13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wall panel. In this case, the plans may call for a more substantial beam or lintel that is inset into the panels as illustrated in Figure 12a, b, c, and d. Figure 12a BEAMS OR LINTELS ABOVE WINDOW AND DOOR OPENINGS Figure 12b BEAMS OR LINTELS ABOVE WINDOW AND DOOR OPENINGS – CROSS SECTION Figure 12c BEAMS OR LINTELS ABOVE WINDOW AND DOOR OPENINGS Figure 12d BEAMS OR LINTELS ABOVE WINDOW AND DOOR OPENINGS – CROSS SECTION 2.8 mm x 63 mm galvanised ring–shank nails Foundation 40 mm x 140 mm soleplate Expanding urethane 50 mm x 110 mm bottomplate Double headplate 50 mm x 110 mm edge timber 100 mm x 110 mm timber posts Strip of OSB3 to cover timber Kingspan TEK lintel Kingspan TEK wall panel DPC Foundation 40 mm x 140 mm soleplate 50 mm x 110 mm bottomplate Double headplate 50 mm x 110 mm edge timber 100 mm x 110 mm timber posts Kingspan TEK lintel Kingspan TEK wall panel DPC 2.8 mm x 63 mm galvanised ring–shank nails Foundation 40 mm x 140 mm soleplate 50 mm x 110 mm bottomplate Double headplate 50 mm x 110 mm edge timber 100 mm x 110 mm timber posts Strip of OSB3 to cover timber Kingspan TEK lintel Kingspan TEK wall panel DPC Foundation 40 mm x 140 mm soleplate 50 mm x 110 mm bottomplate Double headplate 50 mm x 110 mm edge timber 100 mm x 110 mm timber posts Kingspan TEK lintel Kingspan TEK wall panel DPC Expanding urethane Bead of expanding urethane Expanding urethane sealant

Transcript of The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often...

Page 1: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

13

5.10 LARGE OPENINGSVery wide windows and large doors often span morethan a full Kingspan TEK Building System wallpanel. In this case, the plans may call for a moresubstantial beam or lintel that is inset into the panelsas illustrated in Figure 12a, b, c, and d.

Figure 12a BEAMS OR LINTELS ABOVE WINDOWAND DOOR OPENINGS

Figure 12b BEAMS OR LINTELS ABOVE WINDOWAND DOOR OPENINGS – CROSS SECTION

Figure 12c BEAMS OR LINTELS ABOVE WINDOWAND DOOR OPENINGS

Figure 12d BEAMS OR LINTELS ABOVE WINDOWAND DOOR OPENINGS – CROSS SECTION

2.8 mm x 63 mmgalvanisedring–shank nails

Foundation

40 mm x140 mm soleplate

Expandingurethane

50 mm x110 mm bottomplate

Double headplate

50 mm x110 mmedge timber

100 mm x110 mmtimber posts

Strip of OSB3 tocover timber

KingspanTEK lintel

KingspanTEK wallpanel

DPC

Foundation

40 mm x140 mm soleplate 50 mm x

110 mm bottomplate

Doubleheadplate

50 mm x 110 mmedge timber

100 mm x110 mmtimber posts

KingspanTEK lintel

KingspanTEK wallpanel

DPC

2.8 mm x 63 mmgalvanisedring–shank nails

Foundation

40 mm x140 mm soleplate

50 mm x110 mm bottomplate

Doubleheadplate

50 mm x110 mmedge timber

100 mm x110 mmtimber posts

Strip of OSB3 tocover timber

KingspanTEK lintel

KingspanTEK wallpanel

DPC

Foundation

40 mm x140 mm soleplate 50 mm x

110 mm bottomplate

Doubleheadplate

50 mm x110 mmedge timber

100 mm x110 mmtimber posts

KingspanTEK lintel

KingspanTEK wallpanel

DPC

Expandingurethane

Bead ofexpandingurethane

Expandingurethanesealant

Page 2: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

14

6 WALL ASSEMBLY – ENTIRE WALL SECTIONS

6.1 SETTING OUT WALL PANELS PRIORTO ASSEMBLYOrganise the Kingspan TEK Building System wallpanels into their designated positions on a levelsurface, (e.g. if the wall panel is resting on acombination soleplate it will not be level and thereforecannot be pulled together as an entire wall section)external face up, to match the detailed constructiondrawings provided with each project, as illustrated inFigure 13a. At this stage leave a 25 mm gapbetween wall panels to aid assembly.

Hint: Prior to undertaking this method of KingspanTEK Building System wall panel erection it isextremely important to plan the sequence of panelassembly so that site or building constraints canbe accommodated.

The Kingspan TEK Building SystemConstruction Manual

6.2 JOINING PANELS USING OSB3 SPLINESSlide the twin OSB3 splines into the Kingspan TEKBuilding System wall panel joints as illustrated inFigure 13b. Pull the wall panels together using aratchet strap having made sure the OSB3 splines arenot intruding into the 50 mm x 110 mm routedchannel at the top and bottom of the wall panels.

For this method of assembly it is recommended(although not essential) that expanding urethanesealant be injected into the rout through appropriatelysized holes, drilled into the joint at approximately300 mm centres as illustrated in Figure 18 anddescribed in section 6.10. (see page 17). This shouldbe done at a convenient time after the wall panelshave been fixed together from both sides (inaccordance with the fixing specification in Table 1,section 2.6) and lifted into their final position.

Figure 13a ENSURE WALL PANELS ARE LAID FLAT

Figure 13b INSTALL OSB3 SPLINES

Figure 13c BRING WALL PANELS TOGETHER USINGRATCHET STRAPS

100 mm x110 mmtimber post

Siliconesealant

Factoryroutedchannels forOSB3splines

Factory routedchannel toaccommodate50 mm x 110 mmbottomplate

50 mm x110 mmbottomplate

40 mm x140 mmsoleplate

ExpandingurethanesealantFoundation

DPM

DPC

KingspanTEK wallpanel

100 mm x110 mmtimber post

Siliconesealant

OSB3 splinesinserted intofactory routedchannel

Factory routedchannel toaccommodate50 mm x 110 mmbottomplate

50 mm x110 mmbottomplate

40 mm x140 mmsoleplate

ExpandingurethanesealantFoundation

KingspanTEK wallpanel

100 mm x110 mmtimber post

Siliconesealant

Factory routedchannel toaccommodate50 mm x 110 mmbottomplate

50 mm x110 mmbottomplate

40 mm x140 mmsoleplates

Expandingurethanesealant

Foundation

DPM

DPC

KingspanTEK wallsection

DPM

DPC

Page 3: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

15

6.3 JOINING WALL PANELS USING TIMBER POSTSWhere timber posts are shown these should beinserted in accordance with section 5.3. Insert timberposts into these channels having applied expandingurethane sealant just before closing the joint. This isillustrated in Figure 14 below.

Figure 14 TIMBER POST JOINT

6.4 CLOSING JOINTS IN WALL SECTIONSWhen using ratchet straps to close joints, it isimperative that the Kingspan TEK Building Systemwall panel edges are adequately reinforced orprotected to prevent damage to the OSB3 facings, asillustrated in figure 13c.

Caution: Do not attempt to lift large KingspanTEK Building System wall sections manually – usecorrect lifting procedures (See section 6.5).

Expandingurethane sealant

2.8 mm x 63 mmgalvanisedring–shank nails

100 mm x 110mm timber post

Page 4: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

16

Figure 16a FORMATION OF CORNER JOINT INWALL

The Kingspan TEK Building SystemConstruction Manual

Figure 15 BRACING WALL SECTIONS

6.6 FIXING WALL PANELS TOGETHER ATCORNERSFix through the corners into the end timbers throughpre-drilled 4 mm dia. holes in accordance with thefixing specification in Table 1, section 2.6 andillustrated in Figure 16a and b below. It is extremelyimportant to apply two continuous beads of siliconesealant along these types of joint.

Figure 16b FIXING WALL PANELS TOGETHER ATCORNERS

50 mm x110 mmheadplate

Foundation

Bring KingspanTEK wall panelstogether to formcorner joint

Kingspan TEKwall panel

40 mm x140 mmsoleplate

Adjustablesteel wallbrace

Expandingurethanesealant

50 mm x110 mmend timber

Temporarywall braceon outsideedge

DPC

Kingspan TEKwall section

50 mm x 110 mmbottomplate

2.8 mm x 63 mmgalvanisedring–shank nails

Expandingurethane sealant

50 mm x110 mmend timbers

2 beads of silicone sealant

Kingspan TEK wall panel

2.8 mm x 63 mmgalvanisedring–shank nails

50 mm x110 mmend timbers

Silicone sealant

6.0 mm x 210mmsparrennagel

6.5 RAISING THE WALLApply a bead of expanding urethane sealant onto thebottomplate. Tilt the Kingspan TEK Building Systemwall section using either a crane or anotherappropriate piece of mechanical lifting equipmentand following the contractor’s method statement forsafe working. Attach temporary wall braces asrequired. To ensure the wall section is plumb andremains so, brace wall ends on the outside edge asillustrated in Figure 15. Attaching the wall braces tothe outside edge allows room on the floor surface forassembly of further wall sections.

Page 5: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

17

6.8 ASSEMBLY, NAILING AND RAISING OFFURTHER WALL SECTIONSFurther Kingspan TEK Building System wall sectionsshould be constructed and erected in the samemanner as described in sections 6.1 to 6.6.

Hint: Ensure Kingspan TEK Building System wallsections are erected in the correct sequence so asto optimise the use of working space andresource.

Particular care should be exercised when assemblingthe wall sections that include either window or dooropenings. In certain situations some additionaltemporary bracing members may be necessary,nailed across breaks in Kingspan TEK BuildingSystem wall panel edges.

6.9 SEALING PANEL JOINTS IN WALL SECTIONSDrill 10 mm dia. holes at 200 mm centres along theKingspan TEK Building System wall panel joints asshown in Figure 18. Introduce expanding urethanesealant into the hole so that it expands into the paneledge rout to create an airtight joint.

NB This operation should only be undertaken whereapplication of the expanding urethane sealand cannotbe done in advance,

Figure 17 INSTALLING AND FIXING HEADPLATES

Figure 18 SEALING WALL PANEL JOINTS

6.7 INSTALLING HEADPLATESHeadplates tie the Kingspan TEK Building Systemwall panels together and provide a continuous solidsurface to support the first floor construction. Headplatejoints should be staggered so that they offset wallpanel joints by a minimum of 300 mm. All OSB3splines, timber posts and end timbers should notintrude into the routed channel that will accommodatethe headplate. Expanding urethane sealant should beapplied into the routed channel. The headplate shouldthen be located within this channel and fixed inaccordance with the fixing specification in Table 1,section 2.6 as illustrated in Figure 17.

2.8 mm x 63 mmgalvanisedring–shank nails

Installation of 50 mm x 110 mmheadplates

Expandingurethanesealant

KingspanTEK wallpanel

15 mm x 100 mm0SB3 splines

10 mm dia. holes at 300 mmcentres

Application of expandingurethane sealant through 10 mmdia. holes

Kingspan TEK wall panel

2.8 mm x 63 mmgalvanised ring–shank nails

Hint: Ensure that sufficient wall braces are used tostabilise the wall construction during the erectionof the final storey and that these remain in placeuntil the roof has been completed.

Page 6: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

18

7 INSTALLATION OF PRINCIPAL BEAMS WITHIN FLOORS AND ROOFS

7.1 GENERALBeams and purlins may be necessary to support roofand floor constructions. They can be supporteddirectly by the Kingspan TEK Building System wallpanel or in pockets with timber posts beneath. Figure19 below identifies common locations for principalbeams and purlins.

Figure 20b CROSS SECTION THROUGH WALLSHOWING INSTALLED BEAM

The Kingspan TEK Building SystemConstruction Manual

Figure 20a INSTALLATION OF A BEAM IN A WALL

Figure 19 TYPICAL BEAM LOCATIONS

7.2 INSTALLING PURLINS/BEAMSPurlins/beams are located within pockets cut into theKingspan TEK Building System wall panels. A timber post below the pocket supports thepurlin/beam. Timber posts and pockets are locatedon wall panel joints to facilitate routing andpreparation of the beam pocket. Scabs are installedeither side of the beam and should be fixed so theydo not intrude on the routed channel of the wallpanel. This is illustrated in Figures 20a and 20b.

All timber posts below pockets should be sealed inposition using expanding urethane sealant and fixedin accordance with the fixing specification in Table 1,section 2.6.

Temporarybracing toprevent lateraldeflection

Purling

Ridgebeam

Siliconesealant

Kingspan TEKwall panel

2.8 mm x63 mmgalvanisedring–shanknails

50 mm x110 mmscab

2 beads ofsiliconesealant

Siliconesealant

Beam

Factory routedchannel toaccommodate50 mm x 110 mm headplate

Expandingurethanesealant

Expandingurethanesealant

2.8 mm x63 mmgalvanisedring–shanknails

Beam

50 mm x 110 mmheadplates tightlybutted to beam

100 mm x110 mmtimber post

Page 7: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

19

8 FIRST FLOOR DECK

8.1 HANDLING PANELSAll materials for floor construction shall be carefullylifted onto safe working platforms ready for installationusing either a crane or other suitable mechanical liftingequipment. At all times refer to the contractors methodstatement for undertaking these types of procedures.

8.2 INSTALLING FLOOR BEAMSInstall as previously described in section 7.

8.3 POSITIONING AND FIXING JOIST HANGERSONTO THE WALLS AND BEAMSMark out the location of all joists along the headplateof the ground floor wall panels and beams accordingto the design drawings. Fix joist hangers into theheadplate and beams at the marked locations, asillustrated in Figure 21. At all times reference shouldbe made to the joist hanger manufacturersrecommended installation instructions. These can befound in Appendix E.

8.4 INSTALLING FLOOR JOISTSJoists should be located into corresponding joisthangers and fixed in place in accordance with themanufacturers instructions. The top of the installedjoists should be at the same height as the top of theheadplate. This is illustrated in Figure 21.

Where floor joists bear directly over an internal wall,the joist should be fixed in position using 2 No.3.35 mm x 75 mm nails or as per joist manufacturersinstructions (see Appendix E).

For all other details and specifications refer to theappropriate manufacturers installation details andinstructions.

8.5 RIMBOARD/PLATFORM FRAME INSTALLATIONMark out the joist positions and fix the joists in place atthese locations by fixing through the bottom flange intothe headplate, ensuring that sufficient space is left for therimboard (usually between 32 and 60 mm thick). Attachthe rimboard to the ends of the joists and fix through therimboard into the headplate in accordance with thefixing specification in Table 1, Section 2.6. Duringassembly, use silicone to seal between the rimboard andthe headplate. This is illustrated in Figure 22.

For all other details and specifications refer to the joistmanufacturers installation details and instructions(see Appendix E).

Figure 21 LOCATING AND FIXING JOIST HANGERSFOR FIRST FLOOR DECK

Figure 22 LOCATING AND FIXING RIMBOARDSFOR FIRST FLOOR DECK

Kingspan TEKwall panel

2.8 mm x63 mmgalvanisedring–shanknails

3.75 mm x32 mmsquare twistshank nails

50 mm x110 mmheadplate

Joisthanger

I-Beam

2 beads ofsilicone sealant

KingspanTEK wallpanel

50 mm x110 mmheadplate

I-Beam

Rimboard

Expandingurethanesealant

Siliconesealant

1 bead ofsilicone sealant

Page 8: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

20

8.7 FIXING BOTTOMPLATES FOR UPPERSTOREY WALLSThe bottomplates should be fixed through the OSB3deck into the headplate/rimboard in accordance withthe fixing specification in Table 1, section 2.6.The outer edge of the bottomplate should be inset 15 mm from the edge of the OSB3 deck so that theexternal OSB3 face of the upper storey KingspanTEK Building System wall panels will be flush.This is illustrated in Figures 24a and 24b.

8.6 INSTALLING FIRST FLOOR DECKWith the first floor joists in place, the 18 mm tongueand groove OSB3 deck is then installed.

Lay the OSB3 sheets in a staggered pattern,perpendicular to the joists and flush with the outside ofthe external OSB3 facing/rimboard. Immediately priorto installing the OSB3 sheets located around theperimeter of the building a thin layer of silicone sealant should be is applied to the top surface of theheadplate/rimboard to provide an airtight seal. This is illustrated in Figures 23a and 23b.

Fix the OSB3 sheets to the joists and headplate/rimboard in accordance with the fixing specificationin Table 1, section 2.6. At all times this should be inaccordance with the deck manufacturers installationinstructions (see Appendix E).

The Kingspan TEK Building SystemConstruction Manual

Figure 23a INSTALLATION OF JOIST HANGARS

Figure 23b INSTALLATION OF RIMBOARD

Figure 24a INSTALLING BOTTOMPLATE OVER FIRSTFLOOR DECK (JOIST HANGAR DETAIL)

Caution: Temporary handrails or guarding shouldbe placed around all free edges and stairwells.

Figure 24b INSTALLING BOTTOMPLATE OVER FIRSTFLOOR DECK (RIM BOARD DETAIL)

KingspanTEK wallpanel 50 mm x

110 mmheadplate

Expandingurethanesealant

2 beadsof siliconesealant

18 mmOSB3floordecking

2.8 mm x 63 mmgalvanisedring–shank nails

3.75 mm x32 mmsquare twistshank nails

Joisthanger

I-beam

KingspanTEK wallpanel

50 mm x110 mmheadplate

Siliconesealant

1 bead ofsiliconesealant

3.35 mm x 65 mmround wire nails

3.75 mmx 75 mmroundwire nails

I-beam

18 mmOSB3decking

KingspanTEK wallpanel

50 mm x 110 mmbottomplate

3.1 mm x 90 mmgalvanisedring–shank nails2.8 mm x

63 mmgalvanisedring–shanknails

3.75 mm x32 mmsquare twistshank nails

Expandingurethane sealant

Joist hanger

2 beads ofsilicone sealant

18 mmOSB3 floordecking

KingspanTEK wallpanel

50 mm x 110 mmbottomplate

50 mm x110 mmheadplate

3.1 mm x 90 mmgalvanisedring–shank nails

3.35 mm x 65 mmgalvanisedring–shank nails

Expandingurethanesealant

2 beads ofsilicone sealant

18 mmOSB3 floordecking

Page 9: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

21

9 INSTALLING UPPER STOREY WALLPANELS, ATTIC JOISTS AND ROOF

BEAMS / PURLINS

9.1 HANDLING PANELSAll materials should be carefully lifted into position onsafe working platforms ready for installation, usingeither a crane or other appropriate mechanical liftingequipment. At all times refer to the contractors methodstatement for undertaking these types of procedures.

9.2 ERECTION OF WALL PANELSUsing a similar process as that described forKingspan TEK Building System ground floor walls,additional storeys may be constructed.

The uppermost Kingspan TEK Building System wallpanels are often fitted with additional bevelledwallplates to match the roof slope. All wall panelsrequire either a standard headplate or specially cutbevelled headplate, fixed into the factory cut rout inaccordance with the fixing specification in Table 1,section 2.6.

Hint: When erecting Kingspan TEK BuildingSystem gable wall panels, always start from thecentre (e.g. in line with the ridge beam) so whenthe ridge beam is installed it is straight.

Ensure that all wall panels are fully assembled andpermanently fixed in position prior to moving onto thenext stage of the erection. Once the first floor wallshave been erected, the scaffolding can be completedto full height.

Hint: Ensure that sufficient wall braces are used tostabilise the wall construction during the erectionof the final storey and that these remain in placeuntil the roof has been completed.

9.3 INSTALLING FLOORS FOR ROOM-IN-ROOFCONSTRUCTIONIn buildings with a room-in-roof floor, the floorconstruction should be installed in the normal wayensuring that the deck is fully fixed to the perimeterheadplate. A bevelled wallplate should then be fixedin position as shown in the detail below to provide anattachment for the roof panels. This is illustrated inFigure 25.

Figure 25 ROOM–IN–ROOF FLOOR DETAIL

KingspanTEK roofpanel

Kingspan TEK wall panel

50 mm x110 mmheadplate

2.8 mm x 63 mmgalvanised ring-shank nails

Joisthanger

I-beam

2 beads ofsilicone sealant

Siliconesealant

18 mmOSB3 floordecking6.0 mm x

210 mmsparrennagel

Bevelled endtimber

Page 10: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

22

The Kingspan TEK Building SystemConstruction Manual

9.5 INSTALL TEMPORARY BRACES FOR PURLINSAND RIDGE BEAMAll roof beams should be held firmly in position usingtemporary bracing as illustrated in Figure 27 toprevent lateral deflection during the erection of theKingspan TEK Building System roof sections. Bracingshould be spaced at no more than 3.0 m centres.This temporary bracing can be removed once all roofsections have been fixed in their final positions.

9.4 INSTALLATION OF PURLINS/RIDGE BEAMSKingspan TEK Building System gable wall panelsoften support purlins and/or a ridge beam. Thesebeams are installed in exactly the same way as theywere for first floor beams (See section 7). Installationof purlins and ridge beams is illustrated in Figure 26.

For more complicated roof designs that incorporatehip or valley beams, reference should be made to theparticular project specification. Care should be takento ensure that all beams are connected together usingthe correct fixing or connector.

Figure 26 INSTALLING RIDGE BEAMS/PURLINS Figure 27 TEMPORARY BRACING TO PURLIN ANDRIDGE BEAMS

Installationof purlins

Factory routedsockets for ridgebeam and purlins

Installation of temporarybracing to prevent deflection

Page 11: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

23

10 PREFABRICATION ANDINSTALLATION OF ROOF SECTIONS

10.1 LIFTING ROOF SECTIONS INTO POSITIONKingspan TEK Building System roof sections shouldbe lifted into position using a crane fitted with anadjustable chain as illustrated in Figures 28a and 28b.

Hint: Attach timber battens to the internal face ofthe Kingspan TEK Building System roof sectionsimmediately above the lines of support to act aslocators when positioning the roof and to facilitateattachment to the walls/beams. This is illustratedin Figure 28b.

Caution: Lifting and positioning roof sections or panels onto the roof manually should not be attempted.

To lift Kingspan TEK Building System roof sections,drill four holes (25 mm – 40 mm diameter) through theroof section making sure that the holes will not end upover a supporting wall or purlin. Insert a lifting strap intoeach hole, as illustrated in Figure 28a. The straps shouldspread the load through the use of a 50 mm x 50 mm x500 mm solid timber located beneath the roof section.

Caution: Under no circumstances should any sitepersonnel stand underneath or in line with a roofsection panel being hoisted onto a roof.

Figure 28a LIFTING AND POSITIONING ROOFSECTIONS ONTO THE ROOF WITH A CRANE

Figure 28b TIMBER BATTENS ON INTERNAL FACE OFROOF SECTION

Figure 29a INSTALLATION OF ROOF SECTIONS

Figure 29b FIRST OPPOSING PAIR OF ROOFSECTIONS INSTALLED

Installation of firstKingspan TEK roofsection

Adjustablesection inliftingequipment*

Purlins, ridge beamsand temporary bracinginstalled ready toreceive TEK roofsections

*Set correct angle once. Following roof sections can be set without furtheradjustments unless change in roof pitch.

Kingspan TEKroof sections

Kingspan TEKgable wall panel

Kingspan TEKdwarf wall panel

Temporary batten tohold roof panel inplace while fixing

50 mm x 110 mmend timber

2.8 mm x 63 mmgalvanisedring–shank nails

Installation of secondKingspan TEK roof section

10.2 PREPARATION OF ROOF STRUCTURE TORECEIVE ROOF PANELSApply two beads of silicone sealant to all gable wallheadplates, bevelled wallplates, bevelled headplatesof dwarf walls and the bevelled faces of the ridge beam.

10.3 INSTALLATION OF ROOF SECTIONS

Hint: Silicone sealant should always be appliedbetween surfaces that are to be joined rather thanalong the edges of joints once fixed.

All Kingspan TEK Building System roof sectionsshould be accurately lifted into position (at the pitch ofthe roof) avoiding excessive sway. Care should betaken when lowering the roof section into position toavoid wiping off the silicone sealant.

Hint: Kingspan TEK Building System roof sectionjoint locations should be marked on the purlins,ridge beams, wallplates and bevelled headplatesof dwarf walls, so that the roof sections can bequickly positioned and aligned.

Roof sections should ideally be fixed in opposing pairsin order to control lateral loading and deflection asillustrated in Figure 29, although practically this is notalways possible. Also, ensure you apply two beads ofsilicone along the ridge between the roof sections toensure the joint is airtight. This is illustrated in Figure 29.

Page 12: The Kingspan TEKBuilding System...13 5.10 LARGE OPENINGS Very wide windows and large doors often span more than a full Kingspan TEK Building System wallpanel. In this case, the plans

24

Figure 31b FIXING ROOF SECTION INTO GABLEWALL (NO OVER HANG)

Figure 32 WALL/ROOF INTERSECTION SHOWINGANGLED HEADPLATE DETAIL

Figure 33 FIXING ROOF SECTION AT THE RIDGE

The Kingspan TEK™ Building SystemConstruction Manual

10.4 FIXING THE FIRST ROOF SECTION IN PLACEThe Kingspan TEK Building System roof sectionshould then be lifted into place so that the timberbattens bear onto the sides of all bearing points asillustrated in Figures 28a and 28b.

The roof section should then be fixed along the gableheadplate, bevelled wallplate, bevelled headplate ininternal support walls and any intermediate/ridgebeams or purlins in accordance with the fixingspecification in Table 1, section 2.6*. This fixingprocess is illustrated in Figures 30 -33 below.

*Refer to structural calculations for any variations in fixing centres.

Figure 30 FIXING ROOF SECTION INTO PURLIN

Figure 31a FIXING ROOF SECTION INTO GABLEWALL (OVER HANG)

Kingspan TEK gable wall panel

KingspanTEK roofsection

2 beads of silicone sealant

2.8 mm x 63 mm galvanisedring–shank nails

Expanding urethane sealant

6.0 mm x 210 mm sparrennagel

Kingspan TEK gable wallpanel

KingspanTEK roofsection

2 beads of silicone sealant

2.8 mm x 63 mm galvanisedring–shank nails

Expanding urethane sealant

50 mm x 110 mm end timber

50 mm x 110 mm head plate

6.0 mm x 210 mm sparrennagel

Kingspan TEK dwarfwall panel

KingspanTEK roofsection

2 beads ofsilicone sealant

2.8 mm x 63 mmgalvanised ring–shanknailsExpanding urethanesealant

150 mm x 110 mmbevelled end timbers

150 mm x 110 mmbevelled headplate

6.0 mm x 210mm sparrennagel

Temporary batten

KingspanTEK roofsection

Siliconesealant

2.8 mm x 63 mmgalvanisedring–shank nails

Ridgebeam

150 mm x110 mmbevelledend timbers

6.0 mm x210 mmsparrennagel

Purlin

2 beads ofsilicone sealant

6.0 mm x 210 mmsparrennagel

KingspanTEK roofsection