The Hydro Québec De-icer Project at Lévis Substation · The Hydro Québec De-icer Project at...
Transcript of The Hydro Québec De-icer Project at Lévis Substation · The Hydro Québec De-icer Project at...
The Hydro Québec De-icer Project at Lévis Substation
HVDC and FACTS Subcommittee, Calgary, July 29 2009
PresenterChris Horwill : AREVA T&D
> De-icer – 29.07.09 – IEEE PES Calgary2 2
Background
> De-icer – 29.07.09 – IEEE PES Calgary3 3
Why a de-icer?
In December 1998, the Québec region of Canada was hit by one of the worst ice-storms in recorded history
The ice storm generated ice build-up as much as 75mm
An accumulation of ice toppled hydro towers and downed hundreds of kilometres of high-voltage transmission lines.
> De-icer – 29.07.09 – IEEE PES Calgary4 4
De-icer: Location
De-icer atLévis Substation
Québec city
> De-icer – 29.07.09 – IEEE PES Calgary5 5
Lines for de-icing
315 kV183kmRivière du Loup
3078 / 3079
735 kV242kmBergeronnes7007
735 kV78kmAppalaches7097
735 kV62kmJacques Cartier
7010 +7020
735 kV27kmLaurentides7010
VoltageLengthDestinationLine
> De-icer – 29.07.09 – IEEE PES Calgary6 6
De-icer Mode: Main design ratings
Main Ratings:
Standard de-icer mode - “Nameplate rating” :250MW, 7200A / ±17.4kV @ +10°C
Verification mode : 200MW, 5760A / ±17.4kV @ +30°C
1 hour overload :300MW, 7200A / ±20.8kV @ +10°C
Low ambient overload : 275MW, 7920A / ±17.4kV @ - 5°C
> De-icer – 29.07.09 – IEEE PES Calgary7 7
De-icer Mode: Main design ratings
Because of the different characteristics of the sections, the operating range of current and voltage is large
6000 A
DC voltage
DC current600 A 1000 A 7200 A3600 A
2.0 kV
41.6 kVVref = 34.8 kV
Verification
De-icing
Temporary overload
> De-icer – 29.07.09 – IEEE PES Calgary8 8
SVC Mode: Main design ratings
Main ratingsDynamic range
+225 Mvar / -115 Mvar at nominal voltage
Target voltage315 kV ± 5%
Slope
3% on 225 Mvar
> De-icer – 29.07.09 – IEEE PES Calgary9 9
Solution
> De-icer – 29.07.09 – IEEE PES Calgary10 10
One line diagram
TSC154Mvar
5/11 and 7/13filters 70Mvar
HP filter55Mvar
HP filter55/12Mvar
DC filters315kV
43kV
20kV
> De-icer – 29.07.09 – IEEE PES Calgary11 11
One line diagram: De-icer mode
TSC154Mvar
5/11 and 7/13filters 70Mvar
HP filter55Mvar
HP filter55/12Mvar
DC filters315kV
43kV
20kV
> De-icer – 29.07.09 – IEEE PES Calgary12 12
One line diagram: SVC mode
TSC154Mvar
5/11 and 7/13filters 70Mvar
HP filter55Mvar
HP filter55/12Mvar
DC filters315kV
43kV
20kV
> De-icer – 29.07.09 – IEEE PES Calgary13 13
Control Performance Verification
> De-icer – 29.07.09 – IEEE PES Calgary14 14
Testing of Control System
Development of Master Control - DCU (De-icer Control Unit)
Validation of DNP3 Communication
Type test on Real Control (System V)
Static and Dynamic Performance Test on DevelopmentControl Cubicle & Simulator
Additional tests on a Control Replica at IREQ
> De-icer – 29.07.09 – IEEE PES Calgary15 15
Additional Testing on a Control Replica (RSPC1)
Provide additional testing facility ( In parallel to Factory Test)
MBPSS( Multi-Band Power System Stabilizer)Geomagnetic influenceContingencies (additional validation)
Final validation of UCD Validation of Acceptance Test programTraining (Operator and Field technician)
PrimaryPrimary ObjectivesObjectives
Replica connected to HYPERSIM (IREQ simulator)
> De-icer – 29.07.09 – IEEE PES Calgary16 16
Additional Testing on a Control Replica (RSPC1)
TCR VBE
TSC VBE
SVC/Decier Control &Protection
PROFIBUSMASTER
A/I
A/O
D/I
D/O
PowerSupply
HYPERSIM
APEX
UCD
HYPERSIM
PROFIBUSSLAVE
VALVE FIRING
VALVE FIRINGDATA BACK
Interface
FIRING SIGNAL
MBPSSFunction
Equivalent AC networkTSC valveTCR/De-icer valveReactive elementsCoupling transformersEarthing transformersDischarge transformer
> De-icer – 29.07.09 – IEEE PES Calgary17 17
Simulator Setup
HYPERSIM
RSPC1
UCD
> De-icer – 29.07.09 – IEEE PES Calgary18 18
De-icer mode
> De-icer – 29.07.09 – IEEE PES Calgary19 19
Preparation for commissioning
Deicer mode - particular tests singled out 1. Converter Deblocking in current control
2. Review trip sequence – Overvoltage caused by remote isolation of the converter
3. Dc voltage measurement failure
4. Ac Voltage Error (Fuse failure)
> De-icer – 29.07.09 – IEEE PES Calgary20 20
Remote Isolation of the Converter
> De-icer – 29.07.09 – IEEE PES Calgary21 21
Normal Shutdown Sequenceby local breaker opening
> De-icer – 29.07.09 – IEEE PES Calgary22 22
Deicer mode – Remote Shutdown
No control action
Severe Overvoltage
when connected to longest (247km) line
> De-icer – 29.07.09 – IEEE PES Calgary23 23
Deicer mode – Remote Shutdown
Current detection & Control action
No Overvoltage
Preliminary investigationLocal detection preferred
> De-icer – 29.07.09 – IEEE PES Calgary24 24
Limitation of OvervoltageNew Protection Philosophy
629.77
389.12
0
100
200
300
400
500
600
700
600 1200 1800 2400 3000 3600 4200 4800 5400 6000 6600 7200 7800
Iorder (A)
Vhvm
ax (k
V)
Existing With New Prot Philosophy
kV
kV
> De-icer – 29.07.09 – IEEE PES Calgary25 25
De-icer installation
> De-icer – 29.07.09 – IEEE PES Calgary26 26
De-icer installation
DC converter valves
> De-icer – 29.07.09 – IEEE PES Calgary27 27
De-icer installation
AC coupling reactors
> De-icer – 29.07.09 – IEEE PES Calgary28 28
De-icer installation
HV connections and transformer
> De-icer – 29.07.09 – IEEE PES Calgary29 29
De-icer installation
Harmonic filters
> De-icer – 29.07.09 – IEEE PES Calgary30 30
De-icer installation
DC filters and DC bus
> De-icer – 29.07.09 – IEEE PES Calgary31 31
De-icer installation
Aerial view of the de-icer
> De-icer – 29.07.09 – IEEE PES Calgary32 32
De-icing tests
Connecting de-icer to line
> De-icer – 29.07.09 – IEEE PES Calgary33 33
Commissioning
> De-icer – 29.07.09 – IEEE PES Calgary34 34
TCR current
> De-icer – 29.07.09 – IEEE PES Calgary35 35
Response to undervoltage
> De-icer – 29.07.09 – IEEE PES Calgary36 36
Response to overvoltage
> De-icer – 29.07.09 – IEEE PES Calgary37 37
Bridge 2 deblocked
> De-icer – 29.07.09 – IEEE PES Calgary38 38
Ramp Up 3300A to 7200A
> De-icer – 29.07.09 – IEEE PES Calgary39 39
Ramp Up 3300A to 7200A TSC Unblocked
> De-icer – 29.07.09 – IEEE PES Calgary40 40
Ramp Down 5000 A to Standby
> De-icer – 29.07.09 – IEEE PES Calgary41 41
Ramp Down 5000 A to Standby
> De-icer – 29.07.09 – IEEE PES Calgary42 42
Ramp Down 5000 A to Standby
> De-icer – 29.07.09 – IEEE PES Calgary43 43
Shutdown
> De-icer – 29.07.09 – IEEE PES Calgary44 44
Shutdown – Action of ERM
> De-icer – 29.07.09 – IEEE PES Calgary45 45
De-icer
In service as an SVC during the winter
Unique project made possible by good collaboration between Hydro Québec and AREVA
Many technical hurdles overcome to make the installation a success