'The Mactaquac Project'

download 'The Mactaquac Project'

of 12

Transcript of 'The Mactaquac Project'

  • 8/13/2019 'The Mactaquac Project'

    1/12

    Our

    Commitmentto youGeorge Porter February 5, 2014 The GAIA Project

    The Mactaquac Project

  • 8/13/2019 'The Mactaquac Project'

    2/12

    2

    About Mactaquac

    1968 in-service date Local hydro-power generation

    660 MW rated capacity (about 20% of NBs peak need)

    1.6 TWH annual energy (about 12% of NBs yearly need)

    Capacity factor = 1.6TWh/(660MW*8760hrs/yr) = 27%

    Other contributions to power system reliability

    Regulation, load following, and reserve

    Voltage support

    System black start

    Suffering from expansion of concrete

  • 8/13/2019 'The Mactaquac Project'

    3/12

    0 1 2 3 4 5 6 7 8 910

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    22

    23

    24

    Generating to Match UsageOver One Day

    3

    Generation with

    lower fuel costs

    (e.g. nuclear, coal)

    Generation withmedium fuel costs

    (e.g. natural gas)

    Generation with

    higher fuel costs

    (e.g. diesel)

    Hydro with no

    fuel costs

    Usage

  • 8/13/2019 'The Mactaquac Project'

    4/12

    Alkali Aggregate Reaction (AAR)

    4

    The dam is 8taller than whenit was built

    The dams

    expansion inwidth is 24

    Asymmetricthicknessesimply morecomplexdeformations inother areas

  • 8/13/2019 'The Mactaquac Project'

    5/12

    5

    AAR Remediation

    Growth rate has been steady and sustained,

    with no sign of slowing down

    Since 1985, a massive program of investigation

    and remediation has been carried out

    Our work is reviewed by a board of

    international experts at least once a year to

    ensure safety of the facility and value

  • 8/13/2019 'The Mactaquac Project'

    6/12

    Reduce and Shift Demand

    MactaquacsFuture

    Studies indicate a 2030 end-of-life for theconcrete structures

    Timely option analysis and decision-

    making are required to address thisdeadline because:

    the implications are significant

    all options have long lead times

    6

  • 8/13/2019 'The Mactaquac Project'

    7/12

    Reduce and Shift Demand

    Potential Options

    Repower by replacing the spillway andpowerhouse

    Do not repower and maintain the head

    pond by replacing the spillway but not thepowerhouse

    Restore the river/eliminate head pond

    7

    There is no status quo or do nothing option.

    The 2030 deadline is fixed.

  • 8/13/2019 'The Mactaquac Project'

    8/12

    Timeline

    2030

    Decision

    Gate

    2016

    Decision

    Gate

    2019Study 3

    Options:

    Repower Head Pond

    River

    Acquire

    Approvals

    forPreferred

    Option

    Perform Detailed Design & Site Work for Preferred Option

    8

    Mactaquac Project

  • 8/13/2019 'The Mactaquac Project'

    9/12

    Factors to Consider

    Total costs, rates, capital cost, financing

    Environment (e.g. river health, emissions)

    Social impacts (on communities, jobs,

    property owners, culture, recreation, etc.)

    First Nations impacts

    The value provided to the power system Uncertainty and risks

    9

  • 8/13/2019 'The Mactaquac Project'

    10/12

    Reduce and Shift Demand

    Review and Approvals

    Independent reviews to supplement approvalsrequired by law

    Environmental approval (federal & provincial)

    NB Power Board of Directors approval

    Province of NB (utility owner) approval

    Energy and Utilities Board approval

    10

  • 8/13/2019 'The Mactaquac Project'

    11/12

    Reduce and Shift Demand

    Opportunities for Dialogue

    Ongoing First Nations engagement

    Ongoing public engagement

    Environmental assessment consultations

    Energy and Utility Board (EUB) process

    11

  • 8/13/2019 'The Mactaquac Project'

    12/12

    Contact Information

    By email By regular mail By phone

    [email protected] Mactaquac Project

    NB Power

    515 King Street

    PO Box 2000

    Fredericton, NBE3B 4X1

    1-866-754-7727

    If you or your group would like moreinformation about this project, or would like to

    share your point of view, please contact us.

    12

    mailto:[email protected]:[email protected]