The Formwork Experts 10/2010 en-GB 999706002 User information Doka dam formwork 9706-201-01

Transcript of The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam...

Page 1: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

The Formwork Experts

10/2010

en-GB999706002

User information

Doka dam formwork

9706-201-01

Page 2: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

2 999706002 - 10/2010

Introduction User information Doka dam formwork

The Formwork Experts

Introduction

© by Doka Industrie GmbH, A-3300 Amstetten

Page 3: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork Introduction

3999706002 - 10/2010

The Formwork Experts

Contents4 Introduction4 Elementary safety warnings6 Eurocodes at Doka7 Product description

8 Dam formwork D158 Dam formwork D15 K and D15/39 System overview

10 Areas of use11 Dam formwork D15 K12 Dam formwork D15/3

14 Dam formwork D2214 Dam formwork D22 K and F15 System overview16 Areas of use17 Dam formwork D22 - retractable and tiltable

18 General remarks18 Starting up20 Striking, lifting and erecting the formwork22 Starter-block formwork23 Anchoring on the structure26 Platform configurations28 Plumbing & aligning the formwork30 Resetting by crane32 Possible formwork systems34 Structural design35 Doka service offerings

36 Component overview

Page 4: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

4 999706002 - 10/2010

Introduction User information Doka dam formwork

The Formwork Experts

IntroductionElementary safety warnings

User target groups● This User Information booklet (Method Statement) is

aimed at everyone who will be working with the Doka product or system it describes. It contains informa-tion on the standard design for setting up this sys-tem, and on correct, compliant utilisation of the sys-tem.

● All persons working with the product described herein must be familiar with the contents of this man-ual and with all the safety instructions it contains.

● Persons who are incapable of reading and under-standing this booklet, or who can do so only with dif-ficulty, must be instructed and trained by the cus-tomer.

● The customer is to ensure that the information mate-rials provided by Doka (e.g. User Information book-lets, Instructions for Assembly and Use, Operating Instruction manuals, plans etc.) are available to all users, and that they have been made aware of them and have easy access to them at the usage location.

● In the relevant technical documentation and form-work utilisation plans, Doka shows the workplace safety precautions that are necessary in order to use the Doka products safely in the usage situations shown. In all cases, users are obliged to ensure compliance with national OH&S (occupational health and safety) rules throughout the entire project and to take appro-priate additional or alternative workplace safety pre-cautions where necessary.

Hazard assessment● The customer is responsible for drawing up, docu-

menting, implementing and continually updating a hazard assessment at every job-site. This document serves as the basis for the site-spe-cific hazard assessment, and for the instructions given to users on how to prepare and utilise the sys-tem. It does not substitute for these, however.

Remarks on this document● This User Information booklet can also be used as a

generic method statement or incorporated with a site-specific method statement.

● Many of the illustrations in this booklet show the situation during formwork assembly and are therefore not always complete from the safety point of view.Any safety accessories not shown in these illustra-tions must still be used by the customer, in accord-ance with the applicable rules and regulations.

● Further safety instructions, especially warnings, will be found in the individual sections of this document!

Planning● Provide safe workplaces for those using the form-

work (e.g. for when it is being erected/dismantled, modified or repositioned etc). It must be possible to get to and from these workplaces via safe access routes!

● If you are considering any deviation from the details and instructions given in this booklet, or any application which goes beyond those described in the booklet, then revised static cal-culations must be produced for checking, as well as supplementary assembly instructions.

Rules applying during all phases of the assignment:● The customer must ensure that this product is

erected and dismantled, reset and generally used for its intended purpose under the direction and super-vision of suitably skilled persons with the authority to issue instructions. These persons' mental and physical capacity must not in any way be impaired by alcohol, medicines or drugs.

● Doka products are technical working appliances which are intended for industrial/commercial use only, always in accordance with the respective Doka User Information booklets or other technical docu-mentation authored by Doka.

● The stability of all components and units must be ensured during all phases of the construction work!

● The functional/technical instructions, safety warn-ings and loading data must all be strictly observed and complied with. Failure to do so can cause acci-dents and severe (even life-threatening) damage to health, as well as very great material damage.

● Fire-sources are not permitted anywhere near the formwork. Heating appliances are only allowed if properly and expertly used, and set up a safe dis-tance away from the formwork.

● The work must take account of the weather condi-tions (e.g. risk of slippage). In extreme weather, steps must be taken in good time to safeguard the equipment, and the immediate vicinity of the equip-ment, and to protect employees.

● All connections must be checked regularly to ensure that they still fit properly and are functioning cor-rectly. It is very important to check all screw-type connec-tions and wedge-clamped joins whenever the con-struction operations require (particularly after excep-tional events such as storms), and to tighten them if necessary.

Page 5: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork Introduction

5999706002 - 10/2010

The Formwork Experts

Assembly● The equipment/system must be inspected by the

customer before use, to ensure that it is in suitable condition. Steps must be taken to rule out the use of any components that are damaged, deformed, or weakened due to wear, corrosion or rot.

● Combining our formwork systems with those of other manufacturers could be dangerous, risking damage to both health and property. If you intend to combine different systems, please contact Doka for advice first.

● The assembly work must be carried out by suitably qualified employees of the client's.

● It is not permitted to modify Doka products; any such modifications constitute a safety risk.

Erecting the formwork● Doka products and systems must be set up in such

a way that all loads acting upon them are safely transferred!

Pouring● Do not exceed the permitted fresh-concrete pres-

sures. Excessively high pouring rates lead to form-work overload, cause greater deflection and risk causing breakage.

Striking the formwork● Do not strike the formwork until the concrete has

reached sufficient strength and the person in charge has given the order for the formwork to be struck!

● When striking the formwork, never use the crane to break concrete cohesion. Use suitable tools such as timber wedges, special pry-bars or system features such as Framax stripping corners.

● When striking the formwork, do not endanger the stability of any part of the structure, or of any scaf-folding, platforms or formwork that is still in place!

Transporting, stacking and storing● Observe all regulations applying to the handling of

formwork and scaffolding. In addition, the Doka slinging means must be used - this is a mandatory requirement.

● Remove any loose parts or fix them in place so that they cannot be dislodged or fall free!

● All components must be stored safely, following all the special Doka instructions given in the relevant sections of this User Information booklet!

Regulations; industrial safety● Always observe all industrial safety regulations and

other safety rules applying to the application and uti-lisation of our products in the country and/or region in which you are operating.

Instruction as required by EN 13374:● If a person or object falls against, or into, the edge

protection system and/or any of its accessories, the edge protection component affected may only con-tinue in use after it has been inspected and passed by an expert.

Maintenance● Only original Doka components may be used as

spare parts. Repairs may only be carried out by the manufacturer or authorised facilities.

Symbols usedThe following symbols are used in this booklet:

MiscellaneousWe reserve the right to make alterations in the interests of technical progress.

Important noteFailure to observe this may lead to malfunc-tion or damage.

CAUTION / WARNING / DANGERFailure to observe this may lead to material damage, and to injury to health which may range up to the severe or even life-threaten-ing.

InstructionThis symbol indicates that actions need to be taken by the user.

Sight-checkIndicates that you need to do a sight-check to make sure that necessary actions have been carried out.

TipPoints out useful practical tips.

ReferenceRefers to other documents and materials.

Page 6: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

6 999706002 - 10/2010

Introduction User information Doka dam formwork

The Formwork Experts

Eurocodes at DokaIn Europe, a uniform series of Standards known as Eurocodes (EC) was developed for the construction field by the end of 2007. These are intended to provide a uniform basis, valid throughout Europe, for product specifications, tenders and mathematical verification.The EC are the world's most highly developed Stand-ards in the construction field.In the Doka Group, the EC are to be used as standard from the end of 2008. They will thus supersede the DIN norms as the "Doka standard" for product design.

The widely used "Permissible stress design" (compar-ing the actual stresses with the permissible stresses) has been superseded by a new safety concept in the EC.The EC contrast the actions (loads) with the resistance (capacity). The previous safety factor in the permissible stresses is now divided into several partial factors. The safety level remains the same!

Comparison of the safety concepts (example)

Ed Design value of effect of actions (E ... effect; d ... design) Internal forces from action Fd (VEd, NEd, MEd)

Rd Design value of the resistance (R ... resistance; d ... design) Design capacity of cross-section (VRd, NRd, MRd)

Fd Design value of an actionSteel: Rd =

Rk Timber: Rd = kmod ·Rk

Fd = γF · Fk γM γM

(F ... force)Fk Characteristic value of an action

"actual load", service load (k ... characteristic) e.g. dead weight, live load, concrete pressure, wind

Rk Characteristic value of the resistance e.g. moment resistance to yield stress

γF Partial factor for actions (in terms of load; F ... force) e.g. for dead weight, live load, concrete pres-sure, wind Values from EN 12812

γM Partial factor for a material property (in terms of material; M...material) e.g. for steel or timber Values from EN 12812

kmod Modification factor (only for timber – to take account of the moisture and the duration of load action) e.g. for Doka beam H20 Values as given in EN 1995-1-1 and EN 13377

Ed

Rd

Permissible stress design EC/DIN concept

Factual≤ Fpermissible Ed≤ Rd

A Utilisation factor

60 [kN]

60<70 [kN]

115.5 [kN]

� ~ 1.65

Fyield

Fpermissible

Factual

9801

3-10

0

A

90 [kN]

115.5 [kN]

90<105 [kN]

Rk

Rd

Ed

�M

= 1.1

�F

= 1.5

9801

3-10

2

A

The "permissible values" communicated in Doka documents (e.g.: Qpermissible = 70 kN) do not correspond to the design values (e.g.: VRd = 105 kN)!➤ Avoid any confusion between the two!➤ Our documents will continue to state the per-

missible values. Allowance has been made for the following par-tial factors: γF = 1.5 γM, timber = 1.3 γM, steel = 1.1 kmod = 0.9In this way, all the design values needed in an EC design calculation can be ascertained from the permissible values.

Page 7: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork Introduction

7999706002 - 10/2010

The Formwork Experts

Product description

Doka dam formwork - the formwork system for mass concrete struc-turesOn mass concrete structures, it is not normally feasible to place form-ties through to the opposing formwork. For this reason, the pressure of the fresh concrete has to be transferred into the previous concrete block. Doka dam formwork ensures that the forces which occur here are transferred safely and reliably.Areas of use:● Dams and barrages● Run-of-river power stations● Navigation locksThe formwork and dam scaffold are lifted to the next casting section in one single crane cycle.The dam scaffold can be fitted with various different formwork systems, e.g.:● Large-area formwork Top50● Framed formwork● Steel formwork

2 systemsFor optimum adaptation to every construction project, Doka offers two different dam formwork systems, both of which always use the same method of working:

Dam formwork D15

● Dam formwork D15 K- for block heights of up to 3.0 m- formwork is tiltable

● Dam formwork D15/3- optimised for a block height of 3.0 m- formwork is tiltable, and can also be modified to

make it retractable

Dam formwork D22- for block heights of between 3.0 and 4.0 m

● Dam formwork D22 K- formwork is tiltable

● Dam formwork D22 F- formwork is retractable

☞ The Doka dam formwork system is extremely flexible. For this reason, detailed planning and static calculations are required for every single project.

for anchor tensile forces of up to 150 kN

for anchor tensile forces of up to 220 kN

Page 8: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

8 999706002 - 10/2010

Dam formwork D15 User information Doka dam formwork

The Formwork Experts

Dam formwork D15Dam formwork D15 K and D15/3Doka dam formwork D15 is used for forming block heights of up to 3 m. The Dam scaffold D15 can sus-tain anchor tensile forces of up to 150 kN.The formwork can be tilted backwards to leave enough space for preparing the suspension points.Doka dam formwork D15 is easy to adapt to sloping wall surfaces and to kinks in the walls.

2 versions

Dam formwork D15 KWhen tilted backwards, the formwork leaves plenty of space for preparing the suspension points. The plat-forms are a generous 1.7 m wide, making it easy to operate the spindle strut.

Dam formwork D15/3The Dam formwork D15/3 is the optimum dam scaffold for block heights of 3.0 m. Its 2.2 m wide platforms allow great freedom of movement.

Product features● anchor tensile force: 150 kN● easy to anchor● formwork elements are freely selectable● formwork is tiltable, and can also be modified to

make it retractable● easy angle adjustment● accurate, easy-to-use height adjustment● pre-assembly of platform decking is possible● generously sized workspace and access passage● formwork is pressed onto the previous casting sec-

tion quickly and securely● only a small number of different parts

Dam formwork D15 K● block heights of up to 3.0 m● platform width 1.7 m

Dam formwork D15/3● optimised for a block height of 3.0 m● platform width 2.2 m

9706-214-01

The Dam formwork D15/3 can easily be modi-fied to equip it with a travelling unit. This makes the formwork retractable as well.

Page 9: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork Dam formwork D15

9999706002 - 10/2010

The Formwork Experts

System overview● Cantilever bracket D15 K (A)

The cantilever bracket constitutes the working plat-form and the climbing scaffold on which the form-work is stood. The pressure of the fresh concrete is transferred by way of the suspension point and the supporting profile.

● Cantilever bracket D15/3 (B) This cantilever bracket is designed as standard to permit the formwork to be tilted backwards. Retrofit-ting the Retraction set D15 (K) makes it possible for the formwork to be travelled, as well as just tilted.

● Vertical waling D15 3.00 m U120 (C) The vertical waling is for holding and adjusting the formwork element, and for transferring the concrete forces into the cantilever bracket.

● Spindle strut D15 3.00 m (D) This is bolted in between the cantilever bracket and the vertical waling. It has the job of transferring the concrete forces, and is also used for plumbing and striking the formwork elements.

● Swivel bearing plate D15 or D15 S (E) The swivel bearing plate makes it possible to con-nect the vertical waling firmly and tightly to the canti-lever bracket. Thanks to its articulated joint, the ver-tical waling can be inclined forward and back without difficulty.- D15: designed to be used with timber-beam form-

work and framed formwork- D15 S: designed to be used with framed formwork

and steel formwork● Suspension profile D15/D22 (G)

The suspension profile is bolted onto the vertical pro-file of the cantilever brackets.

● Screw-on access bracket MF75 (H) The Screw-on access bracket MF75 is a universal working bracket.- can be used as a pouring platform (fastened to the

vertical waling)- and as a suspended platform (fastened to the sus-

pension profile)

9706-213-01

A

D

E

G

H

H

B

C

K

Page 10: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

10 999706002 - 10/2010

Dam formwork D15 User information Doka dam formwork

The Formwork Experts

Areas of useThe flexibility of Doka dam formwork D15 gives it a very wide spectrum of use. It can master all manner of differ-ent wall sequences:

Straight walls

Forward/rear-inclined walls

Kink in wall

Note:The max. angle of inclination α will depend on the project, and in particular on the constructional height of the formwork system that is being used.

A A project-specific check should be made to determine whether a back-stay is needed

☞ Important note:The system can be used at a forward or rear-ward inclination of up to max. 45° with no need to modify the suspension points. However, where walls have a greater inclination than 45°, this must be co-ordinated and agreed with Doka Engineering.

9706-203-01

9706-203-04

A

9706-203-05

9706-203-02

A

9706-203-03

Page 11: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork Dam formwork D15

11999706002 - 10/2010

The Formwork Experts

Dam formwork D15 K

TiltableThe formwork can be tilted back to leave plenty of space for preparing the suspension point.

9706-216-01

Page 12: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

12 999706002 - 10/2010

Dam formwork D15 User information Doka dam formwork

The Formwork Experts

Dam formwork D15/3The D15/3 is tiltable as standard. The Dam formwork D15/3 can easily be modified to equip it with a travelling unit. This makes the formwork retractable as well.

Tiltable

Modified to be retractable

a ... e.g. with Large-area formwork Top50: max. 45 cm

Travelling unit9706-204-01

Retraction set D15, consisting of: A ... Travelling profile D15 B ... Drive shaft D15 C ... Two Anti-liftout guards D15, one mounted on either side of the Swivel bearing plate

D Ratchet MF 3/4" SW50E Swivel bearing plate D15

9706-204-02

a

9706-223-01

A

D

BC

9706-222-01B

9706-224-01

E

C

Page 13: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork Dam formwork D15

13999706002 - 10/2010

The Formwork Experts

Page 14: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

14 999706002 - 10/2010

Dam formwork D22 User information Doka dam formwork

The Formwork Experts

Dam formwork D22Dam formwork D22 K and FDoka dam formwork D22 is used for forming block heights of up to 4.0 m. The high load-bearing capacity of the dam scaffold enables this formwork to sustain anchor tensile forces of up to 220 kN.

2 versions

Dam formwork D22 K (tiltable)When tilted backwards, the formwork leaves plenty of space for preparing the suspension points. The plat-forms are a generous 1.9 m wide, making it easy to operate the spindle strut. There is also enough space for operators to pass behind the spindle strut.

Dam formwork D22 F (retractable)The formwork can be retracted. This makes it easier to clean and maintain the form-ply, to attach fittings and to place reinforcements. The generous platform width of 2.40 m permits very great freedom of movement.

Product features● block heights of up to 4.0 m● anchor tensile force: 220 kN● easy to anchor● easy angle adjustment● accurate, easy-to-use height adjustment● pre-assembly of platform decking is possible● generously sized workspace and access passage● formwork is pressed onto the previous casting sec-

tion quickly and securely● only a small number of different parts

Dam formwork D22 K● formwork is tiltable● platform width 1.9 m

Dam formwork D22 F● The retractable formwork makes it possible to

- clean the formwork even where there is densely placed reinforcement

- Reinforcement work is carried out under the pro-tection of the formwork

- Mounting and stripping box-outs● Platform width 2.4 m

9706-200-01

Page 15: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork Dam formwork D22

15999706002 - 10/2010

The Formwork Experts

System overview● Cantilever bracket D22 K (A) or F (B)

The cantilever bracket constitutes the working plat-form and the climbing scaffold on which the form-work is stood. The pressure of the fresh concrete is transferred by way of the suspension point and the supporting profile.- D22 K: formwork is tiltable- D22 F: formwork is retractable

● Travelling profile D22 (C) This is used together with the Cantilever bracket D22 F. The travelling profile is bolted onto the swivel bearing plate. Together with the drive pinion of the cantilever bracket, it makes it possible for the entire formwork unit to be moved in and out very smoothly and easily.

● Vertical waling D22 3.00m U160 or 4.00m (D) The vertical waling is for holding and adjusting the formwork element, and for transferring the concrete forces into the cantilever bracket.

● Spindle strut D22 3.00m or 4.00m (E) This is bolted in between the cantilever bracket and the vertical waling. It has the job of transferring the concrete forces, and is also used for plumbing and striking the formwork elements.

● Swivel bearing plate D22 or D22 S (F) The swivel bearing plate makes it possible to con-nect the vertical waling firmly and tightly to the canti-lever bracket. Thanks to its articulated joint, the ver-tical waling can be inclined forward and back without difficulty.- D22: designed to be used with timber-beam form-

work and framed formwork- D22 S: designed to be used with framed formwork

and steel formwork● Suspension profile D15/D22 (G)

The suspension profile is bolted onto the vertical pro-file of the cantilever brackets.

● Screw-on access bracket MF75 (H) The Screw-on access bracket MF75 is a universal working bracket.- can be used as a pouring platform (fastened to the

vertical waling)- and as a suspended platform (fastened to the sus-

pension profile)

9706-212-01

A B

C

D

E

F

G

H

H

Page 16: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

16 999706002 - 10/2010

Dam formwork D22 User information Doka dam formwork

The Formwork Experts

Areas of useThe flexibility of Doka dam formwork D22 gives it a very wide spectrum of use. It can master all manner of differ-ent wall sequences:

Straight walls

Forward/rear-inclined walls

Kink in wall

A A project-specific check should be made to determine whether a back-stay is needed

☞ Important note:The system can be used at a forward or rear-ward inclination of up to max. 45° with no need to modify the suspension points. However, where walls have a greater inclination than 45°, this must be co-ordinated and agreed with Doka Engineering.

9706-205-01

9706-205-04

A

9706-205-05

9706-205-02

A

9706-205-03

Page 17: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork Dam formwork D22

17999706002 - 10/2010

The Formwork Experts

Dam formwork D22 - retractable and tiltable

D22 F - retractablePlenty of space for convenient working.

The retractable forming unit is easy to operateBy turning the Ratchet MF 3/4" SW50, which is placed against the drive pinion, the operator can move the entire formwork unit back and forward.

D22 F without travelling unit - tiltableDam formwork D22 F can also be used without a trav-elling unit. This leaves a wider working platform.

D22 K - tiltablea ... e.g. with Large-area form-

work Top50: max. 65 cm

A Cantilever bracket D22 FB Travelling profile D22C Ratchet MF 3/4" SW50

9706-206-01 9706-206-02

a

C

9706-206-04A

B

9706-206-05

9706-206-03

Page 18: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

18 999706002 - 10/2010

General remarks User information Doka dam formwork

The Formwork Experts

General remarksStarting up

First casting sectionThe system components of the dam formwork can be used right from the first casting section.➤ Use the starter-block unit (A) instead of the canti-

lever bracket.The loads are transferred by way of e.g. pigtail anchors (B) embedded in the base slab.

Second casting section➤ Suspend the pre-assembled scaffold unit (C) , con-

sisting of cantilever brackets and platform decking➤ Hoist the formwork onto the scaffold and fix it in

place.

Instead of the starter-block unit it is also possi-ble to use Doka supporting construction frames

a

H

bc9706-207-01

BA

a

H

f9706-207-02

d

e

a

C

Page 19: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork General remarks

19999706002 - 10/2010

The Formwork Experts

Third casting section➤ Add the suspended platform (D) .

H ... Block heighta ... Distance between top of poured concrete and anchoring pointb ... Width of starter-block unit + vertical walingc ... Constructional height of formworkd ... Distance between suspension point and pressure strute ... Formwork overlapf ... Width of bracket

System dimensions [cm]Type of bracket

D15 K D15/3 D22 K D22 FH up to 300 300 300-400 300-400a 35b 147 147 168 168c depends on the formwork system being usedd 203 253 253 253e 10f 180 228 202 250

9706-207-03

D

Page 20: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

20 999706002 - 10/2010

General remarks User information Doka dam formwork

The Formwork Experts

Striking, lifting and erecting the formworkThe formwork elements, dam scaffolds, pouring plat-forms and suspended platforms are firmly intercon-nected. They are lifted and repositioned as a complete unit, in one crane cycle. This reduces the repositioning time, and thus the crane times.

Striking➤ Remove the Cone screw B 7cm from the positioning-

point.➤ Release the pressure wedges.➤ Detach the formwork element from the concrete by

turning the spindle struts, and tilt it back (or retract it).➤ Tighten the pressure wedges➤ Screw a Cone screw B 7cm into the Universal climb-

ing cone. The next suspension point is now ready for use.

➤ Remove the Universal climbing cone (working from the suspended platform).

How to lift

➤ Attach a crane-cable hook to the suspension bolt of the vertical waling.

➤ Release the connection bolt on the cantilever bracket.

➤ Lift the dam scaffold, together with the formwork ele-ment, and suspend it from the prepared suspension points.

➤ Use connection bolts to secure the cantilever bracket against accidental lift-out.

➤ Detach the crane-cable hook.

9706-208-01

WARNING➤ "Passenger transportation" is forbidden!➤ Remove any loose parts from the scaffold

and formwork before lifting.

9706-208-02

Page 21: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork General remarks

21999706002 - 10/2010

The Formwork Experts

Lifting past overhanging surfacesThe (project-specific) overhanging lifting device makes it possible to lift and reposition dam formwork safely where overhanging concrete surfaces are being formed.Variable hoisting points on the overhanging lifting device enable the entire unit to be held at the required angle during lifting.

Erecting the formwork➤ Release the pressure wedges.➤ Line-and-level the formwork element with the spindle

struts and adjusting spindles.➤ Attach pressure wedges to press the formwork ele-

ment against the previous casting section.➤ Fasten positioning anchors to the formwork.

9706-208-04

9706-208-03

Page 22: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

22 999706002 - 10/2010

General remarks User information Doka dam formwork

The Formwork Experts

Starter-block formworkThe system components of the dam formwork can be used right from the first casting section. However, the starter-block unit (A) is used here instead of the can-tilever bracket.

Anchoring in the base slab

Note:The back-stay (G) makes it easier to line-and-level the formwork.A project-specific check must be made to determine whether the back-stay is also required for structural design reasons.

● The loads from the diagonal anchors are transferred via anchor walings (E) .

● The tie-rod 15.0mm and the super-plate 15.0 (F) together secure the anchor waling so that it cannot tilt or slip out of position.

● For each starter-block unit, two anchors are each placed 15 cm either side of the vertical axis of the starter-block unit.Exception: If the load-bearing capacity is sufficient for 1 anchor per starter-block unit, the anchors on each unit must be placed symmetrically.

Instead of the starter-block unit it is also possi-ble to use Doka supporting construction frames

☞ As a basic rule: The anchoring arrangements for the starter-block formwork are always dimensioned on a project-specific basis.

Formwork system Dimension X Anchor inclina-tion α

e.g. Large-area formwork Top50 40.7 cm45°

e.g. framed formwork Framax 30.6 cm

9706-207-04X

AB

C

G

A Starter-block unitB Pigtail anchorC She-boltD Super-plateE Anchor walingF Tie-rod 15.0mm + Super-plate 15.0

For more information on anchoring in the base slab, see the User Information booklet "Doka supporting construction frames".

9706-220-01

E

B D

C

F

A

Page 23: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork General remarks

23999706002 - 10/2010

The Formwork Experts

Anchoring on the structure

Positioning point and suspension pointComponents:

Both the positioning points and the suspension points are prepared using one single type of cone, the Univer-sal climbing cone (A) .The Cone screw B 7cm (C) also fulfils 2 functions:● On the positioning point - for fastening the Universal

climbing cone.● On the suspension point - as a safe means of sus-

pending the cantilever bracket.Preferably, pigtail anchors (D) are used, or - depend-ing on the characteristics of the structure - stop-anchors (F) .

Dimensioning the suspension point

Preparing the positioning point and suspension point

Tools needed:● Reversible ratchet 3/4"● Spanner for Universal climbing cone 15.0/20.0● Box nut 50 3/4"(for Cone screw B 7cm)

A Universal climbing coneB Sealing sleeve K (expendable anchoring component)C Cone screw B 7cmD Pigtail anchor (expendable anchoring component)E Depth markF Stop-anchor (expendable anchoring component)

The required cube compressive strength of the con-crete at the time of loading must be specified sepa-rately for each project by the structural designer. It will depend on the following factors:● the tensile force actually occurring● length of stop-anchor or pigtail anchor● distance from edgeThe introduction of the forces, the transfer of these forces into the structure, and the stability of the overall construction, must all be verified by the structural designer.The required cube compressive strength fck,cube,current must be at least 10 N/mm2, however.On dam projects using concretes that have been spe-cifically tailored to the project, the required length of the pigtail anchors must be determined in on-site trials (regarding concrete strength, type of concrete etc.).

9751-237-01

A

B

C

E

D

F

E

☞ Important note:ONLY use "Form-tie system 20.0" or "Form-tie system 26.5"!Due to the high loads imposed on the suspen-sion points by dam formworks, the "Form-tie system 15.0" is not suitable!

☞ In standard applications using the dam form-work, the shear forces occurring at the suspen-sion point are very small and so do not need to be allowed for.

WARNING- against not screwing the pigtail anchor or stop anchor far enough into the Universal climbing cone.This may subsequently lead to reduced load-bearing capacity and to the failure of the sus-pension point - resulting in injury and damage.➤ Always screw in components until they fully

engage (i.e. up to the depth mark).

CAUTION➤ For the positioning point and suspension

point, ONLY use Cone screws B 7 cm (head of screw is red, to indicate its high load-bear-ing capacity)!

➤ The axis of the cantilever bracket and the axis of the Universal climbing cone must align - maximum angle-deviation 2°.

➤ Every time the Universal climbing cones are used, fit them with new sealing sleeves first.

WARNINGSensitive rod steel!➤ Never weld or heat tie-rods.➤ Tie rods that are damaged or have been

weakened by corrosion or wear must be withdrawn from use.

➤ Only use approved tie-rods.

Page 24: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

24 999706002 - 10/2010

General remarks User information Doka dam formwork

The Formwork Experts

Positioning pointwith hole drilled through the form-ply➤ Fasten a packing plate (G) (e.g. Dokaplex 15 mm) to

the form-ply (position as per project plan).➤ Drill a diam. 30 mm hole in the form-ply (position as

shown in the project plan).➤ Push the Cone screw B 7cm (C) through the form-

ply, screw it into the Universal climbing cone (A) and tighten it firmly.

➤ Screw the Pigtail anchor (D) into the Universal climb-ing cone (A) , until it engages (up to the depth mark (E) ).

a ... 35 - 45 mm

Note:Universal climbing cones are supplied with Sealing sleeves K (B) . Every time the Universal climbing cones are used again, fit them with new sealing sleeves first!

Form-ply protectionThe "Form-ply protector for cone 15.0" protects the form-ply from damage around the positioning-point. This is a particular advantage for formwork with high numbers of repeat uses.Possible thicknesses of form-ply: 18 - 27 mmIn order to fit the Form-ply protector, a 46 mm diam. hole must be drilled in the form-ply first.

If necessary, the Form-ply protector for cone 15.0 can be closed off with a Ribbed plug d38 (included with product).

● The axis of the universal climbing cone must be at right-angles to the surface of the concrete – maximum angle of deviation: 2°.

● The depth mark on the pigtail anchor or stop-anchor must be right up against the Universal climbing cone = must be screwed in to the full depth.

● The pigtail anchor must be facing down-wards

☞ Important note:The cone-fixing method that involves drilling through the form-ply is the one that is most suit-able for the working conditions encountered on dam construction sites.If the large size of the drilled hole makes it impracticable to use the Cone screw B 7cm for the positioning-point, (e.g. if the suspension points are often not in the same position as in the previous casting section), then the Posi-tioning clamp M30 must be used (hole diam. = 9 mm).The cone should only be fixed with the Posi-tioning disc M30 in exceptional situations! However, in this case additional precautions must be taken to ensure that it is not dislodged from its exact installation location during pour-ing!

a

9706-209-01

D AEG

C

B

A Form-ply protector for cone 15.0 (width-across 70 mm)B Universal climbing coneC Cone screw B 7cm

B

C

A

9706-230-01

Tr768-202-01

Page 25: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork General remarks

25999706002 - 10/2010

The Formwork Experts

Before pouring➤ Check all positioning points and suspension points

once again.

Repeat useUniversal climbing cones are supplied with Sealing sleeves K (B) . Every time the Universal climbing cones are used again, fit them with new sealing sleeves first!

Suspension point➤ Screw the Cone screw B 7cm into the Universal

climbing cone until it engages, and tighten it firmly. A tightening torque of 100 Nm (20 kg assuming a ratchet-length of approx. 50 cm) is sufficient.

Suspending and securing the canti-lever bracket➤ Suspend the cantilever bracket (H) from the Cone

screw B 7cm (C) of the finished suspension point.➤ Push the connection bolt (I) into the cantilever

bracket, at 90° to the platform decking, until it engages.

➤ Turn the connection bolt (I) down onto the platform deck.The cantilever bracket is now secured against acci-dental lift-out.

Ensure that control-dimension b = 30 mm!

9706-209-03

b

C

A

The connection bolt must be in the horizontal!

9706-209-05H

C

I

Page 26: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

26 999706002 - 10/2010

General remarks User information Doka dam formwork

The Formwork Experts

Platform configurationsThe modular "building-set" principle also gives wide scope for different ways of combining and using plat-forms. The pouring platform and suspended platform are both assembled using the same screw-on access bracket.

Pouring platformFor reinforcement and concrete-placing work.The Screw-on access bracket MF75 is attached directly to the vertical waling.Platform width = 75 cm.

Close-up showing how the Screw-on access bracket MF75 is fastened to the vertical waling

Working platformFor manipulating the formwork elements.

9706-200-02

9706

-227

-01

9706-200-03

Page 27: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork General remarks

27999706002 - 10/2010

The Formwork Experts

Suspended platformFor removing the Cone screw B 7cm, for grouting the cone holes and for doing finishing-work on the con-crete.The Screw-on access bracket MF75 is also used here, in the same way as on the pouring platform.Platform width = 75 cm.

Close-up showing how the Screw-on access bracket MF75 is fastened to the Suspension profile D15/D22

Adjusting the inclination / widening the platformUsing the Swivel plate MF, the inclination of the plat-forms can be incrementally adjusted, and the working platform can be widened.

e.g. on working platforms:

Manhole B 70/60cmPassage units provide access to (and between) various platform levels, for instance between the pouring plat-forms, main platforms and suspended platforms.

● Passage units are installed in the platform decking.● Clear opening in passage unit: 700x600 mm● Position the passage units so that the ladders can be

stood on alternate sides.

9706-200-04

9706

-228

-01

☞ Put up safety netting in the ladder and manhole zone, as required by the applicable regulations.

A Passage unit

9706-219-01

30°20°

10°0°

10°20°

30°

9706-218-02

9706-217-01

A

Page 28: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

28 999706002 - 10/2010

General remarks User information Doka dam formwork

The Formwork Experts

Plumbing & aligning the formwork

Adjusting the formworkIn order to permit exact adjustment of the formwork ele-ments in relation to one another and to the structure, they are adjustable in both the vertical and the horizon-tal.

Tools needed:● Hammer● Reversible ratchet 1/2"● Box nut 24 1/2" and● Fork wrench 22/24 (for the threaded joins on the

adjusting spindles)

Preparing the adjusting operation➤ Release the pressure wedge (A) .

➤ Detach the formwork from the concrete.➤ Loosen the Waling-to-bracket holder D22 (B) with

a blow of the hammer.

Length adjustment➤ Push the formwork to either side.

☞ To make it possible to compensate for any deformations during pouring, the formwork should be adjusted with a forward inclination.The extent of this forward inclination (see project plan) will depend on the following fac-tors:● Block height● Pressure of the fresh concrete● Influence width per parallel frame section

9706-200-05

A

9706-210-01

B

9706-215-01

Page 29: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork General remarks

29999706002 - 10/2010

The Formwork Experts

Height and angle adjustmentThe adjusting spindles (C) permit a vertical adjust-ment range of approx. 150 mm. Also, the adjusting spindles can be re-mounted in different holes in the grid of fixing holes on the vertical waling (D) .

Height adjustment➤ Turn both adjusting spindles.

Side angle adjustment➤ Only turn one adjusting spindle.

Ending the adjusting operation➤ Tightly clamp the Waling-to-bracket holders D22

again.

Press the formwork to the concreteFor clean, exact concrete surfaces and transitions, the formwork element must be pressed very tightly against the previous section.This can be done quickly and easily with the pressure wedge of the swivel bearing plate.➤ After adjusting the formwork elements, tighten the

pressure wedges (A) .This presses the formwork element up against the previously cast section.

C

D

9706-210-02

9706-215-03

9706-215-02

CAUTIONThere is a risk of the formwork tipping over in high winds.➤ If high wind speeds are likely, and when

work finishes for the day or before prolonged work-breaks, always take extra precautions to fix the formwork in place.

Suitable precautions: Move the formwork up against the concrete and wedge it firmly against the concrete.

For more information (wind loads etc.) see the section headed "Vertical and horizontal loads" in the Doka Calculation Guide.

9706-200-05

A

Page 30: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

30 999706002 - 10/2010

General remarks User information Doka dam formwork

The Formwork Experts

Resetting by crane

β ... max. 30°

☞ Important note:● Observe all regulations applying to the oper-

ation of cranes where higher wind speeds are experienced.

● Only fasten the crane-cable hook to the sus-pension bolt (A) of the vertical waling.The crane-hoisting lugs on the formwork elements must not be used for lifting the formwork unit.

● Angle of inclination β: max. 30°● Brace the vertical waling sufficiently against

oblique pull (B) . Tightening torque of the couplers (C) : 50 Nm

● Bring the travelling unit as close to the cen-tre-of-gravity position as possible, and secure the Swivel bearing plate with the Swivel bolts.

● If lifting past sloping walls, fasten an over-hanging lifting device to the vertical waling.Where the formwork is inclined forward, check whether a tension guy-bracing chain is needed.

● When a single dam formwork unit is lifted, two open ends are left in the formwork sys-tem. These must be secured by mounting side protection (e.g. Handrail clamp S).

WARNING➤ "Passenger transportation" is forbidden!➤ Remove any loose parts from the scaffold

and formwork before lifting.

Length of chain = at least the space between the slinging pointsThis automatically leads to the required angle of inclinationβ.

A Suspension boltB Bracing against oblique pull (e.g. scaffolding tube)C Screw-on couplers

9706-221-01

A

B

C

Page 31: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork General remarks

31999706002 - 10/2010

The Formwork Experts

Page 32: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

32 999706002 - 10/2010

General remarks User information Doka dam formwork

The Formwork Experts

Possible formwork systems

Timber-beam formworke.g. Large-area formwork Top50With timber-beam formwork, the Swivel bearing plate D15 or D22 (D) must be used.

Attaching the formwork:➤ Fasten the formwork element (A) to the vertical wal-

ing (C) with the Waling-to-bracket holder D22 (B) .

Framed formworke.g. framed formwork Framax XlifeIn the case of framed formwork, the choice of swivel bearing plate (D) must be reviewed on a project-spe-cific basis.

Attaching the formwork:➤ Fasten the Steel waling WS10 Top50 (G) to the

framed formwork using the Framax/supporting con-struction frame bolt 36cm (E) and the Super-plate 15.0 (F) .

➤ Fasten the formwork element (A) to the vertical wal-ing (C) with the Waling-to-bracket holder D22 (B) .

For more information, see the User Information booklet "Doka large-area formwork Top50".

9706-211-01

D

A

C

9706

-211

-04 B

For more information, see the User Information booklet "Doka framed formwork Framax Xlife".

9706-211-02

D

A

9706

-211

-05

E

FG

C

9706

-211

-07

B

Page 33: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork General remarks

33999706002 - 10/2010

The Formwork Experts

Steel formwork Steel formwork must always be planned and dimen-sioned on a project-specific basis:● It must be possible to attach waling-to-bracket hold-

ers● It must be possible to support the adjusting spindlesIn the case of steel formwork, the choice of swivel bear-ing plate (D) must be reviewed on a project-specific basis.

Attaching the formwork:➤ Fasten the formwork element (A) to the vertical wal-

ing (C) with the Waling-to-bracket holder D22 (B) .

9706-211-03

D

A

C

9706

-211

-06 B

Page 34: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

34 999706002 - 10/2010

General remarks User information Doka dam formwork

The Formwork Experts

Structural designThe cantilever centres are computed from various dif-ferent influences:● Pressure of the fresh concrete● Block height● Angle of inclination of formwork● Wind loads

Determining the cantilever centres for perpendicular formwork** Formwork and cantilever bracket perpendicular and in one plane (no kink in wall)

Dam formwork D15

Dam formwork D15/3

Dam formwork D22

☞ This is why dam formwork must always be dimensioned on a project-specific basis.

Pour

ing

heig

ht [m

]

Influence width per bracket [m]

Pour

ing

heig

ht [m

]

Influence width per bracket [m]

Pour

ing

heig

ht [m

]

Influence width per bracket [m]

9706-1003.0

2.9

2.8

2.7

2.6

2.5

2.4

2.3

2.2

2.1

2.00.5 1.0 1.5 2.0 2.5

30 kN/m²

25 kN/m²

35 kN/m²

40 kN/m²

45 kN/m²

50 kN/m²

9706-1013.5

3.4

3.3

3.2

3.1

3.0

2.9

2.8

2.7

2.6

2.50.5 1.0 1.5 2.0 2.5

30 kN/m²

25 kN/m²

35 kN/m²

40 kN/m²

45 kN/m²

50 kN/m²

9706-1024.0

3.9

3.8

3.7

3.6

3.5

3.4

3.3

3.2

3.1

3.00.5 1.0 1.5 2.0 2.5

30 kN/m²

25 kN/m²

35 kN/m²

40 kN/m²

45 kN/m²

50 kN/m²

Allow for the following when performing the structural design calculations:

The formwork used must be dimensioned as required by the cantilever centres (e.g. the correct steel wal-ings must be selected).

Max. service load of the working platform: 1.5 kN/m2 (incl. loads occurring as a result of pouring)

When determining the pressure of the fresh concrete, allow for the following:● Additional loads from concrete spreading devices

(e.g. caterpillar concrete spreader).● Slow setting of the concrete (fly-ash))● Low concrete temperature (cooled concrete)● Low proportion of cement in the concrete

Page 35: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

User information Doka dam formwork General remarks

35999706002 - 10/2010

The Formwork Experts

Doka service offerings

Doka "Ready-to-Use" Service

Ready-to-use formworks - for even the most unusual assignmentsWhatever it is you need to construct from concrete, the Doka Ready-to-Use Service can put together the right formwork for you - quickly, and in guaranteed Doka quality.The professionals from the Doka Ready-to-Use Service plan and make ready-to-use standard and custom formworks exactly to your specifications.By delivering "just-in-time", straight to your site, we save space on your site and reduce the amount of planning and assembly work that you have to do.

Pre-assembled platform decking reduces assembly timesThe pre-assembled platform decking has many advan-tages:● Pre-assembly in the factory or at the depot helps to

cut costs.● Operations scheduling ensures efficient assembly.● High precision ensured by use of assembly bench.● No space problems.● No need for on-site improvisation.● Reduces assembly times on the site.● Cantilever brackets are quickly ready for use.● Low transport volume.

Doka customer training

Formwork training paysForming operations account for the lion’s share of labour costs on concrete construction sites. Modern formwork equipment helps to rationalise operations. By improving the overall construction sequence at the same time, however, further very worthwhile gains in efficiency can be achieved.This requires not only better equipment, but also greater skill in making optimum use of this equipment. Doka can help here, with its specialist training pro-gramme - to help each and every member of the team do his bit towards boosting efficiency and lowering costs.Doka customer training events also look at the form-work equipment and handling methods that are needed in order to achieve optimum safety - knowledge and awareness which can only enhance workplace safety on the site.You’ll find the Doka training programme well worth looking into.Your nearest Doka branch will be pleased to tell you more about Doka's various training offerings.

Page 36: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

Article n°[kg] Article n°[kg]

36 999706002 - 10/2010

Component overview User information Doka dam formwork

The Formwork Experts

Component overviewDoka Climbing SystemsDam formwork

Cantilever bracket D15 K 136.4 580630000Sperrenkonsole D15 K

Cantilever bracket D15/3 170.0 580631000Sperrenkonsole D15/3

Cantilever bracket D22 K 190.0 580610000Sperrenkonsole D22 K

Cantilever bracket D22 F 203.0 580611000Sperrenkonsole D22 F

Vertical waling D15 3.00m U120 87.6 580632000Vertical waling D15 3.50m U140 119.7 580638000Vertical waling D22 3.00m U160 115.5 580613000Vertical waling D22 4.00m U160 154.5 580615000Sperrenriegel D

Spindle strut D15 3.00m 38.0 580633000Spindelstrebe D15 3,00m

Spindle strut D22 3.00m 52.6 580616000Spindelstrebe D22 3,00m

Spindle strut D22 4.00m 55.4 580617000Spindelstrebe D22 4,00m

Swivel bearing plate D15 20.8 580634000Gelenkaufsatz D15

Swivel bearing plate D15 S 18.5 580635000Gelenkaufsatz D15 S

Painted blueWidth: 166 cmDelivery condition: railing included

Painted blueWidth: 215 cmDelivery condition: railing included

Painted blueWidth: 189 cmDelivery condition: railing included

Painted blueWidth: 237 cmDelivery condition: railing included

Painted blue

Painted blueLength: 211 - 252 cm

Painted blueLength: 215 - 258 cm

Painted blueLength: 258 - 301 cm

Painted blueLength: 43.5 cmHeight: 22.8 cm

Painted blueLength: 36.8 cmHeight: 22.4 cm

Page 37: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

Article n°[kg] Article n°[kg]

37999706002 - 10/2010

User information Doka dam formwork Component overview

The Formwork Experts

Swivel bearing plate D22 30.0 580618000Gelenkaufsatz D22

Swivel bearing plate D22 S 26.0 580624000Gelenkaufsatz D22 S

Suspension profile D15/D22 28.6 580621000Hängeprofil D15/D22

Screw-on access bracket MF75 19.0 580669000Anschraubbühne MF75

Swivel plate MF 4.5 580672000Schwenkplatte MF

Manhole B 70/60cm 22.0 581530000Bühnendurchstieg B 70/60cm

Starter block unit D15 48.2 580636000Grundblockriegel D15

Starter block unit D22 80.0 580622000Grundblockriegel D22

Anchor waling 1.95m 76.3 580545000Anchor waling 2.95m 110.0 580546000Ankerriegel

Travelling profile D22 20.0 580619000Fahrprofil D22

Retraction set D15 21.0 580637000Rückfahrset D15

Waling-to-bracket holder 9-24cm 2.9 580639000Riegelhalter 9-24cm

Waling-to-bracket holder D22 2.7 580623000Keilriegelhalter D22

Handrail clamp S 11.5 580470000Schutzgeländerzwinge S

Scaffold tube 48.3mm 1.00m 3.6 682014000Scaffold tube 48.3mm 1.50m 5.4 682015000Scaffold tube 48.3mm 2.00m 7.2 682016000Scaffold tube 48.3mm 2.50m 9.0 682017000Scaffold tube 48.3mm 3.00m 10.8 682018000Scaffold tube 48.3mm 3.50m 12.6 682019000Scaffold tube 48.3mm 4.00m 14.4 682021000Scaffold tube 48.3mm 4.50m 16.2 682022000Scaffold tube 48.3mm 5.00m 18.0 682023000Scaffold tube 48.3mm 5.50m 19.8 682024000Scaffold tube 48.3mm 6.00m 21.6 682025000Scaffold tube 48.3mm .....m 3.6 682001000Gerüstrohr 48,3mm

Painted blueLength: 52 cmHeight: 27 cm

Painted blueLength: 45 cmHeight: 27 cm

GalvanisedHeight: 260 cm

GalvanisedLength: 113 cmHeight: 152 cm

GalvanisedLength: 29 cmHeight: 20 cm

Steel parts galvanisedTimber parts varnished yellowLength: 81 cmWidth: 71 cm

Painted blueLength: 145 cm

Painted blueLength: 147 cm

Painted blue

GalvanisedLength: 114 cm

GalvanisedLength: 114 cm

Galvanised

GalvanisedLength: 31 cmHeight: 31 cm

GalvanisedHeight: 123 - 171 cm

Galvanised

Page 38: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

Article n°[kg] Article n°[kg]

38 999706002 - 10/2010

Component overview User information Doka dam formwork

The Formwork Experts

Screw-on coupler 48mm 50 0.84 682002000Screw-on coupler 48mm 95 0.88 586013000Anschraubkupplung

Swivel coupler 48mm 1.5 582560000Drehkupplung 48mm

Fix-De-Fix remote uncoupling system 3150kg 27.0 586014000Abhängeautomat Fix-De-Fix 3150kg

Warning sign "No entry" 300x300mm 0.70 581575000Verbotsschild "Zutritt Verboten" 300x300mm

Ratchet MF 3/4" SW50 3.8 580648000Antriebsknarre MF 3/4" SW50

Tool box GF 6.5 580390000GF-Werkzeugboxincluded in scope of supply:(A) Reversible ratchet 1/2" 0.73 580580000

GalvanisedLength: 30 cm

(B) Fork wrench 13/17 0.08 580577000(C) Fork wrench 22/24 0.22 580587000(D) Fork wrench 30/32 0.80 580897000(E) Ring spanner 17/19 0.27 580590000(F) Extension 11cm 1/2" 0.20 580581000(G) Extension 22cm 1/2" 0.31 580582000(H) Universal joint coupling 0.16 580583000(I) Nut for box spanner 19 1/2" L 0.16 580598000(J) Box nut 13 1/2" 0.06 580576000(K) Box nut 24 1/2" 0.12 580584000(L) Box nut 30 1/2" 0.20 580575000

Additional tools MF 4.1 580682000Zusatzwerkzeuge MFconsisting of:(A) Reversible ratchet 3/4" 1.5 580894000

GalvanisedLength: 50 cm

(B) Box nut 17 1/2" 0.07 580685000(C) Box nut 50 3/4" 0.81 581449000(D) Extension 20cm 3/4" 0.68 580683000(E) Transition piece A 1/2"x3/4" 0.18 580684000(F) Universal cone spanner 15.0/20.0 0.90 581448000

GalvanisedLength: 9 cmWidth-across: 50 mm

GalvanisedWidth-across: 22 mm

GalvanisedWidth-across: 22 mm

Follow the directions in the "Operat-ing Instructions"!

Galvanised

Page 39: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

Article n°[kg] Article n°[kg]

39999706002 - 10/2010

User information Doka dam formwork Component overview

The Formwork Experts

Tie rod system 20.0

Universal climbing cone 20.0 1.2 581442000Universal-Kletterkonus 20,0

Sealing sleeve K 20.0 0.03 581443000Dichtungshülse K 20,0

Cone screw B 7cm 0.86 581444000Konusschraube B 7cm

Pigtail anchor 20.0 2.0 581450000Wellenanker 20,0

Stop anchor 20.0 22cm 1.6 581452000Sperranker 20,0 22cm

Stop anchor 20.0 45cm 2.1 581453000Sperranker 20,0 45cm

Positioning clamp M30 0.19 581833000Vorlaufklemme M30

Positioning disk M30 0.25 581975000Vorlaufscheibe M30

Tie rod system 26.5

Universal climbing cone 26.5 1.1 581987000Universal-Kletterkonus 26,5

Sealing sleeve K 26.5 0.03 581998000Dichtungshülse K 26,5

Pigtail anchor 26.5 3.6 581900000Wellenanker 26,5

GalvanisedLength: 13 cmDiameter: 5 cmTool: Spanner for universal climbing cone 15.0/20.0

GreenLength: 12 cmDiameter: 6 cm

redLength: 10 cmDiameter: 7 cmWidth-across: 50 mm

Non-treatedLength: 76 cm

Non-treated

Non-treated

GalvanisedDiameter: 4 cm

GalvanisedDiameter: 9 cm

GalvanisedLength: 12.6 cmDiameter: 5 cmTool: Spanner for universal climbing cone 15.0/20.0

VioletLength: 12 cmDiameter: 6 cm

Non-treatedLength: 80 cm

Page 40: The FormworkExperts - ACROW - Scaffolding, Formwork ... · Introduction User information Doka dam formwork The FormworkExperts Eurocodes at Doka In Europe, a uniform series of Standards

999706002 - 10/2010The Formwork Experts

Doka dam formwork is the strong system-solution for all mass concrete structures.

Extremely high load-bearing capacity, and a maximum of workplace safety - these are the distinguishing features of Doka dam formwork. With the twin D15 and D22 systems, you can exploit Doka's long experience in the mass-con-

crete structure field to the full.Doka dam formwork is available for either rental or purchase.

At any of the Doka branches in your region.Why not give us a call?

The Doka Group's central plant at Amstetten, Austria

KazakhstanLatviaLithuaniaLuxembourgMaroccoMexicoNetherlandsNew ZealandOmanPanamaPolandPortugalRomaniaRussiaSenegalSerbiaSlovakiaSloveniaSpainSwitzerlandTaiwanThailandUkraineVietnam

Doka internationalDoka GmbH

Josef Umdasch Platz 1, A 3300 Amstetten, AustriaTel.: +43 (0)7472 605-0, Fax: +43 (0)7472 64430

E-Mail: [email protected]: www.doka.com

AlgeriaSARL Doka Algérie24 A Route de la RassautaBordj-El-Kifane, BP 170, 16120 AlgerTelephone: +213 (0)21 21 27 26Telefax: +213 (0)21 21 28 98E-Mail: [email protected]

CanadaDoka Canada Ltd./Ltée5404 - 36th Street S.E.Calgary AB T2C 1P1Telephone: +1 403 243-6629Telefax: +1 403 243-6787E-Mail: [email protected]

ChinaDoka Formwork (Shanghai) Co. Ltd.Bldg. 2, No.3883 Yuanjiang RoadMinhang DistrictShanghai 201109Telephone: +86 21 6090 0899Telefax: +86 21 6090 1099E-Mail: [email protected]

IndiaDoka India Pvt. Ltd.Hiranandani Business ParkSentinel Bldg 2nd FloorCommercial Premises No 201&202Powai, Mumbai - 400 076Telephone: +91 22 402 64435Telefax: +91 22 402 64436E-Mail: [email protected]

IrelandDoka Ireland Formwork Techn. Ltd.Monasterboice, DroghedaCounty LouthTelephone: +353 (0)41 686 1620Telefax: +353 (0)41 686 1525E-Mail: [email protected]

JapanDoka Japan K.K.Miwanoyama 744-6 Nagareyama-shi270-175 Chiba-KenTelephone: +81 (0)471 78 8808Telefax: +81 (0)471 78 8812E-Mail: [email protected]

KoreaDoka Korea Ltd.Rm.N.220, Doosan Venture Digm Bldg., 126-1 Pyeongchon-Dong, Dongan-Gu, 431-755 Anyang City, Gyeonggi-DoTelephone: +82 31 478 3700Telefax: +82 31 478 3701E-Mail: [email protected]

KuwaitDoka KuwaitDiv. of Riham Gen. Trad.& Cont. Co.P.O. Box 2217 Salmiyah22023 KuwaitTelephone: + 965 2 4822 462Telefax: +965 2 4822 472E-Mail: [email protected]

LebanonDoka Branch LebanonSodeco Square, Block C / 9th floorBeirutTelephone: +961 (0)1 612569Telefax: +961 (0)1 612570E-Mail: [email protected]

NorwayDoka Norge ASHeggstadmoen 4N 7080 HeimdalTelephone: +47 72 89 38 10Telefax:n +47 72 89 38 11E-Mail: [email protected]

Other subsidiaries andrepresentatives:

AngolaAzerbaijanBahrainBelgiumBelarusBosnia andHerzegovinaBrazilBulgariaChileCroatiaCzech RepublicDenmark EgyptEstoniaFinlandFranceGermanyGreece HungaryIceland IranItalyJordan

QatarDoka Qatar WLLP.O.Box 23439Doha, QatarTelephone: +974 44500628Telefax: +974 44500608E-Mail: [email protected]

Saudi ArabiaDoka Formwork TechnologyMahmoud Othman & Sons LLCP.O. Box 7620Jeddah 21472Telephone: +966 0)2 669 10 08Telefax: +966 (0)2 664 86 25E-Mail: [email protected]

SingaporeDoka Formwork Pte. Ltd.9 Gul CircleSingapore 629565Telephone: +65 6897 7737Telefax: +65 6897 8606E-Mail: [email protected]

South AfricaDoka South Africa (Pty) Ltd.Johannesburg BranchCA Brand Bldg, 2 Sebasa RoadChloorkop Ext.10Kempton Park 1619Telephone: +27 (0)11 310 9709Telefax: +27 (0)11 310 9711E-Mail: [email protected]

SwedenDoka Sverige ABKurödsvägen 20S 451 55 UddevallaTelephone: +46 (0)10 45 16 300Telefax: +46 (0)10 45 16 309E-Mail: [email protected]

TunisiaDoka Tunisia Ltd.Bureau de LiaisonZone Industrielle, Rue d l‘usineLe Kram 2015 TunisTelephone: +216 (0)71 977 350Telefax: +216 (0)71 977 856E-Mail: [email protected]

TurkeyDoka Kalip-IskeleSanayi ve Ticaret A.S.Güzeller Org. San. BölgesiInönü Mah. Nazarbayev Sok. No:1941400 Gebze, KocaeliTelephone: +90 262 751 50 66Telefax: +90 262 751 50 05E-Mail: [email protected]

United Arab EmiratesDoka Gulf FZEP.O. Box 61407Jebel Ali Free Zone, DubaiTelephone: +971 (0)4 881 8096Telefax: +971 (0)4 881 8097E-Mail: [email protected]

United KingdomDoka UK Formwork Technologies LtdMonchelsea Farm, Heath RoadBoughton MonchelseaMaidstone, Kent, ME17 4JDTelephone: +44 (0)1622 74 90 50Telefax: +44 (0)1622 74 90 33E-Mail [email protected]

USADoka USA, Ltd.214 Gates RoadLittle Ferry, NJ 07643Telephone: +1 201 329-7839Telefax: +1 201 641-6254E-Mail: [email protected]: www.dokausa.com