpg)
Folded Plate Girder:
• Developed at UNL
• Light Weight
![Page 6: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/6.jpg)
Ultra High Performance Concrete:
• 21,000 psi at 28-days
• Narrow Joints• Minimal
Shrinkage
![Page 7: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/7.jpg)
Primrose BridgeOther Innovative Features:
• Pre-Fabricated Bridge Elements
• Accelerated Bridge Construction (ABC)
![Page 8: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/8.jpg)
DECK CONSTRUCTION:
• Girders Delivered July 1st
• Offsite location used for casting deck
![Page 9: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/9.jpg)
GIRDER DELIVERY• Elevation and
Layout of Girders Matched Bridge
![Page 10: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/10.jpg)
SHORED CONSTRUCTION• No Camber in
Girders• Required
Continuous Unyielding Support
![Page 11: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/11.jpg)
DECK FORMING• Formed and
poured all at once
• Prevented problems with bar interference
![Page 12: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/12.jpg)
DECK POUR• 47BD-4000• White Pigment/
Wet Burlap Cure
![Page 13: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/13.jpg)
8” DECK JOINT• Required
exposed aggregate finish.
• Forms treated with set-retarder
• Power washed 12-24 hours after pour
![Page 14: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/14.jpg)
LIFTING DEVICES• Orientation
required two cranes
![Page 15: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/15.jpg)
BRIDGE SITE• Large Drainage
Area • Flooding
Overtopped Road
• Road Closed for Construction Sept 15
![Page 16: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/16.jpg)
GRS ABUTMENT • 2’ Reinforced
Soil Foundation• 13’ GRS
Abutment• 4’ Integrated
Approach
![Page 17: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/17.jpg)
EXCAVATION• Unsuitable
material removed and replaced with granular fill
• Layout of delivered materials
![Page 18: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/18.jpg)
REINFORCED FOUNDATION• 2 ft thick
“Burrito” beneath abutment and wings
• Extra layer of fabric on abutment side
![Page 19: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/19.jpg)
LEVELING COURSE• Critical to
maintaining wall alignment
• <0.5” of granular to help level
![Page 20: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/20.jpg)
GRS Abutment• Step 1: Place
block
![Page 21: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/21.jpg)
GRS Abutment• Step 1: Place
block• Step 2: Place
Select Granular Backfill and compact
![Page 22: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/22.jpg)
GRS Abutment• Step 1: Place
block• Step 2: Place
Select Granular Backfill and compact
• Step 3: Place Geosynthetic Fabric
![Page 23: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/23.jpg)
CMU BLOCK WALL• Red line at
berm elevation for scour monitoring
• Hollow vs solid block
• Split face block
![Page 24: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/24.jpg)
![Page 25: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/25.jpg)
LOADING GIRDERS • 4 -Flatbed
Trucks• 2-Cranes
![Page 26: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/26.jpg)
SETTING GIRDERS• No rebar
interference problems
![Page 27: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/27.jpg)
![Page 28: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/28.jpg)
UHPC EQUIPMENT• 3.5 cuft mixers• Shipped to site
in advance
![Page 29: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/29.jpg)
UHPC QUALITY CONTROL• All ingredients
are measured out
• Every batch is tested
![Page 30: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/30.jpg)
UHPC JOINT FORMING• Formed an 1/8”
high• Chimneys at 8’
spacing
![Page 31: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/31.jpg)
![Page 32: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/32.jpg)
UHPC JOINT GRINDING• Grind 1/8’” to
remove voids• Hand grinders
vs bump grinder
![Page 33: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/33.jpg)
VOIDS IN UHPC• Filled with non-
cement grout
![Page 34: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/34.jpg)
![Page 35: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/35.jpg)
WATER TESTING OF JOINTS• Joints were
water tight, no additional sealing required
![Page 36: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/36.jpg)
OPEN TO TRAFFIC• November 19th
![Page 37: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/37.jpg)
![Page 38: The Primrose East Bridge](https://reader035.fdocuments.us/reader035/viewer/2022062904/58786cbd1a28ab497b8b5379/html5/thumbnails/38.jpg)
Special ThanksSimon Contractors:
• Dale Burkhead –Project Manager• Sid Smith – Project Superintendent
NDOR District 3• Steve Trosper – Project Manager• Monty Koch- Project Inspector
NDOR Bridge• Fouad Jaber – Asst. State Bridge Engineer• Steve Ferguson- Designer
Boone County• Darrel Thorin – Highway Superintendent