The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours...
Transcript of The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours...
![Page 1: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/1.jpg)
The Horseshoe Project
11 October 2017
![Page 2: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/2.jpg)
Dallas Horseshoe Project
![Page 3: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/3.jpg)
Overview
Scope: $798 Million Design-Build Reconstruction of Existing Interchange Between IH 30 and IH 35E Key Features: Replace Existing Bridges over Trinity
River and Existing Levee System with 8 New Bridges
Additionally; Construct two Calatrava-Designed Steel Arch Structures over Trinity River (Margaret McDermott Signature Bridges)
Reconstruction of IH 30/IH 35E-Multi-Level Interchanges at two locations
![Page 4: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/4.jpg)
Proposed Configuration
![Page 5: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/5.jpg)
IH35E Typical Configuration A-A
![Page 6: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/6.jpg)
Interstate Highway 35E
Before - 2013
After - 2017
![Page 7: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/7.jpg)
Proposed Configuration
![Page 8: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/8.jpg)
Mixmaster Typical Configuration B-B
![Page 9: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/9.jpg)
Mixmaster
Before - 2013
After - 2017
![Page 10: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/10.jpg)
Proposed Configuration
![Page 11: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/11.jpg)
IH30 Typical Configuration C-C
![Page 12: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/12.jpg)
Interstate Highway 30
Before - 2013
After - 2017
![Page 13: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/13.jpg)
Margaret McDermott (MMD) Bridge
City of Dallas Signature Pedestrian Bridges
Designed by Santiago Calatrava & Huitt-Zollars
Single Span of 1,125 ft. w/ Arch Height of 334 ft.
31 ft. Wide Superstructure w/ over 21,000 ft. of Wire
![Page 14: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/14.jpg)
Margaret McDermott (MMD) Bridge
![Page 15: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/15.jpg)
By the Numbers – Drilled Shafts
97,723 LF of Drilled Shafts ranging from 18” to 84” in Diameter
Over 3x the height of Mount Everst
65,766 CY of Concrete for Drilled Shafts
![Page 16: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/16.jpg)
By the Numbers – Columns & Cap
913 Columns on the Project
27,697 CY of Column Concrete
457 Caps on the Project
35,333 CY of Cap Concrete
![Page 17: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/17.jpg)
By the Numbers - Beams
340,032 LF of Precast Concrete Beams
64.4 Miles of Concrete Beams
Stretches from West End of Ft. Worth, TX to East End of Dallas, TX.
![Page 18: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/18.jpg)
By the Numbers - Decks
3,026,059 SF of Bridge Deck
Equivalent to 52.5 football fields in area
82,103 CY of Bridge Deck Concrete
Equivalent to roughly 16.75 Olympic-size pools, 6.5 PLC main offices, or Fluor’s Corporate Headquarters in volume.
![Page 19: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/19.jpg)
By the Numbers - Roadway
Lime Treated Subgrade – 327,439 SY; 8,252 TNS
Cement Treated Base – 334,741 SY; 117,159 TNS
Fill a football field 26 feet high
![Page 20: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/20.jpg)
By the Numbers – Concrete Paving
312,740 SY – 40 Lane Miles of Paving
101,210 CY – Fill a football field 47.5 feet high
![Page 21: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/21.jpg)
By the Numbers – Retaining Walls
MSE Wall - 320,098 SF
![Page 22: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/22.jpg)
By the Numbers - Drainage
Reinforced Concrete Pipe – 47.706 LF ranging from 24” to 72” in size
Box Culverts – 3,949 LF ranging in size from 9x5 to 10x10
![Page 23: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/23.jpg)
Achievements – Safety Record
2014 – 2015 1,000,000 Consecutive Work Hours with No Recordable
2015 – 2016 1,400,000 Consecutive Work Hours with No Recordable
Job-to-Date Over 5.2M Work Hours
Recognitions ZERO Incidents Five-Start Status – 1M Work Hours (2014-2015)
Corporate Award of Health, Safety, & Environmental Excellence (2015)
![Page 24: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/24.jpg)
Achievements – Substantial Completion
SUBSTANTIAL COMPLETION
SEGMENT A
April 23, 2017
![Page 25: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/25.jpg)
Project Management Approach
Effective Meetings vs Number of Meetings - Keep it Simple Easy to get Lost in the Maze of Meetings: i.e. Don’t Meet Just to Meet
![Page 26: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/26.jpg)
Project Management Approach
Construction Driven
Active Technical Work Group (TWG) Participation
Decision Makers Present and Active
![Page 27: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/27.jpg)
Project Management Approach
Proactive Allocation of Risk and Active Risk Management Examples
Oncor Transmission Lines
408 Permit for Work within Levee Limits
City of Dallas
Re-sequenced and Managed Project through Wettest Year on Record
Traffic Management and Effective Utilization of Closures
![Page 28: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/28.jpg)
Project Management : Traffic and Safety
• Dallas Horseshoe Project-
– Lane Rental Fee Bank Balance = $2.4 million
– Results:
• Majority of lane closures were completed overnight, very few single lane closures during the day on the weekend
• All full closures were completed in overnight hours (majority on Friday and Saturday nights)
• No full closures needed during the day on the weekend
• Work during closures was maximized and multiple activities and crews worked safely within the closures.
• Not a single lane closure was not picked up by Time Period A/the peak hour and no lane closures during rush hour
• Multiple work activities during lane closures to maximize work accomplished during a closure
• Overall we believe we have reduced the impact to the traveling public
![Page 29: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/29.jpg)
Project Management : Traffic and Safety
Multiple Activities worked to optimize lane closure
Example of work completed in evening lane closure
![Page 30: The Horseshoe Project...Achievements –Safety Record 2014 –2015 1,000,000 Consecutive Work Hours with No Recordable 2015 –2016 1,400,000 Consecutive Work Hours with No Recordable](https://reader034.fdocuments.us/reader034/viewer/2022051811/60265bc1f6e33709e3001b3e/html5/thumbnails/30.jpg)
Collaborative Project Management
Project First
Honoring Commitments (Do what you
say)
Speaking Straight to the point
(No Games)
Be on the Same Page
Actively Listen
Effective and Active PartneringNo Issues Escalated above Project LevelOwnership at all Levels of the Project Team
Collaborative Project Team Approach