The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

download The Latest Authorities on Claims for Delay Disruption and Loss  Expense ....pdf

of 150

Transcript of The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    1/150

    THE LATEST AUTHORITIES

    ON CLAIMS FOR DELAY, DISRUPTION AND

    LOSS & EXPENSE

    and the Practical Implications for those Preparingand Defending Claims

    8 OCTOBER 2013, TUESDAY

    PRINCE HOTEL

    KUALA LUMPUR

    www.charltonmartin.com

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    2/150

    About Charlton Martin Group The Regions leading Construction Contracts Consultancy

    Consultants who specialise in dispute resolution and dispute

    avoidance after many years of industry experience

    Serving various market sectors including:

    o Engineering

    o Oil & Gas / Petrochemical / Process

    o Construction

    o Power

    2www.charltonmartin.com

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    3/150

    About Charlton Martin Group

    3www.charltonmartin.com

    Michael Charlton andRodney Martin have worked together

    successfully for the past 16 years, the last 6 of which have been

    as Chairman and CEO of the Charlton Martin Group.

    The Charlton Martin Group provides services in 4 key areas:

    Contract Administration

    Claims Preparation / Defense Dispute Resolution

    Training

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    4/150

    Our Offices Hong Kong

    Singapore

    Malaysia

    Plus Regional and Internat ional Coverage

    4www.charltonmartin.com

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    5/150

    What Defines Us?

    5www.charltonmartin.com

    WORK ING HARDER AT WINNING

    To pro vid e hig h quali ty consultanc y servic es which arerelevant

    to ou r clients needs and circumstances in any par t icu lar

    si tuat ion.

    In do ing so to be the construct ion con tracts co nsul tant of

    cho icew ithin the Asia Pacif ic Regio n.

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    6/150

    www.charltonmartin.com

    www.char l tonmart in .com

    6

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    7/150www.charltonmartin.com

    Programme

    09:00 09:45 Lecture 1 by Mr Michael Charlton

    09:45 10:30 Lecture 2 by Mr Rodney Martin

    10:30 11:00 Tea / Coffee Break

    11:00 11:45 Lecture 3 by Mr Michael Charlton

    11:45 12:30 Lecture 4 by Mr Rodney Martin

    12:30 13:00 Questions & Discussion

    13:00 14:00 Lunch

    14:00 15:30 Workshop 1

    15:30 15:45 Tea / Coffee Break

    15:45 17:30 Workshop 2

    17:30 Close

    7

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    8/150www.charltonmartin.com 8

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    9/150www.charltonmartin.com 9

    Lecture 1

    BY

    MR MICHAEL CHARLTON

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    10/150www.charltonmartin.com

    Lecture 1: Introduction & Factual Background

    Introduction

    Factual background toWalter L illy & Co Ltd v Mackay

    10

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    11/150www.charltonmartin.com

    Introduction

    Walter Lil ly & Co L tdvMackay and Ano ther (No 2) [2012]

    EWHC 1773 (TCC)

    Reported in full 139 pages of judgment and 660 paragraphs!

    Also reported in Building Law Reports [2012] BLR 503

    provides a commentary and edited report (lengthy factual and fact

    specific content removed)

    NOTE: Application for leave to appeal against the judgment in

    this case was refused in January 2013.

    11

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    12/150www.charltonmartin.com

    Introduction

    Why theWalter Li l lycase?

    Addresses the following important topics:

    Concurrency in delay

    Practical Completion

    Conditions Precedent and Notices

    Details and Records to Prove Loss and Expense

    Global Claims

    12

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    13/150

    www.charltonmartin.com

    Introduction

    Why theWalter Li l lycase?

    Addresses the following important topics:

    Head Office Overheads and Use of Formulae

    Recovery by Main Contractor of Reasonable Settlements of

    Subcontractors Claims

    13

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    14/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Project from hell!

    Recipes:

    Difficult and determined employer

    Poor and underprovided design

    Architect who was undermined and prevented from operating

    Consultants to further undermine the architects position

    14

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    15/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Recipes:

    Indecision and changes by employer

    Complete breakdown between employer and his design team

    15

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    16/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Messrs Daniel Messrs Mackay Messrs West

    DMW

    Developments

    (Employer)

    Bought and build on a plot of land at 3, Boltons Place, London SW5

    (A house each)

    16

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    17/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Project:

    Contractor: Walter Lilly & Company Ltd (WLC)

    Contract Sum: 15,372,962.83

    QS: Gardiner & Theobald (G&T)

    Architect: Barrett Lloyd Davis Associates (BLDA)

    17

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    18/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Project:

    Date for Possession: 12 July 2004

    Date for Completion: 23 January 2006

    Contract Period: 80 weeks (approx. 18.5 months)

    Contract: JCT 98, without quantities

    WLC only priced Preliminaries, remainder presented as

    provisional sums

    18

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    19/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    WLC were responsible in respect of design for a list of items.

    There was little design or detail available at tender stage.

    19

    PROJECT

    Unit A Unit B Unit C (MrMackays)

    split into 3 contracts viadeed of variation

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    20/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Delays right from the beginning:

    Demolition works

    Piling works

    End of 2004, design information still incomplete due to indecision by

    DMW

    After original completion date (January 2006), major aspects of

    design still not resolved!

    None was considered as WLCs fault at that time

    20

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    21/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Cost plan (drawn on the basis for the provisional sum) became

    inadequate

    High quality and specification demanded by Mr and Mrs Mackay

    (e.g. hand stitched leather to bookshelves) made delays worse

    Issue arose: Who was responsible for delays in dealing with

    provisional sums? Differing views by WLC and DMW

    21

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    22/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    November 2005 : WLC applied for19 weeks EOT

    January 2006 : WLC reported 27 weeks EOT

    April 2006 : WLC requested for33 weeks EOT

    June 2006 : WLC anticipated completion in November 2006 i.e.

    36 weeks delay

    Cost ballooned 5.5 mil to approx. 9.375 mil by May 2006

    22

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    23/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Up to 29 June 2006, BLDA considered the main causes of delay

    are:

    Late instructions and design information

    Splitting of packages into smaller packages

    Poor coordination of services, the lifts and substation

    Problems from only one staircase compared to two in original

    specification

    WLC not taking enough design responsibility (not accepted by WLC)

    23

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    24/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    July 2006: Only 20 weeks EOT granted. WLC applied for another

    EOT, identifying 46 weeks delay due to late instructions by BLDAarising from changes to doors and wall specification

    October 2006: More and more delays!

    Continuous strained ties between Mr Mackay and BLDA and G&T

    prompted him to employ Knowles for contractual and adjudication

    advice.

    24

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    25/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Strategy with Knowles on board:

    Pursue WLC, make them responsible for LD

    and restrain BLDAs actions

    BLDA was accused of masking its own delay by issuing EOTs to

    WLC. Under pressure, BLDA wrote numerous letters to WLC

    omitting sections of work to shorten the contract period.

    25

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    26/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Final EOT extended completion date to 16 February 2007.

    Practical Completion for Unit A certified on 2 February 2007,

    while MrMackays unit was still in delay due to various problems.

    Mr Mackay indicated intention to hold LDs from 16 February 2007

    had client walk around meetings without WLCs presence

    Knowles became influential and advised withholding of 550k for

    defective and outstanding works Knowles involvement raised

    temperature

    26

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    27/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    March 2007: DMW withheld payment BLDA suspend service

    April 2007: WLC requested 71 weeks of EOT as most major

    delays were still ongoing

    Mr Mackay blamed BLDA and continued interfering BLDA

    cannot issue instructions without Knowles agreement

    WLC commenced adjudication with DMW succeed amounts

    withheld for various defects were inappropriate

    27

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    28/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    Knowles aggressive policy:

    Wewould like to create a situation whereby direct work is not

    delaying [Practical Completion] i.e. Practical Completion is

    solely delayed byWLCsworks. WLCsworks can be omitted to

    achieve this if possible

    Recommended BLDA be dismissed

    G&T instructed not to issue any further interim valuations

    28

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    29/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    January 2008 : Delay due to specialist ceiling works

    February 2008 : Mr Mackay fall out with Knowles unpaid bills

    Engaged in highly derogatory dialogues

    Objected Knowles suggestion that DMW were responsible for

    part of the delays

    29

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    30/150

    www.charltonmartin.com

    Factual Background

    Walter Li l lyvMackay

    March 2008 : DMW terminated BLDA. Navigant appointed

    January to August 2008 : Many artists and tradesmen worked on

    the site damaged WLCs work WLC spent time rectifying

    but Navigant were not dealing with their EOT applications

    Navigant: Practical Completion 7 July 2008 (original: 23 Jan 2006)

    G&T: Valuation No. 40 9.1 mil (original: 5.3 mil)

    Dispute continues into 2009 and 2010

    30

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    31/150

    www.charltonmartin.com

    Factual Background

    A Brief Look into the Judgment

    On the witnesses generally favourable to WLC while Mr

    Mackay was found to be an unsatisfactory witness

    On the experts approach

    WLCs expert preferred objective identified critical delay by

    referring to logical sequence of events on the longest path

    MrMackays expert focused on WLC not proving their case

    not expertsjob based on conversation not in evidence

    31

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    32/150

    www.charltonmartin.com 32

    Lecture 2

    BY

    MR RODNEY MARTIN

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    33/150

    www.charltonmartin.com

    Lecture 2: Concurrency, Practical Completion &

    Conditions Precedent and Notice

    Concurrency in Delay

    Practical Completion

    Conditions Precedent and Notices

    33

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    34/150

    www.charltonmartin.com

    Concurrent Delay

    34

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    35/150

    www.charltonmartin.com

    Concurrency in Delay

    35

    Concurrent Delay(work delayed due to two or more competing causes of delay)

    Contractor /

    Subcontractors

    responsibility

    OR Neutral event

    delays occur at the same time

    Architect /

    Engineer /

    Employers

    responsibility

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    36/150

    www.charltonmartin.com 36

    Concurrency in Delay

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    37/150

    www.charltonmartin.com 37

    Concurrency in Delay

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    38/150

    www.charltonmartin.com 38

    Concurrency in Delay

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    39/150

    www.charltonmartin.com 39

    Concurrency in Delay

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    40/150

    www.charltonmartin.com 40

    Concurrency in Delay

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    41/150

    www.charltonmartin.com 41

    Concurrency in Delay

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    42/150

    www.charltonmartin.com

    Concurrency in Delay

    Keating on Construction Contracts:

    Dominant Cause Approach

    Leyland Ship ping v Norw ich[1918]which cause is dominant is a question of fact which is not solved

    by mere point of order in time, but is to be decided applying

    common sense standards

    H Fairweather v Lo nd on Boro ug h of Wand sw orth[1987]

    To assume that it is possible to analyse two causes of delay and

    assess which event is the dominant or predominant cause of

    delay was considered by the court to be inappropriate

    42

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    43/150

    www.charltonmartin.com

    Concurrency in Delay

    Keating on Construction Contracts:

    Apportionment

    Jo hn Doyle v Laing Management[2004]

    City Inn v Shepherd Constru ctio n[2010]

    Favoured in these cases - requires a compromise between the

    parties by allocating total delay among matters causing delay.

    Rejected in other cases and not considered applicable under

    English law where standard form construction contracts are used

    43

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    44/150

    www.charltonmartin.com

    Concurrency in Delay

    Keating on Construction Contracts:

    But For

    Turner Page Musi c v To rres[1997]but for the delay caused by the Architect the delay should not have

    occurred but rejected in this case as being inconsistent with the

    more popular Dominant Cause approach

    44

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    45/150

    www.charltonmartin.com

    Concurrency in Delay

    Keating on Construction Contracts:

    Devlin Approach

    If a Delay is the result of two causes one of which constitutes a breach

    of contract (e.g. late instruction) then the EOT will be calculated using

    the delay caused by the breach

    But this is not a helpful approach where delay caused by both parties

    would result in both parties claims (prolongation cost by contractor and

    LAD by employer) being successful which makes little sense for samedelay period

    45

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    46/150

    www.charltonmartin.com

    Concurrency in Delay

    Keating on Construction Contracts:

    Burden of Proof Approach

    Applies where one of the delays clearly caused by the Contractor

    Contractor must demonstrate that delay to completion was caused by

    matters which entitle him to EOT in isolation of his own delay

    No entitlement where concurrent delays since Contractor could notshow separate liability for delay

    Resulting in same outcome as but for test

    46

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    47/150

    www.charltonmartin.com

    Concurrency in Delay

    Keating on Construction Contracts:

    First Past the Post

    One of the delays occurs first in time (thus first past the post)

    Used for dealing with questions of EOT

    All other delaying matters are then ignored until the first cause has

    ceased to have effect

    47

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    48/150

    www.charltonmartin.com

    Concurrency in Delay

    Keating on Construction Contracts:

    Loss Lies Where It Falls

    Where parallel Contractor and Employer delays occur, Employer

    required to acknowledge the right to EOT and thus will be prevented

    from levying LDs

    Contractor will have no entitlement to loss & expense because this

    would arguably have been incurred in any event due to his own

    culpable delay

    48

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    49/150

    www.charltonmartin.com

    Concurrency in Delay

    Leading Cases

    Wells v Arm y and Navy Co-operati ve Soc iety[1902]

    Where an Employer delays the Contractor, he or she will not be entitledto deduct liquidated damages even though the Contractor is causing

    delay

    49

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    50/150

    www.charltonmartin.com

    Concurrency in Delay

    Leading Cases

    City Inn Ltd v Sheph erd Constru ctio n Ltd[2008]

    Delay that had been caused by matters for which Contractor wasresponsible would not deprive the Contractor of an Extension of Time for

    the delay caused by a Relevant Event

    Architect should apportion responsibility for delay only way for architect

    to give fair result. Similar to contributory negligence.

    But for test rejected.

    50

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    51/150

    www.charltonmartin.com

    Concurrency in Delay

    Leading Cases

    City Inn Ltd v Shepherd Con stru ctio n Ltd[2010]

    Identified concurrency as a delay caused by the Contractor (culpable delay)occurring at the same time as a delay caused by the Employer where both

    cause delay to completion. The appeal decision of the 2008 judgment still

    supported apportionment.

    De Beers UK Lim ited v A tos Orig in IT Serv ices UK Lim ited[2010]

    In considering the principles of concurrency, City Inn and apportionment was

    ignored. Failure by Atos to give notice fatally undermined arguments that

    non payment by De Beers was a repudiatory breach.

    51

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    52/150

    www.charltonmartin.com

    Concurrency in Delay

    Leading Cases

    Ady ard Abu Dhabi v SD Marin e Servi ces[2011]

    Contractors pre-existing delay is relevant to the question of determininga contractors entitlement to an extension of time.

    Thus concurrency in this case was defined as two or more effective

    causes of delay of approximately equal causative potency

    Thus a pre-existing delay might have more causative potency

    52

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    53/150

    www.charltonmartin.com

    Concurrency in Delay

    Leading Cases

    Henry Bo ot Constru ctio n (UK) Ltd v Malmaison Hotel (Manchest er)

    L td[2000]

    If there are two concurrent causes of delay, one which is a Relevant

    Event and other is not, the Contractor is entitled to Extension of Time for

    the period of delays caused by the Relevant Event

    One of the most important cases on how to deal with concurrency and now

    favoured by the courts See Walter Lilly

    53

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    54/150

    www.charltonmartin.com

    Concurrency in Delay

    Leading Cases

    The Royal Brompto n Hosp ital NHS Trust v Frederick Alexander Hammond

    and others[2001]

    Extension of Time can be granted when:

    (1) the Relevant Event has occurred; and

    (2) the Relevant Event is likely to cause the completion of works as a whole

    to be delayed beyond the completion date then fixed under the contract

    The need to show that the relevant event caused actual delay to the completion of

    the project is always necessary notwithstanding any consideration of delay events

    which are pre-existing and ongoing events or those which are truly concurrent

    54

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    55/150

    www.charltonmartin.com

    Concurrency in Delay

    Leading Cases

    Motherw ell Brid ge Cons truc t ion Ltd v Micafi l Vakuum techn ik[2001]

    A full Extension of Time should be awarded where there is concurrent Contractor-caused and Employer-caused delay, if it is fair and reasonable to do so

    55

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    56/150

    www.charltonmartin.com

    Concurrency in Delay

    Standard Forms of Contract References

    Where standard forms are silent on the issue of concurrency, the

    common law position applies.

    In Malaysia, only the IEM 2011 deals with concurrency at Clause 44.3(6):

    the Engineer must not consider in his certification of any extension of

    the Date for Completion the effect of the events due to the Contractors

    fault which operate concurrently with any of the events listed in Clause

    44.1(1).

    56

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    57/150

    www.charltonmartin.com

    Concurrency in Delay

    Decision in Walter Lilly

    Where delay is caused by two or more effective causes, one entitles

    contractor to EOT as Relevant Event, Contractor is entitled to full EOT.

    Logic Many Relevant Events would be acts of prevention and it would

    be wrong in principle to construe Clause 25 to deny contractor full EOT

    in those circumstances

    Relevant Event provides for EOT, nothing suggests there is any sort of

    proviso that EOT be reduced if causation criterion established.

    57

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    58/150

    www.charltonmartin.com

    Concurrency in Delay

    Decision in Walter Lilly

    Architect to award fair and reasonable EOT, does not permit

    apportionment test is causation

    City Inn is persuasive but not applicable in English law

    In the event, by analysis it was found by the experts that there was

    actually no concurrency at all a very common situation

    The Malmaisoncase is now considered good authority in concurrency

    cases

    58

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    59/150

    www.charltonmartin.com

    Concurrency in Delay

    Decision in Walter Lilly

    It is considered that the Walter Lilly decision will be valid in Malaysia

    although this remains to be tested.

    There is no reason to suppose that the City Inn apportionment ruling

    would be applicable in Malaysia.

    The PAM conditions of contract in use in Malaysia in this regard are

    similar to JCT 98 on which the Walter Lilly decision was made.

    59

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    60/150

    www.charltonmartin.com

    Concurrency in Delay

    Society of Construction Law Protocol

    Where Contractor delays to completion occur concurrently with Employer

    delays, the Contractors concurrent delay should not reduce any EOT

    due, even where Employer delays are only overlapping (i.e. ofconcurrent effect rather than truly concurrent) SOCL page 16

    Accords with Walter Lilly judgment

    60

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    61/150

    www.charltonmartin.com

    Practical Completion

    61

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    62/150

    www.charltonmartin.com

    Practical Completion

    What is practical completion?

    An important issue in the Walter Lilly case.

    PAM 2006 Clause 15.1 states:

    When in the opinion of the Architect, the Employer can have full use of the Works

    for their intended purposes, notwithstanding that there may be works and defects

    of a minor nature still to be executed and the Contractor has given to the Architect

    a written undertaking to make good and to complete such works and defects

    within a reasonable time specified by the Architect; and other requirements

    expressly stated in the Contract Documents as pre-requisite for the issuance of

    the Certificate of Practical Completion have been complied with.

    62

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    63/150

    www.charltonmartin.com

    Practical Completion

    What is practical completion?

    CIDB 2000 Clause 1.1 states:

    Practical completion: completion of the works including tests on

    completion under the contract and where the works include equipment

    which requires a licence for its operation, then completion so as to

    render such equipment eligible for issuance of a licence in respect of its

    operation. Provided however the existence of minor outstanding works

    and defects, which do not affect the functional use of the works shall not

    affect Practical Completion.

    63

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    64/150

    www.charltonmartin.com

    Practical Completion

    What is practical completion?

    PWD 203A (Rev. 2010) has similar definition to that of PAM 2006

    IEM 2011 does not provide helpful definition of completion thus

    common law applies

    Note that under PAM 2006, de minimis rule applies to minor works and

    defects in determining practical completion

    64

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    65/150

    www.charltonmartin.com

    Practical Completion

    The Common Law

    J Jarvis v Westm ins ter Corp oratio n[1978]

    I take the words [practical completion] to mean completion for all practical

    purposes

    J Nevil le v Wil liam Press and Sons[1981]

    Ithink the word practically gave the Architect the discretion to certify

    that William Press had fulfilled its obligation, where very minor de minimis

    work had not been carried out, but that if there were any patent defects

    the Architect could not have given a certificate of practicalcompletion

    65

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    66/150

    www.charltonmartin.com

    Practical Completion

    Substantial Completion

    Max Abrahamson on Engineering Law and the ICE Contracts, 4th Ed.

    The Concise Oxford Dictionary equates substantial with virtual which is

    defined as thatis such for practical purposes though not in name or according

    to strictdefinition. It is at least clear on the one hand that the fact that the works

    are or are capable of being used by the Employer does not automatically mean

    that they are substantially complete (anysubstantial part of the Works which

    has both been completedand occupied orused)and on the other hand that

    the Engineer may not postpone his certificate under this Clause until the works

    are absolutely completed and free of alldefects

    66

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    67/150

    www.charltonmartin.com

    Practical Completion

    Decision in Walter Lilly

    When has Practical Completion been achieved?

    What effect does snagging have on PC?

    Judge considered that PC meant completion for all practical purposes

    and that what completion entails must depend upon the nature, scope

    and contractual definitions of the works, as they may have developed by

    way of variations or architects instructions

    67

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    68/150

    www.charltonmartin.com

    Practical Completion

    Decision in Walter Lilly

    De minimis snagging should not be a bar to PC unless there is so much

    of it that the building cannot be used for its intended purpose

    In the Walter Lilly case, work was often omitted and awarded to others

    outside the contract because due to the extensive use of Provisional

    Sums there was no issue in doing so

    In this case once the work was omitted it no longer formed part of the

    contract and did not need to be done or completed in order to obtain PC

    Although it is unusual for all work to be the subject of provisional sums, if

    it were to be the case then none of the Malaysian forms restrict the

    omission of work by definition as a variation

    68

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    69/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    69

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    70/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Notice

    Hudsons, 11th Edition

    Sincethe purpose of such provisions is to enable the owner to considerthe position and its financial consequences, (by cancelling an instruction

    or authorising a variation, for example, he may be in a position to reduce

    his financial liability if the claim is justified), there is no doubt that in

    many if not most cases the courts will be ready to interpret these notice

    requirements as conditions precedent to a claim, so that failure to give

    notice within the required period may deprive the contractor of allremedy.

    70

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    71/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Notice

    PAM 2006 Cl. 24.1(a) Notice within 28 days from start of the

    occurrence of the matter giving rise to claim

    with estimate & relevant info substantiatingthe claim

    IEM 1989 / PWD 203A Notice within 30 days with estimate

    IEM 2011 Cl. 53.1 Notice within 28 days after event. However,

    Cl.53.5 allows the Engineer to makedetermination irrespective of whether the

    Contractor complied with Cl. 53.1 Defeats

    purpose of condition precedent

    71

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    72/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Notice

    CIDB 2000 Cl. 32.1 Notice within 30 days after the event and

    must specify Such notice is a condition

    precedent

    FIDIC 1999 Cl. 20.1 Notice within 28 days after Contractor

    became aware of the event or should

    have become aware of the event

    72

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    73/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Notice

    WW Gear Cons tru ct ion Ltd v Mc Gee Group Ltd[2010]

    Timely application in writing was a precondition to the recovery ofloss and/or expense claim

    73

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    74/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Nature and Form of Notice

    Check contract requirements and comply

    Case law on nature of applications -London Bo rough of Mertonv Stan ley Hugh Leach[1985]

    74

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    75/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Lack of Notice

    Gaymark Investments Pty Ltd v Walter Construct ion Group

    [1999]

    Lack of notice could not deny entitlement to EOT where cause of

    delay was employer act of prevention

    However, the lack of notice did deny the Contractor costs of delay

    75

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    76/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Qualifications in Loss and Expense Clauses

    Usual in standard form construction contracts that only additional

    cost not reimbursed by payment under any other clause of the

    contract will be recoverable.

    Obvious example: variations clauses

    PAM, IEM, PWD & CIDB Forms of Contract

    76

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    77/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Decision in Walter Lilly

    Notice was not really an issue regarding EOT, the issue was more

    related to loss and expense

    Counsel for the parties agreed that timely written application with

    supporting information and details was a condition precedent under JCT

    98 Clause 26

    77

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    78/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Decision in Walter Lilly

    Judge said it was necessary to bear in mind that most of the matters

    which entitle contractor to loss and expense are the fault or risk of

    employer, e.g. variations, late provision of information or instructions

    Notice needed to be interpreted with care and without construing them

    against contractor

    Notice to be served when contractor has incurred loss and expense or is

    likely to incur loss and expense

    78

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    79/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Decision in Walter Lilly

    For time related preliminaries contractor can wait until cost has been

    incurred which will not be until the delay has in fact happened

    Architect may not have to ascertain loss until it has happened

    This may be relevant where loss is head office overheads or profit which

    will not occur until the extended period

    79

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    80/150

    www.charltonmartin.com

    Conditions Precedent and Notices

    Decision in Walter Lilly

    There are two notices to be considered, one relating to application for

    costs and the other relating to the provision of details of loss and

    expense to enable ascertainment to be carried out

    What is to be provided in each case depends on the circumstances of

    each case

    80

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    81/150

    www.charltonmartin.com

    CHARLTON MARTIN ONE DAY SEMINAR

    TEA / COFFEE BREAK

    81

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    82/150

    www.charltonmartin.com 82

    Lecture 3

    BY

    MR MICHAEL CHARLTON

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    83/150

    www.charltonmartin.com

    Lecture 3: Details and Records to Prove Loss and

    Expense & Global Claims

    Details and Records to Prove Loss and Expense

    Global orRolled up Claims

    83

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    84/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Text Book References

    Delay and Disruption in Construction Contracts (3rd Ed, 2005)

    by Keith Pickavance

    [the Contractor] should be required to produce the factual

    evidence underpinning its opinion of the expected effects, together

    with:

    (1) a network programme accurately illustrating how it intended to

    complete the works if the event had not occurred (i.e. a

    workable master programme);

    84

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    85/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Text Book References

    (2) an updated network programme showing what had actually

    been achieved in relation to the proposed programme before

    the event occurred; and

    (3) an impacted network programme demonstrating with

    supporting descriptions, the duration of new or delayed

    activities and their logical interface with the remaining works.

    85

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    86/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Quotations

    Order forms

    Invoices

    Receipts

    86

    Delivery notes

    Evidence of incorporation into works

    Evidence of actual payment

    Cost records required Audit Trail

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    87/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Standard Forms of Contract References

    PWD 203A (Rev. 2010) Clause 44.2:

    the Contractor shall submit full particulars of all claims for

    direct loss or expense ... supporting documents, vouchers,

    explanations and calculations which may be necessary to be

    ascertained by the S.O.

    Only IEM 2011 defines Costs

    87

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    88/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Decision in Walter Lilly

    Useful practical comments offered by the judge which have not

    been addressed in earlier cases

    It should be borne in mind that the architect already has

    knowledge of project and delays and costs from attendance at

    meetings and receipt of applications for EOT

    Has much information at his fingertips

    88

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    89/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Decision in Walter Lilly

    Less information needs to be provided by contractor in

    applications

    Architect only needs to be put in position to form an opinion that

    direct loss and expense has been incurred or is likely to be

    incurred due to disturbance in regular progress of works

    Reference made toMerton

    89

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    90/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Decision in Walter Lilly

    Failure to provide notice on minor item of loss will not invalidate

    major amount claimed

    JCT only requires contractor to submit details which are

    reasonably necessary for ascertainment of loss and expense

    90

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    91/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Decision in Walter Lilly

    Offer to architect or QS to inspect records at contractors office

    may be considered as submission of details of L&E

    Details of L&E do not include backup accounting information

    which may support same

    No need to construe Clause 26 in a strict way or as penalty

    against contractor

    91

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    92/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Decision in Walter Lilly

    Worth noting this, employers and consultants often consider

    notices requirements which are conditions precedent to be apenalty, failure to comply bars all

    Grounds under Clause 26 arise due to fault and risk of employer

    DMW had requested comprehensive list of information which was

    not necessary under contract

    92

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    93/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Decision in Walter Lilly

    QS and architect are aware of and familiar with items which will

    incur additional costs in event of delay

    CP would be fulfilled by reference to BQ preliminary items

    Architect and QS not strangers to contract

    93

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    94/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Decision in Walter Lilly

    The judge posed an unusual and interesting view:

    Arguablethat loss and expense could be valued by reference to

    contract rates or prices for such preliminaries on basis that those

    rates or prices represent the loss (if not the expense) to the

    contractor of having such staff or other preliminary activities onthe project for longer than anticipated

    94

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    95/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Decision in Walter Lilly

    Ascertainment means determine or discover definitely

    Mass of back up detail not necessary

    Inmy judgment it is necessary to construe the words in a sensible

    and commercial way that would resonate with commercial parties in

    the real world. The architect or QS must be put in the position in

    which they can be satisfied that all or some of the loss and expense

    claims are likely to be or have been incurred

    95

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    96/150

    www.charltonmartin.com

    Details and Records to Prove Loss and Expense

    Decision in Walter Lilly

    They do not have to be certain. One has to bear in mind that

    the resolution will be on a balance of probabilities. Tribunal onlyhas to be satisfied that contractor probably incurred loss and

    expense as a result of the events listed.

    96

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    97/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Traditionally, it has been considered that notwithstanding the

    extreme difficulty on occasion of isolating the specific cause and

    relating it to a specific event, if it can be shown that any part of

    the cause arises from the contractors own default, his claim will

    fail entirely.

    The usual response from employers and indeed the courts has

    been that a contractor must take and maintain records.

    97

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    98/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    J Crosby & Sons Ltd v Portland Urban & Distr ict Counc il

    (1967)

    It is therefore impracticable, if not impossible, to assess the

    additional expense caused by delay and disorganization due to

    any one of these matters in isolation from the other matters.

    98

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    99/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    J Crosby & Sons Ltd v Portland Urban & Distr ict Counc il

    (1967)

    Ican see no reason why he (the arbitrator) should not recognize

    the realities of the situation and make individual awards in

    respect of those parts of individual items of claim which can bedealt with in isolation and a supplementary award in respect of

    the remainder of these claims as a composite whole. (J

    Donaldson)

    99

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    100/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    London Borough of Merton v Stanley Hug h Leach(1985)

    The loss or expense attributable to each head of claim cannot in

    reality be separated.

    100

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    101/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    Wharf Prop ert ies Ltd and Ano ther v Eric Cum ine As so ciates and

    Others(1991)

    The Court of Appeal in Hong Kong decided that the pleadings were

    hopelessly embarrassing, as they stood (some seven years after the

    action began) and an unparticularised pleading in such a form should not

    be allowed to stand. (HK C of A)

    The failure even to attempt to specify any discernible nexus between the

    wrong alleged and the consequent delay provides, to use [counsels]

    phrase no agenda for the trial (Privy Council)

    101

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    102/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    John Doy le Constr uc tion Ltd v Laing Management (Sco tland)

    Ltd(2004)

    A total cost claim

    the contractor might reasonably have expected to perform the work

    for a particular sum, usually the contract price;

    the proprietor committed breaches of contract;

    102

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    103/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    John Doy le Constr uc tion Ltd v Laing Management (Sco tland)

    Ltd(2004)

    the actual reasonable cost of the work was a sum greater than the

    expected cost.

    This involves an assertion that, given that the breaches of contract

    caused some extra cost, they must have caused the whole of the

    extra cost because no other relevant cause was responsible for any

    part ofit.

    103

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    104/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    John Ho lland Cons tru ctio n & Eng ineering Pty Ltd v Kvaerner

    RJ Brown Pty Ltd[1996]

    In such a case, if an event or events for which the employer is

    responsible can be described as the dominant cause of an item

    of loss, that will be sufficient to establish liability, notwithstandingthe existence of other causes that are to some degree at least

    concurrent.

    104

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    105/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    Ley land Sh ipp ing Company L td v Norwich Un ion Fi re

    Ins uranc e Soc iety Ltd[1918] AC 350

    Ifan item of loss results from concurrent causes, and one of

    those causes can be identified as the proximate or dominant

    cause of the loss, it will be treated as the operative cause, andthe person responsible for it will be responsible for the loss

    105

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    106/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    Ley land Sh ipp ing Company L td v Norwich Un ion Fi re

    Ins uranc e Soc iety Ltd[1918] AC 350

    Itmay be said that such an approach (of apportionment)

    produces a somewhat rough and ready result. This procedure

    does not, however, seem to us to be fundamentally different innature from that used in relation to contributory negligence or

    contribution among jointwrongdoers

    106

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    107/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    Ley land Sh ipp ing Company L td v Norwich Un ion Fi re

    Ins uranc e Soc iety Ltd[1918] AC 350

    Itseems to us that in such cases the contractor should be

    able to recover for part of his loss and expense, and we are

    not persuaded that the practical difficulties of carrying out theexercise (of apportionment) should prevent him from doing so.

    107

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    108/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Leading cases

    Ley land Sh ipp ing Company L td v Norwich Un ion Fi re

    Ins uranc e Soc iety Ltd[1918] AC 350

    Itmay be possible to use a process of apportionment to

    divide the pursuers increased costs between the two sets of

    causes

    The straight denial simply because a claim is global no longer

    appears to be appropriate

    108

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    109/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Decision in Walter Lilly

    Many of the above cases considered

    WLC had claimed L&E across three residential units using a

    notional splitthis was considered reasonable and there was no

    purpose in trying to analyse precisely.

    Claims were made for thickening of preliminaries due to

    additional input cause by delay etc.

    109

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    110/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Decision in Walter Lilly

    Global or total cost claims are not terms of art or statutorily

    defined terms

    Claiming all costs incurred on a project does not make the claim

    global

    110

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    111/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Decision in Walter Lilly

    A global claim identifies numerous potential or actual causes of

    delay and/or disruption, a total cost on the job, a net paymentfrom the employer and a claim for the balance between costs and

    payment attributed without more and by inference to the causes

    of delay and disruption relied on

    Judge not convinced WLCs claims were global

    111

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    112/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Decision in Walter Lilly

    Prolongation costs related solely to delays asserted for which

    EOT applied

    Costs mostly for staff for extended period

    Actual costs used

    Evidence submitted on thickening

    112

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    113/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Decision in Walter Lilly

    To prove global claims, evidence must be proved as fact

    On balance of probabilities

    First; events occurred giving entitlement

    Second; those events caused delay

    Third; those events incurred loss and expense

    113

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    114/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Decision in Walter Lilly

    JCT do not lay down that direct loss and expense cannot be

    ascertained by appropriate assessments

    No set way to prove the three elements of claim

    Nothing in principle wrong with global claim

    Added evidential difficulties in proving on balance of probabilities

    Must show that tender sufficiently well priced to make some net

    return, no other matters which actually caused loss

    114

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    115/150

    www.charltonmartin.com

    Global or Rolled up Claims

    Decision in Walter Lilly

    Concurrent events which cause loss which contractor responsible for do

    not preclude some recovery

    Necessary to make adjustment to allow for loss caused by contractor

    1m claim does not fail because contractor responsible for 50k loss, it

    is simply deducted from entitlement

    Claim simply adjusted for losses caused by contractor

    Particulars in prose form relating to thickening costs were acceptable

    115

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    116/150

    www.charltonmartin.com 116116

    Lecture 4

    BY

    MR RODNEY MARTIN

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    117/150

    www.charltonmartin.com 117

    Lecture 4: Head Office Overheads and Use of

    Formulae & Recovery of Main Contractor

    of Reasonable Settlement of Sub-

    Contractors Claims

    Head Office Overheads and the Use of Formulae

    Recovery by Main Contractor of Reasonable Settlement of Sub-

    Contractors Claims

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    118/150

    www.charltonmartin.com 118

    Head Office Overheads and the Use ofFormulae

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    119/150

    www.charltonmartin.com 119

    Head Office Overheads and the Use of Formulae

    Offices, plant and yards

    Running costs

    Directors salaries

    Head office staff salaries

    Administrative expenses

    Travelling expenses

    Legal and professional fees

    Depreciation

    Head Office Overheads

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    120/150

    www.charltonmartin.com 120

    Head Office Overheads and the Use of Formulae

    Head Office Overheads

    Two approaches:

    Actual increased overhead expended, or

    The opportunity cost orloss ofopportunity method formula

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    121/150

    www.charltonmartin.com 121

    Head Office Overheads and the Use of Formulae

    The Actual Cost Approach

    Identify actual head office costs affected by delay

    May be difficult identifying which costs arise directly or indirectly

    from delay

    Should be possible for key head office staff to generate a

    timesheet for delay period and compare with normal time sheet

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    122/150

    www.charltonmartin.com 122

    Head Office Overheads and the Use of Formulae

    The Actual Cost Approach

    Support services such as accounts, secretarial, clerical, rent,

    stationery etc. can be included a proportion of costs to be

    allocated to key staff

    Alternatively compare actual costs with amount included in tender

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    123/150

    www.charltonmartin.com 123

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Hudsons Formula

    HO/Profit Percentage* x Contract Sum x Period of Delay

    100 Contract Period (weeks)

    (in weeks)

    *Percentage in Contract

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    124/150

    www.charltonmartin.com 124

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Emdens Formula

    Head Office Overhead %** x Contract Sum x Period of Delay

    100 Contract Period

    **The HO/Profit percentage is arrived at by dividing the total overhead cost and

    profit of the Contractors organization as a whole by the total turnover

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    125/150

    www.charltonmartin.com 125

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Eichleay Formula

    i.e. Value of work during contract period x Total Head Office OverheadTotal value of work for the company During Contract Period

    as a whole during contract period

    = Head office Overheads Allocated to the Contract

    Head Office Overheads Allocated x Period of Delay Allocated to the Contract

    Contract Period

    = Amount Claimed

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    126/150

    www.charltonmartin.com 126

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    J F Finnegan L td v Sheffi eld City Counc il(1988)

    It is generally accepted that, on principle, a contractor who isdelayed in completing a contract due to the default of his employer,

    may properly have a claim for head office or off-site overheads

    during the period of delay, on the basis that the workforce, but for the

    delay, might have had the opportunity of being employed on another

    contract which would have had the effect of funding the overheads

    during the overrun period.

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    127/150

    www.charltonmartin.com 127

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Ellis Don Ltd v The Parkin g Autho rity of Toro nto(1978)

    The court accepted the use of the Hudsons formula

    Wh ittall Buil ders v Ches ter Le Street Dis tic t Cou nc il(1985)

    The court accepted the use of the Emdens formula which improved

    on the Hudsons formula by using the actual head office / profitpercentage and not that used at tender

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    128/150

    www.charltonmartin.com 128

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Tate & Ly le v Greater Lo ndon Coun ci l[1983]

    After many years of success, the opportunity cost approach and theformula in general fell out of favour when in this case the court would

    not accept a calculation of head office overheads based upon a

    simple percentage requiring actual additional cost to be proved

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    129/150

    www.charltonmartin.com 129

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Alfred McA lp ine Homes North v Proper ty and Land Contractors

    (1995)

    Emdens formula was rejected not because the opportunity costmethod was not appropriate but because they were not appropriate

    in this particular case because of the companys method of working

    and the prevailing economic climate

    The arbitrator accepted the additional costs

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    130/150

    www.charltonmartin.com 130

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    The difficulty in proving and assessing the actual additional costs

    incurred in respect of head office overheads have recently led to the

    courts taking a more relaxed view of the degree of proof necessary.

    Claims using loss of opportunity approach and formulae are re-

    appearing no better alternative has yet to be devised

    For example:

    Norwest Hols t Const ruct ion Ltd v Co-opera t ive Wholesa leSociety(1989)

    Emden formula used with a significantly reduced percentage

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    131/150

    www.charltonmartin.com 131

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Opportunity cost method using formula relies upon:-

    1. Overhead percentage capable of being earned at time of

    delay

    2. Overhead percentage reasonable

    3. Work at same level of overhead recovery available during

    period of delay

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    132/150

    www.charltonmartin.com 132

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Opportunity cost method using formula relies upon:-

    4. Method of working suitable to formula approach, i.e.

    contractor seeking further work on on-going basis

    5. Contractor denied opportunity of earning overheads

    elsewhere as result of being detained on site during period

    of delay

    Contractor must prove above criteria

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    133/150

    www.charltonmartin.com 133

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Following usually required:-

    Audited accounts for appropriate period

    Showing that level of overheads claimed is reasonable

    Company trading and actively seeking work other than during

    alleged delay period

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    134/150

    www.charltonmartin.com 134

    Head Office Overheads and the Use of Formulae

    The Lost Opportunity Approach

    Following usually required:-

    Evidence of tender activity, invitation to tender, declinedduring period of delay

    Increased margins applied to tenders which were

    consequently unsuccessful

    Company prevented from obtaining work during alleged delay

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    135/150

    www.charltonmartin.com 135

    Head Office Overheads and the Use of Formulae

    Loss of Profit

    Principles similar to overheads

    Some contracts exclude claims for loss of profit

    Unless contract excludes both under contract and at common law

    then loss of profit a legitimate claim

    Problems in showing that a profit may have been made but for

    the delay

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    136/150

    www.charltonmartin.com 136

    Head Office Overheads and the Use of Formulae

    Loss of Profit

    Evidence of opportunities to tender on other contracts

    Show all tenders submitted and awarded to demonstrate profit

    level

    Demonstration on balance of probability

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    137/150

    www.charltonmartin.com 137

    Head Office Overheads and the Use of Formulae

    Decision in Walter Lilly

    Judge considered many of above cases

    Contractor can recover overheads and profit lost as result of

    delay on project caused by factors which entitle it to loss andexpense

    Necessary to show on balance of probability criteria as listed

    previously

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    138/150

    www.charltonmartin.com 138

    Head Office Overheads and the Use of Formulae

    Decision in Walter Lilly

    Architect and QS do not need to be certain that loss has occurred.

    Needs to be confident that loss and expense being allowed had

    actually been incurred as a result of the delay and disruption

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    139/150

    www.charltonmartin.com 139

    Recovery by Main Contractor of ReasonableSettlement of

    Sub-Contractors Claims

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    140/150

    www.charltonmartin.com 140

    Recovery by Main Contractor of Reasonable

    Settlement of Sub-Contractors Claims

    Settlement with Sub-Contractor

    WLC had reached a full and final settlement with their sub-

    contractor Norstead at 1,750,000

    26k above amount claimed as entitlement

    Issue as to whether the settlement was reasonable

    R b M i C f R bl

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    141/150

    www.charltonmartin.com 141

    Recovery by Main Contractor of Reasonable

    Settlement of Sub-Contractors Claims

    Decision in Walter Lilly

    Judge referred to Supershield Ltd v Siemens Bui ld in g

    Technolo gies FE Ltd [2010] BLR145

    Employer liable to contractor for contractors liability to his sub-

    contractor

    Not necessary for contractor to prove on balance of probability

    that contractor was liable to sub-contractor or that he would have

    been liable for that amount

    R b M i C t t f R bl

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    142/150

    www.charltonmartin.com 142

    Recovery by Main Contractor of Reasonable

    Settlement of Sub-Contractors Claims

    Decision in Walter Lilly

    For Employer to be liable to contractor, contractor must show

    breach by employer has caused the loss incurred as for causation

    of damages

    Damages not too remote

    Claim and settlement sufficiently strong to be considered

    reasonable

    R b M i C t t f R bl

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    143/150

    www.charltonmartin.com 143

    Recovery by Main Contractor of Reasonable

    Settlement of Sub-Contractors Claims

    Decision in Walter Lilly

    Unless claim so weak that reasonable person would not take itsufficiently seriously to offer settlement, cannot be said that

    settlement was not caused by breach

    Loss must be within contemplation of parties

    R b M i C t t f R bl

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    144/150

    www.charltonmartin.com 144

    Recovery by Main Contractor of Reasonable

    Settlement of Sub-Contractors Claims

    Test for Settlement

    Is amount within range of amounts reasonable people in position of

    settling party might have made

    Following relevant:-

    Strength of claim

    Whether settlement made as result of legal advice

    Uncertainties and expenses of litigation

    R b M i C t t f R bl

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    145/150

    www.charltonmartin.com 145

    Recovery by Main Contractor of Reasonable

    Settlement of Sub-Contractors Claims

    Test for Settlement

    Following relevant:-

    Benefits of settling rather than expenses of litigation

    Question of whether settlement reasonable it to be assessed

    at date of settlement

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    146/150

    www.charltonmartin.com 146

    Conclusion

    Walter Lilly Judgment

    Offers very helpful practical comments and decisions particularly on:-

    Concurrency

    Notices and provision of information as condition precedent

    Amount of information which is contemplated by typical conditions

    Global claims

    Other topics including Practical Completion, Head Office Overheads,

    Recovery of Settlement amounts

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    147/150

    www.charltonmartin.com 147

    CHARLTON MARTIN ONE DAY SEMINAR

    QUESTIONS AND DISCUSSION

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    148/150

    www.charltonmartin.com 148

    CHARLTON MARTIN ONE DAY SEMINAR

    LUNCH BREAK

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    149/150

    www.charltonmartin.com

    CHARLTON MARTIN ONE DAY SEMINAR

    WORKSHOP

    149

  • 8/14/2019 The Latest Authorities on Claims for Delay Disruption and Loss Expense ....pdf

    150/150

    CHARLTON MARTIN ONE DAY SEMINAR

    CLOSE