Transcript of The New I-64 Design-Build Project October 2007. 2 Three Design-Build Contracts Legislative...
The New I-64The New I-64Design-Build Design-Build
ProjectProject
October 2007
2
Three Design-Build Three Design-Build ContractsContracts
• Legislative authorization in 2004
• I-64, St. Louis
– Awarded November 2006
• Safe and Sound Bridge Program
– Contractor to be selected November 2007
• kcICON, Kansas City
– Contractor to be selected November 2007
3
Why Do Design-Build?Why Do Design-Build?
• Faster
• Less expensive
• Opportunities for innovation
4
Design-Build BenefitsDesign-Build Benefits
Source: Southeast Corridor Contractors, TREX, Denver, Colorado
11.4% lessSchedule Growth
5.2% lessCost Growth
33.5% fasterDelivery Speed
12% fasterConst. Speed
6.1% lowerUnit Cost
Design-Build vs. Design-Bid-BuildMetric
5
How Does It Work?How Does It Work?
• MoDOT provides conceptual design
• MoDOT issues Request for Proposal
• Contractor team selected on “Best Value”
• Contractor completes the design and builds the project in parallel instead of linear path
6
New Design-Build New Design-Build ModelModel• Streamlining internal approvals & reviews
• Flexible
• Limited requirements
– Meet federal design/construction standards
– Propose state design/construction standards
• Innovation and creativity of private sector
• Best value for taxpayers with maximum improvements for the budget
kcICON: Interstate 29/35kcICON: Interstate 29/35Connections ProjectConnections Project
I-64/US Route 40 I-64/US Route 40 ReconstructionReconstruction
St. Louis City and County
Regional ProjectRegional Project
Deteriorated Roads and Deteriorated Roads and BridgesBridges
• Originally built 1930s to 1960s
• Designed for slower traffic and less volume
• 32 bridges
• Half are near closure!
Spoede Road
I-64 over I-170
• On/Off ramps too short
• No dedicated exit lanes
• Minimal shoulders
CongestionCongestion
Project GoalsProject Goals
• Complete within budget of $535 million
• Complete on time, July 31, 2010
• Improve traffic flow on I-64
• Minimize construction impacts
• Provide a quality product
• Demonstrate a new model for reconstructing interstates
Project BudgetProject Budget
• $535 million total budget with $420 million for contractor Design-Build
• MoDOT conceptual design including EIS activities
• Property acquisition
• MoDOT staff and overhead
• Utilities
• Contingencies
• Contractor design and construction costs
Quality OversightQuality Oversight
• Contractor responsible for QC & QA
• Quality plan for each area of Contractor’s work
• MoDOT audits 10% of Contractor’s work
• Oversight focuses on – High risk elements– Processes more than products
Maintenance of TrafficMaintenance of Traffic
Requirements:
• Don’t close entire road for entire time
• Keep regional traffic moving
Contractor proposed:
• Lane closure durations
• Segment completion dates
• Project completion date
UtilitiesUtilities
• SUE work up front reduced risk
• Master Utility Agreements focus on process
• Utility information sheets– Each relocation– All parties agree on conflict and relocation
• 3-party work orders for each relocation– Scope of work – Cost– Time
Workforce Development PlanWorkforce Development Plan
• Meet the following goals
• 14.7% minorities and 6.9% women
• 20% On-the-Job training
• 5% additional On-the-Job above 20%
• 5% incentive for professional services individuals
• Hire and retain pre-apprenticeship graduates
• Maximize relationships with training and hiring programs
• Provide diversity and sensitivity training
I-64 Evaluation ItemsI-64 Evaluation Items
AreaAvailable
Points
DBE Commitments/Workforce
10
Public Information 10
Project Definition 45
Completion Schedule 15
Maintenance of Traffic 20
TOTAL 100
BenefitsBenefits
• MoDOT got everything we needed for the project
• Dollars stretched to provide most project possible
• Completion dates are very aggressive
• Flexibility = great value
Winning ContractorWinning Contractor
Gateway Team Gateway Team MembersMembers
Major Participants• Granite Construction• Fred Weber• Millstone Bangert• Parsons
Transportation• URS Other Team Members
• Gerstner Electric• Crawford, Bunte,
Brammeier• Horner & Shifrin• Terracon• Vector Communications
What will be builtWhat will be built
• 10 miles of roadway
• Direct ramps from I-64 to I-170
• 12 interchanges & 6 overpasses
• Additional lane from I-270 to I-170
How it will be builtHow it will be built
KingshighwayKingshighway
TammTamm
Bellevue, Highland, Bellevue, Highland, BolandBoland
I-170I-170
How it will be builtHow it will be built
How it will be builtHow it will be built
How it will be builtHow it will be built
I-64/I-170 InterchangeI-64/I-170 Interchange
Regional Traffic Regional Traffic ImprovementsImprovements
Infoline 314-524-9191Infoline 314-524-9191
www.thenewi64.orwww.thenewi64.orgg
I-64 Project ContactI-64 Project Contact