The MoPac Improvement ProjectProject Fast Tracked 4 July - August 2010 July – October 2010 October...
Transcript of The MoPac Improvement ProjectProject Fast Tracked 4 July - August 2010 July – October 2010 October...
The MoPac Improvement Project
Sean Beal Engineering Manager Central Texas Regional Mobility Authority
A Successful Regional Partnership
The MoPac Corridor
• 11-mile limited access freeway
• Developed corridor with constrained
right-of-way
– Mixed residential and
commercial use
• One of the few north/south
corridors through Austin
• Active and vocal stakeholders in
corridor
– No additional right-of-way
– No elevated structures
– Wanted noise walls
• First managed express lane project
in Central Texas
2
The MoPac Improvement Project
• Need:
– Correct unreliable operations caused by increasing congestion
• Purpose:
– Improve mobility
– Manage congestion
– Provide a reliable transit route to reduce travel times
– Improve emergency response
– Maximize use of the facility
3
Project Fast Tracked
4
July -
August
2010
July –
October
2010
October &
December
2010
May – August
2011
Fall 2011 March 2012 Spring 2012
Restart Environmental
Study and Public
Involvement
Develop and Refine
Preliminary Alternatives
Conduct Open House
Meetings then Narrow
Preliminary Alternatives
Conduct Aesthetics
Open House and Sound
Wall Workshops
Narrow Reasonable Alternatives
Conduct Additional
Open House Meetings
Release Draft Environmental Assessment
for Public Review
May 2012
Conduct Public Hearings on
the Draft Environmental Assessment
Finding of No
Significant Impact
August 2013
Benefits of Expedited Schedule
• Project was shovel ready when unexpected $130 million
became available
– Community able to establish $230 million regional
infrastructure fund
• Drivers to experience improved mobility faster
• Neighbors receive sound mitigation sooner than anticipated
• Able to take advantage of recession related cost
environment
5
Critical Factors for Success
• Production schedule
– Very detailed
– Used as a management tool
• Support for the project
– Political
– Staff level
– Key stakeholders
• True partnering between agencies
– “One Team”
6
Production Schedule
• Developed by the Project Team
• All schedule decisions were discussed with the entire
Project Team
• If schedule slid, entire Project Team took responsibility to
get it back on track
• Scheduled Technical Working Group meetings
– Need and purpose determination
– Context Sensitive Solutions
– Noise walls
– Indirect and cumulative impacts
• Scheduled comment resolution meetings
7
Benefits of Using Production Schedule
• Clear direction on critical path and next steps
• Accountability
– Meetings and activities were scheduled
• Made 7 open house meetings, a public hearing, and 7
noise wall workshops a manageable process
• Technical Working Group meetings lead to reduced number
of comments
• Comment resolution meetings facilitated approval
• Allowed quarterly reporting on project status
8
Public Involvement Strategies
• Political Support
– Press Conference to launch study held on July 7, 2010
– Continued engagement throughout study
• Staff level support
• Stakeholder support through outreach
– Systematic Development of Informed Consent
– Early and often outreach
– Created project champions
• Neighborhood groups
• Business community
• Bike and pedestrian advocates
9
Benefits of Public Involvement
• Misinformation was easily corrected
• Maintained continuity
• Generated strong support for project at Public Hearing
• Greater understanding of Managed Express Lane concept
10
True Partnering
• “One Team” with one objective
• Open communication
– Tri-weekly meetings with Project Team
– Quarterly updates to Mobility Authority Board
and Commission
– Early and regular communication with
stakeholders
• Trust between agencies
• Cost sharing between agencies
• Focus on project not individual team members
11
Benefits of True Partnering
• One response to the public from the Project Team
• Allowed flexibility and innovation
– Noise wall analysis conducted early
– Additional public outreach
– Expedited contracting
• Allowed agencies to capitalize on each others strengths
• Accomplished goal
12
Project Management Decision
13
• Time and quality emphasized over cost for environmental
clearance
Results of Successful Partnership
• Project was environmentally cleared in two years
• Increased credibility with elected officials, community
leaders and neighborhood residents
• Established good communication with stakeholders for
transition to construction
• Solidified relationships between partner agencies
• Being used as model for other projects
– Ongoing public involvement activities throughout study
– Open and regular communication between Project Team
– Identifying project champions
14
The MoPac Improvement Project
Sean Beal Engineering Manager Central Texas Regional Mobility Authority
A Successful Regional Partnership