The Ohio Department of Transportation 1
I-280 Trench Project Public MeetingMonday, October 20, 2008
Ted Strickland, Ohio Governor James Beasley, P.E./P.S. ODOT Director
David R. Dysard, ODOT District Two Deputy Director
ODOT I-475 Salisbury
Interchange Modification
Presented by:Michael T. Gramza
Theresa PollickPublic Information Officer
2
Presented by:David R. Dysard, AICP
District Two Deputy Director
Michael T. Gramza, P.E., VGCS Project Manager
John CrandallCo-Chairman, Tribute Planning Committee
I-280 Trench Project Public Meeting
I-280 Trench Project Agenda
• Trench Project Description• Schedule and Traffic Impacts• Tribute Park Update with VGCS Tribute Committee
The Ohio Department of Transportation 3
I-280 Trench ProjectOverview
• Realignment of Front and Summit streets to intersect with the Craig Bridge
• Work includes…– Reconnecting city streets and North Toledo
neighborhoods– Modification of the Craig Bridge– Filling existing trench
The Ohio Department of Transportation 4
I-280 Trench Project Overview
• Cost: $21,245,747.53• Contractor: Posen Construction• Construction Starts: October 2008• Estimated Completion: Winter 2010
The Ohio Department of Transportation 5
I-280 Trench ProjectOverview
The Ohio Department of Transportation 6
North Side Land Use
The Ohio Department of Transportation 7
FORD ROAD
East Side Land Use
The Ohio Department of Transportation 8
FORD ROAD
9The Ohio Department of Transportation
Tribute Park Site Plan
The Ohio Department of Transportation 10
• From Greenbelt, over Craig Bridge into Tribute Park• Craig Bridge: bike lane• East side of the bridge: A path to Tribute Park,
another under VGCS• Along Front Street
I-280 Trench ProjectBike Paths
I-280 Trench Project Filling the Trench
The Ohio Department of Transportation 11
• North of the river: Filled to height of existing overpasses• South of the river: close to existing Craig Bridge grade• Fill dirt will come from:
- Summit/I-280 interchange- Woodville Road/I-280 interchange- I-75/I-280 interchange
Since 2001 ODOT has stored over 40,000 truck loads of fill as a cost savings measure
I-280 Trench Project Before
The Ohio Department of Transportation 12
I-280 Trench ProjectAFTER
The Ohio Department of Transportation 13
I-280 Trench Project
Schedule and Time Impacts
The Ohio Department of Transportation 14
15
October 14, 2008 to November 2008
Remove existing Erie St. bridge, and build temporary pavement and sidewalk
Detour via Buffalo St., Ontario St., and Buckeye St.
Two-way traffic on Erie St. between Buffalo St. and bridge
Two-way local traffic only on Ash St. and River Place between Superior St. and Summit St.
Erie Street
The Ohio Department of Transportation
November 2008 to Winter 2009
Local Traffic only on Michigan St. and Ontario St. between Galena St. and Bridges
Local Traffic only on Buffalo St. Between Erie St. and Huron St.
Detours to be coordinated with City of Toledo
16
Michigan, Ontario, Ash and Huron streets
The Ohio Department of Transportation
17
November 2008 to Spring 2009
Two-way Traffic on EB Summit St.
NB Craig bridge to EB Summit St. Closed
WB Summit St. to SB Craig bridge closed
Ash St. and River Place closed at Summit St.
Summit Street
The Ohio Department of Transportation
18
Spring 2009 to Winter 2009
Craig Bridge NB & SB Closed
All Ramps to and from Craig Bridge closed
NB I-280 to WB and EB Front Street open
WB and EB Front Steet to SB I-280 open
Front Street and Craig Bridge
The Ohio Department of Transportation
19
Spring 2009 to Winter 2009
Craig bridge NB & SB closed
All ramps to and from Craig bridge closed
Close Ash St. and River Pl. at Summit St.
Summit Street and Craig Bridge
The Ohio Department of Transportation
Spring 2010 to Fall 2010
Rebuild Ash from Ontario to Summit; Completing Huron reconstruction; Completing Erie permanent pavement
Two-way traffic on Erie from Buffalo to work site
Two-way traffic on Superior, Buckeye and Ash
Two-way traffic on River Place between Superior and Summit
20The Ohio Department of Transportation
Erie, Huron and Ash streets
21
Winter 2009 toWinter 2010
Craig Bridge Open
Ramp from NB I-280 to Front St. and ramp from Front St. to SB I-280 will be open
Two-way traffic on new Front St. with minor shifts to construct closure segments of pavement
The Ohio Department of Transportation
Complete Front Street
22
Winter 2009 to Winter 2010
Craig Bridge Open
Two-way traffic on new Summit Street with minor shifts to construct closure segments of pavement
Complete Summit Street
The Ohio Department of Transportation
I-280 Trench ProjectTribute Park
John Crandall Co-Chairman, Tribute Planning Committee
The Ohio Department of Transportation 23
I-280 Trench ProjectTribute Park
• A memorial to those who have fallen and all who contributed to the construction of the VGCS
• Bike Paths through and to the Park• Champlain Street bridge and railroad bridge at north end
of park to remain
The Ohio Department of Transportation 24
25The Ohio Department of Transportation
Tribute Park Site Plan
Questions?
The Ohio Department of Transportation 26
Questions?
Questions?