THE KENYA POWER LIGHTING COMPANY LIMITED ... - · PDF fileUPDATED RETAIL TARIFFS APPLICATION...

59
THE KENYA POWER & LIGHTING COMPANY LIMITED UPDATED RETAIL TARIFFS APPLICATION TO ENERGY REGULATORY COMMISSION INITIAL SUBMISSION ON 4 TH FEBRUARY 2011 UPDATED VERSION DATED 7 TH FEBRUARY 2013

Transcript of THE KENYA POWER LIGHTING COMPANY LIMITED ... - · PDF fileUPDATED RETAIL TARIFFS APPLICATION...

 

THE KENYA POWER & LIGHTING COMPANY LIMITED   

UPDATED RETAIL TARIFFS APPLICATION   

TO   

ENERGY REGULATORY COMMISSION  

INITIAL SUBMISSION ON 4TH FEBRUARY 2011  

UPDATED VERSION DATED 7TH FEBRUARY 2013        

      

  i

TABLE OF CONTENTS  

1. ............ Performance of the Company since the last Tariffs Review  1 1.1. ......... Introduction  1 2. ............ Power Supply Situation  2 2.1. ......... Projected Demand/Medium –Term Committed Generation Projects  3 3. ............ Revenue Requirements for Committed Power plants  4 3.1. ......... Committed KenGen Power Plants  4 3.2. ......... Outstanding existing bulk PPA issues needing re‐negotiation between KPLC and 

KenGen  4 3.3. ......... Committed Independent Power Producers Power Plants  5 4. ............ Revenue Requirements for Transmission and Distribution Business  5 4.1. ......... Historical Expansions of Transmission and Distribution Network  5 4.2. ......... Number of Customers per Tariff Category  5 4.3. ......... Staff Analysis  5 4.4. ......... System Losses Projections  6 4.5. ......... Transmission and Distribution Investment Projects  7 4.6. ......... T&D Operations and Maintenance Costs  7 4.7. ......... Existing Rural Electrification Schemes Operating Framework  8 4.8. ......... Transmission and Distribution  Wheeling Arrangement  8 4.9. ......... Proposal for Low Voltage System Expansion  9 4.10. ....... Proposal by ERC to Implement a Hydro‐Risk Mitigation Fund  10 4.11. ....... Proposed implementation of Time of use tariffs  11 4.12. ....... Way leave Levies & charges demand by Government Institutions  11 4.13. ....... Other Proposed Government Institutions Levies  12 4.14. ....... Rate Asset Base and Revenue Requirement  13 4.15. ....... Average  Revenue Requirement Per Unit of Electricity Sales  14 4.16. ....... Breakdown of Average per Unit Projected Retail Tariffs  15 4.17. ....... Financial Projections  15 4.17.1. .... Energy Balance  15 4.17.2. .... Projected Financial Results  16 4.18. ....... Pre‐paid Metering  17 5. ............ Tariff Design  17 5.1. ......... Proposed Retail Tariff Rates  17 5.2. ......... Proposed Retail Tariffs by Customer Categories  18 5.3. ......... Proposed changes in FCC, FERFA and INFA formulae  19 5.4. ......... Effective Date  20 6. ............ Conclusion and Recommendation  20 6.1. ......... Conclusion  20 6.2. ......... Recommendation  20  APPENDICES  21 Appendix 1: Proposed Schedule of Tariffs & Rates 2013 21 Appendix 2 – Financial Projections Assumptions  44 Appendix 3:  Tables 15, 16, 17, 18, 19 and 20 (as described below)  47 

      

  ii

LIST OF TABLES  Table 1  Financial Projection Vs. Actual Performance          1   Table 2:  Committed Generation Projects            3 Table 3:  Committed KenGen Power Plants Charge Rates        4   Table 4:  IPP Committed Power Plants Charge Rates          5 Table 5:  Staff Analysis (Permanent & Contract)          6 Table 6:  Customer Power Connection Costs Vs Capital Contribution 2007/08 to  

2011/12                  9 Table 7:  Wayleave Levies Demanded by Local Authorities and GoK Agencies  11 Table 8:  Total Revenue Requirement for KPLC           13 Table 9:  KPLC Revenue Requirement (In September 2012 prices) KShs/kWh   14 Table 10:  Breakdown of Revenue Requirement in KShs/kWh (in Sept 2012 prices)  15 Table 11:  Projected Financial Performance 2012/13 to 2015/16      16 Table 12:  Proposed Retail Tariff Rates              17 Table 13:  Distribution of Proposed Tariff Revenue Requirement Yield Change in  

Percentage Per Applicable Period            18 Table 14:  CBK Mean Exchange Rates of Major Currencies        19 Table 15:  Number of customers by Tariff Categories          47 Table 16:  Medium Term Capacity Balance for Average Hydrology (MW)    48 Table 17:  Medium Term Energy Balance for Average hydrology (GWh)    50 Table 18:  Transmission and Distribution Investment Plan        52 Table 19:  Transmission and Distribution Lines, Circuit Lengths in Kilometres    54 Table 20:  Transformers  in Service, Total Installed Capacity in MVA      55   

                       

  iii

  

Acronyms and abbreviations  EDF    Electricitè De France EPZ     Export Processing Zone ERC    Energy Regulatory Commission F.I.T.    Feed‐in‐ Tariff FCC    Fuel Cost Charge FERFA    Foreign Exchange Rate Fluctuation Adjustment  FOM              fixed operation and Maintenance G.T.    Gas Turbine GoK    Government of Kenya GWh    Gigawatt hour IPPs    Independent Power Producers: KEEP    Kenya Electricity Expansion Project KenGen     Kenya Electricity Generating Company KETRACO    Kenya Electricity Transmission Company   KPLC    The Kenya Power & Lighting Company Limited  kV      Kilovolt kVA    Kilovolt Ampere kWh    Kilowatt Hour kW‐yr    Kilowatts  per year LCPD    Least Cost Power Development LRMC    Long Run Marginal Cost MSD    Medium Speed Diesel MVA    mega Volts Amperes MW    Mega Watt NBV    Net Business Value NDZ    New Development Zones O&M    Operations and Maintenance Opex    Operation Expenditure p.a.    Per Annum PPAs    Power Purchase Agreements  PRG     Partial Risk Guarantee RAB    Regulated Rate Base RE      Rural Electrification REA     Rural Electrification Authority REP    Rural Electrification Programme T&D    Transmission & Distribution V      Voltage   VOM    Variable operation and Maintenance  

      

  1

1. Performance of the Company since the last Tariffs Review 

 

1.1. Introduction 

 This submission  is an update of  the Retail Tariff Review Application dated 4th February 

2011  and  submitted  to  the  Energy  Regulatory  Commission  (ERC)  on  the  same  date,  in accordance with  the agreement  reached at various meetings between  the Government of Kenya, KPLC and the Commission, to enable the Commission process our requests for retail electricity  tariff  review  for  the  tariff  control  period  2011/12  to  2013/14  (now  to  cover 2012/13 to 2015/16).  

KPLC  purchases  electric  power  capacity  and/or  energy  from  the  Kenya  Electricity Generating  Company  Limited  (KenGen)  and  six  Independent  Power  Producers  (IPPs), who currently  are,  Iberafrica  Power  (EA),  Tsavo  Power  Company  Limited  (TPC),  Rabai  Power Limited, OrPower4 Inc. (OrPower4), Mumias Sugar Company Limited and Imenti Tea Factory Small hydros.  The Company also purchases energy from Tanzania Electricity Supply Company Limited  (TANESCO)  and  Uganda  Electricity  Transmission  Company  Limited  (UETCL)  and Ethiopian Electric Power Corporation  (EEPCO). The purchase of generating  capacity and/or energy  from  all  of  these  generators  is  made  under  Power  Purchase  Agreements  (PPAs) approved by ERC.  

The existing  retail tariffs were approved by  the Energy Regulatory Commission  (ERC)  in June 2008 for implementation from 1st July 2008. Table 1 shows the financial performance of KPLC for the period 2008/09 to 2011/12 financial years and a comparison with the financial projections  for  the period 2008/09 and 2010/11, upon which  the 1st  July 2008  tariffs were set. 

Table 1: Financial Projection Vs Actual Performance 

   2008/09  2009/10  2010/11  2011/12 

KPLC  Proj  Actual  Proj  Actual  Proj  Actual  Actual 

Units Sold(Exc. RE) in GWh  5,462  5,182  5,852  5,345  6,299  5,816  6,033 

System Losses (in %)  16.40% 16.30% 15.90% 16.00% 15.40%  16.20%  17.30% 

Non‐Fuel Yield (Ksh/kWh)  7.00  7.13  7.01  7.48  7.33  8.12  8.91 

Fuel  Cost Charge in Ksh/kWh  5.54  5.46  3.46  6.21  2.68  4.46  6.94 

Unit Yield(Ksh/kWh)  12.55  12.58  10.47  13.69  10.01  12.58  15.86 

in Ksh. Million                      

Non‐Fuel Revenue  39,839  36,940  42,757  39,976  48,098  47,241  53,767 

  2

   2008/09  2009/10   2010/11    2011/12 

KPLC  Proj  Actual  Proj  Actual  Proj  Actual  Actual 

Fuel Recovery  31,539  28,269  21,085  33,191  17,553  25,913  41,896 

Other Revenues     1,154     1,541     1,413  1,788 

Total Revenue  71,378  66,363  63,842  74,708  65,651  74,567  97,451 

Power  Purchase:                      

Total Gen Non‐Fuel  18,185  18,770  20,155  20,516  23,661  23,639  26,173 

                  Fuel  31,539  28,348  21,085  33,331  17,553  26,151  42,789 

Total  49,724  47,118  41,240  53,847  41,214  49,790  69,962 

Trading margin  19,689  19,245  22,602  20,861  24,437  24,777  27,489 

Trading Margin as % of Total Revenue 

28%  29%  35%  28%  37%  33%  28% 

Total T&D costs  15,392  13,570  15,747  14,911  16,222  18,522  18,982 

Pre­tax Profit  4,297  4,782  4,663  5,633  5,669  6,255  8,507 

 From the  foregoing,  it  is clear that the projected sales  levels were not realized due to 

the  depressed  economic  performance  as  a  result  of  adverse  effects  of multiple  shocks 

including  the post‐general election violence  in early 2008, a  severe drought  that affected 

most parts of the country, high  international commodity prices and spill‐over of the global 

financial  crisis.  Further,  although  the  system  losses  target  for  the  initial  two  years of  the 

current tariff control period were met, going forward additional system losses reduction will 

continue to be a challenge for KPLC especially  taking into account the current transmission 

capacity  constraints,  distribution  network  expansion,  increased  customer  connectivity 

activities and the intensified Rural Electrification Programme.

2. Power Supply Situation  

The  Interconnected  Installed Capacity currently stands at 1,672 MW,  including  the 120 MW of the emergency capacity.  The current national interconnected system peak demand is 1,330MW  (or  1334MW  inclusive  of  Uganda)  recorded  in  January  2013.    This  peak  is considered suppressed due to unmet demand when  it occurred and would have been even higher were  it not for high fuel costs as a result of high international commodity prices and stepped  up  thermal  generation,  slower  than  expected  recovery  of  the  economy  due  to 

  3

multiple local factors and spillover of the global financial crisis and some customers being out of supply due to power outages and load shedding.  There was no reserve margin when the peak  demand  was  recorded  but measures  are  on‐going  to  fast‐track  implementation  of generation projects aimed at boosting the reserve margin to at least 15% which is necessary to take care of unplanned system outages.   The  lack of reserve margin continues to expose the power system to instability and national blackouts in the event of unplanned outages of larger generating units.  

Several  committed  power  generation  projects  are  currently  under  implementation.  These will displace the 120 MW of emergency power, improve security of supply, reduce cost impact to customers and assist in meeting the forecast demand in the medium to long term.  

 2.1. Projected Demand/Medium –Term Committed Generation Projects  

The overall generation expansion projects for the next five years will entail an additional  1,248 MW to meet growth in electricity demand which has averaged 5% annually in the last 4 years. Under the Government medium term‐ fiscal framework, real gross domestic product is expected  to have  increased by between 3.5% and 4.5%  in 2012 calendar year compared  to the World Bank forecast of 4.3%. KPLC estimates that  in 2012/13 electricity demand growth rate will be  4% based on  trends  recorded upto December  2012  and  the  economic  growth forecast  for  the  current  financial  year  riding  on  on‐going  economic  recovery.  In  the  years 2013/14, 2014/15 and 2015/16 the demand growth rate is assumed to be  6% per year.  

 As shown in Table 2, generation capacity of 851MW is planned to be developed by IPPs 

and 397MW by KenGen, respectively. The plants are expected to be commissioned between 2013 and 2016. 

 Table 2: Committed Generation Projects  

   Project  Type Capacity (MW) 

Est. Commissioning Date 

KENGEN     

   Wellhead Units  Geothermal  10  Jun‐2013 

   Wellhead Units  Geothermal  15  Dec‐2013 

   Wellhead Units  Geothermal  40  Dec‐2014 

   Ngong phase II   Wind  13.6  Jul‐2014 

   Ngong 1 phase II  Wind  6.8  Jul‐2014 

   Kindaruma 3rd unit  Hydro   32   June 2012‐June 2013 

   Olkaria IV   Geothermal  140  Sep‐2014 

   Olkaria 1 –Life Extension  Geothermal  140  Jun‐2014 

Sub‐Total        397     

IPPs     

   Athi River 1  Diesel  80  Jan‐2014 

   Athi River 2  Diesel  83  Feb‐2014 

   Thika 1  Diesel  87  Jun‐2013 

   Lake Turkana   Wind  300  Jul‐2015 

   Aeolus wind  Wind  60  Jan‐2015 

   Orpower4  Geothermal  36  Mar‐2013 

  4

   Project  Type Capacity (MW) 

Est. Commissioning Date 

   Orpower4  Geothermal  16  Mar‐2014 

   Kipeto  Wind  100  Jul‐2015 

   Prunus  Wind  50  Jul‐2015 

   Kwale Sugar Co. Ltd  Biomass  18  Dec‐2014 

  Small Hydros (Genpro, Gura and Hydel)  hydro   21  Jul‐2015 

Sub‐ Total         851    

Total         1,248     

3. Revenue Requirements for Committed Power plants  

3.1. Committed KenGen Power Plants 

The Least Cost Power Development Plan has committed KenGen plants that are expected to be commissioned  in the Review Period and whose estimated charge rates would entail a review of the KPLC revenue requirement so as to meet the incremental power purchase cost for the next tariff control period as shown in Table 3. 

 Table 3: Committed  KenGen Power Plants Charge Rates  

         Cap. Charge     FOM  VOM 

     Capacity  KSh/kW‐yr  Comm. 

KSh/kW‐yr 

KSh/kWh 

   Plant  MW     Year  (escal.)  (escal.) 

1  Olkaria 1‐ Extension (Units & 5)   140  19,463 Jun‐14 5,551  0.9252 

2  Olkaria 1V   140  22,156 Sep‐14 5,536  0.9282 

3  Olkaria 1 Interim       Jun‐14    3.2562 

 Energy Plants                                                                                                                              in US$/kWh  

4  Well heads units  75     Jun‐11    0.085 

                          Kshs/kWh 

            Esc   Non‐Escal  Total 

5  Sangoro  20    1.60  5.189  6.789 

6  Eburru Geothermal  2.2    2.00  5.44  7.44 

7  Ngong Phase II*  13.6      1.30  4.79  6.09 

8  Ngong 1 Phase II*  6.8      1.30  4.79  6.09  

*The rate assumed for Ngong phase II are those of existing 5MW  

3.2. Outstanding existing bulk PPA issues needing re‐negotiation between KPLC and KenGen 

 This application does not  take  into account  the outstanding  issues between KPLC and 

KenGen on existing PPAs. KPLC proposes  the Commission  to  issue advice and guidance on the way forward. 

  5

3.3. Committed Independent Power Producers Power Plants  

 The  Least Cost Power Development Plan’s  committed  IPP plants, whose estimated 

charge rates would entail a review of the KPLC revenue requirement so as to meet the incremental power purchase cost for the Review Period, are shown in Table 4. 

 Table 4: IPP Committed Power Plants Charge Rates 

     Capacity In Service Fixed  Escalable  Variable    MW  year  Capacity Charge  (escal.)   Plant  US$/kW‐yr  US$/kW‐yr  US$/kWh   IPP 1   Orpower  36  Mar‐13  262.5  285  0.02304 2  Orpower  16  Mar‐14  262.5   285  0.02304 3  Triumph Gen. 

Plant  87  Jun‐13  157.5  36  0.0074 

4  Aeolus Wind  160  Nov‐12  0.12 5  L.Turkana Wind  300  Jul‐13      0.12 6  Kipeto  100  Jul‐15       0.12 7  Prunus  50  Jul‐15       0.12 8  Kwale Sugar  18  Dec‐14   0.10 9  FIT Hydros  21  Jul‐15       0.0825            €/kW‐yr  €/kW‐yr  €/kWh 

10  Thika Power  87  Jun‐13  157.5  37.71  0.0074 11  Gulf Power  85  Feb‐14  164.36  37.17  0.0063 

 

4. Revenue Requirements for Transmission and Distribution Business  4.1. Historical Expansions of Transmission and Distribution Network  

Transmission  and  distribution  line  lengths  grew  by  22.2%  and  2.6%,  in  2006/07  and 2011/12  respectively,  as  shown  in  Table  19.  Generation,  transmission  and  distribution substations capacities have  increased  from 1,596 to 1,846, respectively,  in the same period as shown in Table 20. The installed MVA capacity of distribution transformers increased from 3,515  to  5,784  corresponding  to  a  growth  of  64%.  The  transmission  and  distribution expansion has been necessary  to support peak demand  that grew by 35%  from 987MW  in 2006/07 to 1,330MW in 2012/13.  4.2. Number of Customers per Tariff Category  KPLC customer base shown in Table 15  recorded an  annual average growth rate of 20% 

over  the  last  five years with  significant parts of  the overall    increase   being  recorded  from   domestic customers category that expanded by 22%. This is attributed to the Company focus on  increasing  new  customer  connectivity  in  line  with  Government  objective  to  increase penetration rate of electricity from the current 30% to 40% by 2020. 

 4.3. Staff Analysis The  customer  to  staff  ratio  in  2011/12 was  199:1  compared  to  159:1  in  2007/08.  The 

Company  utilizes  day  casuals  mainly  during  the  construction  of  network  reinforcement schemes. The total KPLC labour costs were Kshs 9,773 million for financial year 2011/12. Table 5 shows KPLC permanent and contract staff numbers for the period 2007/08 to 2011/12. 

  6

Table 5: Staff Analysis (Permanent and Contract)   

As at 30th JUNE 2007/08 2008/09 2009/10 2010/11 2011/12 Total No. of Staff*  6,668  7,015  7,279  8,543  10,252 

   % Increase p.a.  4.2%  5.2%  3.8%  17.4%  20.0% 

Gender:                Male  5,351  5,565  5,774  6,856  8,303 

   Female  1,317  1,450  1,505  1,687  1,949 

   Ratio‐ Male/Female  4.1  3.8  3.8  4.1  4.3 

Customer to staff Ratio  159  181  201  205  199 

*Upto 2010/11 the numbers of staff indicated did not include temporary staff.    4.4. System Losses Projections  

System losses comprise both technical and commercial losses, the former being inherent in  the network as power  flows, while  the  latter  is a  result of erroneous metering or  theft. Over  the  current Review Period,  losses were  targeted  to  reduce by 0.5% per  year from 16.9% in 2007/08 to 15.4% in 2010/11. The following table shows the percentage of total system losses achieved against the targets set for the last tariff control period.  

Year  Target %  Actual %2005/06    19.6 2006/07    17.9 2007/08  16.62008/09  16.4  16.3 2009/10  15.9  16.0 2010/11  15.4  16.2 2011/12  15.4 17.3

 It will be noted from the table that although there was a steady decrease in losses up 

to 2009/2010, over the  last two years, actual  losses have deviated  from the target and are on an increasing trend. This is attributable to the following factors; 

 i) Increase in transmission losses 

The  commissioning  of  the  115MW  Kipevu  III MSD  plant  in March  2011  without corresponding  increase  in  the  transmission capacity between Mombasa and upcountry has  led  to  an  increase  in  transmission  losses on  the Rabai‐Nairobi, Rabai‐Kiambere  as well  as  the  lines  between Nairobi  and  the  hydros.  This  situation will  prevail  until  the 400KV Mombasa‐Nairobi line is put into service. 

 During this period no transmission reinforcement project was completed. The system 

peak demand on the other hand grew by 30% and energy sales by 34% over  the same period.  This  also  translates  into  increased  technical  losses.  Various  projects  aimed  at reinforcing  the  distribution  network  by  extending  the  transmission  network  were completed.  These  include  the  132kV  lines  to  Kisii,  Meru  and  Diani.  While  reducing distribution  and  therefore  overall  system  losses,  these  projects  had  the  effect  of increasing transmission losses. The above factors resulted in an increase in transmission losses from about 3.5% to 4.1% 

 

  7

ii) Accelerated connection of new customers The number of electricity customers has more than doubled from 924,324 at the end 

of 2007/08  to 2,060,449  in 2011/12. The bulk of  these new customers are on  the  low voltage  network.  Although  a  lot  has  been  invested  in  the  medium  voltage  system especially in the urban and peri‐urban areas, the increase in the low voltage losses due to extensions has exceeded the reduction in medium voltage losses due to these efforts. 

 iii) Extension of medium voltage network for rural electrification 

The rapid expansion of the rural electrification program by REA has had two effects on the distribution losses 

a) A large number of long medium voltage and low voltage lines b) A  large  number  of  lightly  loaded  distribution  transformers  which  have  high 

percentage  losses due  to  the proportion of  fixed  iron  losses. This  situation will continue until the demand in these areas pick up.  

The above factors affecting transmission and distribution  losses are expected to prevail over the next two to three years. Projects in the pipeline for reinforcing the transmission and distribution  system  will  assist  to  contain  the  rise  in  losses  but  no  reduction  is  expected before 2014/2015. The commissioning of the Mombasa‐Nairobi 400KV  line, expected  in the last  quarter  of  2013/2014  is  expected  to  reduce  transmission  losses  by  about  0.2%.  It  is estimated that other reinforcement projects to be completed starting 2014/2015 will result into 0.2% reduction of losses annually resulting into the following trend.   

Year  Proposed System losses reduction path % 2011/12 (Actual)  17.3 2012/13  17.5 2013/14  17.32014/15  17.1 2015/16  16.9 

  4.5. Transmission and Distribution Investment Projects 

 Transmission  and  distribution medium‐term  investment  plan  for  the  period  2012/13‐

2015/16  is  as  shown  in  Table  18.  KPLC  plans  to  spend  US$  210  million  on  electricity expansion project (KEEP)  being the second distribution upgrade project,  US$ 529.5 million in other distribution projects and support equipment and US$ 199.5 million on refurbishing the existing  KPLC  owned  transmission  system.  At  the  same  period,  KETRACO  and  REA  will implement new transmission and Rural Distribution network at an approximate cost of US$ 2.261 billion and US$ 1 billion,  respectively with  funding  from  the Government during  the Review Period.  

 4.6. T&D Operations and Maintenance Costs 

 The operating and maintenance costs  of providing transmission and distribution services 

to improve power reliability and general efficiency for the next tariff control period has been assumed as  follows; 

i.) Current T&D costs provided  in KPLC audited accounts has been assumed as base cost for the next tariff control period.  

  8

ii.) Additional operating and maintenance  cost  for existing  transmission and distribution networks is assumed at 2.5% and 3.5% respectively, of the additional  increase in gross investment plant in service value. 

iii.) Rural Electrification Scheme  is assumed to operate as described  in Section 4.7 of this application. 

iv.) Additional  operating  and  maintenance  cost  for  new  Ketraco  transmission  lines assumed at 2.5% of the capital cost on the next year following the commissioning of a transmission project. 

v.) Phasing of X‐factor of 50% in local inflation adjustment formulae since the introduction of the indices calculated using Geometric mean by Kenya National Bureau of Statistics was intended to remove the volatility of the inflation indices basket.  

 4.7. Existing Rural Electrification Schemes Operating Framework 

 Under the Energy Act 2006 that became operational in July 2007, the management of RE 

schemes was  fully  transferred  to  the Rural Electrification Authority  (REA) with effect  from July  2008.  The  RE  Schemes  assets  are  owned  by  REA  and  KPLC  signed  a  service  level agreement  to operate and maintain  the RE distribution  system. Further,  the MOE directed that current revenues and attendant operation losses for RE schemes except off‐Grid isolated power  plants  to  be  assumed  as  factored  in  the  retail  tariffs,  effective  July  2008. Consequently,  the  revenue  requirement  necessary  to  cover  transferred  RE  schemes operating and attendant  losses estimated at Kshs 1,364 million as  incurred  in 2009/10 has been factored in the Application. However, if the actual operation and maintenance costs for RE‐Schemes  exceed  the  current  available  revenue  as  a  result  of  the  accelerated  rural electrification  programme  during  the  Review  Period,  then  KPLC  proposes  to  bill  the Government for any deficits.  

 It  is assumed that the REP  levy shall remain at the current  level of 5% of revenue  from 

electricity units sales and that if more funding of REA became necessary, the same would not be sourced from electricity customers.  

 Continued  improvement  in KPLC operations requires substantial  investment  in terms of 

capital,  and  operation  and  maintenance  expenditures.  In  order  to  access  the  resources necessary  to  support  these  investments,  it  is  imperative  that  the  Company  remains financially viable. Efficiency improvement measures must therefore, be complemented by an opportunity to recover a fair return on investment while attracting new capital. 

 4.8. Transmission and Distribution  Wheeling Arrangement  

The Commission  is undertaking a Cost of Service Study through SNC Lavalin Consultants which will  inform the setting of both transmission and distribution network wheeling tariff. The planned introduction of Transmission and Distribution Wheeling tariffs is expected to be developed using annual revenue requirements of utilities mandated to provide transmission and  distribution  system  capacity.  KPLC  opines  that  expected  wheeling  tariffs  should  be adequate  to promote efficient use of  the  transmission and distribution  system and attract continued  investment  in  the power  system.  In  the  KPLC Retail Tariff Application dated  4th February 2011 which  is pending with  the Commission, we had proposed 2.5 % of Ketraco transmission  lines  Project  cost  taking  into  account  the  target  commissioning  dates  as estimated  operation  and maintenance  cost  for  Ketraco  transmission  assets  as  part  of  the revenue requirement. Given that the Cost of Service Study is almost complete, Transmission 

  9

and Distribution wheeling tariffs setting for this retail tariff control period may be guided by the outcome of this Study.  

 4.9. Proposal for Low Voltage System Expansion 

 The  current  electricity  connection  policy  came  into  operation  in  2004  in  an  effort  to 

facilitate accelerated connectivity country wide. As tabulated below, cumulative connections countrywide  in  the  last 8  years  (2004‐2011) grew  from 735,000  to 2,060,449  representing 280% growth. New additions have  increased annually from 48,949  in 2004/05 to 307,101  in 2011/12.  

Year   2004/ 05 

2005/ 06 

2006/ 07 

2007/08  2008/09  2009/10  2010/11  2011/12 

Annual Connections 

48,949  67,105 122,080 136,054 206,815 196,441 289,709  307,101

Total Connections 

735,144  802,249  924,329  1,060,383  1,267,198  1,463,639  1,753,348  2,060,449 

 

The driving policy was a  fixed customer cost of Kshs 32,480  (Kshs 28,000+ 16% VAT of Kshs 4,480) and Kshs 44,080 (Kshs 38,000 +16% VAT of Ksh 6,080) for a single phase and a three phase connection, respectively, for those customers within 600 meters from existing transformers.  In addition customers also pay refundable accounts deposit of Kshs. 2,500/= and Kshs. 5,000/= for single phase and three phase, respectively.  This raises the total initial payments of single phase connection to Kshs 34,980/= and Kshs 49,080/=  for three phase connection. At the  inception of the policy, these charges were adequate to expand the LV network and connect customers within the 600 meters transformer coverage radius. Since then, the costs of materials, labour and transport have significantly increased progressively with key  items’ prices over the  last 5 years rising as follows:‐Diesel by 47%, Poles by 45%, Transformers by 100%, Copper and aluminium cables by 220%.  

 The  aggregated  impact  of  the  above  items’  price  change  would  be  to  increase  the 

connection of service cost to Kshs 75,580 for single phase and Kshs 89,680 for a three phase connection inclusive of VAT. As shown in Table 6 below, the growing difference in actual cost and  customer  contributions has been met by Kenya Power. This  cost  to Kenya Power has risen from Kshs 1.05 Billion in 2007/08 to Kshs 7.5 Billion in 2011/12.  Table 6: Customer Power Connection Costs  Versus Capital Contribution 2007/08 

to 2011/12 

 Year     2007/08  2008/09  2009/10  2010/11  2011/12 No of Connections     38,484  69,757  82,519  111,727  123,495 Actual connection costs   Kshs m’  2,392  4,870  6,233  9,846  11,856 

Capital Contribution  Kshs m’  1,339  2,581  3,179  3,889  4,327 Net Costs/required Funding  Kshs m’ 1,052 2,289 3,054 5,957  7,528

 As a result, KPLC has had to divert funds borrowed or raised  for critical capital projects 

meant to improve the quality of power supply to  meet part of the subsidy in projects whose return on  investment are very  long term. Some of the funds utilised  included medium term loans of Shs. 7 billion and Shs. 10 billion  in 2011. Currently,  the Company  is  sustaining  its operations with overdraft/short  term  facilities  from banks which amount  to about Shs.5.3 billion. Additionally, KPLC has  fallen back on payments  to material  suppliers amounting  to 

  10

KShs. 2.1 billion and has delayed payments to power suppliers by over 10 days beyond the contractual credit period  

Kenya power  is unable to sustain the  financing to maintain the connection momentum which  is one of  the  key economic drivers  in Vision 2030  as  it has heavily  impacted on  its liquidity  and  profitability  (due  to  rising  financial  costs).  The  adverse  impact  of  reduced liquidity and profitability will erode  lenders’  confidence due  to non‐compliance of existing financial  covenants with World Bank  and  other multilateral  financial  institutions,  some  of which Kenya Power has already defaulted. Operations to maintain electricity supply will not be sustainable. 

 Section  56  of  the  Energy  Act  obligates  licensees  to  construct,  operate  and maintain 

suitable and  sufficient distribution network  to enable  supply  to be provided  in  the  licence area.  If the development of electricity network was being  implemented  in accordance with the  Energy  Act,  applicants  for  new  electricity  connections  would  be  within  reasonable distances from the reticulation. Currently, it is a recognised fact that cost of new connections is  prohibitive  to  most  Kenyans.    In  order  to  continue  with  the  current  rate  of  new connections to increase electricity access to many Kenyans, KPLC requires additional revenue of Kshs 7.5 billion.    Kenya Power therefore proposes the following to raise this amount; 

 i) To increase the connection charges for single phase connection with demand of less than 

8KVA from the current Kshs 34,980 to Kshs 60,000; ii) Require that three phase customers pay full cost of extension; iii) Customers  requiring more  than  8KVA  continue  paying  full  cost  of  extension  as  is  the 

current practice; iv) The above measures will leave a deficit of approximately KShs 5,025 million per annum. 

Kenya  Power  proposes  that  this  amount  be  raised  through  a  charge  to  electricity consumers  of  Kshs  0.70  per  KWh.  This  charge  has  been  included  in  the  revenue requirement. 

4.10. Proposal by ERC to Implement a Hydro‐Risk Mitigation Fund   

During the last tariff review, there were proposals to set up a hydro risk mitigation fund for  securing  dependable  supply  during  dry  hydrology  as  a  tariff  rates  stabilization mechanism.   At  the  time,  the  commission  indicated  that  the  issue would be  subjected  to stake  holders’  review  at  a  separate  process  from  the  retail  tariffs  review.  KPLC’s  initial comment  is  that,  if utilities were asked  to contribute a significant portion of  the proposed fund  requirement,  this would  largely erode  the  rate of  return on  regulated asset base and reduce the ability of the Company to attract investment.  

 KPLC  notes  that  the  Commission  at  her  own  volition  has  indicated  the  intention  to 

implement  this Review objective. However,  the Company has no  specific proposal on  this issue and will therefore wait for the Commission guidance on the way forward.  

    

  11

4.11. Proposed implementation of Time of use tariffs  

Capacity charge regime exposes KPLC to significant fixed costs and we propose that the plan by  the Commission to  introduce Time‐of‐Use  tariffs should be preceded by a separate study on the impact of capacity regime to electricity consumers and the off‐taker.  This Study should analyse in detail power consumption patterns of commercial and industrial customer categories  to estimate  the amount of consumption  that could be shifted  to  low  load  times and the level of tariff reduction required to motivate such shifting.  In the end when Time ‐of‐Use rates will be  fully  implemented, KPLC’s only concern  is to be  left revenue neutral even after the adoption of Time ‐of‐Use rates. In the interim, we would request the Commission to factor  in  a  20%  discount  on  consumption  between  23.00Hrs  and  07.00Hrs  and  a  10% premium for other times (for industrial and commercial customers) on non‐fuel tariff only as a pilot scheme while the results of the study are awaited. This will help to provide real‐time and practical information and complement the results of the pilot study. 

   4.12. Way leave Levies & charges demand by Government Institutions  

Some  Local  Authorities,  Kenya  Wildlife  Service,  Kenya  Forest  Services  and  Kenya Railways have variously imposed fees and charges for way‐leave rights that may be granted within their jurisdiction. The demand by local authorities and other government agencies, including  the effect of  the Roads Act, and  the estimated expected claims  from  individual landowners would demand extra revenue of approximately Kshs 4.5 billion as detailed  in Table  7  which  would  result  to  an  increase  in  the  retail  tariff  energy  charge  of  Kshs 0.81/kWh.  This  revenue  requirement  does  not  include  the  extrapolated  debt  arrears  of Kshs 8.2 billion which also need to be considered in the resolution of this issue.  Although the company is currently facing operational and legal challenges due to existing demand of levies/charges, this requirement has not been factored in our Review Period application as the  Company  has  requested  the  Government  to  intervene  with  a  view  to  having  the demand  by  Local  Authorities  and  other  GoK  agencies  resolved  through  the  National Budget. This is in line with earlier advice from the Government and also the guidance given by  ERC on  levies by Government  Institutions  and Agencies during  the  last  Tariff Review process.    The  Company  will  continue  to  use  all  efforts  pursue  the  resolution  of  these charges  and  levies  with  the  Government  and  to  defend  suits  brought  by  claimants. However,  should  a  court  of  law  compel  the  Company  to  pay  any  of  the  amounts, we propose that such charges will be passed through to customers.  

 Table 7: Wayleave Levies Demand by Local Authorities & GoK Agencies  

WAYLEAVES LEVIES DEMANDS BY GOVERNMENT INSTITUTIONS DESCRIPTION  

A  Government Institutions that have demanded Way leaves levies 1  Local Council Authorities  2  Kenya Wildlife Service  3  Kenya Forest Service  4  Kenya Railways  B   1 

The Local Councils pole levies demand is estimated by extrapolating alleged arrears totaling Kshs3.6 billion as at July 2007 to‐date, figures using 227% growth of Nairobi City Council demand from Kshs 164,000,000 in 2007 to  Kshs 372,184,800 to date. 

2 Estimated that 4% or 1,972km of 33kV and11kV power lines pass through the Kenya Forests Service areas.   

  12

WAYLEAVES LEVIES DEMANDS BY GOVERNMENT INSTITUTIONS DESCRIPTION  

3 Estimated that 6% or 2,958km of 33kV and11kV of power lines pass through the Kenya Wildlife Service areas. 

4  Estimated that there are 300 rail crossings in the country at the moment.  

5 Estimated that out of existing 220kV and 132kV lines 30% or 1063km and 10% or 531km pass through KWS and KFS land areas, respectively 

6  Estimated that  Kshs1.6 billion annually is required to meet the Roads Act  

C ESTIMATED TOTAL COST OF WAYLEAVES LEVIES DEMANDED  ON KPLC 

Amount (Kshs) 

 Annual Amount (Kshs) 

1 Local Council Authorities‐ ( total alleged arrears of 3.6 billion by 2007 extrapolated by 227% 

     8,172,000,000  

  1,021,500,000 

Kenya Wildlife Service levies assuming trace area of 5 square metres for the 2,958km at a rental charge of Kshs 24 per square metre    

  354,960,000 

Kenya Forest Service levies assuming trace area of 10 square metres for the 1,972km at a rental charge of Kshs 2.50 per square metre    

  49,300,000 

Kenya Railways  levies assuming 300 crossings at  application  fee of Kshs 120,000 per railway crossing    

  36,000,000 

5 Estimated effect of 220 kv / 132 kv charges (assume 30% in KWS and 10% in KFS lands)    

  965,325,000 

6  Estimated effect of the Roads Act          1,600,000,000 

   Sub‐total          4,027,085,000 

7 Likely estimated individual demand if Government Institutions were to be paid    

  500,000,000 

   Total  Annual Wayleave Levies Cost Required           4,527,085,000 

D  TARIFF  REQUIREMENT      

   Assuming annual electricity sales of 5,600 GWh  in Kshs/kWh                        0.81 

i  ANNUAL TARIFF  REQUIREMENT  in Kshs       4,527,085,000 

ii  Required Tariff increase to meet current level of levies   in Kshs/kWh                        0.81 

iii Likely arrears exposure for past period (extrapolated debt)  in Kshs 

  8,172,000,000.00 

 4.13. Other Proposed Government Institutions Levies  

The Water Resources Management Authority has charged KenGen a water  levy of Kshs 0.05/kWh for electricity generation from hydro sources. KPLC has included this charge to the energy  charge  rate  for  KenGen  hydros  in  determination  of  the  proposed  base  revenue requirement. 

     

  13

4.14. Rate Asset Base and Revenue Requirement  

The  revenue  requirement  has  been  prepared  for  KPLC  as  an  entity  with  distinct Transmission and Distribution businesses units since  the unbundling of  the company  is not anticipated within  the Review Period.  The  revenue  requirements  comprise  the  return  and taxes on regulated asset base, the cost of purchases of generation capacity and energy and KPLC operation and maintenance costs as key components. KPLC, therefore, has updated its investment plan for the next five years as described in Section 4.5 covering the Transmission and Distribution systems. 

The result for the re‐computed revenue requirement (in real September 2012 prices)  in reference  to  financial  years  starting 2012/13 using previous Tariff  Study methodology  and assumptions  listed  in  Appendix  2  is  Kshs  113,725 million,  Kshs  128,908 million  and  Kshs 109,079 million and Kshs 111,432 million for financial years 2012/13, 2013/14, 2014/15 and 2015/16 respectively, as shown in Table 8. 

 Table 8:  Total Revenue Requirement for KPLC 

 

REVENUE REQUIREMENT        2nd  Tariff control Period Financial Year     2010/11  2011/12  2012/13  2013/14  2014/15  2015/16    KPLC Opex  KSh million  13542  15136  18285  18999  21020  23594 

Provision for Bad debt  KSh million  306  0  1183  1445  1224  1249 

Depreciation  KSh million  3,847  4,544  5,412  5,930   4,560   4,194 

Debt portion  %  66%  66%  66%  66%  68%  70%            

Rate Base   

Fixed assets (NBV)     65,819  84,312  92,422  93,720  97,692  103,713 

Working capital  KSh million                   

Cash  KSh million  1,693  1,892  2,286  2,375  2,628  2,949 

Inventory  KSh million  8,961  10,286  10,649  11,074  11,582  12,215 

Total Rate Base  KSh million  76,473  96,491  105,356  107,169  111,902  118,877 

ADJUSTMENT TO RAB                      

Purchase of Pre‐ paid meters  KSh million     1,425  1,425  1,425  1,425  1,425 

Customer Service  Facilities  KSh million     1,069  1,069  1,069  1,069  1,069 

IT&T  Equipment  KSh million     955  955  955  955  955 

Adjusted RAB     76,473  99,938  108,804  110,617  115,350  122,325 

Cost of equity ‐ after tax  %  12.5%  12.5%  12.5%  12.5%  12.5%  12.5% 

Equity portion  %  34%  34%  34%  34%  32%  30% 

Debt portion  %  66%  66%  66%  66%  68%  70% 

Average cost of debt  %  2.1%  5.2%  5.1%  7.4%  3.8%  3.8% 

Income tax rate  %  30%  30%  30%  30%  30%  30% 

After tax return on equity  KSh million  3,274  4,215  4,556  4,704  4,512  4,531 

Income tax  KSh million  1,403  1,806  1,953  2,016  1,934  1,942 

Interest expenses  KSh million  1,051  3,466  3,711  5,412  2,849  3,157 

Depreciation  KSh million  3,847  4,544  5,412  5,930  4,560  4,194            

Interest income  KSh million  171  489  110  35  35  154            Capital related Revenue Requirements  KSh million  9,406  13,544  15,525  18,029  13,821  13,672            

Cost of electricity purchase                      

Non Fuel cost  KSh million  26,394  30,935  33,763  41,002  52,545  66,186 

    Fuel cost  KSh million  28,130  45,782  43,786  47,988  19,244  5,483 

                       

thereof: Capacity related cost  KSh million  25,602  30,007  32,750  39,772  50,969  64,200 

  14

REVENUE REQUIREMENT        2nd  Tariff control Period Financial Year     2010/11  2011/12  2012/13  2013/14  2014/15  2015/16 

thereof: Energy related cost  KSh million  28,922  46,710  44,799  49,218  20,821  7,468            

Actual /Allowed losses % of energy purchased  16.2%  17.3%  17.5%  17.3%  17.1%  16.9% 

Allowed energy related cost  KSh million  28,922  46,710  44,799  49,218  20,821  7,468 Operation and maintenance cost                      

KPLC Opex  KSh million  13,848  15,136  19,468  20,444  22,245  24,843            

Provision for Bad debt  KSh million  306  0  1,183  1,445  1,224  1,249            

Total Operating Cost  KSh million  68,679  91,853  98,200  110,879  95,258  97,761            

Revenue Requirement  KSh million  78,084  105,397  113,725  128,908  109,079  111,432            

Energy sold   GWh  6,123  6,341  6,581  6,993  7,430  7,895            Average Revenue Requirement   KSh / kWh  12.75  16.62  17.28  18.43  14.68  14.15 

 4.15. Average  Revenue Requirement Per Unit of Electricity Sales 

 Table 9 summarizes KPLC revenue requirements per unit. 

  Table 9: KPLC Revenue Requirement (in Sept 2012 prices) Kshs/kWh  

Financial Year  2011/12  2012/13  2013/14  2014/15  2015/16 

4 Years (2012 – 2015) Levelized Tariff 

Non‐Fuel revenue requirements 

   10.63  11.61  12.09   13.45   12.01 

System Expansion Revenue     0.7 0.7 0.7  0.7  0.7

Adjusted Non Fuel Revenue  9.40  11.33  12.31  12.79   14.15   12.71 

% Increase     21% 9% 4%  11%  35%                    

Average Overall  Revenue Requirements 

   17.28 18.47 14.68  14.15  16.04

System Expansion Revenue     0.7 0.7 0.7  0.7  0.7

Adjusted  Overall Revenue Requirements  

16.62 17.98 19.17 15.38  14.85  16.74

% Increase     8% 7% ‐20%  ‐3%  1% 

It  can be observed  that  there will be  an  increase  in  required non‐fuel    revenue  yield from Kshs 9.40/kWh  in 2011/12 to a three year  levelised yield of Kshs 12.71 equivalent to 35%, and an increase  in overall yield (including fuel costs) from Kshs 16.62/kWh in 2011/12 to a  three  year  levelised  yield 16.74/kWh equivalent  to 1%. The  increased  cost of power purchase,  rising  from  the  additional  committed  generating  capacity  by  KenGen  and Independent  Power  Producers,  additional  operating  costs  as  a  result  of  inflation‐related escalation,  as  well  as  financial  requirements  to  sustain  the  implementation  of  the 

  15

transmission  and  distribution  electricity  network  expansion  programme  has  necessitated the need to generate additional revenue from the proposed retail tariffs.  4.16.  Breakdown of Average per Unit Projected Retail Tariffs  

The  revenue  requirement power purchase  component  is  expected  to  evolve  from  the 2011/12 actual level of Kshs 4.88/kWh to a four year‐ levelized of Kshs 6.70/kWh during the Review Period  to  take  into account  the expected capacity payment  for committed KenGen and  IPPs Power plants, this will constitute the main cause of revenue requirement  increase being  sought  by  the  company  as  shown  in  Table  10.  The  Transmission  and  Distribution component will remain relatively stable during the Review Period and is expected to change from the 2011/12 actual level of Kshs 4.52/kWh to a four year‐levelized of Kshs 5.32/kWh to cater for the expanded network operation and maintenance. The fuel component is expected to slightly reduce overtime as more long term non‐fuel base power plants are developed.  Table 10: Breakdown of Revenue requirement in Kshs/kWh (in Sept 2012 prices)  

REVENUE REQUIREMENT                 4‐yrs 

Levelised 

      2010/11  2011/12  2012/13  2013/14  2014/15  2015/16  2012‐15 

Power Purchase Component    Actual  Actual                

       Non‐ Fuel   KSh / kWh  4.31  4.88  5.13  5.86  7.07  8.38  6.70 

        Fuel   KSh / kWh  4.59  7.22  6.65  6.86  2.59  0.69  4.03 

Sub‐Total  KSh / kWh  8.90  12.10  11.78  12.73  9.66  9.08  10.73 

T& D Component                        

            KPLC Capital Related  KSh / kWh  1.54  2.14  2.36  2.61  1.86  1.76  2.13 

            KPLC O&M  KSh / kWh  2.29  2.37  3.12  3.09  2.92  2.84  2.99 

            Ketraco Lines O&M  KSh / kWh  0.02  0.02  0.01  0.05  0.24  0.46  0.20 

Sub‐Total  KSh / kWh  3.85  4.52  5.50  5.74  5.02  5.07  5.32        

Overall  Revenue Requirement   KSh / kWh  12.75  16.62  17.28  18.47  14.68  14.15  16.04 

Non‐fuel Revenue Requirement   KSh / kWh  8.16  9.40  10.63  11.61  12.09   13.45   12.01 

System Expansion Revenue          0.70  0.70  0.70   0.70   0.70 

Adjusted Revenue Requirement                         

    Overall     12.75  16.62  17.98  19.17  15.38   14.85   16.74 

   Non‐Fuel      8.16  9.40  11.33  12.31  12.79   14.15   12.71 

Overall % change           8.2%  6.6%  ‐19.8%  ‐3.5%  ‐3.5% Non‐Fuel % change     20.5% 8.7% 3.9%  10.6%  35.2%

 4.17. Financial Projections  

4.17.1. Energy Balance  

The projected capacity and energy balances for the financial years 2011/12 to 2016/17 is as shown  in Tables 16 and 17,  respectively. The power balance  in Table 16 shows  that  the planned project will be more than adequate to meet the projected  interconnected demand. The  projected  capacity  surplus  assumes  full  availability  of  hydros  and  about  15 %  reserve margin for maintenance and spinning allowance.  

     

  16

4.17.2. Projected Financial Results  

The  summary  financial  projections  based on  assumptions  in Appendix  2  are  shown  in Table 11. Assuming the proposed retail adjustment is granted as requested, then the KPLC’s financial performance  in the medium‐term  is expected  to be satisfactory and  the Company will  continue  to operate  as  a  commercially  viable  enterprise  that  is  able  to  attract  capital investment to fund the planned expansions and customer growth. 

 Table 11: Projected Financial Performance 2012/13 to 2015/16  

   2011/12  2012/13  2013/14  2014/15  2015/16    Actual  Projected          Units purchased (GWh)  7,670  7,977  8,456  8,963   9,501 System Losses  17.3%  17.5%  17.3%  17.1%  16.9%    Total Sales ‐GWh  6,341  6,581  6,993  7,430   7,895 Profit & Loss Accounts                Revenue                     ‐ Electricity                             Non‐Fuel  45,008  62,520  81,747  90,353   106,190              Fuel Recovery  41,896  43,129  47,268  18,956   5,346              Forex Adjustment  8,759  0  0  0   0      ‐ Others  1,788  2,100  500  500   500 Total revenue  97,451  107,750  129,515  109,809   112,036 Operating costs                      Power purchases                             Non‐Fuel   24,787  33,763  41,002  52,545   66,186              Fuel  45,175  43,786  47,988  19,244   5,483 Sub‐Total  69,962  77,549  88,990  71,789   71,669 Gross margin  27,488  30,201  40,525  38,020   40,368      T&D cost  15,136  19,468  20,444  22,245   24,843       Depreciation  4,544  5,412  5,930  4,560   4,194 Sub‐Total  19,680  24,881  26,373  26,804   29,037 Gross margin as % Sales  28.2%  28.0%  31.3%  34.6%  36.0% Total operating cost  89,642  102,429  115,364  98,594   100,705 Operating surplus  7,809  5,320  14,151  11,215   11,331         Net Finance (income)/cost  (698)  1,357  3,139  1,005   184                  Profit/(Loss) before tax  8,507  3,963  11,012  10,211   11,147                  Balance Sheet                Fixed and Current Assets                Current assets  28,359  28,153  32,190  38,745   44,911 Fixed assets  105,773  111,026  123,378  143,045   168,086 Total assets  134,132  139,178  155,568  181,791   212,997                  Equity and Liabilities                Current liabilities  37,010  29,759  21,044  18,850   33,731 Non current liabilities  51,866  62,792  81,598  104,304   114,316 Capital and Reserves  45,256  46,628  52,926  58,637   64,950 Total equity and liabilities  134,132  139,178  155,568  181,791   212,997                  

  17

   2011/12  2012/13  2013/14  2014/15  2015/16    Actual  Projected          Financial Performance Indicators                 Net Cash balance  1,972  (10,894)  (123)  10,264   15,453 Current Ratio   0.8  0.9  1.5  2.1  1.3 Debt Service Coverage  2.1  1.4  3.4  2.3  1.8 Self Financing Ratio  30%  ‐90%  62%  45%  87% Days' Receivable  45.4  42.0  42.0  42.0  42.0 

 4.18. Pre‐paid Metering 

 KPLC has installed approximately 175,000 pre‐paid meters by December 2012. During the 

Review Period 2012/13  to 2015/16 KPLC plans  to  install  to more  than 1 million customers prepaid meters  at an estimated project cost of ksh 8,000 per installation.  

 

5. Tariff Design 5.1. Proposed Retail Tariff Rates  

The proposed electricity tariff adjustment  for the Review Period  is  intended to be cost‐reflective, efficient and sustainable  in provision of services by KPLC. The existing base non‐fuel retail tariffs are expected to be adjusted to the proposed retail tariffs as shown on Table 12. This results in overall base non‐fuel tariff increases of 21%, 9%, 4%, and 11% proposed to be applicable in 1st March 2013, 1st July, 2013, 1st July, 2014 and 1st July 2015 respectively.        Table 12: Proposed Retail Tariff Rates 

Customer Category        PROPOSED RATES 

Code  Customer  Type 

Charge Method 

Unit cost Existing Rate  

2012/2013 

2013/2014 

2014/ 2015 

2015/2016 

DC  Domestic  Fixed KSh/month 120 200  250  250  300 

     Energy KSh/kWh 2.00 5.10 5.10 5.75  5.75

   "  Energy KSh/kWh 8.10 11.40  11.90  12.30  13.64 

   "  Energy KSh/kWh 18.57 19.30  23.36  23.86  24.80 

SC  Small Commercial   Fixed KSh/month 120 200  250  250  300 

     Energy KSh/kWh 8.96 13.66  14.55  15.00  16.62 

CI1  Comm./industrial  Fixed KSh/month 800 2,000 2,200 2,200  2,500

     Energy KSh/kWh 5.75 9.75 10.80 11.60  13.00

     Demand KSh/kVA 6,00 800  800  800  800 

CI2  Comm./industrial  Fixed KSh/month 2,500 4,000  4,500  4,500  5,000 

     Energy KSh/kWh 4.73 7.95  8.90  9.15  10.30 

     Demand KSh/kVA 400 520  520  520  520 

CI3  Comm./industrial  Fixed KSh/month 2,900 4,500 5,000 5,000  6,000

     Energy KSh/kWh 4.49 7.35 8.15 8.35  9.35

     Demand KSh/kVA 200 270  270  270  270 

 CI4  Comm./industrial  Fixed KSh/month

 4,200

 6000 

 6500 

 6,500 

 7,000 

     Energy KSh/kWh 4.25 7.05  7.80  8.00  9.05 

     Demand KSh/kVA 170 220  220  220  220 

CI5  Comm./industrial  Fixed KSh/month 11,000 16,000 17,000 17,000  18,000

     Energy KSh/kWh 4.10 6.90 7.70 7.90  8.90

  18

Customer Category  PROPOSED RATES 

Code  Customer  Type 

Charge Method 

Unit cost Existing Rate  

2012/2013 

2013/2014 

2014/ 2015 

2015/2016 

     Demand KSh/kVA 170 220  220  220  220 

IT  Interruptible  Fixed KSh/month 120 200 250 250  300

     Energy KSh/kWh 4.85 13.50 14.50 15.30  16.60

DC IT   "  Fixed KSh/month

240 400 500 500  600

SC IT   "  Fixed KSh/month

240 400 500 500  600

SL  Street Lighting  Fixed KSh/month 120 200 250 250  300

   Energy KSh/kWh 7.50 11.20  12.30 

 12.80 

 14.00 

 5.2. Proposed Retail Tariffs by Customer Categories  

This  results  in an average base non‐fuel  retail  tariff  increase of 21%  from  the 2011/12 derived average non‐fuel tariff yield  level of Kshs 9.40/kWh. The distribution of the average retail  tariff per  customer  category  is  as  shown on  Table 13  and  the  increase would  range from 17% to 25% on various new consumer categories except for water heating Interruptible tariff  which  has  been  adjusted  to  be  in  line  with  current  customers’  consumption characteristic.   

 Table 13: Distribution of the Proposed Tariff revenue requirement yield change in 

percentage per applicable period  

      New Tariff Rates % increase 

  Base Tariff  Proposed increases 

       1st Mar‐ 2013 

 1st Jul‐ 2013 

1st Jul‐ 2014 

1st Jul‐ 2015 

 Domestic  DC  9.96  17%  13%  4%  11% 

   SC  11.32  25%  10%  3%  11% 

Commercial/Industrial   CI1  10.24  21%  15%  6%  10% 

   CI2  7.79  21%  13%  2%  11% 

   CI3  6.79  21%  12%  2%  11% 

   CI4  6.34  21%  12%  2%  12% 

   CI5  6.31  21%  13%  2%  12% 

Off‐Peak  IT                

   DC,IT               

   SC,IT                

      12.88  21%  15%  5%  10% 

Street Lighting  SL  9.60  21%  15%  4%  10% 

Overall Tariff     9.40  21%  9%  4%  11% 

   

  19

The  levelised  retail  tariffs  described  in  the  above  sections  are  base  rates  in  constant September 2012 prices.   5.3. Proposed changes in FCC, FERFA and INFA formulae  

Through  this  tariff  application,  KPLC  proposes  the  retention  of  the  current  Fuel  Cost Charge  (FCC),  Foreign  Exchange  Rate  Fluctuation  Adjustment  (FERFA)  and  inflation adjustment formulae with the following amendments.  

i.) The loss factor be allowed at estimated actual  level of 17.5%  in base year 20112/13, thereafter, the allowed target losses level  have been assumed arrived after taking to account a reduction of 0.2%  in overall system  losses to be  in  line with the proposed loss reduction path shown in Section 4.4 (iii). 

ii.) Take into consideration additional fuel displacement charge rates for wind and feed‐in‐tariff geothermal renewable generation sources 

iii.) To  take  into  account  the  specific  fuel  consumption  for  new Medium  speed  diesel being  developed  by  KenGen/IPPs  and  also  those  related  to  new  off‐grid  system generation  

iv.) Change of base  inflation  indices basket  from February 2009  that was derived using Geometric mean methodology mean of September 2012  

v.) To  take  into  account  changes  in  Base  Exchange  rates  for major  foreign  currencies since 2008. We propose setting of Base Exchange rates for selected major currencies at CBK mean exchange rate as shown in Table 14. 

               Table 14:  CBK Mean Exchange Rates of Major Currencies 

FOREIGN CURRENCY  September 2012 May 2009 March 2008

US Dollar  84.6133 77.8614 64.9242

STG Pound  136.2555 120.0302 130.0783

Euro  108.7977 106.2277 100.7930

SA Rand  10.2256 9.2839 8.1443

AE Dirham  23.0367 21.1988 17.6814

Can $  86.4971 67.5520 65.0696

Swiss Francs  90.0162 70.2685 64.1707

JPY(100)  108.2463 80.6318 64.0416

SW Kroner  12.8098 10.0445 10.6474

NOR Kroner  14.7146 12.0684 12.8074

DAN Kroner  14.5971 14.2576 13.4244

IND Rupee  1.5516 1.6044 1.6104

Hongkong Dollar  10.9119 10.0450 8.3401

Saudi Riyal  22.5626 20.7623 17.3168

Chinese Yuan  13.3844 11.4092 9.1613

Australian Dollar  87.9535 59.4860 60.0525

  

  20

5.4. Effective Date  

Pursuant  to  Section 45 of  the  Energy Act, 2006,  that provides  for  a  variation of  the effective  rates  and  tariffs  charged  to  consumers  for  the  supply  and  consumption  of electricity, KPLC  assumes  the  approval of  a multi‐  year    retail  tariffs  application become effective  commencing 1st March 2013, 1st July 2013 , 1st July 2014 and 1st July 2015 . 

 

6. Conclusion and Recommendation  6.1. Conclusion  

The effect of the proposed retail tariff adjustment  if approved  in  its entirety by ERC will be  increases of 21%, 9%, 4%, and 11% proposed to be applicable in 1st March 2013, 1st July, 2013, 1st July, 2014 and 1st July 2015 respectively. The retail tariffs adjustment is necessary to meet  the  additional  power  purchase  costs,  and  costs  of  expanding,  operating  and maintaining the transmission and distribution system, as well as to reflect changes in the cost of  fuel  as  well  as  cost  of  servicing  the  industry's  foreign  currency  expenditures  due  to exchange rate fluctuations. 

 KPLC is aware that the application is brought at a time when the power sector in Kenya is 

facing  increasing demand for electricity, coupled with rising cost of supply and an  increased reliance on  thermal generation  in  the medium  term.  In summary,  therefore, KPLC assumes that  the application to adjust  retail tariffs shall be approved  in  its entirety as  the Company may face operational challenges if review is not granted, which challenges include but are not limited to the following;‐ 

 

i.) Refurbishment and upgrade of the transmission and Distribution system may have to be scaled down; 

ii.) Proposed bulk supply tariff for new power projects   may   accumulate arrears as the plants continue enter into full commercial operation; 

iii.) The  Company  may  experience  financial  constraints  since  its  required  continued improvement in service needs substantial investment in terms of capital expenditure and operating expenditure; 

iv.) The Company may lose ability to attract new investment;  

v.) Ability to run expanding  Rural Electrification Schemes; and 

vi.) Ability to implement low voltage system expansion; 

vii.) Ability  to meet  agreed  financial  covenants  with  the World  Bank  and  other multilateral financial institutions. 

 6.2. Recommendation 

The  last  tariff  increase was approved  to  take effect  from 1st  July 2008. The proposed 

tariff  increases of 21%, 9%, 4%, and 11% proposed to be applicable  in 1st March 2013, 1st July, 2013, 1st July, 2014 and 1st July 2015 respectively, reflect the real price  increases  for cost  of  service  using  2011/12  cost  base.  The  spread  of  the  tariff  increase  to  all  new consumer  categories  is  shown  in  the proposed  Electricity  Tariffs  and  Tariffs Rates  2013, which is attached hereto as Appendix 1.  

  

  21

 

APPENDICES 

 

Appendix 1:   Proposed Schedule of Tariffs & Rates 2013 

 APPROVAL  OF  SCHEDULE  OF  TARIFFS  FOR  SUPPLY  OF  ELECTRICITY  BY  THE  KENYA POWER  AND  LIGHTING  COMPANY  LIMITED  SET  BY  THE  ENERGY  REGULATORY COMMISSION UNDER POWERS CONFERRED UNDER SECTION 45 OF THE ENERGY ACT, 2006 

 NOTICE  is  hereby  given  that  pursuant  to  section  45  of  the  Energy  Act,  2006,  the  Energy 

Regulatory  Commission  has  set  out  the  following  Schedule  of  Tariffs,  2013,  prescribing  the Tariffs,  Charges,  Prices  and  Rates  to  be  charged  by  The  Kenya  Power  and  Lighting  Company Limited to the consumers for electrical energy consumed by them. 

   PART I 

   GENERAL  

1.  This Schedule of Tariffs, 2013, hereby set shall take effect on 1stMarch, 2013 and shall  for each consumer become effective so as to apply to all bills raised based on meter readings taken on or after that date. 

 2  In  this  document,  unless  the  context  otherwise  requires,  the  following  words  and 

expressions shall have the following meanings:  

"Act" means the Energy Act No. 12 of 2006 and any Act or Acts amending or replacing the same; 

 "Billing  Period"  means  the  period  of  time  elapsing  between  the  issuing  of  two 

consecutive bills by the Company but with the exception of their first and last period; each such period of time shall be as near to thirty days as possible; 

 “Commission” means the Energy Regulatory Commission established under Section 4of 

the Act;  

"Company" means The Kenya Power and Lighting Company Limited;  

“Consumer” means any person supplied with electrical energy, but does not include a person supplied with electrical energy for delivery or supply to another person; 

 "Contract" means the agreement made by a Consumer with the Company for a supply 

of electrical energy, in force on the date of commencement of this Schedule of Tariffs and includes all contracts entered into with consumers after this date; 

 

  22

"Demand" means the maximum electric power demand drawn by a Consumer  in each Billing Period; 

   “Electric  Power  Producer” means  a  person  who  owns  or  operates  facilities  for 

generation of electrical energy pursuant to a generating licence issued by the Commission;  "Fixed Charge" means  the  charge  to be made per Billing Period  in  addition  to  those 

charges accruing in respect of Units and, when applicable, demand supplied;  

"Interconnected System" means those works  inclusive of power stations, transmission and  distribution  lines  electrically  interconnected  forming  the  main  supply  grid  in  the Republic of Kenya; 

 “KenGen” means the Kenya Electricity Generating Company Limited; 

 "kVA"  means Kilovolt Ampere; 

 "Meter" means  any  and  every  kind  of machine,  device  or  instrument  used  for  the 

measurement of the quantity of electrical energy, and  includes such auxiliary appliances as resistors, shunts, reactance, current  transformers, voltage transformers and time switches, external and necessary to the meter;  

 "Off‐Grid System" means those works inclusive of power stations, and distribution lines 

electrically and physically separate from the Interconnected System;  "Power  factor"  means  the  decimal  fraction  obtained  by  dividing  the  Demand  in 

kilowatts by the Demand in kilovolt amperes and shall be ascertained by suitable apparatus installed by the Company; 

 “Tariff” means  the  prices,  rates,  costs  and  all  other  charges  including  adjustments, 

formulae and other terms, conditions and information contained in parts II, III and IV of this Schedule of Tariffs, 2013. 

 "Unit" means one kilowatt hour (kWh); 

 “Units  Sent  Out” means  electricity measured  in  kWh  generated  by  the  Company’s 

Power Plants or Electric Power Producers Power Plants delivered to and purchased by the Company; 

          

  23

   

PART II  

SCHEDULE OF NON‐FUEL TARIFFS FOR ELECTRICAL ENERGY SUPPLIED BY THE COMPANY 

Part II – (A) – Applicable 1st March 2013  The Tariffs to be applied by the Company for the supplies of electrical energy from the 

Interconnected System and also from the Off‐Grid Systems, in each Billing Period shall be as detailed below: 

 METHOD DC:  Applicable to Domestic Consumers metered by the Company at 240 or 415 

volts and whose  consumption does not exceed 15,000 Units per Billing Period. 

a) A Fixed Charge of KSh200.00* 

b) Energy charges of : i) KSh5.10per Unit for 0 ‐ 50 Units consumed; ii) KSh11.40per Unit for 51‐1,500 Units consumed; iii) KSh19.30per Unit for Units consumed above 1,500. 

* If Method DC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both Methods of Charge shall be KSh400.00. 

 METHOD SC:  Applicable to non‐domestic Small Commercial Consumers metered by the 

Company  at  240  or  415  volts  and whose  consumption  does  not  exceed 15,000 Units per Billing Period. a) A Fixed Charge of KSh200.00* b) Energy charge of KSh13.66per Unit for all Units consumed. 

* If Method SC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both Methods of Charge shall be KSh400.00  

METHOD CI1:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided and metered by the Company at 415 volts three phase four‐wire and whose consumption exceeds 15,000 Units per Billing Period. a)  A Fixed Charge of KSh2,000.00 b) Energy charge of KSh9.75 per Unit consumed. c) Demand charge of KSh800.00 per kVA. 

   METHOD CI2:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 11,000 volts, per Billing Period. a) A Fixed Charge of KSh4,000.00.  b) Energy charge of KSh7.95per Unit consumed. c) Demand charge of KSh520.00 per kVA. 

 

  24

METHOD CI3:  Applicable  to Commercial and  Industrial Consumers  for supplies provided and metered by the Company at 33,000 volts, per Billing Period. a) A Fixed Charge of KSh4,500.00 b) Energy charge of KSh7.35 per Unit consumed. c) Demand charge of KSh270.00 per kVA 

 METHOD CI4:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 66,000 volts, per Billing Period. a) A Fixed Charge of KSh6,000.00 b) Energy charge of KSh7.05 per Unit consumed. c) Demand charge of KSh220.00 per kVA. 

 METHOD CI5:  Applicable  to Commercial  and  Industrial Consumers  for  supplies provided 

and metered by the Company at 132,000 volts, per Billing Period. a) A Fixed Charge of KSh16,000 b) Energy charge of KSh6.90 per Unit consumed. c) Demand charge of KSh220.00 per kVA. 

 METHOD IT:  Interruptible off‐peak  supplies of electrical energy  to ordinary  consumers 

metered  by  the  Company  whose  consumption  does  not  exceed  15,000 Units per Billing Period. a) A Fixed Charge of KSh200.00*  b) Energy charge of KSh13.50 per Unit consumed. 

 *  If Method  IT  is used  in  conjunction with Method DC or SC at  the  same  supply 

terminals,  then  the  combined  Fixed  Charge  for  both  Methods  of  Charge  shall  be KSh400.00 

   Notes: 

Note 1  The  electrical  energy  which  shall  be  supplied  and  charged  under  this method  of  charge  shall  be  available  at  all  times  other  than  during  peak periods which  shall be  such periods of high demand as may occur during each day not exceeding sixteen hours in the aggregate and during which the supply  of  electrical  energy may  be  restricted,  the  time  or  times  of  such restriction and the duration thereof being controlled by the Company at its sole discretion. 

Note 2  This  tariff  is only available  for  installations so arranged  to  the Company's satisfaction,  that  they  cannot  be  operated  on  any  other  tariff  and  also where  there  is  no  duplication of  the off‐peak  circuits by other  electrical circuits unrestricted as  to  time of use  so enabling  the  supply on another method of charge to be used for a similar function. 

Note 3  The  Company  shall  provide  and maintain  apparatus  up  to  a  maximum capacity of 15 amperes, single phase, to control the period of availability of the  supply  and  shall  take  all  reasonable  steps  to  ensure  the  reliability thereof, but shall not be responsible  for any  loss, damage or  injury which may result from any mal‐operation of this control equipment. 

 

  25

METHOD SL:  Applicable to public and  local authorities metered by the Company at 240 or  415  volts  for  supplies  of  electrical  energy  to  public  lamps  (Street Lighting). a) A Fixed Charge of KSh200.00. b) Energy charge of KSh11.20 per Unit consumed 

 Supplies under this Method of Charge shall be available for a minimum period of 11 hours per night for public lamps and for no other purpose. 

 The attention of public and  local authorities  taking  supplies on  this  tariff  is 

drawn to the fact that where public lamps are fitted on the Company's poles, all maintenance  of  the  lamps,  switch  wire  and  associated  equipment  must  be carried out by the Company, and shall be charged for on the basis of net costs of materials, labour and transport plus 25%. 

 Note: Every Consumer shall pay to the Company  in addition to the charges specified  in Part  II of this Schedule of Tariffs a Fixed Charge at a rate not exceeding KSh 50.00 per kVA per Billing Period  of  nameplate  kVA  continuous  rating  in  respect  of  all  electric  welding  plant,  as adjusted by any power factor equipment in use.  

Part II – (B) – Applicable 1stJuly  2013  

The  Tariffs  to  be  applied  by  the  Company  for  the  supplies  of  electrical  energy  from  the Interconnected System and also from the Off‐Grid Systems, in each Billing Period shall be as detailed below: 

 METHOD DC:  Applicable to Domestic Consumers metered by the Company at 240 or 415 

volts and whose  consumption does not exceed 15,000 Units per Billing Period. 

a) A Fixed Charge of KSh250.00* 

b) Energy charges of : i.KSh5.10per Unit for 0 ‐ 50 Units consumed; ii.KSh11.90 per Unit for 51‐1,500 Units consumed; iii.KSh23.36per Unit for Units consumed above 1,500. 

* If MethodDC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both Methods of Charge shall be KSh500.00. 

 METHOD SC:  Applicable to non‐domestic Small Commercial Consumers metered by the 

Company  at  240  or  415  volts  and whose  consumption  does  not  exceed 15,000 Units per Billing Period. a) A Fixed Charge of KSh250.00* b) Energy charge of KSh14.55per Unit for all Units consumed. 

* If Method SC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both Methods of Charge shall be KSh500.00 

 

  26

METHOD CI1:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided and metered by the Company at 415 volts three phase four‐wire and whose consumption exceeds 15,000 Units per Billing Period. a)  A Fixed Charge of KSh2,200.00 

      b)  Energy charge of KSh10.80per Unit consumed. c) Demand charge of KSh800.00 per kVA. 

   METHOD CI2:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 11,000 volts, per Billing Period. a) A Fixed Charge of KSh4,500.00.  b) Energy charge of KSh8.90 per Unit consumed. c) Demand charge of KSh520.00 per kVA. 

 METHOD CI3:  Applicable  to Commercial and  Industrial Consumers  for supplies provided 

and metered by the Company at 33,000 volts, per Billing Period. a) A Fixed Charge of KSh5,000.00 b) Energy charge of KSh8.15per Unit consumed. c) Demand charge of KSh270.00 per kVA 

 METHOD CI4:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 66,000 volts, per Billing Period. a) A Fixed Charge of KSh6,500.00 b) Energy charge of KSh7.80 per Unit consumed. c) Demand charge of KSh220.00 per kVA. 

 METHOD CI5:  Applicable  to Commercial  and  Industrial Consumers  for  supplies provided 

and metered by the Company at 132,000 volts, per Billing Period. a) A Fixed Charge of KSh17,000 b) Energy charge of KSh7.70 per Unit consumed. c) Demand charge of KSh220.00 per kVA. 

 METHOD IT:  Interruptible off‐peak  supplies of electrical energy  to ordinary  consumers 

metered  by  the  Company  whose  consumption  does  not  exceed  15,000 Units per Billing Period. a) A Fixed Charge of KSh250.00*  b) Energy charge of KSh14.50 per Unit consumed. 

 *  If Method  IT  is used  in  conjunction with Method DC or SC at  the  same  supply 

terminals,  then  the  combined  Fixed  Charge  for  both  Methods  of  Charge  shall  be KSh500.00 

   Notes: 

Note 1  The  electrical  energy  which  shall  be  supplied  and  charged  under  this method  of  charge  shall  be  available  at  all  times  other  than  during  peak periods which  shall be  such periods of high demand as may occur during each day not exceeding sixteen hours in the aggregate and during which the supply  of  electrical  energy may  be  restricted,  the  time  or  times  of  such 

  27

restriction and the duration thereof being controlled by the Company at its sole discretion. 

Note 2  This  tariff  is only available  for  installations so arranged  to  the Company's satisfaction,  that  they  cannot  be  operated  on  any  other  tariff  and  also where  there  is  no  duplication of  the off‐peak  circuits by other  electrical circuits unrestricted as  to  time of use  so enabling  the  supply on another method of charge to be used for a similar function. 

Note 3  The  Company  shall  provide  and maintain  apparatus  up  to  a  maximum capacity of 15 amperes, single phase, to control the period of availability of the  supply  and  shall  take  all  reasonable  steps  to  ensure  the  reliability thereof, but shall not be responsible  for any  loss, damage or  injury which may result from any mal‐operation of this control equipment. 

 METHOD SL:  Applicable to public and  local authorities metered by the Company at 240 

or  415  volts  for  supplies  of  electrical  energy  to  public  lamps  (Street Lighting). a) A Fixed Charge of KSh250.00. b) Energy charge of KSh12.30 per Unit consumed 

 Supplies  under  this  Method  of  Charge  shall  be  available  for  a  minimum period of 11 hours per night for public lamps and for no other purpose. 

 The attention of public and  local authorities  taking  supplies on  this  tariff  is drawn to the fact that where public lamps are fitted on the Company's poles, all maintenance of the lamps, switch wire and associated equipment must be carried out  by  the Company,  and  shall  be  charged  for  on  the  basis  of  net costs of materials, labour and transport plus 25%. 

 Note: Every Consumer shall pay to the Company in addition to the charges specified in Part II of 

this Schedule of Tariffs a Fixed Charge at a rate not exceeding KSh 50.00 per kVA per Billing Period  of  nameplate  kVA  continuous  rating  in  respect  of  all  electric  welding  plant,  as adjusted by any power factor equipment in use. 

   Part II – (C) – Applicable 1stJuly  2014  

The  Tariffs  to  be  applied  by  the  Company  for  the  supplies  of  electrical  energy  from  the Interconnected System and also from the Off‐Grid Systems, in each Billing Period shall be as detailed below: 

 METHOD DC:  Applicable to Domestic Consumers metered by the Company at 240 or 415 

volts  and whose  consumption  does  not  exceed  15,000  Units  per  Billing Period. 

a) A Fixed Charge of KSh250.00* 

b) Energy charges of : i.KSh5.75per Unit for 0 ‐ 50 Units consumed; ii.KSh12.30per Unit for 51‐1,500 Units consumed; iii. KSh23.86per Unit for Units consumed above 1,500. 

  28

* If Method DC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both Methods of Charge shall be KSh500.00. 

 METHOD SC:  Applicable to non‐domestic Small Commercial Consumers metered by the 

Company  at  240  or  415  volts  and whose  consumption  does  not  exceed 15,000 Units per Billing Period. a) A Fixed Charge of KSh250.00* b) Energy charge of KSh15.00 per Unit for all Units consumed. 

* If Method SC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both Methods of Charge shall be KSh500.00 

 METHOD CI1:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 415 volts three phase four‐wire and whose consumption exceeds 15,000 Units per Billing Period. a)  A Fixed Charge of KSh2,200.00 

      b)  Energy charge of KSh11.60per Unit consumed. c) Demand charge of KSh800.00 per kVA. 

   METHOD CI2:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 11,000 volts, per Billing Period. a) A Fixed Charge of KSh4,500.00.  b) Energy charge of KSh9.15 per Unit consumed. c) Demand charge of KSh520.00 per kVA. 

 METHOD CI3:  Applicable  to Commercial and  Industrial Consumers  for supplies provided 

and metered by the Company at 33,000 volts, per Billing Period. a) A Fixed Charge of KSh5,000.00 b) Energy charge of KSh8.35 per Unit consumed. c) Demand charge of KSh270.00 per kVA 

 METHOD CI4:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 66,000 volts, per Billing Period. a) A Fixed Charge of KSh6,500.00 b) Energy charge of KSh8.00per Unit consumed. c) Demand charge of KSh220.00 per kVA. 

 METHOD CI5:  Applicable  to Commercial  and  Industrial Consumers  for  supplies provided 

and metered by the Company at 132,000 volts, per Billing Period. a) A Fixed Charge of KSh17,000 b) Energy charge of KSh7.90 per Unit consumed. c) Demand charge of KSh220.00 per kVA. 

 METHOD IT:  Interruptible off‐peak  supplies of electrical energy  to ordinary  consumers 

metered  by  the  Company  whose  consumption  does  not  exceed  15,000 Units per Billing Period. a) A Fixed Charge of KSh250.00*  b) Energy charge of KSh15.30 per Unit consumed. 

 

  29

*  If Method  IT  is used  in  conjunction with Method DC or SC at  the  same  supply terminals,  then  the  combined  Fixed  Charge  for  both  Methods  of  Charge  shall  be KSh500.00 

   

  Notes: 

Note 1  The  electrical  energy  which  shall  be  supplied  and  charged  under  this method  of  charge  shall  be  available  at  all  times  other  than  during  peak periods which  shall be  such periods of high demand as may occur during each day not exceeding sixteen hours in the aggregate and during which the supply  of  electrical  energy may  be  restricted,  the  time  or  times  of  such restriction and the duration thereof being controlled by the Company at its sole discretion. 

Note 2  This  tariff  is only available  for  installations so arranged  to  the Company's satisfaction,  that  they  cannot  be  operated  on  any  other  tariff  and  also where  there  is  no  duplication of  the off‐peak  circuits by other  electrical circuits unrestricted as  to  time of use  so enabling  the  supply on another method of charge to be used for a similar function. 

Note 3  The  Company  shall  provide  and maintain  apparatus  up  to  a  maximum capacity of 15 amperes, single phase, to control the period of availability of the  supply  and  shall  take  all  reasonable  steps  to  ensure  the  reliability thereof, but shall not be responsible  for any  loss, damage or  injury which may result from any mal‐operation of this control equipment. 

 METHOD SL:  Applicable to public and  local authorities metered by the Company at 240 

or  415  volts  for  supplies  of  electrical  energy  to  public  lamps  (Street Lighting). a) A Fixed Charge of KSh250.00. b) Energy charge of KSh12.80 per Unit consumed 

 Supplies  under  this  Method  of  Charge  shall  be  available  for  a  minimum 

period of 11 hours per night for public lamps and for no other purpose.  

The attention of public and  local authorities  taking  supplies on  this  tariff  is drawn to the fact that where public lamps are fitted on the Company's poles, all maintenance  of  the  lamps,  switch  wire  and  associated  equipment  must  be carried out by the Company, and shall be charged for on the basis of net costs of materials, labour and transport plus 25%. 

 Note: Every Consumer shall pay to the Company in addition to the charges specified in Part II of 

this Schedule of Tariffs a Fixed Charge at a rate not exceeding KSh 50.00 per kVA per Billing Period of nameplate kVA continuous rating in respect of all electric welding plant, as adjusted by any power factor equipment in use. 

   Part II – (D) – Applicable 1stJuly  2015  

  30

METHOD DC:  Applicable to Domestic Consumers metered by the Company at 240 or 415 volts  and whose  consumption  does  not  exceed  15,000  Units  per  Billing Period. 

a) A Fixed Charge of KSh300.00* 

b) Energy charges of : i. KSh5.75 per Unit for 0 ‐ 50 Units consumed; ii. KSh13.64 per Unit for 51‐1,500 Units consumed; iii. KSh24.80 per Unit for Units consumed above 1,500. 

* If Method DC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both Methods of Charge shall be KSh600.00. 

 METHOD SC:  Applicable to non‐domestic Small Commercial Consumers metered by the 

Company  at  240  or  415  volts  and whose  consumption  does  not  exceed 15,000 Units per Billing Period. a) A Fixed Charge of KSh300.00* b) Energy charge of KSh16.62 per Unit for all Units consumed. 

* If Method SC is used in conjunction with Method IT at the same supply terminals, then the combined Fixed Charge for both Methods of Charge shall be KSh600.00 

 METHOD CI1:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 415 volts three phase four‐wire and whose consumption exceeds 15,000 Units per Billing Period. a)  A Fixed Charge of KSh2,500.00 b)  Energy charge of KSh13.00per Unit consumed. c) Demand charge of KSh800.00 per kVA. 

   METHOD CI2:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 11,000 volts, per Billing Period. a) A Fixed Charge of KSh5,000.00.  b) Energy charge of KSh10.30 per Unit consumed. c) Demand charge of KSh520.00 per kVA. 

 METHOD CI3:  Applicable  to Commercial and  Industrial Consumers  for supplies provided 

and metered by the Company at 33,000 volts, per Billing Period. a) A Fixed Charge of KSh6,000.00 b) Energy charge of KSh9.35 per Unit consumed. c) Demand charge of KSh270.00 per kVA 

 METHOD CI4:  Applicable  to Commercial and  Industrial Consumers  for  supplies provided 

and metered by the Company at 66,000 volts, per Billing Period. a) A Fixed Charge of KSh7,000.00  b) Energy charge of KSh9.05 per Unit consumed. c) Demand charge of KSh220.00 per kVA. 

 METHOD CI5:  Applicable  to Commercial  and  Industrial Consumers  for  supplies provided 

and metered by the Company at 132,000 volts, per Billing Period. a) A Fixed Charge of KSh18,000 

  31

b) Energy charge of KSh8.90 per Unit consumed. c) Demand charge of KSh220.00 per kVA. 

 METHOD IT:  Interruptible off‐peak  supplies of electrical energy  to ordinary  consumers 

metered  by  the  Company  whose  consumption  does  not  exceed  15,000 Units per Billing Period. a) A Fixed Charge of KSh300.00*  b) Energy charge of KSh16.60 per Unit consumed. 

 *  If Method  IT  is used  in  conjunction with Method DC or SC at  the  same  supply 

terminals,  then  the  combined  Fixed  Charge  for  both  Methods  of  Charge  shall  be KSh600.00 

   Notes: 

Note 1  The  electrical  energy  which  shall  be  supplied  and  charged  under  this method  of  charge  shall  be  available  at  all  times  other  than  during  peak periods which  shall be  such periods of high demand as may occur during each day not exceeding sixteen hours in the aggregate and during which the supply  of  electrical  energy may  be  restricted,  the  time  or  times  of  such restriction and the duration thereof being controlled by the Company at its sole discretion. 

Note 2  This  tariff  is only available  for  installations so arranged  to  the Company's satisfaction,  that  they  cannot  be  operated  on  any  other  tariff  and  also where  there  is  no  duplication of  the off‐peak  circuits by other  electrical circuits unrestricted as  to  time of use  so enabling  the  supply on another method of charge to be used for a similar function. 

Note 3  The  Company  shall  provide  and maintain  apparatus  up  to  a  maximum capacity of 15 amperes, single phase, to control the period of availability of the  supply  and  shall  take  all  reasonable  steps  to  ensure  the  reliability thereof, but shall not be responsible  for any  loss, damage or  injury which may result from any mal‐operation of this control equipment. 

 METHOD SL:  Applicable to public and  local authorities metered by the Company at 240 

or  415  volts  for  supplies  of  electrical  energy  to  public  lamps  (Street Lighting). a) A Fixed Charge of KSh300.00. b) Energy charge of KSh14.00 per Unit consumed 

 Supplies  under  this  Method  of  Charge  shall  be  available  for  a  minimum period of 11 hours per night for public lamps and for no other purpose. 

 The attention of public and  local authorities  taking  supplies on  this  tariff  is drawn to the fact that where public lamps are fitted on the Company's poles, all maintenance of the lamps, switch wire and associated equipment must be carried out  by  the Company,  and  shall  be  charged  for  on  the  basis  of  net costs of materials, labour and transport plus 25%. 

 Note: 

  32

Every Consumer shall pay to the Company in addition to the charges specified in Part II of this Schedule of Tariffs a Fixed Charge at a rate not exceeding KSh 50.00 per kVA per Billing Period of nameplate kVA continuous rating in respect of all electric welding plant, as adjusted by any power factor equipment in use. 

  

            PART III 

OTHER CHARGES 

 1. Fuel Cost Charge (a) All Tariff for electrical energy specified  in Part  II of this Schedule of Tariffs 2013shall 

be  liable  to  Fuel  Cost  Charge  which  shall  be  calculated  in  accordance  with  the following formula:  Fuel Cost Charge in Kenya cents/Unit calculated to the nearest one cent:  

=  1001

⎭⎬⎫

⎩⎨⎧ Σ+Σ

×− G

PSGCL

iiii  

  Where: Ci  =   Actual price in KSh/kg paid by the Company or Electric Power Producers for 

fuel  consumed by Plant  i, where  i= 1, 2, … n, during  the  calendar month immediately preceding each Billing Period at all existing thermal plants on the  Interconnected System and  the Off‐Grid System, as  the  case may be. This shall also include other thermal power plants to be constructed and in respect of which the Company shall enter into Power Purchase Agreements with Electric Power Producers for the supply of electricity to the Company from those power plants with the approval of the Commission. 

 Gi=   All Units generated and or purchased by the Company from Electric Power 

Producers’  Plant  i,  where  i=  1,  2,  …,  n,  during  the  calendar  month immediately preceding each Billing Period at each existing thermal plant on the  Interconnected System and  the Off‐Grid System, and  imports/exports from Uganda Electricity Transmission Company Limited adjusted for system losses  as  the  case may  be.    This  shall  also  include  other  thermal  power plant(s) to be constructed and in respect of which the Company shall enter into Power Purchase Agreement(s) with Electric Power Producer(s) for the supply  of  electricity  to  the  Company  from  those  power  plants with  the approval of the Commission. 

 G=   Total  of  all  Units  purchased  by  the  Company  from  Electric  Power 

Producer(s),  generated  by  the  Company  and  net  imports  during  the calendar  month  immediately  preceding  each  meter  reading  period, including all hydro stations, Off‐Grid power stations and imports. 

 Si =  Specific fuel consumption in kg/Unit for the following thermal plants: 

 

  33

EmbakasiGas Turbine I & II      0.315 kg/Unit purchased Kipevu I Diesel Plant        0.217 kg/Unit purchased  Kipevu II Diesel Plant (Tsavo)    0.219 kg/Unitpurchased Kipevu III Diesel Plant    0.2095 kg/Unit purchased  Iberafrica Diesel Plant:  Using 1% Sulphur HFO                   0.225kg/Unit purchased  Using 1.8% Sulphur HFO    0.226 kg/Unit purchased Iberafrica Additional Plant    0.224 kg/Unit purchased Rabai Diesel Plant*: 

  With steam turbine or above 33MW    0.1971 kg/Unit purchased Without steam turbine or below 33MW      0.208 kg/Unit purchased Triumph Diesel Plant        0.191 kg/Unit purchased  Gulf Diesel Plant           0.215 kg/Unit purchased  Garissa Diesel Plant        0.220 kg/Unit purchased Melec Diesel Plant       

           With steam turbine or above 33MW      0.199 kg/Unit purchased Without steam turbine or below 33MW       0.215 kg/Unit purchased  Emergency Plants         0.223 kg/Unit purchased  

      Diesel Plants in Off‐Grid System**   

Garissa Diesel Plant         0.278 kg/Unit purchased Lamu Diesel Plant (Existing):       0.306 kg/Unit purchased  Lamu Diesel Plant (New):        0.280 kg/Unit purchased   Lodwar            0.282 kg/Unit generated  Mandera            0.266 kg/Unit generated  Marsabit  IDO        0.284 kg/Unit generated  Marsabit   AGO        0.279 kg/Unit generated  Wajir   IDO            0.260 kg/Unit generated  Wajir   AGO            0.260 kg/Unit generated  Moyale            0.277 kg/Unit generated  Mpeketoni            0.290 kg/Unit generated  Habaswein            0.290 kg/Unit generated  Hola            0.290 kg/Unit generated  Merti            0.290 kg/Unit generated  Elwak            0.290 kg/Unit generated  Mfangano            0.290 kg/Unit generated Baragoi            0.290 kg/Unit generated Lokichogio              0.290 kg/Unit generated Takaba             0.290 kg/Unit generated Eldas             0.290 kg/Unit generated Rhamu              0.290 kg/Unit generated  

*Rabai: The higher specific fuel consumption for Rabai Diesel Plant also applies for a period of 2.5 hours during start up after a plant shutdown of more than 8 hours.  

 

  34

** Specific fuel consumption for Off‐Grid System (except Garissa and Lamu) estimated at 0.290 kg/unit  shall also apply  to other  thermal power plants  to be  constructed  for  the  supply of electricity to the Company from that Power Station with the approval of the Commission. The estimated  specific  fuel  consumption  for  Mpeketoni,  Habaswein,  Hola,  Merti,  Mfangano, Baragoi,Elwak, Lokichogio, Takaba, Eldas and Rhamu shall be amended  to actual  rates after the completion of the machine test run following full commissioning and stabilisation of the load.  

Pi =   Sum  of  fuel  displacement  costs  and  other  pass  through  charges  based  on  power purchased  from Power Plant  i, where  i  =1, 2  ... n.  This  refers  to Mumias, Emergency Power Plants and other power plants to be constructed in respect of which the Company shall  enter  into  a  Power  Purchase  Agreement with  Electric  Power  Producers  for  the supply of electricity to the Company  from that Power Station with the approval of the Commission.   i) The fuel displacement costs, Pi, for the Mumias Power Plant shall be computed 

using the formula Pi = Gi×DCRi,   

Where,   

Gi =   Units purchased by the Company from the plant during the calendar month immediately preceding each Billing Period,  

DCRi  =  the  approved  Displacement  Charge  Rate  for  the  plant  being  US$ 0.034/kWh. 

 ii) The pass  through cost, PTC,  for Emergency Power plants  shall be  calculated as 

follows:    PTC =Σ (Gj x ECR)    Where,     ECR is the energy charge rate for the plant being US$ 0.009/kWh for Emergency 

Power Plants.    Gjare  units  purchased  from  each  emergency  plant  in  the month  immediately 

preceding the current Billing Period.    All fuel displacement and pass through costs shall be converted to Kenya Shillings 

using the CBK mean exchange rate of the calendar month immediately preceding each Billing Period.    

 iii) The  fuel  displacement  costs,  Pi,  for  the Geothermal Well Head Units  shall  be 

computed using the formula Pi = Gi×DCRi,   Where,   Gi =   Units  purchased  by  the  Company  from  the  plant  during  the  calendar month 

immediately preceding each Billing Period,  

  35

DCRi =   the  approved  Displacement  Charge  Rate  for  the  plant  being  US$ 0.0595/kWh  

 iv) The fuel displacement costs, Pi, for the Aeolus, Kipeto and Prunus Power 

Plants shall be computed using the formula Pi = Gi×DCRi,   Where,   Gi =   Units  purchased  by  the  Company  from  the  plant  during  the  calendar month 

immediately preceding each Billing Period,  DCRi =   the  approved  Displacement  Charge  Rate  for  the  plant  being  US$ 

0.084/kWh   v) The fuel displacement costs, Pi, for Power Plant plants procured through 

the FiT Policyshall be computed using the formula Pi = Gi×DCRi,   Where,   Gi =   Units  purchased  by  the  Company  from  the  plant  during  the  calendar month 

immediately preceding each Billing Period,  DCRi =   the approved Displacement Charge Rate for the plant being 70% of the 

applicable FiT tariff   vi) The fuel displacement costs, Pi, for the Lake Turkana Wind Power Plant 

shall be computed using the formula Pi = Gi×DCRi,   Where,   Gi =   aggregate of NEOp1  +0.5*NEOp2  +  DGEp  NEOp1 = the aggregate Net Electrical Output (kWh) of the Plant in that month, when 

the cumulative sum of the Net Electrical Output and the Deemed Generated Energy in the  Operating  Year  to  date  that  is  already  invoiced  for  is  equal  to  or  less  than 1,445,400,000 KWh.

NEOp2 = the aggregate Net Electrical Output (kWh) of the wind farm in that month, when the 

cumulative sum of the Net Electrical Output and the Deemed Generated Energy in the Operating Year to date that is already payable  is greater than 1,445,400,000 KWh.

DGEp = the aggregate Deemed Generated Energy (kWh) of the Plant in that month, when 

the cumulative sum of the Net Electrical Output and the Deemed Generated Energy in the  Operating  Year  to  date  that  is  already  payable  for  is  equal  to  or  less  than 1,445,400,000 KWh.

     

  36

DCRi =  aggregate of DCRi1 + DCRi2      DCRi1 =  the  approved  Displacement  Charge  Rate  for  the  plant  being 

€0.05264/kWh    DCRi2 =  the approved Displacement Charge Rate for the plant being €0.023/kWh 

to  cater  for  the  difference between  Feed‐in‐Tariff  and  energy  plant  converted using base exchange rate 

   L =  Target  System  loss  factor  in  transmission  and  distribution  equal  to  17.5%  in 

2012/13, 17.3% in 2013/14,17.1% in 2014/15 and 16.9% in 2015/16.  

(b)  The Company shall publish each month a notice in the Kenya Gazette showing the Fuel Cost Charge rate applicable to all Units billed during the month of publication of such notice.  

 2. Foreign Exchange Rate Fluctuation Adjustment 

 (a)  All prices for electrical energy specified in Part II of the Schedule of Tariffs shall be liable 

to  Foreign  Exchange  Rate  Fluctuation  Adjustment  which  shall  be  calculated  in accordance with the following formula: 

 Foreign Exchange Rate Fluctuation Adjustment  in Kenya  cents/Unit  calculated  to  the nearest one cent 

 

tFERFA =L−1

1×{ ( ( ) ) (( ) ) ( ( ) )

GXZIPPXZHXZF ottottott ××Σ+××Σ+××Σ −−− 111 }×100 

         Where, 

 

  1−tF   =  Sum  of  the  foreign  currency  costs  incurred  by  KenGen  in  the  calendar month 

immediately preceding current Billing Period. 

  1−tH = Sum of the foreign currency costs  incurred by the Company other than those costs 

relating  to  Electric  Power  Producers  in  the  calendar  month  immediately preceding current Billing Period. 

  1−tIPP = Sum of the foreign currency costs paid by the Company to Electric Power Producers 

(except KenGen) in the calendar month immediately preceding current Billing Period. 

 The  factor Zt  is  the proportionate change  in  the exchange  rate  (Xt)  in  the current 

Billing  Period  t  from  the  Base  Exchange  rate  (Xo)  in  the  base  period  and  shall  be determined according to the following formula:  

 

Zt=  o

ot

XXX −

 

  37

                         Where; 

tX =  CBK  mean  exchange  rate  for  the  calendar  month  immediately 

preceding current Billing Period.  

oX = CBK mean exchange rate  as tabulated below. 

    CBK Mean Exchange Rates 

Foreign Currency September 

2012 May 2009   March  2008 

US Dollar  84.6133  77.8614  64.9242STG Pound  136.2555  120.0302  130.0783 Euro  108.7977  106.2277  100.7930 SA Rand  10.2256  9.2839  8.1443 AE Dirham  23.0367  21.1988  17.6814Canadian Dollar  86.4971  67.5520  65.0696Swiss Francs  90.0162  70.2685  64.1707 JPY(100)  108.2463  80.6318  64.0416 SW Kroner  12.8098  10.0445  10.6474 NOR Kroner  14.7146  12.0684  12.8074 DAN Kroner  14.5971  14.2576  13.4244IND Rupee  1.5516  1.6044  1.6104 Hongkong Dollar  10.9119  10.0450  8.3401 Saudi Riyal  22.5626  20.7623  17.3168 

Chinese Yuan  13.3844  11.4092  9.1613

Australian Dollar  87.9535  59.4860  60.0525

               Note:  The  CBK mean  exchange  rates  for May  2009  and March  2008  shall  only  apply  to 

KenGen  Kenya  shillings  denominated  charge  rates  as  stipulated  in  the  Power Purchase Agreements.    

G=   Total  of  all  Units  purchased  by  the  Company  from  Electric  Power  Producer(s), generated  by  the  Company  and  net  imports  during  the  calendar  month immediately preceding each meter reading period, including all hydro stations, Off‐Grid power stations and imports. 

 L =   Target System loss factor in transmission and distribution equal to  17.5% in 2012/13, 17.3% in 2013/14, 17.1% in 2014/15 and 16.9% in 2015/16. 

 (b) The Company shall publish a notice  in  the Kenya Gazette showing  the amount of  the 

Foreign  Exchange  Rate  Fluctuation  Adjustment  applicable  to  all  Unit  charges specified in Part II of the Schedule of Tariffs for all meter readings taken during the month of publication of the said notice.  

 3. Inflation Adjustment 

 (a) All prices for electrical energy specified in Part II of the Schedule of Tariffs shall be liable 

to an Automatic adjustment for  inflation at the end of every six month period starting from 1st July, 2011.  

 

  38

The effect of domestic and international inflation on cost of supply shall be calculated in accordance with the following formula: 

 

INFAt = L−1

1× (

p

KPLCIPPKenGen

GINFAINFAINFA ++ ) ×100 

Where,  

INFAt = Total Inflation Adjustment in Kenya cents per Unit for the half year period t. The first adjustment shall be effected on 1stJuly2013. 

 L     =   Target System loss factor in transmission and distribution equal to  17.5% in 2012/13, 17.3% in 2013/14, 17.1% in 2014/15 and 16.9% in 2015/16. 

 Gp =   Total projected Units generated or purchased by the Company from Electric Power 

Producer(s), during  the half‐year Adjustment Period.   This shall also  include other power plants  to be constructed and  in  respect of which  the Company  shall enter into a Power Purchase Agreement with Electric Power Producers for the supply of electricity  to  the  Company  from  those  power  plants  with  the  approval  of  the Commission. 

 i) INFAKenGen 

 

INFAKenGen = ∑ iINFAKP  

 Where, 

 INFAKPi=  Specific Inflation Adjustment in half‐year period, relating to 

contracted  KenGen Plant i, which shall be determined as follows:  

[ ] ⎥⎦

⎤⎢⎣

⎡⎟⎟⎠

⎞⎜⎜⎝

⎛−+⎟⎟

⎞⎜⎜⎝

⎛−+= 1

USCPIUSCPI3.01

CPIUCPIU5.0x7.0xxVOMCRGkxFOMCRKPINFAKP

b

t

b

tbiibiii

 Where: 

 KPi           =      Contracted capacity for KenGen Plant i in kW. 

 FOMCR bi=       The base Escalable Capacity Charge Rate for KenGen Plant i in 

KSh/kW/year for September 2012, divided by two  

VOMCR bi  =   The base escalable  Variable Operation and Maintenance Charge Rate or variable energy charge rate as applicable, for KenGen plant i in KSh/kWhfor September 2012 

 Gki=    Projected Units purchased from KenGen plant i in kWh in the 

half‐year Adjustment Period.   CPIUb =  The Geometric Underlying Consumer Price  Index  for September 

2012as posted by Kenya National Bureau of Statistics (Index base – February 2009 = 100), being 126.15. 

 

  39

CPIUt =  The Underlying Consumer  Price  Index  for  the month of March for  adjustments  effected  in  the  period  July  –  December;  and September for adjustments effected in the period January – June every year as provided by the Kenya National Bureau of Statistics (Index base – February 2009 = 100). 

 USCPIb =  The “Consumer Prices Index for all urban consumers (CPI ‐ U) for 

the US city average for all items 1982 ‐ 84 =100" as published by the  United  States  Department  of  Labour  Statistics  index  for September 2012, being 231.407. 

 USCPIt =  The “Consumer Prices Index for all urban consumers (CPI ‐ U) for 

the US city average for all items 1982 ‐ 84 =100" as published by the United States Department of Labour Statistics  index  for the month  of March  for  adjustments  effected  in  the  period  July  – December;  and  for  September  for  adjustments  effected  in  the period January – June every year.  

 ii) INFAIPP 

  

INFA IPP= ∑ iINFAIPP   

Where,  

INFAIPPi=  Specific Inflation Adjustment in half‐year period, relating to contracted  Electric Power Producer’s (excluding KenGen) Plant i, which shall be determined as follows: 

  

[ ] ⎥⎦

⎤⎢⎣

⎡−+= 1

USCPIUSCPIxxECRGIPPxCCRIPPINFAIPP

b

tbiibiii * 

 Where, 

 IPPi  = Contracted capacity for IPP Plant i in kW. 

 CCRbi      =      Base escalable capacity charge rate for IPP plant i in US$/kW/year, 

for September 2012, divided by two.  GIPPi=  Projected Units purchased  from  IPP plant  i  in  kWh  in  the half‐

year Adjustment Period.   

ECRbi=              Base  escalable  energy  charge  rate  for  IPP  plant  i  in US$/kWh  for September 2012.  

 USCPIb =  The “Consumer Prices Index for all urban consumers (CPI ‐ U) for 

the US city average for all items 1982 ‐ 84 =100" as published by the  United  States  Department  of  Labour  Statistics  index  for September 2012, being  231.407. 

 

  40

USCPIt =  The “Consumer Prices Index for all urban consumers (CPI ‐ U) for the US city average for all items 1982 ‐ 84 =100" as published by the United States Department of Labour Statistics  index  for the month  of March  for  adjustments  effected  in  the  period  July  – December;  and  for  September  for  adjustments  effected  in  the period January – June every year.  

  *Note: For Euro denominated costs   

CCRbi  =   Base  escalable  capacity  charge  rate  for  IPP  plant  i  in    €/kW/year,  for September 2012, divided by two. 

 ECRbi=      Base  escalable  energy  charge  rate  for  IPP  plant  i  in  €/kWh            for 

September 2012.   

USCPIb=   The Monetary Union Index of Consumer Prices for European Union as published by Eurostat for September 2012being 116.44. 

 USCPIt=     The Monetary Union Index of Consumer Prices for European Union as 

published by Eurostat  for  the month of March  for adjustments effected  in  the  period  July‐December;  and  for  September  for adjustment effected in the period January‐June every year. 

 All  inflation adjustment costs  for  IPPs shall be converted to Kenya Shillings using the base exchange rates in this Schedule of Tariffs and Rates 2013. 

 iii) INFAKPLC 

      INFAKPLC            Is  theSpecific  Inflation  Adjustment  in  half‐year  period,  relating  to  the 

Company’s  transmission and distribution operation and maintenance costs, which shall be determined as follows: 

 

⎥⎦

⎤⎢⎣

⎡⎟⎟⎠

⎞⎜⎜⎝

⎛−+⎟⎟

⎞⎜⎜⎝

⎛−= 1

USCPIUSCPI3.01

CPIUCPIU5.0x7.0TDOMINFA

b

t

b

tbKPLC  

 Where,  

 TDOM b =  The  transmission  and  distribution  network  operation  and 

maintenance costs excluding depreciation of assets and provision for bad debts in year2011/12, divided by two.  

 CPIUb =  The Geometric Underlying Consumer Price  Index  for September 

2012as posted by Kenya National Bureau of Statistics (Index base – February 2009 = 100), being 126.15. 

 CPIUt =  The Underlying Consumer  Price  Index  for  the month of March 

for  adjustments  effected  in  the  period  July  –  December;  and September for adjustments effected in the period January – June every year as provided by the Kenya National Bureau of Statistics (Index base – February 2009 = 100). 

 

  41

USCPIb =  The “Consumer Prices Index for all urban consumers (CPI ‐ U) for the US city average for all items 1982 ‐ 84 =100" as published by the  United  States  Department  of  Labour  Statistics  index  for September 2012, being 231.407. 

 USCPIt =  The “Consumer Prices Index for all urban consumers (CPI ‐ U) for 

the US city average for all items 1982 ‐ 84 =100" as published by the United States Department of Labour Statistics  index  for the month  of March  for  adjustments  effected  in  the  period  July  – December;  and  for  September  for  adjustments  effected  in  the period January – June every year.  

        Note:   Any difference between the total inflation costs and the actual billed amount for a 

given half year adjustment period shall be adjusted  for  in the following half year period. 

 (b) The Company shall publish in the first month of the half‐year inflation adjustment 

period a notice  in  the Kenya Gazette  showing  the half‐year  Inflation Adjustment rate applicable to all Units billed during that half‐year period.  

 4. Taxes and Levies 

 The consumer shall pay any taxes, levies or duties imposed from time to time by the Government.  At present, the following are levied by the Government: 

 i) VAT at 12% charged to : 

a) Fixed Charge  b) Demand Charge c) Foreign Exchange Fluctuation Adjustment  d) Fuel Cost and;  e) Taxable  value  of  electrical  energy  consumed  in  a manner  required  by  the 

Government.   

ii) Rural Electrification Programme (REP) levy at 5% of revenue from Unit sales.  

iii) Energy Regulatory Commission (ERC) levy at 3 Kenya cents/kWh.  

 

 

 

 

  42

PART IV 

OTHER IMPORTANT CONDITIONS 

 a) In  the  event of  the  supply of  electrical  energy  to  the  installation of  any Consumer 

having  a  Power  Factor  of  less  than  0.90,  then  the  Company  may  give  to  such Consumer thirty days notice in writing requiring him to improve the Power Factor of his installation to or in excess of 0.90. 

 b) If a Consumer fails to comply with such notice as aforesaid, then and in any such case, 

the  Company  shall  be  at  liberty  until  such  time  as  the  Power  Factor  of  such Consumer’s installation is, or is in excess of 0.90 to impose a surcharge as follows:‐ 

 

i)   for  Consumers  charged  under Methods  DC,  SC,  SL  and  IT,  the  payment  for electrical energy consumed  in each Billing Period (exclusive of VAT, Fuel Cost, Foreign  Exchange  Rate  Fluctuation Adjustment,  REP  and  ERC  levies)  shall  be increased by 2 per cent for each complete 1 per cent by which the power factor is below 0.90. 

 ii)  for  Consumers  charged  under Methods  CI  ‐  the  payment  for  electrical  energy 

consumed and chargeable KVA of Demand in each Billing Period (exclusive of VAT, Fuel Cost,  Foreign  Exchange Rate  Fluctuation Adjustment,  REP  and  ERC  levies) shall be increased by 2 per cent for each complete 1 per cent by which the Power Factor is below 0.90.  

c) Any apparatus installed by the Company for the purpose of ascertaining the power factor of any Consumer's installation or of any part thereof shall be installed and maintained at the sole expense of the Company. 

 d) The Company  shall determine  the  voltage  at which  a  supply of electrical energy  shall be 

provided to any Consumer’s supply terminals and  this voltage shall be maintained by  the Company subject to the permissible variations as provided for in the Act.  

             

     

  43

  REPUBLIC OF KENYA    THE ENERGY ACT 2006  

  Pursuant to Section 45 of The Energy Act 2006 I hereby approve the Schedule of Tariffs and 

Rates  2013  for  supply of  electricity by  KPLC  attached hereto,  to  come  into  force on  the 

............... day of ..................., 2013. 

   APPROVED................................................      ENG. JOHN MWIRICHIA   DIRECTOR GENERAL   ENERGY REGULATORY COMMISSION 

  

  Dated at NAIROBI this ..................... day of ........................................., 2013  

  Pursuant to the above Approval, the Schedule of Tariffs and Rates 2011       are made this .............................. day of .............................................., 2013 

       

  MANAGING DIRECTOR  & CEO   THE KENYA POWER & LIGHTING COMPANY LIMITED 

  44

Appendix 2 – Financial Projections Assumptions   

            PROJECTED FINANCIAL PERFORMANCE 2012/13 TO 2015/16   

1. A transmission and distribution loss of 17.3% of units purchased was achieved in  2011/12  compared  to  the  regulatory  target  average  system  losses  of 15.4%.  From  2012/13,  the  proposed  loss  reduction  path  for  the  Review period is as shown below.  

          

2. The  target  system  losses  level  in  (1)  above  is  assumed  to  be  allowed  by Energy Regulatory Commission  (ERC)  in  the determination of KPLC Revenue Requirement for the three year tariff control period 2012/13 to 2015/16. 

 3. The  sales  projection  is  based  on  an  energy  balance  in  January  2012  using 

updated load forecast that assumes actual electricity demand growth rate of 3.6% in 2011/12. In 2012/13 the demand growth rate is assumed at 4.0%, and 6% for each subsequent year from  2013/14 to 2015/16.  

 4. Average fuel prices of 2011/12 have been assumed from 2012/13 onwards. 

 5. GOK Emergency power is assumed to be purchased by KPLC at a Capacity price 

of US$ 16.22/kW/Month for the remaining 120MW capacity contract period.  

6. All wind projects under FIT policy are assumed  to  require 30% of  the project guaranteed revenues to be provided through the base tariffs while the balance is  to be collected  through a pass‐through mechanism  in accordance with  the policy. 

 7. Lake  Turkana Wind  Power’s  required  guaranteed  revenue  is  assumed  to  be 

provided through the proposed base tariffs of 1st July 2015.    

8. Committed  KenGen  Power  plants  expected  to  be  commissioned  in  the  next three years estimated charge rates used in the projections are shown in Table1. 

 

Duration  

Losses Reduction Path 2012/ 2013   17.5 2013‐2014  17.3 2014‐2015  17.1 2015‐2016  16.9 

  45

Table 1: Committed KenGen Power Plants Estimated Charge Rates  

         Cap. Charge     FOM  VOM 

     Capacity  KSh/kW‐yr  Comm. 

KSh/kW‐yr 

KSh/kWh 

   Plant  MW     Year  (escal.)  (escal.) 

1  Olkaria 1‐ Extension (Units & 5)   140  19,463 Jun‐14 5,551  0.9252 

2  Olkaria 1V   140  22,156 Sep‐14 5,536  0.9282 

3  Olkaria 1 Interim       Jun‐14    3.2562 

 Energy Plants                                                                                                                              in US$/kWh  

4  Well heads units  75     Jun‐11    0.085 

                          Kshs/kWh 

            Esc   Non‐Escal  Total 

5  Sangoro  20    1.60  5.189  6.789 

6  Eburru Geothermal  2.2    2.00  5.44  7.44 

7  Ngong Phase II*  13.6      1.30  4.79  6.09 

8  Ngong 1 Phase II*  6.8      1.30  4.79  6.09 

*The rate assumed for Ngong phase II are those of existing 5MW  

9. Committed IPPs Power plants expected to be commissioned in the next three years estimated charge rates used in the projections are as shown in Table 2.  Table 2:  IPP Committed Plants Expected Charge Rates 

 

      Capacity In Service 

Fixed   Escalable  Variable 

      MW  Year  Capacity charge  (escal.) 

   Plant        US$/kW‐yr  US$/kW‐yr  US$/kWh 

   IPP                

1   Orpower  36  Mar‐13 262.5        285  0.02304

2  Orpower  16  Mar‐14 262.5    285  0.02304

3  Triumph Gen. Plant   87  Jun‐13 157.5 36  0.0074

4  Aeolus Wind  160  Nov‐12      0.12

5  L.Turkana Wind  300  Jul‐13      0.12

6  Kipeto  100  Jul‐15         0.12

7  Prunus  50  Jul‐15         0.12

8  Kwale Sugar  18  Dec‐14         0.10

9  FIT Hydros  21  Jul‐15         0.0825 

         €/kW‐yr  €/kW‐yr  €/kWh 

10  Thika Power  87  Jun‐13 157.5 37.71  0.0074

11  Gulf Power  85  Feb‐14 164.36 37.17  0.0063

  

  46

10. Local and foreign inflation rates recorded upto September 2012 was used to project costs in September 2012 prices. Thereafter, any escalation  in  cost  is assumed  to be  recovered  in future by the allowed a pass‐through mechanism formula.  

   11. CBK mean Exchange  rates  for major currencies  for month of September 2012 have been 

assumed as base  rates  from 2012/13 onwards. There have not been escalated  for  future period because inflation impact is now provided for as a pass‐through element. 

                12. Local  interest  rate/overdraft  rate  for  the entire period  from 2012/13  is assumed at 14%, 

whereas the foreign interest rate has been pegged to 9%.  

13. A 20% Ordinary stock dividend payment has been assumed from 2012/13 onwards.  

14. Bad debts have been assumed at 2.5% of total electricity revenue for 2012/13 onwards.  

15. The  recorded stock  level  in 2011/12 was Kshs.10,286 million. The stock balance grows by 5% of additional plant in service on average from 2012/13 onwards to take into account the resources required for the accelerated new customer creation initiative. 

 16. The creditors’ period has been assumed to be an average of 35 days. 

 17. Electricity  debtors  are  assumed  to  be  sustained  at  42  days  of  total  electricity  revenue  in 

2012/13  annually.  The  collection  from  Government  Ministries,  Local  Authorities  and Parastatals will be pursued with assistance from Ministry of Energy. 

 18. Debtors,  other  than  electricity  ones  and  Rural  Electrification  Schemes,  are  assumed  to  be 

equal  to  approximately  19%  the  level  of  electricity  debtors  based  on  five  years  average historical

  47

Appendix 3:  Tables 15, 16, 17, 18, 19 and 20 (as described below) 

 Table15: Number of Customers by Tariff Categories 

TARIFF   MAIN TYPE    AS AT 30th JUNE

        

   OF CUSTOMERS                   

   COVERED BY   2007  2008  2009  2010  2011  2012 

   THIS TARIFF                      DC  only  Domestic                   

     KPLC  626,099  724,283  873,764  1,017,266  1,239,873  1,428,363 

     REP  91,672  114,820  150,964  189,850  237,602  304,298    DC  & 

IT  Domestic                   

     KPLC  54,284  55,573  57,678  54,076  46,437  43,482 

     REP  358  367  1,002  949  872  830    SC    only  Small Commercial                    

     KPLC  103,617  111,446  124,251  134,601  150,687  163,117 

     REP  40,752  46,010  53,185  60,008  70,552  77,242    SC   & 

IT  Small Commercial                    

     KPLC  1,150  1,149  1,167  1,248  1,266  1,280 

     REP  185  71  72  178  171  178 

   B0     Irrigation Load                   

     KPLC  213  196  0                  ‐                    ‐                     ‐   

     REP  3  3  0                  ‐                    ‐                     ‐   

   B1   Medium Commercial and 

Industrial                   

   KPLC  3,208  3,412  0                  ‐                    ‐                     ‐   

   REP  53  55  0                  ‐                    ‐                     ‐   

   B2   Medium Commercial and 

Industrial                   

   KPLC  65  68  0                  ‐                    ‐                     ‐   

   B3   Medium Commercial and 

Industrial                   

   KPLC  2  4  0                  ‐                    ‐                     ‐   

   CI1    Large Commercial                   

    KPLC   317  321  2,250  2,373  2,457  2,478 

     REP  2  2  37  43  41  28 

   CI2    Large Commercial and 

Industrial                   

   KPLC  168  177  233  255  277  290 

   CI3   Large Commercial and 

Industrial                   

   KPLC  18  16  23  26  29  31 

   CI4 Large Commercial and 

Industrial                   

  48

TARIFF   MAIN TYPE    AS AT 30th JUNE

        

   OF CUSTOMERS                   

   COVERED BY   2007  2008  2009  2010  2011  2012 

   THIS TARIFF                   

   KPLC  1  1  14  16  19  22 

   CI5   Large Commercial and 

Industrial                

   KPLC  1  1  13  15  21  21    IT  only  Off‐peak                   

     KPLC  677  659  631  622  566  13,984 

     REP  8  9  9  8  8  7 

SL  Street lighting                   

     KPLC  1,462  1,723  1,887  2,085  2,429  2,926 

     REP  14  17  18  20  41  48 

   TOTAL (KPLC)  791,282  899,029  1,061,911  1,212,583  1,444,061  1,655,994 

   TOTAL (R.E.P.)  133,047  161,354  205,287  251,056  309,287  382,631 

   GROSS TOTAL  924,329  1,060,383  1,267,198  1,463,639  1,753,348  2,038,625 

   % INCREASE P.A.  15.2%  14.7%  19.5%  15.5%  19.8%  16.3% 

                

     Table 16: Medium‐Term Capacity Balance for Average Hydrology(MW)  

   2011/12  2012/13  2013/14  2014/15  2015/16 

Hydro (MW)                

   Small hydros   

10.9            10.9             10.9             10.9             10.9     Tana              20              20               20               20               20     Masinga              40              40               40               40               40     Kamburu              90              90               90               90               90  

   Gitaru   

216             216              216              216              216     Kindaruma              64              64               72               72               72  

   Kiambere   

164             164              164              164              164  

   Turkwel   

105             105              105              105              105     Sondu‐Miriu              60              60               60               60               60     Sang'oro (Sondu Additional Plant)              20              20               20               20               20  

Total Hydro  (MW)   

790             790              798              798              819                   GEOTHERMAL                   Olkaria I  44  44  44  44   44    Olkaria II  101  101  101  101   101    Olkaria IV           140   140    Eburru  2.2  2.2  2.2  2.2   2.2    Wellheads  5  5  25  70   70 

  49

   2011/12  2012/13  2013/14  2014/15  2015/16    Olkaria I Life Extension           140   140 Total KenGen Geothermal  152  152  172  497  497                  THERMAL                                    Kipevu I Diesel  60  60  60  60   60    Kipevu Kvaener GT 1                    30               30               30  

   Kipevu Kvaener GT 2              30              30               30               30               30  

Kipevu III MSD   

115             115              115              115              115  

Total KenGen Thermal   

205             205              235              235              235  

  Aggreko Embakasi 8              60              60              60       

  Aggreko Embakasi 7              30              30              30       

  Aggreko Muhoroni              30              30              30       

Total EPP  120  120  120  0  0 

                 

WIND                

 Ngong 1& 2             5.1             5.1              5.1             25.5             25.5  

Total Wind                5                5                 5               26               26  Total KenGen + EPP Interconnected  

  1,272          1,272           1,330           1,556           1,577  

IPPs                

   Iberafrica Diesel              56              56               56               56               56  

  Iberafrica II   

52.5            52.5             52.5             52.5             52.5  

   Tsavo Power               74              74               74               74               74  

   Orpower 4  geothermal              52              52               52               52               52  

   Orpower 4  geothermal 2                 36               36               52               52  

   Rabai MSD               90              90               90               90               90  

   Athi River 1‐Triumph                    83               83               83  

   Athi River 2‐Gulf        80  80   80 

   Thika MSD‐Melec     87  87  87   87 

   Mumias Bagasse              26              26               26               26               26  

Turkana Wind                         300  

Aeolus Wind‐Kinangop                       60               60  Kwale International Sugar Company Ltd                       18               18  

Prunus                          50  

Kipeto                         100  FiT projects(genpro,gura and hydel)                          21  

Total IPPs   

351             474              637              731           1,181  

  50

   2011/12  2012/13  2013/14  2014/15  2015/16 Total Interconnected System 

  1,623          1,746           1,967           2,286           2,457  

Maintenance & Spinning Allowance                 15% of Projected Peak Demand 

  185             200              207              219              232  

Peak demand (Actual )   

1,236             Projected Interconnected System Peak 

  1,236          1,330           1,379           1,462           1,549  

   

Table 17: Medium‐Term Energy Balance for Average Hydrology (GWh)   

THE INTERCONNECTED SYSTEM   

   2011/12  2012/13  2013/14  2014/15  2015/16 

KenGen  Interconnected                

   Small hydros   

66   

66   

66               66    

66    Sang'oro (Sondu Additional Plant)               7 

  102 

  102             102  

  102 

Main hydros   

3,379  3,282  3,067  3,067  3,067 

Total Hydro    GWh  3,452  3,450  3,235  3,235  3,235 

                 

GEOTHERMAL                

                     Olkaria I   279   362   327   308    251 

                     Olkaria II   819   832   832  814   796 

                     Olkaria IV    ‐  0  0  846  1,042 

                     Eburru   5  17  15  15  15 

                     Wellhead Units   3  39  138  263  184                      Olkaria I Rehab/Optimization    ‐  0  0  1,128  1,042 

Total Geothermal  1,107  1,251  1,312  3,375   3,331 

                 

THERMAL                

                 

   Kipevu I Diesel   256   263   263   74    26 

   Kipevu Kvaener GT 1    ‐    ‐   26   13     ‐ 

   Kipevu Kvaener GT 2   33   39   26   13     ‐ 

Kipevu III MSD   525   604   554   181    32 

     ‐             

Total KenGen Thermal   814   907   869   281    58 

  Aggreko Embakasi 8   253   173   39    ‐     ‐ 

  51

THE INTERCONNECTED SYSTEM   

   2011/12  2012/13  2013/14  2014/15  2015/16 

  Aggreko Embakasi 7   78   129   20    ‐     ‐ 

  Aggreko Muhoroni   49   50   80    ‐     ‐ 

Total EPP   381   352   139    ‐     ‐ 

                 

WIND                

     Ngong  14.6   14   16  59  78 

Total Wind   

15   14   16   59    78 

                 Total  KenGen  Interconnected 

  5,768 

  5,974 

  5,572          6,950  

  6,703 

                 

IPPs                

   Iberafrica Diesel   350   294   245   74    10 

  Iberafrica II   355   276   230   69    9 

   Tsavo Power    283   311   348   130    13 

   Orpower 4  geothermal   392   437   437   428    387 

   Orpower 4  geothermal 2              ‐     74   336   428    387 

   Rabai MSD    

338   407   394   145    39 

   Athi River 1‐Triumph              ‐      ‐   145   145    36 

   Athi River 2‐Gulf              ‐      ‐   140   140    35 

   Thika MSD‐Melec              ‐     19   419   152    38 

   Mumias Bagasse   

100   96   96   80    91 

Turkana Wind              ‐      ‐    ‐    ‐    1,445 

Aeolus Wind‐Kinangop              ‐      ‐    ‐   102    53 Kwale International Sugar Company Ltd              ‐      ‐    ‐   24    24 

Prunus              ‐      ‐    ‐    ‐    44 

Kipeto              ‐      ‐    ‐    ‐    88 FiT projects(genpro,gura and hydel)              ‐                 ‐                 ‐                 ‐                 ‐   

Total IPPs   

1,819   1,914   2,792   1,918    2,699 

                 

IMPORT                

   UETCL   36   38   38   38    38 

   TANESCO    1.1   1   1   1    1 

   Ethiopia Imports    ‐    ‐    ‐    ‐     ‐ 

Total Import  38  39  39  39   39 

                 

  52

THE INTERCONNECTED SYSTEM   

   2011/12  2012/13  2013/14  2014/15  2015/16 Total Interconnected System  7,625  7,927  8,402  8,907   9,441 

                 

                 

KenGen Off‐Grid                

  Garissa   18.5   21.5   25.0   29.1    33.8 

   Lamu  6.6   7.3   8.0   8.8    9.7 

Total KenGen Off‐Grid  25  26  28  29   31 

                 

REF Off‐grid Diesels GWh                

Total REP Off‐Grid  23  24  26  27   29 PROJECTED INTERCONNECTED  ENERGY DEMAND  7,622   7,927   8,402   8,907    9,441 

TOTAL PROJECTED SALES  6,297   6,581   6,993   7,430    7,895 ACTUAL/PROJECTED TOTAL ENERGY DEMAND  7,670   7,977   8,455   8,963    9,500 Purchased Surplus/(Shortfall)    GWh               3 

  (0) 

  0                 0  

  0 

 Table 18: Transmission and Distribution Investment Plan 

Item 

Project Title 

Estimated  Cost EXPENDITURE INCIDENCE US$ Million 

KES$ Million 

2012/13 2013/14 2014/15  2015/16 2016/17

Distribution Projects & Equipments      

A  Distribution KPLC      

1  ESRP  Projects  4.45  360  180  180 

2 Electricity expansion (KEEP) Projects  210  16,991  3,398  5,097  5,097  3,398 

3  New Distribution projects  194.0  15,693  3,139  3,139  3,139  3,139  3,139 

4  LV Reinforcement  25  2,023  405  405  405  405  405 

5 Purchase of meters (Customer Service)  15  1,214  225  255  275  235  224 

6 Customer connectivity fund  16.7  1,351  101  417  416  417  0 

7 Supplies & Stores Facilities  10.2  825  63  290  311  161  0 

8  Re‐branding Commercial    6.5  526  86  150  145  145  0 

9 Office space & Facilities‐Admin.   37.5  3000  1000  1000  1000 

10  IT & T Projects  33.5  2,711  320  630  630  560  571 

11  Pre‐paid meters  150  12,000  4,000  4,000  4,000 

11 Specialized equipment and Motor Vehicles  30  2,427  450  500  500  500  477 

12 Other Equipment and Tools  6.7  542  102  110  110  110  110 

   Sub Total ‐Distribution KPLC  739.5  47664  5070  14473  16028  15769  8323 

  53

Item 

Project Title 

Estimated  Cost EXPENDITURE INCIDENCE US$ Million 

KES$ Million 

2012/13 2013/14 2014/15  2015/16 2016/17

Transmission  Projects  

B  Existing KPLC Transmission Projects 

1 Nairobi region additional TX 188.5MVA in 4 S/S  25.0  2,023  405  405  405  405  405 

2 220‐kV ring around Nairobi & associated S/S  74.0  5,987  1,197  1,197  1,197  1,197  1,197 

3  132/66 Sub stations  27.0  2,185  437  437  437  437  437 

4 Coast region additional TX 58MVA in 5 S/S  12.0  971  194  194  194  194  194 

Mt Kenya region additional TX 75MVA in 8 S/S  14.0  1,133  227  227  227  227  227 

West Kenya region additional TX 60MVA in 12 S/S  27.5  2,225  445  445  445  445  445 

7 Upgrade of existing lines and S/S (no 11)  20.0  1,618  324  324  324  324  324 

  Sub‐Total‐ KPLC transmission Proj  199.5  16,142  3,228  3,228  3,228  3,228  3,228 

C  KETRACO Trnasmission Projects Expected commissioning date 

1  Chemosit ‐ Kisii Line  14.1  1,137  1,137    

2  Kamburu ‐  Meru Line   18.3  1,482  1,482    

3  Rabai ‐ Galu Line  14.8  1,200  1,200    

4 Kilimambogo ‐ Thika – Gatundu‐Githambo   15.5  1,253 

1,253   

5  Thika – Kiganjo (Gatundu) 

4.0  322 

 322 

 

6 Githambo‐ Othaya‐Kiganjo  

7  Mumias‐Rang'ala   11.1  902  902   

8 Rabai‐Malindi‐Garsen ‐ Lamu   112.6  9,109 

9,109    

9 Kindaruma‐Mwingi ‐ Garissa   24.8  2,006 

  2,006

10  Kisii ‐ Awendo   10.4  840    840 

11  Eldoret‐Kitale   11.7  950   950 

12  Olkaria ‐ Lessos ‐ Kisumu 140.4 11,360 11,360   

13  Lessos‐Kabarnet   13.9  1,128    1,128

14  Nanyuki ‐ Nyahururu   13.9  1,128    1,128

15  Olkaria‐Narok   13.9  1,128    1,128

16  Ishiara‐Kieni  13.9  1,128   1,128

17 Mwingi‐Kitui‐Wote‐Sultan Hamud  13.9  1,128 

  1,128

18  Meru‐Isiolo‐Nanyuki   24.1 1,950   1,950

19  Kisii ‐ Sondu   24.6  1,990 

  1,990

20  Bomet‐Sotik   11.1  902    902 

21  Mombasa‐Nairobi  210.1  17,000  17,000   

22  Loyangalani‐Suswa  248.3 20,090 20,090   

23  Nairobi Ring  157.3  12,730    12,730

24  Isinya ‐ Suswa  88.4  7,156  7,156   

25 Ethiopia‐Kenya (Suswa) Interconnector  501.3  40,560 

  40,560

26 Kenya ‐ Tanzania Interconnector  44.5  3,600 

  3,600

27  Lessos‐ Tororo (Uganda)  57.3  4,640    4,640

28  Kindaruma – Athi River  69.2  5,600 

    5,600

  54

Item 

Project Title 

Estimated  Cost EXPENDITURE INCIDENCE US$ Million 

KES$ Million 

2012/13 2013/14 2014/15  2015/16 2016/17

29  Meru‐ Maua  21.0  1,700      1,700

30  Nyahururu ‐ Maralal  36.8  2,980      2,980

31 Awendo – Migori – Isabenia  23.5  1,900 

    1,900

32 Sondu – Homa Bay – Ndhiwa ‐ Awendo  29.7  2,400 

    2,400

33  Turkwel – Ortum  36.3  2,940      2,940

34 Sultan Hamud – Loiitokitok  41.5  3,360 

    3,360

35  Konza – Machakos  15.6  1,260     1,260

36 Konza – Kajiado – Namanga  41.8  3,380 

    3,380

37  Garsen ‐ Hola ‐ Garissa  49.7  4,020      4,020

38  Garissa ‐ Wajir  58.6  4,740      4,740

39  Galu ‐ Lunga Lunga  23.5  1,900      1,900

   Sub‐Total KETRACO   2,261.7  183,000  3,819  9,109  58,083  75,809  36,180 

  Table 19: Transmission & Distribution Lines, Circuit length in Kilometers  

VOLTAGE

AS AT 30th JUNE

2007 2008 2009 2010 2011 2012 220 kV 1,323 1,323 1,331 1,331 1,331 1,331 132 kV 2,085 2,085 2,112 2,211 2,343 2,343 66 kV 632 632 649 655 655 758 40 kV 29 29 29 0 0 0 33 kV 11,163 12,633 13,031 13,812 15,271 15,384 11 kV 21,918 23,573 24,334 25,485 26,250 27,219 TOTAL 37,149 40,274 41,486 43,494 45,850 47,035 % INCREASE P.A. 22.2% 8.4% 3.0% 4.8% 5.4% 2.6%

                  

  55

Table 20: Transformers in Service, Total Installed Capacity in MVA  

AS AT 30th JUNE 2007 2008 2009 2010 2011 2012 Generation Substations 11/220kV 472 472 544 544 544 544 11/132kV 675 675 694 694 889 889 11/66kV 146 183 121 121 171 171 11/33kV 280 280 238 238 238 238 11/40kV 5 5 0 0 0 0 3.3/11/40kV 10 10 0 0 0 0 3.3/40kV 4 4 0 0 0 0 3.3/33kV 4 4 4 4 4 4 TOTAL 1,596 1,633 1,601 1,601 1,846 1,846 Transmission Substations

132/220kV 620 620 620 620 620 620 220/132kV 730 730 730 730 730 730 220/66kV 360 360 360 360 450 450 132/66kV 375 375 375 375 375 375 132/33kV 629 652 687 756 779 801 TOTAL 2,714 2,737 2,772 2,841 2,954 2,976 Distribution Substations

66/11kV 1,058 1,114 1,206 1,206 1,206 1,288 66/33kV 77 77 77 90 90 90 40/11kV 11 11 11 11 11 11 33/11kV 729 750 823 934 937 1053 TOTAL 1,874 1,951 2,117 2,241 2,244 2,442Distribution Transformers 11/0.415kV and 33/0.415kV 3,515 4,138 4,307 4,688 5,069 5,784