1 February 19, 2016
The Gateway Program and
Hudson Tunnel Project
Northeast Corridor Infrastructure and Investment Development
2
Huge NEC Train Growth at Penn Station Station NY
Penn Station NY Weekday Train
Movements 1976- 2014
156 216 216
358
554 578 147
274
456 52
52
0
200
400
600
800
1000
1200
1400
1976 2001 2014
Amtrak Empire
NJ Transit
LIRR
Amtrak NEC
Note: Movements east and west of Station counted as two trips with exception of LIRR
3
Relying On 2 Tracks From NJ to NY
0
50
100
150
200
250
300
350
400
450
500
550
600
650
700
750
800
TR
AIN
S pe
r DA
Y
VRE
MARC
LIRR
NJT
SEPTA
CSX
NS
MBTA
MN
SLE
P&W
AMTRAK
The NEC narrows to roughly two tracks between Newark, NJ and Penn Station, NY – and accommodates 450 train movements a day.
Portal Bridge Spanning the Hackensack River
4
Leading to an Overcrowded Penn Station NY Crowding
1st, 2nd and 3rd largest commuter rail systems in the nation serve New York City
• PENN STATION NY– 429,000 average weekday passenger trips (FY 2014) • Long Island Railroad – 226,000 trips
• NJ Transit – 174,000 trips
• Amtrak – 29,000 trips
• PLUS NYC Transit - 356,000 avg weekday trips at Penn Station (FY2014)
• 1/2/3 - 185,000 trips
• A/C/E - 171,000 trips • Total station trips have doubled since formation of
commuter agencies.
5
Supported by Assets in Critical Condition
Crumbling benchwall inside Hudson River Tunnel
Portal Bridge demands frequent miter rail maintenance and complete replacement
Sawtooth Bridge is supported by falsework and requires complete replacement
Dock Bridge needs overhaul of electrical and mechanical components
6
Super Storm Sandy Impacts
• Superstorm Sandy forced ~4-day closure of the NEC:
• Inundated substations
• Inundated East River and Hudson River Tunnel systems
• Ongoing damage to internal components requires complete renewal of inundated tunnels.
• Tunnel reconstruction requires closure of each tube for outages of >1 year.
• Rebuilding of the existing Hudson River Tunnel cannot begin until the new Hudson Tunnel is built and commissioned.
8
Gateway Program Principles
Service Preservation and Resiliency • Preserve existing service to Penn Station NY • Rebuild Existing Infrastructure • Provide resiliency / storm protection • Bring to State of Good Repair
Capacity • 100% increase trans-Hudson River • Expansion of Penn Station NY • Build redundancy for stable operations
• Prioritize modular project designs with independent utility.
• Advance elements together as a coherent Program, as permitted by funding.
9
Secaucus Junction
Penn Station Newark
4th Track at Harrison
Sawtooth Bridge
Portal South Bridge
Hudson Tunnel Project
Secaucus Loop
PRESERVATION AND RESILIENCY
• Hudson Yards Concrete Casing • Hudson Tunnel Project, including:
• New Hudson Tunnel, and • Rehab of Existing Hudson River
Tunnel
• Portal North Bridge • Sawtooth Bridge • Highline State of Good Repair
OPERATIONAL CAPACITY IMPROVEMENTS
• Penn Station Southern Expansion • Secaucus Loop • Secaucus Junction Track
Reconfiguration
• Harrison 4th Track • Highline Expansion • Portal South Bridge • Newark Circulation Improvements
Penn Station Southern Expansion
Portal North Bridge
Highline State of Good Repair
Highline Expansion
HY Concrete Casing
10
“Penn South” – More Tracks for More Trains
Penn Station
Expanded Concourse
Existing Tunnel Tracks
New Tunnel Tracks
Moynihan Station
Huds
on R
iver
11
• Expand Penn Station to the South adding new tracks and platforms (yellow)
• Preserve access to future deep cavern HSR station (blue)
• Preserve ability to extend tracks to the East
Expanded Penn Station Concourses
12
First Up … Hudson Tunnel Project
• NEPA Environmental Review and Preliminary Engineering • Expected 2-3 year process to start this year • FRA will act as USDOT Federal Lead Agency • NJ Transit will act as NEPA Manager • Amtrak will manage Preliminary Engineering • Evaluating options for expediting NEPA with FRA and Gateway Development
Corporation
13
Immediate Next Steps: Portal North Bridge
Portal North Bridge rendering
• Portal North Bridge has record of decision (ROD) from FRA and has completed final design.
• Exploring funding and financing scenarios with New Jersey, New York, Federal, and Amtrak participation.
• Early Action Contract # 1 for relocation of utilities and other civil works using $16M in TIGER grant to NJ TRANSIT awaiting application to FRA.
• Real Estate requirement approximately 15 acres at an estimated value of $7M (2013 $’s)
14 Amtrak Northeast Corridor Infrastructure Investment and Development 14
Western Rail Yard 60% Final Design
Concrete Casing Phase I - Complete
11th
Ave
Ext
. U
nder
Con
stru
ctio
n
30th St & 12th Ave Shaft Hudson Tunnel Project
• 60% Final Design was completed in May 2015. • Coordination with Related Companies to incorporate or separate the developer’s
overbuild from the concrete casing and expedite final design
Immediate Next Steps: Hudson Yard Phase III
15
• Complete replacement of existing structure required
• Environmental and historic preservation analysis currently in progress.
• Categorical Exclusion / Section 4(f) / MOA to be submitted to FRA in June 2016.
Immediate Next Steps: Sawtooth Bridge
16
• Port Authority, Amtrak, USDOT, NJ Transit, NYS, and Senators Schumer and Booker staff working together to launch the Gateway Development Corporation
• Key issues include: – Governance – Team Building – Funding and Finance Plan – Early investments
Gateway Development Corporation