The integrated master plan and integrated master schedule

108
The Integrated Master Plan And Integrated Master Schedule The Integrated Master Plan and Integrated Master Schedule are one of the six elements of a Credible Performance Measurement Baseline (PMB). The PMB is the source of data for the Program Manager. Some of this data is used in the Integrated Program Measurement Report (IPMR). Some is used in the assessment of the Program’s risk. Some define the deliverables and their Technical Performance Measures. 1 5 V8.5

description

The Integrated Master Plan (IMP) and Integrated Master Schedule( (IMS) provide a strategy for the incremental delivery of program outcomes through increasing maturity assessments with Measures of Effectiveness, Measures of Performance, Technical Performance Measures, and Key Performance Parameters. These assessment assure the needed capabilities of the project are met at each assessment point to confirm physical percent complete as planned in the Integrated Master Plan

Transcript of The integrated master plan and integrated master schedule

Page 1: The integrated master plan and integrated master schedule

The  Integrated  Master  Plan  And  Integrated  Master  Schedule  

The  Integrated  Master  Plan  and  Integrated  Master  Schedule  are  one  of  the  six  elements  of  a  Credible  Performance  Measurement  Baseline  (PMB).  The  PMB  is  the  source  of  data  for  the  Program  Manager.  Some  of  this  data  is  used  in  the  Integrated  Program  Measurement  Report  (IPMR).  Some  is  used  in  the  assessment  of  the  Program’s  risk.  Some  define  the  deliverables  and  their  Technical  Performance  Measures.    

1  

5

V8.5  

Page 2: The integrated master plan and integrated master schedule

The  IMP  tells  us  where  is  the  program  going?  

The  Plan  describes  where  we  are  going,  the  various  paths  we  can  take  to  reach  our  desLnaLon,  and  the  progress  or  performance  assessment  points  along  the  way  to  assure  we  are  on  the  right  path.  These  assessment  points  measures  the  “maturity”  of  the  product  or  service  against  the  planned  maturity.  This  is  the  only  real  measure  of  progress  –  not  the  passage  of  Lme  or  consumpLon  of  money.  

The  Integrated  Master  Plan  (IMP)  Is  A  Strategy  For  The  Successful  Comple=on  Of  The  Project  

2  

5.0  Start  with  the  IMP  

Page 3: The integrated master plan and integrated master schedule

3  

5.0  Start  with  the  IMP  

Page 4: The integrated master plan and integrated master schedule

Quick  View  to  IMP/IMS  

!  VerLcal  traceability  defines  the  increasing  maturity  of  key  deliverables  

!  Horizontal  traceability  defines  the  work  acLviLes  needed  to  produce  this  increasing  maturity  

!  Both  are  needed,  but  the  verLcal  traceability  is  the  starLng  point  

!  Program  Events,  Significant  Accomplishments,  and  Accomplishment  Criteria  must  be  defined  before  the  horizontal  work  acLviLes  can  be  idenLfied  

!  For  all  IMP  elements,  Key  Risks  must  be  idenLfied  and  assigned  from  Day  One,  even  without  miLgaLons  

4  

5.0  Start  with  the  IMP  

Page 5: The integrated master plan and integrated master schedule

The  IMP/IMS  is  Needed  on    Both  Sides  of  the  Contract  

!  Ver%cal  traceability  defines  the  increasing  maturity  of  the  program’s  deliverables  measures  in  EffecLveness  (MoE)  and  Performance  (MoP)  for  the  Government.  

!  Horizontal  traceability  defines  the  progress  to  plan  for  MoE’s  and  MoP’s  with  tangible  evidence  for  both  the  Government  and  the  Contractor.  

!  Ver%cal  traceability  provides  the  Government  with  insight  into  the  progress  of  the  MoE’s  and  MoP’s  and  Technical  Performance  Measures.  

!  Horizontal  traceability  provides  insight  into  Cost  and  Schedule  performance  for  the  Contractor,  reportable  through  the  IPMR  to  the  Government.  

5  

5.0  Start  with  the  IMP  

Page 6: The integrated master plan and integrated master schedule

MisconcepLons  of    the  IMP  /  IMS  

Why  we  don’t  need/want  an  IMP/IMS    !  Only  required  for  ACAT  I  programs  !  Too  big  and  burdensome  for  our  small  dollar  value  program  !  Contractor  spends  B&P  and  program  budget  generaLng  and  

maintaining  the  IMP,  without  measurable  benefit  !  Doesn’t  apply  on  a  services  contractors  !  Management  tool,  not  a  technical  tool  !  Doesn’t  apply  to  technology  programs  !  Doesn’t  apply  to  R&D  efforts  !  Doesn’t  apply  to  the  government  !  Help  me  get  a  waiver  so  I  don’t  have  to  use  an  IMP/IMS  

6  

5.0  Start  with  the  IMP  

Page 7: The integrated master plan and integrated master schedule

Aeributes  of  IMP  

!  Traceability  –  Expands  and  complies  with  the  SOO,  Performance  Requirements,  CWBS,  and  CSOW  

–  Based  on  the  customers  WBS  –  Is  the  basis  of  the  IMS,  cost  reports,  and  award  fees  

!  Implements  a  measurable  and  trackable  program  –  Accomplishes  integrated  product  development  –  Integrates  the  funcLonal  acLviLes  of  the  program  –  Incorporates  funcLonal,  lower  level  and  S/C  IMPs  

!  Provides  for  evaluaLon  of  Program  Maturity  –  Provides  insight  into  the  overall  effort  –  Level  of  detail  is  consistent  with  risk  and  complexity  per  §L  –  Decomposes  events  into  a  logical  series  of  accomplishments  –  Measurable  criteria  demonstrate  compleLon  /  quality  of  accomplishments  

7  

5.0  Start  with  the  IMP  

Page 8: The integrated master plan and integrated master schedule

Aeributes  of  the  IMS  

!  Integrated,  networked,  mulL-­‐layered  schedule  of  efforts  required  to  achieve  each  IMP  accomplishment  – Detailed  tasks  and  work  to  be  completed  –  Calendar  schedule  shows  work  compleLon  dates  – Network  schedule  shows  interrelaLonships  and  criLcal  path  

–  Expanded  granularity,  frequency,  and  depth  of  risk  areas  

!  Resource  loading  !  Correlates  IMS  work  with  IMP  events  

8  

5.0  Start  with  the  IMP  

Page 9: The integrated master plan and integrated master schedule

The  Importance  of  the  IMP  

!  The  IMP/IMS  is  the  single  most  important  document  to  a  program’s  success  –  It  clearly  demonstrates  the  providers  understanding  of  the  program  requirements  and  the  soundness  of  the  approach  a  represented  by  the  plan  

!  The  program  uses  the  IMP/IMS  to  provide:  –  Up  Front  Planning  and  commitment  from  all  parLcipants  –  A  balanced  design  discipline  with  risk  miLgaLon  acLviLes  –  Integrated  requirements  including  producLon  and  support  – Management  with  an  incremental  verificaLon  for  informed  program  decisions  

9  

5.0  Start  with  the  IMP  

Page 10: The integrated master plan and integrated master schedule

Just  A  Reminder,  before  moving  on  

10  

Page  47,  Defense  AcquisiLon  Guide,  January  10,  2012  

Page  317,  Defense  AcquisiLon  Guide,  January  10,  2012  

5.0  Start  with  the  IMP  

Page 11: The integrated master plan and integrated master schedule

Our  Goal  is  simple  …    

How  can  we  recognize  the  Reality  of  the  Program’s  current  status  and  its  future  performance?  

The  top  spins  conLnuous  while  in  a  dream  –  stops  spinning  in  the  real  world  –  Cobb’s  totem,  Incep=on  

11  

5.0  Start  with  the  IMP  

Page 12: The integrated master plan and integrated master schedule

12  

Page 13: The integrated master plan and integrated master schedule

Principles  of  Building  a  Credible  Integrated  Master  Plan  

Building  the  IMP  is  a  Systems  Engineering  ac<vity.  The  Integrated  Master  Plan  is  the  Program  Architecture  in  the  same  way  the  hardware  and  soBware  are  the  Product  Architecture.  Poor,  a  weak,  or  unstructured  Programma<c  Architecture  reduces  visibility  to  the  Product  Architecture’s  performance  measures  of  cost  and  schedule  connected  with  Technical  Performance  Measures.    

1  

6

V8.5  

Page 14: The integrated master plan and integrated master schedule

Quick  View  of  Building  the  IMP  

!  Start  with  each  Program  Event  and  define  the  Significant  Accomplishments  their  entry  and  exit  criteria  to  assess  the  needed  maturity  of  the  key  deliverables  

!  Arrange  the  Significant  Accomplishments  in  the  proper  dependency  order    

!  Segregate  these  Significant  Accomplishments  into  swim  lanes  for  IPTs  

!  Define  the  dependencies  between  each  SA  2  

6.0  Build  IMP  

Page 15: The integrated master plan and integrated master schedule

A  Cri<cal  Understanding  of  the  IMP  

3  

The  IMP  defines  the  connec<ons  between  the  Product  maturity  –  Ver<cal  –  and  the  implementa<on  of  this  Product  maturity  through  the  Func<onal  ac<vi<es  –  the  Horizontal    

6.0  Build  IMP  

Page 16: The integrated master plan and integrated master schedule

Benefits  of  this  Formality  

4  

Objec&ve   Implementa&on  Event  Driven  Plan  versus  Schedule  Driven  Plan  is  based  on  comple<on  of  tasks  not  passage  of  <me  

Separate  the  plan  (IMP)  from  the  schedule  (IMS)  but  link  elements  with  numbering  system  

Condensed,  easy  to  read  “Plan”  showing  the  “Events”  rather  than  the  work  effort   Indentured,  outline  format  –  not  text  

Pre-­‐defined  entry  and  exit  criteria  for  major  Program  Events  

Significant  Accomplishments  for  each  key  Program  Event  

Objec<ve  measures  of  progress  and  comple<on  for  each  Accomplishment  

Pre-­‐defined  Accomplishment  Criteria  (AC)  for  each  Significant  Accomplishment  (SA)  

Stable,  contracture  plan,  flexible  enough  to  portray  program  status  

IMP  part  of  the  contract,  IMS  is  a  data  item  

Capture  essence  of  the  func<onal  progress  without  manda<ng  a  par<cular  process  for  performing  the  work  

Split  IMP  into  Product  and  Process  

6.0  Build  IMP  

Page 17: The integrated master plan and integrated master schedule

Risk  Management  

Building  the  IMP  Starts  at  the  RFP  

5  

SOW  SOO  

ConOps  WBS   Techncial  and  Opera<onal  

Requirements  

CWBS  &  CWBS  Dic<onary  

Integrated  Master  Plan  (IMP)  

Integrated  Master  Schedule  (IMS)    

Earned  Value  Management  System  

Objec<ve  Status  and  Essen<al  Views  to  support  the  proac<ve  management  processes  needed  to  keep  the  program  GREEN  

Performance  Measurement  Baseline  

Measures  of  Effec<veness  

Measures  of  Performance  

Measures  of  Progress  

JROC    Key  Performance  Parameters  

Program    Specific  Key  Performance  Parameters  

Technical  Performance  Measures  

1.0  Introduc<on  

Page 18: The integrated master plan and integrated master schedule

The  IMP  /  IMS  Structure  

6  

IMS

IMP Describes how program capabilities will be delivered and how these capabilities will be recognized as ready for delivery

Supplemental Schedules

Work Packages and Tasks

Criteria

Accomplishment

Events or

Milestones

1  

6.0  Build  IMP  

Page 19: The integrated master plan and integrated master schedule

The  IMP/IMS  provides  Horizontal  and  Ver<cal  Traceability  of    progress  to  plan  

!  Ver<cal  traceability  AC  "  SA  "  PE  !  Horizontal  traceability  WP  "  WP  "  AC  

7  

Program Events Define the maturity of a Capability at a point in time.

Significant Accomplishments Represent requirements that enable Capabilities.

Accomplishment Criteria Exit Criteria for the Work Packages that fulfill Requirements.

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  package  

6.0  Build  IMP  

Page 20: The integrated master plan and integrated master schedule

The  IMP’s  role  during  Execu<on  

8  

Program Execution PMB for IBR Proposal Submittal DRFP & RFP

Performance Measurement Baseline

Tasks (T)

BOE

% Complete

Statement of Work

Program Deliverables

IMP

Accomplishments (A)

Criteria (C)

EVMS

Events (E)

Budget Spreads by CA & WP CAIV

Capabilities Based Requirements

X BCWS =

Probabilistic Risk Analysis

=

Time keeping and ODC =

Technical Performance Measure

BCWP

ACWP

Cost & Schedule Risk Model

BCWS

Decreasing technical and programmatic risk using Risk Management Methods

IMS

Physical % Complete

Continuity and consistency from DRFP through Program Execution

WBS

6.0  Build  IMP  

Page 21: The integrated master plan and integrated master schedule

1st,  Principle  –    IMP  Building  is  a  Full  Contact  Sport  

9  

6.0  Build  IMP  

Page 22: The integrated master plan and integrated master schedule

Our  First  Approach  to  the    IMP  /  IMS  Paradigm  

!  The  1st  approach  defines  Program  Events  (PE),  Significant  Accomplishments  (SA),  and  Accomplishment  Criteria  (AC),  derived  from  the  Work  Breakdown  Structure  or  the  SOW  

!  This  1st  approach  can  be  done  in  6  easy  steps  

10  

6.0  Build  IMP  

1.  Iden<fy  the  Program  Events  (PE)  (as  the  ACQ  Guide  tells  us)  

2.  Iden<fy  the  Significant  Accomplishments  (SA)  from  the  WBS  deliverables    

3.  Iden<fy  the  Accomplishment  Criteria  (AC)  needed  to  produce  these  deliverables  

4.  Iden<fy  the  Work  Packages  for  each  Accomplishment  Criteria  

5.  Sequence  the  Work  Packages  6.  Assemble  the  IMP/IMS  

Page 23: The integrated master plan and integrated master schedule

This  approach  doesn’t  give  us  visibility  into  what  “done”  looks  like  

!  We  must  measure  increasing  product  maturity  in  units  meaningful  to  the  decision  makers  

!  We  must  see  the  risks  before  they  arrive  so  we  can  take  correc<ve  ac<on  

11  

6.0  Build  IMP  

Page 24: The integrated master plan and integrated master schedule

First  Look  at  a  Significant  Accomplishment  (SA)  

!  SAs  are  interim  and  final  steps  to  define,  design,  develop,  verify,  produce,  and  deploy  the  product  or  system.    

!  SAs  must  occur  in  a  manner  that  ensures  a  logical  path  is  maintained  throughout  the  development  effort.    

!  SAs  are  event  related  and  not  just  <me  coincidental.    !  SAs  should  have  one  or  more  of  the  following  

characteris<cs:    –  Consists  of  a  discrete  step  in  the  process  of  planned  development  that  must  be  complete  prior  to  an  event  

–  Produces  a  desired  result  at  a  specified  event  that  indicates  a  level  of  design  maturity  (or  progress)  directly  related  to  each  product  and  process  

–  Defines  interrela<onships,  interdependencies,  or  “hand-­‐off”  points  of  different  func<onal  disciplines  applied  to  the  program    

12  

6.0  Build  IMP  

Page 25: The integrated master plan and integrated master schedule

First  look  at  an  Accomplishment  Criteria  (AC)  

!  ACs  are  defini<ve  measures  directly  suppor<ng  successful  comple<on  of  a  significant  accomplishment.    

!  ACs  show  objec<ve  evidence  of  work  progress  (maturity  of  a  product);  i.e.,  be  seen,  read,  demonstrated,  or  quan<fied.  These  results  are  usually  incorporated  into  a  report  or  document  as  evidence  of  accomplishment.    

!  ACs  are  prerequisites  for  comple<on  of  an  SA  (i.e.,  exit  criteria).    

!  The  ques<ons  that  need  to  be  repeatedly  asked  when  developing  ACs  are:  –  How  do  I  know  when  an  accomplishment  has  been  completed?  –  Is  the  criteria  directly  related  to  the  accomplishment?    –  Is  it  proof?    –  What  is  the  work  product?”  

13  

6.0  Build  IMP  

Page 26: The integrated master plan and integrated master schedule

The  IMP  speaks  to  Measures  of  Effec<veness  (MoE)  and  Measures  of  Performance  (MoP)  

14  

6.0  Build  IMP  

!  This  is  where  TPMs    are  connected  with  the  MoE’s  and  MoP’s  

!  For  each  deliverable  from  the  program,  all  the  “measures”  must  be  defined  in  units  meaningful  to  the  decision  makers.  

! Here’s  some  “real”  examples.  

1.  Provide  Precision  Approach  for  a  200  FT/0.5  NM  DH  

2.  Provide  bearing  and  range  to  AC  plaporm  

3.  Provide  AC  surveillance  to  GRND  plaporm    

Measures  of  Effec<veness  (MoE)  

1. Net  Ready  2. Guidance  Quality  3.  Land  Interoperability  4. Manpower  5. Availability  

JROC  Key  Performance  Parameters  (KPP)  

1. Net  Ready  !  IPv4/6  compliance  ! 1Gb  Ethernet  

2. Guidance  quality  ! Accuracy  threshold  p70  @  6M  

!   Integrity  threshold  4M  @  10-­‐6  /approach  

3.  Land  interoperability  ! Processing  capability  meets  LB  growth  matrix  

4. Manpower  ! MTBC  >1000  hrs  ! MCM  <  2  hrs  

5. Availability  ! Clear  threshold  >99%  !  Jam  threshold  >90%  

Measures  of  Performance  (MoP)  

1. Net  Ready  ! Standard  message  packets  

2. Guidance  Quality  ! Mul<path  alloca<on  budget  ! Mul<path  bias  protec<on  

3.  Land  Interoperability  ! MOSA  compliant  ! Civil  compliant  

4. Manpower  ! Opera<ng  elapsed  <me  meters  

! Standby  elapsed  <me  indicators  

5. Availability  ! Phase  center  varia<ons    

Technical  Performance  Measures  (TPM)  

Mission  Capabili<es  and  Opera<onal  Need  

Technical  Insight  –  Risk  adjusted  performance  to  plan    

Page 27: The integrated master plan and integrated master schedule

The  1st  Problem  with  the  Ini<al  IMP/IMS  Paradigm  

!  There  is  no  single  source  of  guidance  for  construc<ng  a  credible  IMP  and  IMS  – A  DOD  Guidebook,  but  s<ll  in  Version  0.9  – A  few  DOD  service  pamphlets  – A  commercial  guidebook  – Many  contractor  guidelines  

!  No  defini<ve  guidance  from  DoD  on  what  makes  a  good  IMP  

!  No  defini<ve  DID  requiring  an  IMP  on  specific  programs  

15  

6.0  Build  IMP  

Page 28: The integrated master plan and integrated master schedule

The  IMP  is  a  good  start,  but  we’re  really  aBer  the  IMP  Narra<ves  

!  The  IMP  Narra<ves  start  with  the  Statement  of  Objec<ves  (SOO)  or  Concept  of  Opera<ons  (ConOps)  – These  iden<fy  the  top  level  program  objec<ves  – They  define  the  big  picture  and  provide  pre-­‐award  trade  space  

– They  provide  the  framework  for  the  Contractor  to  develop  the  proposal  through  the  IMP  

! With  the  Government’s  Execu<ve  summary,  provides  the  contractor  an  understanding  of  what  is  needed  and  what  is  important  

16  

6.0  Build  IMP  

Page 29: The integrated master plan and integrated master schedule

The  IMP  Process  Narra<ve  

The  IMP  Process  Narra<ve  describes  how  the  technical  and  business  elements  of  the  program  will  be  conducted,  monitored,  and  controlled.    Narra<ves  provide  the  customer  visibility  into  the  contractor’s  key  func<onal  processes  and  procedures,  the  rela<onship  of  these  processes  and  procedures,  and  an  overview  of  the  effort  required  to  implement  them.  

17  

6.0  Build  IMP  

Page 30: The integrated master plan and integrated master schedule

IMP  Narra<ve  for  PDR  Program  Event   Event  Descrip&on   PE  Maturity  Assessment  

shown  in  SAs  

PDR   PDR  establishes  the  “design-­‐  to”  allocated  baseline  to  the  subsystem  level,  assures  this  design  meets  the  func<onal  baseline,  assures  system  requirements  have  been  properly  allocated  to  the  proper  subsystem.  PDR  establishes  the  feasibility  of  the  design  approach  to  meet  the  technical  requirements  and  provide  acceptable  interface  rela<onships  between  the  hardware  and  other  interfacing  items.    Any  changes  to  the  requirements  that  have  occurred  since  the  System  Requirements  Review  (SRR2)  will  be  verified  at  the  PDR.    PDR  assures  the  design  is  verifiable,  does  not  pose  major  IMS  or  Cost  risk,  and  is  mature  enough  to  advance  to  the  detailed  design  phase  –  CDR  

!  Subsystem  level  opera<onal  concepts  defined  

!  System  level  interfaces  baselined  

!  Supportability  plans  established  

!  SoBware  requirements  finalized  

!  Subsystem  requirements  finalized  &  allocated  

!  System  verifica<on,  valida<on  &  cer<fica<on  plans  updated  

!  PDR  subsystem  design  completed  

18  

6.0  Build  IMP  

Page 31: The integrated master plan and integrated master schedule

What  the  IMP  Narra<ve  Tells  Us?  

!  States  the  objec<ve  of  the  processes  used  to  build  the  products  

!  Provides  the  governing  documents,  compliance,  and  reference  for  the  process  ac<vi<es  

!  Explains  the  process  approach  –  Portrays  the  key  ac<vi<es  of  the  approach  –  Illustrates  the  processes  tailored  for  the  specific  program  

19  

Inputs  

Ac<vity  3  

Ac<vity  5  

Ac<vity  4  

Tools  

Ac<vity  1  

Ac<vity  2  

Outputs  

Metrics  

6.0  Build  IMP  

Page 32: The integrated master plan and integrated master schedule

Some  Guidance    

20  

6.0  Build  IMP  

Page 33: The integrated master plan and integrated master schedule

The  Defense  Acquisi<on  Guide  (DAG)  Tells  Us  About  the  IMP  

21  

6.0  Build  IMP  

Page 34: The integrated master plan and integrated master schedule

The  DAG  Also  Tells  Us  

22  

6.0  Build  IMP  

Page 35: The integrated master plan and integrated master schedule

5000.01  Part  2.B.3  Acquisi<on  Strategies,  Exit  Criteria,  and  Risk  Management  

“Event  driven  acquisi<on  strategies  and  program  plans  must  be  based  on  rigorous,  objec<ve  assessments  of  a  program’s  status  and  the  plans  for  managing  risk  during  the  next  phase  and  the  remainder  of  the  program.    The  acquisi<on  strategy  and  associated  contrac<ng  ac<vi<es  must  explicitly  link  milestone  decision  reviews  to  events  and  demonstrated  accomplishments  in  development,  tes<ng,  and  ini<al  produc<on.    The  acquisi<on  strategy  must  reflect  the  interrela<onships  and  schedule  of  acquisi<on  phases  and  events  based  on  logical  sequence  of  demonstrated  accomplishments  not  on  fiscal  or  calendar  expediency.”  

23  

6.0  Build  IMP  

Page 36: The integrated master plan and integrated master schedule

What  makes  a  good    Program  Event  (PE)?  

!  Events  are  the  conclusion  of  an  interval  of  major  program  accomplishments  (SA)  with  their  criteria  (AC)    

!  IMP  events  represent  key  decision  transi<on  points  between  major  ac<vi<es  distributed  over  the  contract  period  –  The  IMP  is  a  Mini  Authoriza;on’s  to  Proceed  (ATP)  to  the  next  Program  Event  (PE)  

!  Some  guidance  for  establishing  program/product  events:  –  Customer  Given  Events.    –  Key  Decisions  Needed  –  Risk  Mi<ga<on  Event  –  DOD  Systems  Engineering  Technology  Review  (SETR)  Guidance  

24  

6.0  Build  IMP  

Page 37: The integrated master plan and integrated master schedule

What  makes  a  good  Significant  Accomplishment  (SA)?  

!  IPT  can  manage  it  at  a  working  level  !  Shows  comple<on  and  result  s  of  discrete  steps  in  the  

development  process  !  Indicates  maturity  of  the  product  through  MoEs  and  MoPs  !  Its  “significance”  measures  program  event  status  !  Relevant  and  logically  linked  to  the  proper  PE  

–  Just  because  the  work  occurs  during  the  <me-­‐frame  for  PE  A  doesn’t  mean  it’s  logically  linked  to  PE  A  

!  Uses  consistent  language,  style,  format  through  verb  dic<onary,  for  example:  –  Segment  build  4  detailed  design  completed  –  Analysis  of  structural  integrity  completed  –  Structural  integrity  verified  

25  

6.0  Build  IMP  

Page 38: The integrated master plan and integrated master schedule

IMP  Significant  Accomplishments  

!  SAs  are  NOT  just  a  list  of  “things”  to  do  before  the  Program  Event  (PE)  

!  They  are  sequenced  accomplishments,  each  of  which  leads  to  the  PE,  e.g.  Cri<cal  Design  Review  (CDR)  –  SA  #  1  =  CDR  mee<ng  conducted  –  SA  #  2  =  CDR  ac<on  item  work-­‐off  plan  established  –  SA  #  3  =  85%  drawings  completed  –  SA  #  4  =  CDR  CDRLs  delivered  –  SA  #  5  =  Development  environment  opera<onal  –  SA  #  6  =  Cri<cal  methods  analyses  completed  –  SA  #  7  =  RVTM  approved  

26  

6.0  Build  IMP  

Page 39: The integrated master plan and integrated master schedule

What  makes  a  good  Accomplishment  Criteria  (AC)?  

!  Provides  objec<ve,  measureable  and,  explicit  proof  of  comple<on  and  closure  of  the  work  ac<vi<es  

!  Defines  condi<ons  for  closing  the  Significant  Accomplishment  (SA)  

!  Answers  the  ques<on  how  do  we  know  when  a  Significant  Accomplishment  has  been  completed?  

27  

6.0  Build  IMP  

Page 40: The integrated master plan and integrated master schedule

!  Not  Significant  –  Too  small  to  significantly  contribute  to  successful  event  comple<on  –  Would  lead  to  trivial  tasks  (e.g.,  1  day  dura<on)  

!  Ambiguous  –  Read  can’t  tell  what  Done  looks  like  

!  Wrong  verb  –  Uses  a  verb  that’s  not  on  the  list  (Dic<onary)  –  Uses  a  listed  verb  incorrectly  –  Doesn’t  have  a  verb  at  all  

!  Not  measurable  –  Can’t  tell  when  we’re  done  

!  Too  Many  SAs  or  ACs  –  Confuses  the  reader  and  confuses  the  execu<on  process  of  the  

program  –  Dilutes  the  MoE  and  MoP  –  Reduces  visibility  into  increasing  maturity  

28  

What  makes  a  Not  So  Good    SA  or  AC?  

6.0  Build  IMP  

Page 41: The integrated master plan and integrated master schedule

!  Program  Event  (PE)  – A  PE  assess  the  readiness  or  comple<on  as  a  measure  of  progress  

–  First  Flight  Complete  !  Significant  Accomplishment  (SA)  

–  The  desired  result(s)  prior  to  or  at  comple<on  of  an  event  demonstrate  the  level  of  the  program’s  progress  

–  Flight  Test  Readiness  Review  Complete  !  Accomplishment  Criteria  (AC)  

– Defini<ve  evidence  (measures  or  indicators)  that  verify  a  specific  accomplishment  has  been  completed  

–  SEEK  EAGLE  Flight  Clearance  Obtained  29  

F-­‐22  Example  6.0  Build  IMP  

Page 42: The integrated master plan and integrated master schedule

!  PE’s  are  easy,  they  are  in  the  SETR  and  Integrated  Logis<cs  Lifecycle  Management  System  

!  The  SA’s  can  be  defined  from  the  program’s  deliverables  –  these  may  not  be  obvious  but  can  be  discovered  with  a  Product  Development  Kaizen  process  (more  later)  

!  It’s  the  AC’s  that  are  hard  part  –  the  ACs  must  represent  the  exit  criteria  for  the  series  of  Work  Packages  that  do  the  work  to  produce  the  product  

30  

Now  the  Hard  Part  6.0  Build  IMP  

Page 43: The integrated master plan and integrated master schedule

6  Steps  to  IMP  Development  

Let’s  start  to  build  the  IMP.    This  step-­‐by-­‐step  process  needs  to  be  followed  carefully.  The  IMP  is  constructed  one  Program  Event  at  a  Cme  –  LeE  to  Right  in  Cme.    To  do  otherwise  allows  confusion  and  disconnecCon  between  Program  Events  to  occur  and  dilutes  our  focus  on  defining  what  Done  looks  like  for  each  Program  Event.      

1  

7

V8.5  

Page 44: The integrated master plan and integrated master schedule

2  

7.0  6  Steps  

Page 45: The integrated master plan and integrated master schedule

Quick  View  of  Step-­‐By-­‐Step  IMP  

IdenCfy  Program  Events  IdenCfy  Significant  Accomplishments  IdenCfy  Accomplishment  Criteria  IdenCfy  Work  Packages  needed  to  complete  the  Accomplishment  Criteria  Sequence  the  Work  Packages  (WP),  Planning  Packages  (PP),  Summary  Level  Planning  Packages  (SLPP)    in  a  logical  network.  Adjust  the  sequence  of  WPs,  PPs,  &  SLPPs  to  miCgate  major  risks.  

3  

7.0  6  Steps  

1

2

3

4

5

6

Page 46: The integrated master plan and integrated master schedule

IdenCfy  the  Program  Events  

Actors   Processes   Outcomes  

Systems  Engineer  

Define  the  process  flow  for  product  producCon  from  contract  award  to  end  of  contract  

!  Confirm  Program  Events  represent  the  logical  process  flow  for  program  maturity  

Program  Manager  Confirm  customer  is  willing  to  accept  the  process  flows  developed  by  the  IMP  

!  Engage  with  contracts  and  customer  for  PE  definiCon  

Project  Engineer  IdenCfy  interdependencies  between  program  event  work  streams  

!  IdenCfy  Value  Stream  components  at  the  PE  level  before  flowing  them  down  to  the  SA  level  

IMP/IMS  Architect  Capture  Program  Event  contents  for  each  IPT  or  work  stream  

!  Establish  foundaCon  for  a  structure  to  support  the  descripCon  of  the  increasing  mature  as  well  as  the  flow  to  needed  work.  

Copyright  ©  2012,  Glen  B.  Alleman,  Niwot  Ridge,  LLC   4  

1

7.0  6  Steps  

Page 47: The integrated master plan and integrated master schedule

Outcomes  of  Step  

!  Confirm  the  end  to  end  descripCon  of  the  increasing  maturity  of  the  program’s  deliverables  

!  Establish  of  RFP  or  Contract  target  dates  for  each  Event.    

!  Socialize  the  language  of  speaking  in  “Events”  rather  than  Cme  and  efforts  

5  

1

7.0  6  Steps  

Page 48: The integrated master plan and integrated master schedule

Events  Define  the  Assessment    of  the  Program’s  Maturity  

6  

! Program  Events  are  maturity  assessment  points  in  the  program  

! They  define  what  levels  of  maturity  for  the  products  and  services  are  needed  before  proceeding  to  the  next  maturity  assessment  point  

! The  entry  criteria  for  each  Event  defines  the  units  of  measure  for  the  successful  compleCon  of  the  Event  

! The  example  below  is  typical  of  the  purpose  of  a  Program  Event  

The  Cri+cal  Design  Review  (CDR)  is  a  mul+-­‐disciplined  product  and  process  assessment  to  ensure  that  the  system  under  review  can  proceed  into  system  fabrica+on,  demonstra+on,  and  test,  and  can  meet  the  stated  performance  requirements  within  cost  (program  budget),  schedule  (program  schedule),  risk,  and  other  system  constraints.    

1

7.0  6  Steps  

Page 49: The integrated master plan and integrated master schedule

IdenCfy  the  Significant  Accomplishments  (SA)  for  Each  Program  Event  (PE)  

7  

Actors   Processes   Outcomes  

System  Engineer   IdenCfy  Integrated  Product  Teams  (IPT)  responsible  for  the  SA’s    

! Define  the  boundaries  of  these  programmaCc  interfaces  

! Define  technical  and  process  risk  categories  and  their  bounds  

Technical  Lead  Confirm  the  sequence  of  SA’s  has  the  proper  dependency  relaConships  

! Define  the  product  development  flow  process  improves  maturity  

! Define  technical  risk  drivers  

Project  Engineer   Confirm  logic  of  SA’s  for  project  sequence  integrity  

! Define  the  program  flows  improves  maturity    

Control  Account  Manager  

Validate  SA  outcomes  in  support  of  PE  entry  condiCons  

!  Confirm  budget  and  resources  adequate  for  defined  work  effort  

IMP/IMS  Architect  

Assure  the  assessment  points  provide  a  logical  flow  of  maturity  at  the  proper  intervals  for  the  program  

! Maintain  the  integrity  of  the  IMP,  WBS,  and  IMS  

2

7.0  6  Steps  

Page 50: The integrated master plan and integrated master schedule

Outcomes  of  Step  

!  The  Significant  Accomplishments  are  the  “road  map”  to  the  increasing  maturity  of  the  program  

!  The  “Value  Stream  Map”  resulCng  from  the  flow  of  SA’s  describes  how  the  products  or  services  move  through  the  maturaCon  process  while  reducing  risk  

!  The  SA  map  is  the  path  to  “done”    

8  

2

7.0  6  Steps  

Page 51: The integrated master plan and integrated master schedule

SAs  define  the  entry  criteria  for  each  Program  Event  

9  Preliminary  Design  Review  Complete  

3

7.0  6  Steps  

Page 52: The integrated master plan and integrated master schedule

IdenCfy  Accomplishment  Criteria  (AC)  for  each  Significant  Accomplishment  (SA)  

Actors   Processes   Outcomes  

CAM  

Define  and  sequence  the  contents  of  each  Work  Package  and  select  the  EV  criteria  for  each  Task  needed  to  roll  up  the  BCWP  measurement  

!  Establish  ownership  for  the  content  of  each  Work  Package  and  the  Exit  Criteria  –  the  Accomplishment  Criteria  (AC)  

Project  Engineer  

IdenCfy  the  logical  process  flow  of  the  Work  Package  to  assure  the  least  effort,  maximum  value  and  lowest  risk  path  to  the  Program  Event  

!  Establish  ownership  for  the  process  flow  of  the  product  or  service  

Technical  Lead   Assure  all  technical  processes  are  covered  in  each  Work  Package  

!  Establish  ownership  for  the  technical  outcome  of  each  Work  Package  

IMP/IMS  Architect  

Confirm  the  process  flow  of  the  ACs  can  follow  the  DID  81650  structuring  and  Risk  Assessment  processes  

! Guide  the  development  of  outcomes  for  each  Work  Package  to  assure  increasing  maturity  of  the  program   10  

3

7.0  6  Steps  

Page 53: The integrated master plan and integrated master schedule

Outcomes  of  Step  

!  The  definiCon  of  “done”  emerges  in  the  form  of  deliverables  rather  than  measures  of  cost  and  passage  of  Cme.  

!  At  each  Program  Event,  the  increasing  maturity  of  the  deliverables  is  defined  through  the  Measures  of  EffecCveness  (MoE)  and  Measures  of  Performance  (MoP)  

11  

3

7.0  6  Steps  

Page 54: The integrated master plan and integrated master schedule

ACs  are  higher  fidelity  descripCons  of  “Done”  than  SAs  

12  Cri9cal  Design  Review  Complete  

4

7.0  6  Steps  

Page 55: The integrated master plan and integrated master schedule

IdenCfy  the  Work  for  Each  Accomplishment  Criteria  in  Work  Packages  

Actors   Processes   Outcomes  

Control  Account  Manager  

IdenCfy  or  confirm  the  work  acCviCes  in  the  Work  Package  represent  the  allocated  work  

! Define  bounded  work  effort  defined  “inside”  each  Work  Package  

Technical  Lead   Confirm  this  work  covers  the  SOW  and  CDRLs  

! Define  all  work  effort  for  100%  compleCon  of  deliverable  visible  in  a  single  locaCon  –  the  Work  Package  

!  Confirm  risk  drivers  and  duraCon  variances  

IMP/IMS  Architect   Assist  in  the  sequencing  the  work  efforts  in  a  logical  manner  

! Develop  foundaCon  of  the  maturity  flow  starCng  to  emerge  from  the  contents  of  the  Work  Packages  

Earned  Value  Analyst  

Assign  iniCal  BCWS  from  BOE  to  Work  Package  

!  ConfirmaCon  of  work  effort  against  BOEs  

! Define  EVT  for  measures  progress  to  plan   13  

4

7.0  6  Steps  

Page 56: The integrated master plan and integrated master schedule

Outcomes  of  Step  

!  The  work  idenCfied  that  produces  a  measurable  outcome.  

!  This  work  defined  in  each  Work  Package  !  The  Accomplishment  Criteria  (AC)  state  explicitly  what  “done”  looks  like  for  this  effort  

! With  “done”  stated,  measures  of  Performance  and  measures  of  EffecCveness  can  be  defined  

14  

4

7.0  6  Steps  

Page 57: The integrated master plan and integrated master schedule

Work  is  done  in  “packages”  that  produce  measureable  outcomes  

15  Launch  Readiness  Review  Complete  

5

7.0  6  Steps  

Page 58: The integrated master plan and integrated master schedule

Sequence  Work  Packages  (ACs)  for  each  Significant  Accomplishment  (SA)  

16  

Actors   Processes   Outcomes  

Control  Account  Manager  

Define  the  order  of  the  Work  Packages  needed  to  meet  the  Significant  Accomplishments  for  each  Program  Event  

! Define  the  process  flow  of  work  and  the  resulCng  accomplishments.  

! Assure  value  is  being  produced  at  each  SA  and  the  AC’s  that  drive  them  

IMP/IMS  Architect  

Assure  that  the  sequence  of  Work  Packages  adheres  to  the  guidance  provided  by  DCMA  and  the  EVMS  System  descripCon  

!  Begin  the  structuring  of  the  IMS  for  compliance  and  loading  into  the  cost  system  

Program  Controls  Staff  

Baseline  the  sequence  of  Work  Packages  using  Earned  Value  Techniques  (EVT)  with  measures  of  Physical  Percent  Complete  

! Develop  insight  to  progress  to  plan  with  measures  of  physical  progress  for  each  Work  Packages  (EVT)  

5

7.0  6  Steps  

Page 59: The integrated master plan and integrated master schedule

Outcomes  of  Step  

! Work  Packages  parCCon  work  efforts  into  “bounded”  scope  

!  Interdependencies  constrained  to  Work  Package  boundaries  prevents  “spaghek  code”  style  schedule  flow  

!  Visibility  of  the  Increasing  Flow  of  Maturity  starCng  to  emerge  from  the  flow  of  Accomplishment  Criteria  (AC)  

17  

5

7.0  6  Steps  

Page 60: The integrated master plan and integrated master schedule

Sequence  Work  Packages  (AC’s)  into  an  IMS  for  each  Program  Event  

18  

6

7.0  6  Steps  

Page 61: The integrated master plan and integrated master schedule

Assemble  Final  IMP/IMS  Actors   Processes   Outcomes  

IMP/IMS  Architect  

StarCng  with  the  AC’s  under  each  SA’s  connect  Work  Packages  in  the  proper  order  for  each  Program  Event  

!  Establish  the  Performance  Measurement  Baseline  framework.  

!  IdenCfy  MoE  and  MoP  points  in  the  IMP  

Program  Manager  Confirm  the  work  efforts  represent  the  commiled  acCviCes  for  the  contract  

!  Review  and  approval  of  the  IMS  –  ready  for  baseline.  

!  Review  and  approve  risk  drivers  and  duraCon  variance  models  

Project  Engineer   Assess  the  product  development  flow  for  opCmizaCons  

!  Review  and  approval  of  the  IMS  –  ready  for  baseline.  

!  IdenCfy  risk  drivers  and  their  miCgaCons  

Systems  Engineer  Confirm  the  work  process  flows  result  in  the  proper  products  being  built  in  the  right  order  

!  Confirm  risk  drivers  and  duraCon  variances.  

!  Review  and  approval  of  the  IMS  –  ready  for  baseline   19  

6

7.0  6  Steps  

Page 62: The integrated master plan and integrated master schedule

Outcomes  of  Step  

!  Both  the  maturity  assessment  criteria  and  the  work  needed  to  reach  that  level  of  maturity  are  described  in  a  single  locaCon  

!  Risks  are  integrated  with  the  IMP  and  IMS  at  their  appropriate  levels  –  Risks  to  EffecCveness  –  risk  to  JROC  KPPs  –  Risks  to  Performance  –  risk  to  program  KPPs  and  TPMs  

!  Leading  and  Lagging  indicator  data  provide  through  each  measure  to  forecast  future  performance  

  20  

6

7.0  6  Steps  

Page 63: The integrated master plan and integrated master schedule

The  Previous  6  Steps  Result  In  A  Credible  IMP/IMS  

21  

!  The  IMP  is  the  “Outer  Mold  Line”,  the  Framework,  the  “Going  Forward”  Strategy  for  the  Program.  

!  The  IMP  describes  the  path  to  increasing  maturity  and  the  Events  measuring  that  maturity.  

!  The  IMP  tells  us  “How”  the  program  will  flow  with  the  least  risk,  the  maximum  value,  and  the  clearest  visibility  to  progress.  

!  The  IMS  tells  us  what  work  is  needed  to  produce  the  product  or  service  at  the  Work  Package  level.  

Our  Plan  Tells  Us  “How”  We  are  Going  to  Proceed  The  Schedule  Tells  Us  

“What”  Work  is  Needed  to  Proceed  

7.0  6  Steps  

Page 64: The integrated master plan and integrated master schedule

Significant  Accomplishments  for  an  actual  Program  Event  Flight  Test  Ascent  Aerodynamics  Confirmed  

22  

7.0  6  Steps  

Page 65: The integrated master plan and integrated master schedule

Horizontal  and  VerCcal  Traceability  of  the  IMP/IMS  

Integrated  Master  Schedule  Work  sequenced  to  produce  outcomes  

for  each  WP.  

!  VerCcal  traceability  AC  "  SA  "  PE  !  Horizontal  traceability  WP  "  WP  "AC  

Program Events Define the maturity of a Capability at a point in time.

Significant Accomplishments Represent requirements that enable Capabilities.

Accomplishment Criteria Exit Criteria for the Work Packages that fulfill Requirements.

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  Package  

Work  package  

Work  Package  

Work  Package  

23  

7.0  6  Steps  

Page 66: The integrated master plan and integrated master schedule

The  IMP’s  connecCon  to  the  WBS  !  Start  with  the  Significant  Accomplishments  and  sequence  

them  to  the  maturity  flow  for  each  Program  Event  !  The  WBS  connecCons  then  become  orthogonal  to  this  flow  

24  

7.0  6  Steps  

Program  Event  

SRR   SDR   PDR   CDR   TRR   ATLO  Work  Breakdown  Structure  

4.920-­‐SDAI   A01,  A02   B01   C01,  C02   D01   E01   F01  

4.200-­‐Sys  Test   A05   B03,  B04   D02,  D03   E02   F02  

4.300-­‐Radar   A03   B02   C03   E03  

4.330-­‐O&C  Sys   A06,  A07   B05   C04   D04   E04   F03,  F04  

4.400-­‐  I&T   A08   C05   E05,  E06   F05  

4.500-­‐Support   A09   D05   E07   F06,  F07  

Page 67: The integrated master plan and integrated master schedule

25  

7.0  6  Steps  

Page 68: The integrated master plan and integrated master schedule

26  

7.0  6  Steps  

Page 69: The integrated master plan and integrated master schedule

27  

7.0  6  Steps  

Page 70: The integrated master plan and integrated master schedule

28  

7.0  6  Steps  

Page 71: The integrated master plan and integrated master schedule

29  

7.0  6  Steps  

Page 72: The integrated master plan and integrated master schedule

30  

7.0  6  Steps  

Page 73: The integrated master plan and integrated master schedule

Nuances  Of  These  6  Steps  

Building  the  Program  Event,  to  Significant  Accomplishment,  to  Accomplishment  decomposi?on  is  straight  forward.  For  each  Program  Event,  simply  iden?fy  what  are  the  needed  Significant  Accomplishment  for  the  entry  and  exit  criteria,  and  the  Accomplishment  Criteria  for  the  Work  Packages  that  produce  the  AC.  

Yea  Right,  no  problem  

1  

8

V8.5  

Page 74: The integrated master plan and integrated master schedule

2  

8.0  Nuances  

Page 75: The integrated master plan and integrated master schedule

Quick  View  of  the  Nuances  

!  Unfortunately  building  a  credible  IMP/IMS  is  a  nuanced  process,  subject  to  many  opportuni?es  for  diversions,  blind  alleys,  and  false  starts    

!  It  is  slightly  counter  intui?ve  from  the  tradi?onal  scheduling  approach  to  start  with  the  ver?cal  integra?on  –  but  it  is  cri?cal  to  start  ver?cally  

!  Success  requires  the  full  par?cipa?on  of  Systems  Engineering,  CAMs,  and  the  Program  Manager  

!  Success  requires  everyone  to  understand  the  nuances  of  the  IMP  building  efforts  

3  

8.0  Nuances  

Page 76: The integrated master plan and integrated master schedule

The  1st  Nuance  We  need  to  change  the  Planning  Paradigm  

Beginner     Intermediate   Advanced  

! Take  the  program  events  and  use  the  WBS  to  define  the  SAs  and  ACs.  

!  Iden?fy  the  tasks  to  produce  the  ACs  and  SAs  

! Collect  them  into  Program  Events  

! Organize  the  tasks  by  Work  Package  

! Sequence  the  work  packages  (AC’s)    

! Examine  the  exit  criteria  for  the  Program  Events  –  what  does  Done  look  like?  

! Ask  what  the  entry  criteria  are  for  each  Program  Event  

! Build  the  AC’s  to  support  these  entry  criteria  

! Pull  these  together  under  each  SA  

! Determine  the  Technical  and  Programma?c  maturity  for  each  Program  Event  from  the  Concept  of  Opera?ons  

! Assess  the  SA’s  for  each  Integrated  Product  Team  in  terms  of  their  streams  maturity  at  that  point  in  the  program  

! Sequence  the  SA’s  for  each  PE  and  assess  the  units  of  measure  of  “maturity”  

! Build  the  AC’s  to  support  each  SA’s  level  of  maturity  

Copyright  ©  2012,  Glen  B.  Alleman,  Niwot  Ridge,  LLC   4  

8.0  Nuances  

Page 77: The integrated master plan and integrated master schedule

The  2nd  Nuance  We  need  to  speak  about  Increasing  Maturity  

Beginner   Intermediate   Advanced  

! The  sequence  of  work  closely  matches  the  horizontal  schedules  of  the  past  

! Align  this  work  with  the  WBS  elements  

! Focus  on  the  WBS  Dic?onary  of  the  delivered  products  or  services  

! No  explicit  TPM,  MOE,  and  MOP  elements  

 

! The  sequence  of  work  is  related  to  the  Program  Events,  but  essen?ally  “hangs”  from  the  PE  to  the  SA’s  and  then  the  AC’s  

! All  deliverables  are  visible  but  their  TPMs  and  other  system  measures  are  not  stated  in  the  IMP  or  its  narra?ve.  

! There  is  a  narra?ve  in  the  form  of  SA’s  and  AC’s  that  describes  how  the  program  moves  from  lef  to  right  alone  its  maturity  path  

! Risk  buy  down  and  re?rement  are  visible  

!  Intermediate  Technical  Performance  Measures,  Measures  of  Effec?veness,  and  Measures  of  Performance  are  visible  in  the  IMP  

Copyright  ©  2012,  Glen  B.  Alleman,  Niwot  Ridge,  LLC   5  

8.0  Nuances  

Page 78: The integrated master plan and integrated master schedule

The  3rd  Nuance  Everything  Foot  and  Ties  to  the  IMP  &  IMS  

Beginner   Intermediate   Advanced  

! The  IMS  contains  all  the  proper  fields  in  columns  and  is  horizontally  linked  

! The  WBS  elements  can  be  found  for  all  work  elements  

! CDRL’s  are  visible  and  their  mul?ple  delivery  dates  connected  to  each  Program  Event  

! WBS  is  structured  in  a  product  manner  or  possibly  a  func?onal  manner  with  some  deliverables  defined  in  the  terminal  nodes  

! The  WBS  is  properly  formed  inside  each  AC  with  incremental  deliverables  

! WBS  numbers  form  a  “well  structured”  tree,  but  s?ll  is  not  “pure”  in  the  sense  of  deliverables  only,  no  func?onal  

! Each  column  and  each  field  can  be  “pivoted”  to  form  a  proper  “tree”  of  value  flow.  

! The  WBS  is  a  “pure”  Product  Breakdown  Structure  (PBS)  and  the  services  needed  to  produce  those  products  

! The  WBS  defines  the  structure  of  the  delivered  product  or  service  

! The  Ver?cal  trace  of  the  IPM  describes  the  flow  of  increasing  maturity  of  these  products  or  services  

! The  Horizontal  trace  of  the  IMP  describes  to  work  to  be  done  to  produce  this  maturity   6  

8.0  Nuances  

Page 79: The integrated master plan and integrated master schedule

The  4th  Nuance  IMP/IMS  is  Programma?c  Architecture  

Beginner   Intermediate   Advanced  

! The  IMP  is  built  from  the  WBS  for  each  Program  Event.  

! The  IMP  is  seen  as  a  compliance  document  that  lists  the  Program  Events  and  a  “bunch  of  stuff”  underneath.    

! The  IMP  is  structured  around  separate  Program  Events,  but  below  the  SA’s  looks  like  a  “shop  floor”  schedule  with  lijle  ver?cal  connec?vity.  

! The  IMP  is  built  as  a  “value  stream”  flow  for  the  program  but  the  Systems  Engineers  

! This  programma?c  architecture  is  built  in  the  same  way  the  technical  system  architecture  is  built  

!  It  is  derived  from  the  ConOps  and  Tier  1  System  Requirements  

! The  IMP  shows  explicitly  how  these  are  supported  in  the  flow  of  the  SA’s  

7  

8.0  Nuances  

Page 80: The integrated master plan and integrated master schedule

The  5th  Nuance  The  IMP/IMS  connects  all  the  dots  

8  

8.0  Nuances  

Measure  of  Effec?veness  

Measure  of  Performance  

Technical  Performance  Measure  

Risk  

Aleatory  Uncertainty  

Epistemic  Uncertainty  

Reference  Classes  

Past  Performance  

SME  

Past  Performance  

System  Architecture  

AHP  

Page 81: The integrated master plan and integrated master schedule

Connec&ng  The  IMP  To  Program  Performance  Measures  

Assembling  the  IMS  from  the  IMP  appears  to  be  a  straight  forward  process  –  details  the  tasks  that  support  the  Accomplishment  Criteria.  But  there  are  some  cri&cal  steps  that  must  be  done  in  the  right  order  to  end  up  with  a  risk  tolerant  IMS.  

Let’s  do  this  for  TSAS  

1  

9

V8.5  

Page 82: The integrated master plan and integrated master schedule

The  Primary  Role  for  the  IMP  is  to  describe  what  done  looks  like  in  MoE’s  and  MoP’s  

2  19  October  1899  Robert  Goddard  decided  that  he  wanted  to  "fly  without  wings"  to  Moon.  

9.0  Framework  

Page 83: The integrated master plan and integrated master schedule

Quick  View  to  IMP/IMS  Framework  

! Measures  of  increasing  maturity  for  the  key  deliverables  is  the  founda&on  for  increasing  the  Probability  of  Program  Success  

! Measures  of  Effec&veness  (MoE)  and  Measures  of  Performance  (MoP)  are  defined  in  the  Integrated  Master  Plan  (IMP)  Narra&ve  

!  Key  Performance  Parameters  (KPP)  –  both  JROC  and  program  specific  are  needed  

!  Technical  Performance  Measures  (TPM)  are  needed  for  all  key  deliverables  

3  

9.0  Framework  

Page 84: The integrated master plan and integrated master schedule

Star&ng  out  on  the  Right  Foot  …  

!  Most  IMP/IMS  literature  states  how  to  build  an  IMP  from  the  RFP  and  contractual  elements,  in  simple  and  maybe  simple  minded  terms  –  Decompose  the  events  into  SAs,  ACs,  and  their  Tasks  –  sounds  easy  

!  This  approach  fails  to  provide  advice  for  several  things:  –  How  to  minimize  the  topological  connec&ons  between  Events  –  How  to  increase  the  concurrency  between  IPTs  –  How  to  increase  the  tolerance  of  the  IMS  to  disrup&ve  events  

•  Known  and  knowable  risk  •  Unknown  and  possibly  unknowable  risk  

!  The  construc&on  of  the  IMS  needs  to  take  place  in  what  seems  to  be  a  reverse  order  –  Build  the  IMP  as  a  Value  Stream  Map  describing  the  increasing  maturity  –  and  

therefore  the  increasing  VALUE  of  the  deliverables  to  the  customer.  –  It’s  the  delivery  of  Customer  Value  that  inverts  the  management  process,  and  

focuses  on  Keeping  the  Program  GREEN  as  planned  that  maximizes  value  to  the  customer  (the  Government)    

4  

9.0  Framework  

Page 85: The integrated master plan and integrated master schedule

SETR  Program  Events  

5  hdps://acc.dau.mil/docs/technicalreviews/dod_tech_reviews.htm  

9.0  Framework  

Page 86: The integrated master plan and integrated master schedule

Build  PEs  Leg  to  Right  Start  with  SRR  (or  something  on  the  leA)  and  completely  define  its  compleDon,  before  moving  to  the  next  PE  

!  Define  the  SAs  for  an  Event  and  construct  a  work  flow  of  the  ac&vi&es  needed  to  sa&sfy  the  SA  –  These  ac&vi&es  are  yet  tasks,  so  don’t  commit  too  soon  to  defining  the  detailed  work  

–  Isolate  the  SAs  by  event  first  –  only  work  on  one  event  at  a  &me  

!  Iden&fy  the  par&cipants  in  the  work  – What  IPTs  par&cipate  in  this  work?  – What  swim  lanes  are  needed  to  isolate  the  IPTs?  

!  Define  the  elements    –  Ac&vi&es  performed  to  sa&sfy  the  SA  –  Deliverables  that  result  from  these  ac&vi&es  

!  There  are  s&ll  not  Accomplishment  Criteria  (AC),  but  that  comes  next  

6  

9.0  Framework  

Page 87: The integrated master plan and integrated master schedule

The  Accomplishment  Criteria  (AC)  

!  A  defini&ve  measure  or  indicator  that  verifies  comple&on  of  work  for  the  accomplishment  – Completed  work  effort    

•  Manufacturing  Plan  Completed  – Confirma&on  of  performance  compliance    

•  Flight  Test  Report  Approved  –  Incremental  verifica&on    

•  Maintenance  Demonstra&on  Completed  – Completed  cri&cal  process  ac&vi&es  

•  Risk  Management  Plan  Approved  

7  

9.0  Framework  

Page 88: The integrated master plan and integrated master schedule

The  Accomplishment  Criteria  (AC)  

!  Defines  the  measure  by  which  an  Accomplishment  (SA)  is  considered  “done”  

!  Terms  like  complete,  delivered,  closed  have  no  “units  of  measure”  in  the  context  of  a  Significant  Accomplishment  (SA)  and  are  open  to  interpreta&on  

!  Terms  like  …  –  Measures  of  comple&on  –  80%  of  drawings  approved  for  release  –  Counts  of  available  items  –  75%  of  pin-­‐outs  assigned  voltage  –  Fidelity  of  a  design  –  outer  mold  line  defined  within  90%  of  target  

–  Error  bounds  –  spacecraA  mass  known  to  ±20%  –  Performance  parameters  –  disconnect  force  within  allowed  limits  

–  Maturity  parameters  –  flight  arDcle  successful  in  last  3  tests  …  are  used  to  define  the  “exit  criteria”  

8  

9.0  Framework  

Page 89: The integrated master plan and integrated master schedule

2  Types  of  Accomplishment    Criteria:  Entry  and  Exit  

!  Entry  Criteria  –  Substan&ates  readiness  for  the  review  

!  Exit  Criteria  –  Substan&ates  successful  comple&on  of  the  review  

!  Cri&cal  Design  Review  (CDR)  example  – Are  we  ready  for  the  Flight  Test  Readiness  Review?  

– How  do  we  know  the  FTRR  a  success?  – What  did  we  learn  from  the  FTRR  that  increases  the  maturity  of  the  program’s  deliverables.  

9  

9.0  Framework  

Page 90: The integrated master plan and integrated master schedule

The  IMP  Focuses  us  on  Measures  of  Effec&veness  and  Performance  

10  

MoE  

KPP  

MoP   TPM  Mission  Need  

Acquirer  Defines  the  Needs  and  Capabili&es  in  terms  of  Opera&onal  Scenarios  

Supplier  Defines  Physical  Solu&ons  that  meet  the  needs  of  the  Stakeholders  

Opera3onal  measures  of  success  related  to  the  achievement  of  the  mission  or  opera3onal  objec3ve  being  evaluated.  

Measures  that  characterize  physical  or  func3onal  aAributes  rela3ng  to  the  system  opera3on.  

Measures  used  to  assess  design  progress,  compliance  to  performance  requirements,  and  technical  risks.  

9.0  Framework  

Page 91: The integrated master plan and integrated master schedule

Measure  of  Effec&veness  (MoE)  

! Measures  of  Effec&veness  …  !  Are  stated  in  units  meaningful  to  the  buyer,  !  Focus  on  capabili&es  independent  of  any  technical  implementa&on,  

!  Are  connected  to  the  mission  success.  

The  opera&onal  measures  of  success  that  are  closely  related  to  the  achievements  of  the  mission  or  opera&onal  objec&ves  evaluated  in  the  opera&onal  environment,  under  a  specific  set  of  condi&ons.  

“Technical  Measurement,”  INCOSE–TP–2003–020–01  

MoE’s  Belong  to  the  End  User  

11  

9.0  Framework  

Page 92: The integrated master plan and integrated master schedule

Measure  of  Performance  (MoP)  

! Measures  of  Performance  are  …  !  Adributes  that  assure  the  system  has  the  capability  to  perform,  

!  Assessment  of  the  system  to  assure  it  meets  design  requirements  to  sa&sfy  the  MoE.  

Measures  that  characterize  physical  or  func&onal  adributes  rela&ng  to  the  system  opera&on,  measured  or  es&mated  

under  specific  condi&ons.  

“Technical  Measurement,”  INCOSE–TP–2003–020–01  

MoP’s  belong  to  the  Program  –  Developed  by  the  Systems  Engineer,  Measured  By  CAMs,  and  Analyzed  by  PP&C    

12  

9.0  Framework  

Page 93: The integrated master plan and integrated master schedule

Key  Performance  Parameters  (KPP)  Both  JROC  and  Program  Specific  

!  Key  Performance  Parameters  …  !  Have  a  threshold  or  objec&ve  value,  !  Characterize  the  major  drivers  of  performance,  

!  Are  considered  Cri&cal  to  Customer  (CTC).  

Represent  the  capabili&es  and  characteris&cs  so  significant  that  failure  to  meet  them  can  be  cause  for  

reevalua&on,  reassessing,  or  termina&on  of  the  program  

“Technical  Measurement,”  INCOSE–TP–2003–020–01  

The  acquirer  defines  the  KPPs  during  the  opera&onal  concept  development  –  KPPs  say  what  DONE  looks  like  

13  

9.0  Framework  

Page 94: The integrated master plan and integrated master schedule

 Technical  Performance  Measures  (TPM)  for  key  deliverables    

!  Technical  Performance  Measures  …  !  Assess  design  progress,  !  Define  compliance  to  performance  requirements,  

!  Iden&fy  technical  risk,  !  Are  limited  to  cri&cal  thresholds,  !  Include  projected  performance.  

“Technical  Measurement,”  INCOSE–TP–2003–020–01  

Adributes  that  determine  how  well  a  system  or  system  element  is  sa&sfying  or  expected  to  sa&sfy  a  technical  

requirement  or  goal  

14  

9.0  Framework  

Page 95: The integrated master plan and integrated master schedule

What  are  Technical  Performance  Measures  Really?  

!  TPMs  are  measures  of  the  system  technical  performance  that  have  been  chosen  because  they  are  indicators  of  system  success.  They  are  based  on  the  driving  requirements  or  technical  parameters  of  high  risk  or  significance  -­‐  e.g.,  mass,  power  or  data  rate.  

!  TPMs  are  analogous  to  the  programma&c  measures  of  expected  total  cost  or  es&mated  &me-­‐to-­‐comple&on.  There  is  a  required  performance,  a  current  best  es&mate,  and  a  trend  line.  

!  Actual  versus  planned  progress  of  TPMs  are  tracked  so  the  systems  engineer  or  project  manager  can  assess  progress  and  the  risk  associated  with  each  TPM.    

!  The  final,  delivered  system  value  can  be  es&mated  by  extending  the  TPM  trend  line  and  using  the  recommended  con&ngency  values  for  each  project  phase.  

!  The  project  life  trend-­‐to-­‐date,  current  value,  and  forecast  of  all  TPMs  are  reviewed  periodically  (typically  monthly)  and  at  all  major  milestone  reviews.  

15  

9.0  Framework  

Page 96: The integrated master plan and integrated master schedule

!  Tracking  TPMs  and  comparing  them  to  the  resource  growth  provides  an  early  warning  system  to  detect  deficiencies  or  excesses  

!  Reserve  alloca&ons  narrow  as  design  proceeds  !  TPMs  that  violate  reserve  alloca&ons  or  have  trends  that  

do  not  meet  the  final  performance  trigger  correc&ve  ac&ons  

16  

Tracking  the  Technical    Performance  Measures  

9.0  Framework  

Page 97: The integrated master plan and integrated master schedule

No&onal  TPM  Design  Margin  Guidelines  

17  

9.0  Framework  

Page 98: The integrated master plan and integrated master schedule

Sample  IMP:  A  Flight  Avionics  System  (Con&nued)  

Hardware  PDR  –  Purpose    !  Ensure  system  hardware  ini&al  design  has  been  updated,  and  meets  

func&onal  and  allocated  performance  requirements  within  program  constraints.    

!  Opera&onal  security  concept  assessed.    !  Ensure  training  requirements  have  been  analyzed  and  their  objec&ves  

have  been  defined  for  training  missions.    !  Confirma&on  training  objec&ves  and  MTC  design  and  integra&on  conform  

to  the  Air  Force  syllabus  and  Ready  Aircrew  Program  (RAP).    !  Training  plan  will  be  updated.  !  Hardware  PDR  –  Expecta&ons  !  Team  agrees  system  hardware  ini&al  design  has  been  updated  and  can  

proceed  to  the  detailed  design  phase.    !  Team  agrees  training  plans  and  objec&ves  correlate  with  the  Air  Force  

syllabus,  RAP  and  training  planning,  development  can  con&nue.    !  System  Specifica&on  and  TTL  requirements  are  traceable  to  the  allocated  

hardware  design.    18  

9.0  Framework  

Page 99: The integrated master plan and integrated master schedule

Sample  IMP:  A  Flight  Avionics  System  (Con&nued)  

!  Hardware  PDR  –  Entry  Criteria  !  Func&onal  Baseline  Authen&cated  (FBA)  !  Ini&ate  system  hardware  ini&al  design  and  allocate  func&ons  to  the  appropriate  Configura&on  Items  

!  All  specifica&ons  updated  and  required  documenta&on  is  made  available  including  an&cipated  lower  level  design  documenta&on  

!  All  SRR/SFR  ac&on  items  closed  or  disposi&oned    

19  

9.0  Framework  

Page 100: The integrated master plan and integrated master schedule

Sample  IMP:  A  Flight  Avionics  System  (Con&nued)  

Hardware  PDR  –  Accomplishments  !  System  hardware  ini&al  design  complete.    

–  Func&ons  allocated  to  one  or  more  hardware  configura&on  items  and  are  traceable  to  the  MTC  SSS  and  TSSC  SSS.    

–  Human,  safety,  R&M,  EMI,  opera&onal  security,  instructor  and  operator  interfaces,  etc,  design  factors  have  been  reviewed.    

!  Drag  instructor  and  operator  manuals  reviewed    !  Program  risks  updated,  assessed,  and  reviewed.    

–  Mi&ga&on  plans  in  place.  !  Program  schedule  and  constraints  updated  and  reviewed.    

–  Cri&cal  schedule  path  drivers  reviewed.    !  Design  criteria  for  the  simula&on  and  database  development  

reviewed  and  updated.  !  Program  processes  and  metrics  reviewed.  !  Test  Planning  ac&vi&es  and  relevant  documenta&on  reviewed  by  

test  team.  20  

9.0  Framework  

Page 101: The integrated master plan and integrated master schedule

Sample  IMP:  A  Flight  Avionics  System  (Concluded)  

Hardware  PDR  –  Exit  Criteria    !  Hardware  (ownership,  visual,  IOS,  brief/debrief)  design  reviewed,  allocated  to  a  

hardware  configura&on  item  and  updated  to  include  instructor  and  operators  interfaces,  malfunc&on  and  control  requirements,  etc.    

!  RTM  updated,  MTC  SSS,  TSSC  SSS  and  TTL  traceable  to  allocated  hardware  design  to  include  ESOH  requirements.    

!  Human,  safety,  R&M,  EMI,  opera&onal  security,  instructor  and  operator  interfaces,  etc,  design  factors  reviewed.    

!  MTC  and  TSSC  allocated  baselines  established  and  controlled  by  appropriate  level  documenta&on  for  PDR.  

!  Drag  instructor  and  operator  manuals  reviewed  with  user  concurrence  and  incorporate  sa&sfactory  human  factor  design  factors  into  the  operator  interfaces.    

!  Risk  management  and  mi&ga&on  plans  updated,  in  place,  addresses  ESOH  plans  and  risks,  and  within  program  constraints.    

!  Risks  assesses,  understood,  documented,  accepted  and  understood  by  team.  !  Program  schedule  reviewed    

–  Cri&cal  path  drivers  iden&fied    –  IMS  Updated  and  reflects  cri&cal  paths  

21  

9.0  Framework  

Page 102: The integrated master plan and integrated master schedule

One  More  IMP  Sample  

!  (SA)  System  &  Segment  Requirements  Updated  &  Allocated  –  (AC)  SRR  /  SDR  Update  Review  Conducted  

–  (AC)  Preliminary  System  Specifica&on  Documents  (A011)  Baselined  

–  (AC)  Preliminary  Spacecrag  Segment  Specifica&on  Baselined  

–  (AC)  Preliminary  Ground  Segment  Specifica&on  Baselined  

–  (AC)  Preliminary  Specifica&on  Tree  Baselined  

!  (SA)  Preliminary  ICDs  Baselined  For  Customer  Review  

–  (AC)  Preliminary  Space-­‐Ground  ICD  Baselined    

!  (SA)  PDR  System  Design  Completed  –  (AC)  Top  Level  System  Architecture  Updated  

–  (AC)  PDR  Level  System  Analyses  Completed  

–  (AC)  PDR  Level  Reliability  /  Availability  Analysis  Completed  

–  (AC)  Preliminary  System  Level  Risk  Assessment  Completed  

–  (AC)  System  Level  Plans  Updated  For  PDR  

–  (AC)  Flight  Long  Lead  Review  Conducted  

22  

Preliminary  Design  Review  

9.0  Framework  

Page 103: The integrated master plan and integrated master schedule

The  “But”  for  this  Guidance  

! With  these  samples  and  the  SETR  guidance  we’ve  just  started  

!  The  program  needs  to  define  program  specific  events  to  assure  the  actual  maturity  measures  are  captured  – The  IMP  provides  sufficient  definiDon  to  track  the  step-­‐by-­‐step  compleDon  of  the  required  accomplishments  for  each  event  and  to  demonstrate  saDsfacDon  of  the  compleDon  criteria  for  each  accomplishment.  [AFMC  PAMPHLET  63-­‐5]   23  

9.0  Framework  

Page 104: The integrated master plan and integrated master schedule

IMP  Verbs  for  Significant  Accomplishments  

24  

Integrated  Master  Plan  Allowable  Verbs  

Allocated:  Segment  requirement  is  flowed  down  from  the  System  Specifica&on  

Released:  Approved  item  for  delivery  for  intended  customer  or  supplier;  all  internal  distribu&on  and  sign  offs  complete.  An  electronic  version  is  made  accessible  on  the  IDE  

Completed:  The  subject  item,  data,  document,  or  process  is  prepared  or  concluded,  and  reviewed  and  accepted  by  the  responsible  IPT.  Suppor&ng  documenta&on  is  available  through  IDE  

Reviewed:  The  subject  item,  data,  document,  or  process  is  prepared  or  concluded,  and  documented  for  comple&on.  Suppor&ng  documenta&on  is  available  through  IDE  

Conducted:  The  subject  mee&ng  or  review  has  been  held  with  all  required  par&cipants.  The  charts  or  minutes  are  available  through  the  IDE  

Updated:  The  subject  process,  data,  or  document  has  been  reevaluated  using  later  informa&on,  and  adjustments  incorporated.  

Defined:  The  subject  configura&on  items,  data,  or  document  was  submided  to  the  customer  

Validated:  Requirements  are  validated,  received  contractor  approvals,  were  distributed,  and  are  available  through  the  IDE  

Established:  The  subject  items  is  created  and  set  in  place  in  a  manner  consistent  with  its  intended  use  ager  review  and  accepted  by  the  IPT  

Verified:  Requirements  are  verified  or  processed  in  accordance  with  established  prac&ce.  

9.0  Framework  

Page 105: The integrated master plan and integrated master schedule

The  IMP  Process  Narra&ve  

!  ObjecFve:  a  brief  statement  explaining  why  this  process  set  is  applied  for  this  program  

!  Governing  DocumentaFon:  lists  of  the  guidance  or  compliance  documents;  e.g.,  specifica&ons,  manuals,  and  procedures  including  company,  government,  and  industry  references  

!  Approach:  concise  descrip&on  as  to  who  owns  each  process;  what  are  the  roles  and  responsibili&es;  and  the  overall  process  including  a  process  flow  diagram.  

25  

9.0  Framework  

Page 106: The integrated master plan and integrated master schedule

Generic  IMP  Evalua&on  Criteria  !  Do  the  Program  Events  and  Accomplishments  reflect  the  logical  evolu&on  and  progress  of  the  overall  Program?  –  Do  program  events  and  their  defini&ons  clearly  demonstrate  the  maturity  of  the  program  over  its  life?  

–  Do  the  selected  Accomplishments  and  associated  Criteria  iden&fy  meaningful  and  measurable  progress  toward  the  key  goals  of  the  Program?  

!  Do  the  Accomplishments  for  each  event  demonstrate  a  meaningful  understanding  of  the  program  requirements  or  are  they  tasks  that  anyone  could  do  for  any  contract?  –  Do  they  reflect  your  SOW  requirements?    

!  Does  the  IMP  structure  readily  map  to  the  IPT  structure  such  that  each  IPT  can  easily  visualize  the  scope  of  their  responsibility?    

!  When  awarded,  could  the  contractor  use  the  Accomplishments  as  discrete  ac&vity  cost  accounts  in  their  earned  value  system?  Or  are  they  level  of  effort  in  nature?    

!  Is  sufficient  visibility  provided  to  iden&fy  and  track  the  Program  Risk  Plan  and  associated  risk  mi&ga&on  accomplishments  and/or  con&ngencies?  

–  Does  criteria  suppor&ng  the  accomplishments  include  key  performance  requirements?  

!  Are  IPT  cross-­‐dependencies  and  dependencies  external  to  the  Program  appropriately  reflected  if  they  reflect  poten&al  schedule  or  performance  risks  to  the  success  of  the  Program?  

!  Is  the  submided  "Contract  IMP"  (the  Product  IMP  that  is  to  be  included  as  part  of  the  Program  Contract)  defined  to  the  appropriate  level:  –  Do  the  Accomplishments  and  associated  Criteria  go  down  to  a  level  sufficient  to  provide  visibility  into  key  subcontractor  ac&vi&es  upon  which  the  success  of  the  Program  may  be  dependent?  

–  Are  the  Events  and  Accomplishments  included  in  the  IMP  at  such  a  level  as  to  make  the  maintenance  of  the  'Contractual  IMP'  prac&cal  or  does  it  include  an  unnecessary  level  of  detail?  

26  

9.0  Framework  

Page 107: The integrated master plan and integrated master schedule

Program  Management  Levels  Program Levels" IMP/IMS Elements" CWBS"

Tier 1!Program Manager!Technical Leads!IPT Manager!Technical performance goals!

Major Program Events (PE)!!!!Significant Accomplishments (SA)!

Level 1 & 2!Links to CLINs!Level 3 & 4!Control Packages!Link to PBS!Integrated EVMS!

Tier 2!Control Account Managers !Product Work Plan!Responsible organization elements!!

Accomplishment Criteria (AC)!!!!!Tasks (NA)!

Level 5!Cost Account Package!Cost Collection Level!Links to WBS by OBS!Resource summaries!Early warning EVMS analysis!

Tier 3!Work Package Manager!

Detailed plans! Work package!Earned value calculations!

27  

9.0  Framework  

Page 108: The integrated master plan and integrated master schedule

Connec&ng  the  Components    of  the  IMP/IMS  

!  The  assembled  IMP/IMS  links  all  work  ac&vi&es  ver&cally  to  the  ACs,  SAs,  and  PEs  

28  

IMS  

Customer  Requirements   IMP  

ORG  

IPTs  

ORG  

IPTs  

Performance  

Analysis/  Management  

Review  

Events (E)  Events (E)  

Accomplishments  Process  

Narratives  Criteria  

Integrated Master  Schedule (IMS)  

Integrated Master  Schedule (IMS)  

Control Account  Control Account  

Work Package  Work Package  

Work Package Tasks  Work Package Tasks  

WBS  

Program  Performance  Management  

System  

Supplemental Schedules  

Risk and  opportunity  Risk and  

opportunity  

9.0  Framework