The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours...

30
The Horseshoe Project 11 October 2017

Transcript of The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours...

Page 1: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

The Horseshoe Project

11 October 2017

Page 2: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Dallas Horseshoe Project

Page 3: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Overview

Scope: $798 Million Design-Build Reconstruction of Existing Interchange Between IH 30 and IH 35E Key Features: Replace Existing Bridges over Trinity

River and Existing Levee System with 8 New Bridges

Additionally; Construct two Calatrava-Designed Steel Arch Structures over Trinity River (Margaret McDermott Signature Bridges)

Reconstruction of IH 30/IH 35E-Multi-Level Interchanges at two locations

Page 4: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Proposed Configuration

Page 5: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

IH35E Typical Configuration A-A

Page 6: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Interstate Highway 35E

Before - 2013

After - 2017

Page 7: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Proposed Configuration

Page 8: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Mixmaster Typical Configuration B-B

Page 9: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Mixmaster

Before - 2013

After - 2017

Page 10: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Proposed Configuration

Page 11: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

IH30 Typical Configuration C-C

Page 12: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Interstate Highway 30

Before - 2013

After - 2017

Page 13: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Margaret McDermott (MMD) Bridge

City of Dallas Signature Pedestrian Bridges

Designed by Santiago Calatrava & Huitt-Zollars

Single Span of 1,125 ft. w/ Arch Height of 334 ft.

31 ft. Wide Superstructure w/ over 21,000 ft. of Wire

Page 14: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Margaret McDermott (MMD) Bridge

Page 15: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

By the Numbers – Drilled Shafts

97,723 LF of Drilled Shafts ranging from 18” to 84” in Diameter

Over 3x the height of Mount Everst

65,766 CY of Concrete for Drilled Shafts

Page 16: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

By the Numbers – Columns & Cap

913 Columns on the Project

27,697 CY of Column Concrete

457 Caps on the Project

35,333 CY of Cap Concrete

Page 17: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

By the Numbers - Beams

340,032 LF of Precast Concrete Beams

64.4 Miles of Concrete Beams

Stretches from West End of Ft. Worth, TX to East End of Dallas, TX.

Page 18: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

By the Numbers - Decks

3,026,059 SF of Bridge Deck

Equivalent to 52.5 football fields in area

82,103 CY of Bridge Deck Concrete

Equivalent to roughly 16.75 Olympic-size pools, 6.5 PLC main offices, or Fluor’s Corporate Headquarters in volume.

Page 19: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

By the Numbers - Roadway

Lime Treated Subgrade – 327,439 SY; 8,252 TNS

Cement Treated Base – 334,741 SY; 117,159 TNS

Fill a football field 26 feet high

Page 20: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

By the Numbers – Concrete Paving

312,740 SY – 40 Lane Miles of Paving

101,210 CY – Fill a football field 47.5 feet high

Page 21: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

By the Numbers – Retaining Walls

MSE Wall - 320,098 SF

Page 22: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

By the Numbers - Drainage

Reinforced Concrete Pipe – 47.706 LF ranging from 24” to 72” in size

Box Culverts – 3,949 LF ranging in size from 9x5 to 10x10

Page 23: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Achievements – Safety Record

2014 – 2015 1,000,000 Consecutive Work Hours with No Recordable

2015 – 2016 1,400,000 Consecutive Work Hours with No Recordable

Job-to-Date Over 5.2M Work Hours

Recognitions ZERO Incidents Five-Start Status – 1M Work Hours (2014-2015)

Corporate Award of Health, Safety, & Environmental Excellence (2015)

Page 24: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Achievements – Substantial Completion

SUBSTANTIAL COMPLETION

SEGMENT A

April 23, 2017

Page 25: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Project Management Approach

Effective Meetings vs Number of Meetings - Keep it Simple Easy to get Lost in the Maze of Meetings: i.e. Don’t Meet Just to Meet

Page 26: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Project Management Approach

Construction Driven

Active Technical Work Group (TWG) Participation

Decision Makers Present and Active

Page 27: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Project Management Approach

Proactive Allocation of Risk and Active Risk Management Examples

Oncor Transmission Lines

408 Permit for Work within Levee Limits

City of Dallas

Re-sequenced and Managed Project through Wettest Year on Record

Traffic Management and Effective Utilization of Closures

Page 28: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Project Management : Traffic and Safety

• Dallas Horseshoe Project-

– Lane Rental Fee Bank Balance = $2.4 million

– Results:

• Majority of lane closures were completed overnight, very few single lane closures during the day on the weekend

• All full closures were completed in overnight hours (majority on Friday and Saturday nights)

• No full closures needed during the day on the weekend

• Work during closures was maximized and multiple activities and crews worked safely within the closures.

• Not a single lane closure was not picked up by Time Period A/the peak hour and no lane closures during rush hour

• Multiple work activities during lane closures to maximize work accomplished during a closure

• Overall we believe we have reduced the impact to the traveling public

Page 29: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Project Management : Traffic and Safety

Multiple Activities worked to optimize lane closure

Example of work completed in evening lane closure

Page 30: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable

Collaborative Project Management

Project First

Honoring Commitments (Do what you

say)

Speaking Straight to the point

(No Games)

Be on the Same Page

Actively Listen

Effective and Active PartneringNo Issues Escalated above Project LevelOwnership at all Levels of the Project Team

Collaborative Project Team Approach