The INDOT CORS 2007 Indiana GIS ConferenceMarch 13, 2007By William A. Schmidt, PE, LSManager of Aerial Engineering, INDOTThomas A. Mahon, PE, LSSurvey Group Manager, Woolpert Inc
-
What is a CORS?Continuously Operating Reference StationOperated by Others Operates continuouslyData available for Post-ProcessingData may be available in real-time
-
Advantages of a CORSSingle coordinate systemUniform precisionNo need to setup base stationsAvoids base station radio issuesFrees up base stations as roversIncreases productivityEase of use
-
Existing CORSNGS
-
Existing CORS (contd)Seiler Instruments
-
INDOTs Primary Network17 New Stations plus Bloomington (IUCO)
-
Typical Installation
-
Initial Installations
-
Primary Monumentation
-
Primary Monumentation (Contd)
-
Primary Monumentation (Contd)
-
Secondary Monumentation
-
Station SponsorsPrimary StationsIndiana Department of TransportationSecondary StationsOther State AgenciesMunicipalities/Counties (Possibly)Higher Education (Possibly)Private Contractors (Not at this time)
-
Network AdministrationINDOT to Fund Primary NetworkIndiana Office of Technology (IOT) to Maintain ServersServers dedicated to INDOT CORS
-
BudgetsInitial Capital CostsPrimary Network: $400,000Secondary Network: $800,000
Annual Operating Budget: to be determinedHardware and Software UpgradesAdditional User LicensesNetwork Administration
-
ScheduleProcurement Bids March 2007Bids Received April 2007Bid Awarded April 2007Begin Primary Installations May 2007Complete Primary Installation, including operational network December 2007Begin Secondary Installation August 2007Complete Secondary Installation - TBD
-
CORS AccessPost-ProcessingFree & Available thru www, location to be determinedReal-Time KinematicControlled by user name and passwordUp to 250 concurrent users w/o paying for additional access licensesMay develop a fee-based system of access to support maintenance and upgrades
-
CORS Access (Contd)Real-Time DifferentialCoast Guard Beacons (10 m h 68%)WAAS FAA (7 m h&v 95%)Third Party Vendors Omnistar (submeter 95%)INDOT CORS (subdecimeter 95%)Potential fee schedule similar to RTK
-
CORS Access (Contd)
-
CORS Access (Contd)
-