W3 Test Automation
5/1/2013 11:30:00 AM
The Pathologies of Failed Test
Automation Projects
Presented by:
Michael Stahl
Intel
Brought to you by:
340 Corporate Way, Suite 300, Orange Park, FL 32073
888-268-8770 ∙ 904-278-0524 ∙ [email protected] ∙ www.sqe.com
Michael Stahl
Michael Stahl is a software validation architect at Intel, working with a team that validates Intel's graphics hardware drivers. In this role, Michael defines testing strategies and work methodologies for test teams, and tests part of the product himself - the work he enjoys most. As a twenty-two year veteran and senior engineer, he has been witness to what works - and what doesn’t - in test strategies, communications, and automation. An avid teacher, Michael enjoys sharing his observations with others. Contact Michael at [email protected] and review previous conference presentations on his website testprincipia.com.
Based, in part, on work done with Alon Linetzki, Best Testing (www.best-testing.com)
The Pathologies of failed
Test Automation Projects
Michael Stahl, Intel Apr 2013
© Michael Stahl, 2013, all rights reserved
• Automation failure patterns
• What can we do?
• Summary
On the Menu… 2
Based, in part, on work done with Alon Linetzki, Best Testing (www.best-testing.com)
© Michael Stahl, 2013, all rights reserved
Disclaimers
Names and brands referenced herein may be claimed as the property of
third parties
The views expressed in this presentation are solely my own, and do not in any manner represent the views of my employer
Information in this presentation is provided “AS IS” without any warranties or representations of any kind
© Michael Stahl, 2013, all rights reserved
Once upon a time…
A common automation story… 4
Mr. Otto Mate Cool!
Can you make it…
Otto’s Team
I can automate my work!...
© Michael Stahl, 2013, all rights reserved
5
Mr. Otto Mate
Perfect!
Can you add…
Otto’s Team
Piece of cake!
Mr. Mann a. Ger
What a wonderful
world!...
A common automation story…
© Michael Stahl, 2013, all rights reserved
6
Mr. Otto Mate
Otto! The
last release
fails!... Otto’s Team
Arggghhh! Fix Fix Fix
Mr. Mann a. Ger
Makes sense… Sir! I need time! I need help!
… and mates
A common automation story…
© Michael Stahl, 2013, all rights reserved
7
Mr. Otto Mate … and mates
… and mates
… and mates
A common automation story…
© Michael Stahl, 2013, all rights reserved
… and mates
… and mates
8
Mr. Oto Mate … and mates
Let’s REDESIGN!!!
#$&@***!!!
Mr. Mann a. Ger
A common automation story…
© Michael Stahl, 2013, all rights reserved
A pattern emerges…
9
© Michael Stahl, 2013, all rights reserved
Pattern #1: Mushrooming
© Michael Stahl, 2013, all rights reserved
11
Stage 1 – Small & Local
Single User / Developer
Simple Tool
A pattern…
© Michael Stahl, 2013, all rights reserved
Stage 2 – Generalization
12 12
Multiple Users / Single Developer
Enhanced Tool
A pattern…
© Michael Stahl, 2013, all rights reserved
13 13
A pattern…
Multiple Users &
Developers
Complicated Tool
Stage 3 – Staffing
© Michael Stahl, 2013, all rights reserved
14 14
A pattern…
Test Case
Management
Multiple Users &
Developers
Stage 4 – Non-core features
© Michael Stahl, 2013, all rights reserved
15 15
A pattern…
Stage 5 – Overload
Arghhh!
© Michael Stahl, 2013, all rights reserved
Pattern #2: The Competition
16
© Michael Stahl, 2013, all rights reserved
Team B
Pattern #2 – The Competition (ver. 1) 17
Team A
© Michael Stahl, 2013, all rights reserved
Team B
Pattern #2 – The Competition (ver. 2) 18
Team A
Team C
Team D !!!
© Michael Stahl, 2013, all rights reserved
Team B
Pattern #2 – The Competition (ver. 3) 19
Team A
Team C
Team D
!!!
!!!
!!! …
…
…
© Michael Stahl, 2013, all rights reserved
Pattern #3: The Night Run Fallacy
© Michael Stahl, 2013, all rights reserved
Pattern #3 – The Night Run Fallacy 21
© Michael Stahl, 2013, all rights reserved
Pattern #3 – The Night Run Fallacy 22
Night Time
Test Time
© Michael Stahl, 2013, all rights reserved
Pattern #3 – The Night Run Fallacy 23
Add a snapshot – or a movie snippet – of PAVE
Corporate Truism:
It’s easier to get budget for machines than for more testers
© Michael Stahl, 2013, all rights reserved
Pattern #3 – The Night Run Fallacy 24
Add a snapshot – or a movie snippet – of PAVE
© Michael Stahl, 2013, all rights reserved
Pattern #3 – The Night Run Fallacy 25
Test Automation Truism:
Machines create work for more testers
© Michael Stahl, 2013, all rights reserved
The Tragedy of the Commons
multiple individuals…
will ultimately deplete a shared limited resource…
even when it is not in their long-term interest
Garrett Hardin, Science, 1968
© Michael Stahl, 2013, all rights reserved
Pattern #4: Going for the Numbers
© Michael Stahl, 2013, all rights reserved
28
© Michael Stahl, 2013, all rights reserved
29
Pattern #5 – Going for the Numbers
© Michael Stahl, 2013, all rights reserved
Robustness is Invisible
30
Pattern #4 – Going for the Numbers
© Michael Stahl, 2013, all rights reserved
Pattern #5: The Magician Apprentice Syndrome
© Michael Stahl, 2013, all rights reserved
Pattern# 5 – The Magician Apprentice 32
© Michael Stahl, 2013, all rights reserved
33
Recap: The Patterns
Mushrooming
The Competition
The Night time Fallacy
Going for the Numbers
The Magician Apprentice
© Michael Stahl, 2013, all rights reserved
So... 34
What can we do?
© Michael Stahl, 2013, all rights reserved
Are the patterns… 35
Unavoidable ??
© Michael Stahl, 2013, all rights reserved
Counter measures 36
© Michael Stahl, 2013, all rights reserved
Mushrooming 37
© Michael Stahl, 2013, all rights reserved
How to use this information?
GPS Locate the stage you are at
Get directions for the way out
Map
Start right and avoid
the wrong turns
38
Alert Signals & Counter Measures
© Michael Stahl, 2013, all rights reserved
Alert Signals 39
© Michael Stahl, 2013, all rights reserved
40
Alert Signals
© Michael Stahl, 2013, all rights reserved
Failing the project
Failing the project
Failing the project
Failing the project
Failing the project
41
Alert Signals
© Michael Stahl, 2013, all rights reserved
Single feature test tool?
The creator is the user?
“Skunk works”?
Key words: “Tool”
“Utility”
42
Alert Signals: Stage 1 Small, local, feature-centered
© Michael Stahl, 2013, all rights reserved
Ensure the following… and relax:
Code control
Documentation User Manual (Usage line…)
“Green” in the code
High level design
43
Counter Measures: Stage 1 Small, local, feature-centered
© Michael Stahl, 2013, all rights reserved
Additional features?
Multiple users?
Automation web site?
>25% of the tester’s time?
Key words: “Use by other testers”
“Common Libraries”
44
Alert Signals: Stage 2 Generalization
© Michael Stahl, 2013, all rights reserved
45
Counter Measures: Stage 2 Generalization
“The hardest part of building a software system is deciding
precisely what to build... No other part of the work so cripples
the resulting system if done wrong. No other part is more
difficult to rectify later” - Fred P. Brooks (author of “The Mythical Man-Month”)
© Michael Stahl, 2013, all rights reserved
Stage 1 measures
Strategy
Architecture
Lightweight PM Version control
Scope control
Bugs & Requests database
46
Counter Measures: Stage 2 Generalization
© Michael Stahl, 2013, all rights reserved
Alert Signals: Stage 3
Requests for additional heads?
Automation F2F?
Tool-related delays in execution?
Key words: “Tool Owner”; “Automation team”
“Framework”; “Infrastructure”
“Roll back”
“Bug fix release”
47 Institutionalization and staffing
© Michael Stahl, 2013, all rights reserved
48 48
© Michael Stahl, 2013, all rights reserved
Stage 1, 2 counter measures
Management level decision time Programming language
Framework focus
Code and release management
Acceptance tests
Skillset development
Metrics
49 Institutionalization and staffing
Counter Measures: Stage 3
© Michael Stahl, 2013, all rights reserved
Counter Measures: Stage 3
Metrics suggestions
Automation framework quality Number of false fails
Framework’s test results; Bug trends
ROI Number of runs
Invested effort by type (new,
maintenance, rewrite)
Number of bugs found by Automation (?)
50 Institutionalization and staffing
© Michael Stahl, 2013, all rights reserved
Generic features?
Test log wading?
False fails?
Key words: “test suite / cycle generation”
“robustness enhancement”
“setup issues”
51
Alert Signals: Stage 4 Change of focus: Technology Management
© Michael Stahl, 2013, all rights reserved
Stage 1, 2, 3 counter measures
Build VS Buy
Re-architect Core / Non-Core
Solid infrastructure
Influence upstream Testability hooks
Design for Test (automation)
52
Counter Measures: Stage 4 Change of focus: Technology Management
© Michael Stahl, 2013, all rights reserved
Stage 4 – Non-core features
Build VS Buy?
(hint: Buy)
See: http://www.stickyminds.com/s.asp?F=S17601_COL_2
Counter Measures: Stage 4
© Michael Stahl, 2013, all rights reserved
Build (VS Buy) if… Competitive edge
Existing expertize
Core competency
Cheaper; Faster
Good use of resources
Acceptable risk
Long term support
54
Counter Measures: Stage 4 Change of focus: Technology Management
Main source: Allen Eskelin http://www.informit.com/articles/article.aspx?p=21775
© Michael Stahl, 2013, all rights reserved
Maintenance & logistics overload?
Limitations overplay?
Loss of credibility?
Stage 1 initiatives?
Key words “Did it fail in manual test?”
“Architecture limitation”
“refactoring”; “redesign”
“…I can write a small program…”
55
Alert Signals: Stage 5 Maintenance overload; Re-design
© Michael Stahl, 2013, all rights reserved
Loss of credibility
56
Alert Signals: Stage 5 Maintenance overload; Re-design
© Michael Stahl, 2013, all rights reserved
Options:
Continue…
Give up problematic areas
Partial return to Stage 1
“We value Robustness over New Features”
Prepare for re-design – with a new map...
57
Counter Measures: Stage 5 Maintenance overload; Re-design
© Michael Stahl, 2013, all rights reserved
GPS
Locate the stage you are at
Get directions for the way out
Be alert for Alerts
Identify your stage
Analyze your situation
Implement Counter
Measures
How to Use this information? 58
© Michael Stahl, 2013, all rights reserved
Plan your trip
Be alert for Alerts
Analyze your situation
Implement Counter
Measures
How to Use this information? 59
Map
Start right and avoid
the wrong turns
© Michael Stahl, 2013, all rights reserved
The Competition 60
© Michael Stahl, 2013, all rights reserved
Pattern #2 – The Competition (ver. 1) 61
Salvageable up to stage 2
Stage 3 and up: Merge the teams
EOL both tools
Start a 3rd
© Michael Stahl, 2013, all rights reserved
Pattern #2 – The Competition (ver. 2) 62
Plugin Architecture
© Michael Stahl, 2013, all rights reserved
Pattern #2 – The Competition (ver. 3) 63
Fix the main problem
Accept, encourage Stage 1 stuff…
Maintaining vigil:
Avoid ver.1 pattern
© Michael Stahl, 2013, all rights reserved
The Night Run Fallacy 64
© Michael Stahl, 2013, all rights reserved
Pattern #3 – The Night Run Fallacy 65
Never forget test time, test efficiency
Balance test skills VS automation skills
Allocate machines or machine time
65
65
65
© Michael Stahl, 2013, all rights reserved
Going for the Numbers 66
© Michael Stahl, 2013, all rights reserved
Pattern #4 – Going for the Numbers 67
Change how you count “Done”
© Michael Stahl, 2013, all rights reserved
The Magician Apprentice Syndrome 68
© Michael Stahl, 2013, all rights reserved
Pattern# 6 – The Magician Apprentice 69
http://www.youtube.com/watch?v=zlnz1rSJj7Y
© Michael Stahl, 2013, all rights reserved
Pattern# 6 – The Magician Apprentice 70
Automation should not necessarily mimic humans…
… it should get the job done
© Michael Stahl, 2013, all rights reserved
Pattern# 6 – The Magician Apprentice 71
http://www.youtube.com/watch?v=qDVYIT85ntg
© Michael Stahl, 2013, all rights reserved
Pattern# 5 – The Magician Apprentice 72
Holistic approach VS “test after test”
Re-think, re-strategize, re-evaluate before automating
Identify Actions, Keywords (KDT)
© Michael Stahl, 2013, all rights reserved
Summary 73
© Michael Stahl, 2013, all rights reserved
74
The Patterns
Mushrooming
The Competition
The Night time Fallacy
Going for the Numbers
The Magician Apprentice
© Michael Stahl, 2013, all rights reserved
The patterns are pervasive
Almost inevitable
Awareness is key (engineers; managers)
Driven by organizational and human nature
The solution is only partially technical
75
Summary
© Michael Stahl, 2013, all rights reserved
Thank You!
Questions time…
www.testprincipia.com