THE GATEWAY PROGRAM OVERVIEW AND UPDATE
February 2018
Amtrak Corporate Planning
Marie Corrado
Amtrak Sr. Director – Gateway Program
2 | Amtrak Corporate Planning
THE MOST URGENT INFRASTRUCTURE PROGRAM IN AMERICA
» Busiest section of NEC is between Penn Station New York & Newark, NJ (450 trains, 200k trips/day) constrained by two-track bottleneck.
» North River Tunnel, Portal Bridge & other infrastructure dates to early 1900’s
» PSNY regularly operates at capacity (1,300 train movements daily on 21 tracks)
» Capacity constraints + aging infrastructure = risk to 10% of U.S. GDP
» Super Storm Sandy accelerated degradation of these assets
4 | Amtrak Corporate Planning
HISTORIC GROWTH OF PENN STATION NEW YORK
Train and passenger volumes have doubled since 1976More than 650,000 subway, commuter and intercity passengers daily
156268 267
358
554 581147
274
456
0
200
400
600
800
1000
1200
1400
1976 2001 2016
NJ Transit
LIRR
Amtrak
Weekday Train Movements
1976- 2016
6 | Amtrak Corporate Planning
PROJECTS TO ADDRESS IMMEDIATE NEEDS
Hudson Tunnel Project
Portal North Bridge
7 | Amtrak Corporate Planning
BUILDING FOR THE FUTURE
–CapacityPortal South Bridge
Secaucus Station Expansion
Bergen Loop
NJ Rail Yard - Site TBD
Penn Station Expansion
Sawtooth Bridge Replacement
8 | Amtrak Corporate Planning
GATEWAY PROGRAM FUNDING PARTNERSHIP
• New York & New Jersey Governors & U.S. Senators public pronouncement of funding framework:
• NY/NJ, Port Authority of NY & NJ, and GDC to fund 50% of Gateway Program.
• Federal partners (Amtrak, FTA, FRA) to fund 50%.
• Partners incorporated Gateway Program Development Corporation (GDC) in November 2016 in State of New Jersey as nonprofit corporation to effectuate planning, funding/financing, construction and delivery of the Gateway Program.
• GDC has signed an Emerging Projects Agreement with US DOT – an important first step to unlock billions of dollars in low cost federal loans.
• GDC will be borrower with debt to be paid by funding provided to GDC by local partners.
9 | Amtrak Corporate Planning
• Replace century-old swing bridge over the Hackensack River in NJ with new, high-level, fixed span
• Fully designed, permitted
• Early work underway, funded by TIGER grant + local match
• Local funding commitment in place
• Port Authority to repay $284m Federal loan to Gateway Program Development Corp.
• NJT & Amtrak commitments in place
• Accepted into project development pipeline for FTA Core Capacity grant program
• Requested entry into engineering phase in November 2017. Re-rating from FTA is pending.
PORTAL NORTH BRIDGE PROJECT
Portal Bridge rotates open for river traffic
Rendering of the new bridge – a high-level fixed span
12 | Amtrak Corporate Planning
HUDSON YARDS CONCRETE CASING: SECTION 3
Section 1
Construction Complete
$185m – Sandy Relief
Section 2
Construction Complete
$50m – Sandy Relief
$5.5m – NJ TRANSIT
$5.5m – LIRR
$5.5m – Amtrak
Section 3
$25m for Early Work
(Amtrak/Port Authority)
Fully permitted & designed
Add’l Funding Needed
14 | Amtrak Corporate Planning
HUDSON TUNNEL PROJECT ALIGNMENT
» Preferred alignment makes use of Access to the Region’s Core (ARC) engineering in New Jersey.
15 | Amtrak Corporate Planning
• Accelerated environmental review led by NJT/FRA nearing completion
• On schedule for FEIS/ROD in Spring 2018. Draft EIS published July 2017 available for download at www.hudsontunnelproject.com. Expedited process to be complete in half the time typically needed for projects of this magnitude. Preliminary Engineering led by Amtrak advancing in support of NEPA.
• Financial plan in development, preliminary plan submitted as part of FTA rating package
• $12.7 billion project accepted into project development pipeline for FTA New Starts grant
• Port Authority 10-year Capital Plan includes $2.7 billion commitment to repay federal loans through Gateway Program Development Corporation
• Request for Information issued this summer by Gateway Program Development Corp.
HUDSON TUNNEL PROJECT UPDATE
16 | Amtrak Corporate Planning
HUDSON TUNNEL PROJECT FINANCIAL PLAN
• Construction of new tunnel + rehab of existing North River Tunnel + completion of Hudson Yards Concrete Casing
• $12.7 billion project cost
• Local commitments to date:• $1.9 billion – NJ TRANSIT• $1.9 billion – Port Authority• $1.75 billion – State of NY
• Federal share to consist of:• Amtrak• FRA, FTA and/or other federal
grants
• Construction start: 2019 or sooner
17 | Amtrak Corporate Planning
THE GATEWAY PROGRAM WILL DELIVER…
Preservation and Resiliency
Replacement of century-old critical infrastructure
Preservation of existing NEC service to Penn Station New York
Protection from weather-related and man-made events
Capacity
Roughly double trans-Hudson capacity (approx. 48 trains/hr)
Elimination of two-track bottleneck at busiest point on Northeast Corridor
Redundancy for stable operations