The Future of Sludge Disposal: A Fresh Perspective after Sandy Jim Meehan – Executive Director...
-
Upload
jocelin-pitts -
Category
Documents
-
view
212 -
download
0
Transcript of The Future of Sludge Disposal: A Fresh Perspective after Sandy Jim Meehan – Executive Director...
The Future of Sludge Disposal: A Fresh Perspective after Sandy
Jim Meehan – Executive Director
Rahway Valley Sewerage Authority
Recent Plant UpgradeRecently completed a plant expansion, including:
• Increased pumping capacity based on 100 year storm
• Raised grade along river approximately 10 feet
• Upgraded backup electric including a Cogeneration facility, allowing us to go on “Island Mode” for 16 days during Superstorm Sandy
(Approximate Construction Cost: $170M)
Storm Response Considerations• Additional Storage Tanks; think outside the
box:• Utilize offline primary or secondary tanks• Temporarily increase SVI in secondary
• Plan for out of state disposal sites• Modify bid specifications for sludge
disposal/hauling to include alternate
Review Possible Last Resort Options• Disposal at garbage incinerator facilities
– Establish which facilities are available to a plant– Review any technology limitations to accepting biosolids.– Review permit barriers and weather emergency approvals
would be possible. Begin discussions with appropriate agencies.
• Onsite open air storage of dried/dewatered biosolids
– Establish a location suitable for storage– Review storm water protection measures required
Conclusions:• Advanced preparation will save time during
emergency:» Plan a temporary thickening/dewatering scenario
• Involve vendors early to establish a plan of action and have the required utilities and piping connections available
» Review options for power generation and establish backup locations where temporary generators can be connected to critical equipment• May not be able to use plant distribution. Have equipment
and/or building specific utility connection options.