The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for...

28
- 999806002 10/2013 en-GB The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02

Transcript of The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for...

Page 1: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

-999806002 10/2013en-GB

The Formwork Experts.

User InformationInstructions for assembly and use (Method statement)

Dokaflex 15

98060-201-02

Page 2: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

2 999806002 - 10/2013

User Information Dokaflex 15

Contents3 Introduction3 Elementary safety warnings6 Doka services

88 Product description

10 System logic for all floor-slabs up to 15 cm thick

11 Instructions for assembly and use18 Adaptability19 Dokaflex 15 system components – also for

slab thicknesses of over 15 cm20 Floor formwork around edges and drop

beams25 Fall-arrest systems on the structure

26 Component overview

Page 3: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15 Introduction

3999806002 - 10/2013

IntroductionElementary safety warningsUser target groups

▪ This manual is aimed at all persons who will be work-ing with the Doka product or system that it describes. It contains information on the standard design for setting up this system, and on correct, compliant uti-lisation of the system.

▪ All persons working with the product described herein must be familiar with the contents of this man-ual and with all the safety instructions it contains.

▪ Persons who are incapable of reading and under-standing this booklet, or who can do so only with dif-ficulty, must be instructed and trained by the cus-tomer.

▪ The customer is to ensure that the information mate-rials provided by Doka (e.g. User Information book-lets, Instructions for Assembly and Use, Operating Instruction manuals, plans etc.) are available to all users, and that they have been made aware of them and have easy access to them at the usage location.

▪ In the relevant technical documentation and form-work utilisation plans, Doka shows the workplace safety precautions that are necessary in order to use the Doka products safely in the usage situations shown. In all cases, users are obliged to ensure compliance with national laws, Standards and rules throughout the entire project and to take appropriate additional or alternative workplace safety precautions where necessary.

Hazard assessment

▪ The customer is responsible for drawing up, docu-menting, implementing and continually updating a hazard assessment at every job-site. This document serves as the basis for the site-spe-cific hazard assessment, and for the instructions given to users on how to prepare and utilise the sys-tem. It does not substitute for these, however.

Remarks on this document

▪ This manual can also be used as a generic method statement or incorporated with a site-specific method statement.

▪ Many of the illustrations in this booklet show the situation during formwork assembly and are therefore not always complete from the safety point of view.Any safety accessories not shown in these illustra-tions must still be used by the customer, in accord-ance with the applicable rules and regulations.

▪ Further safety instructions, especially warnings, will be found in the individual sections of this document!

Planning

▪ Provide safe workplaces for those using the form-work (e.g. for when it is being erected/dismantled, modified or repositioned etc). It must be possible to get to and from these workplaces via safe access routes!

▪ If you are considering any deviation from the details and instructions given in this booklet, or any application which goes beyond those described in the booklet, then revised static cal-culations must be produced for checking, as well as supplementary assembly instructions.

Regulations; industrial safety

▪ All laws, Standards, industrial safety regulations and other safety rules applying to the utilisation of our products in the country and/or region in which you are operating must be observed at all times.

▪ If a person or object falls against, or into, the side-guard component and/or any of its accessories, the component affected may only continue in use after it has been inspected and passed by an expert.

Page 4: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

4 999806002 - 10/2013

Introduction User Information Dokaflex 15

Rules applying during all phases of the assignment:

▪ The customer must ensure that this product is erected and dismantled, reset and generally used for its intended purpose in accordance with the applica-ble laws, Standards and rules, under the direction and supervision of suitably skilled persons. These persons' mental and physical capacity must not in any way be impaired by alcohol, medicines or drugs.

▪ Doka products are technical working appliances which are intended for industrial/commercial use only, always in accordance with the respective Doka User Information booklets or other technical docu-mentation authored by Doka.

▪ The stability of all components and units must be ensured during all phases of the construction work!

▪ The functional/technical instructions, safety warn-ings and loading data must all be strictly observed and complied with. Failure to do so can cause acci-dents and severe (even life-threatening) damage to health, as well as very great material damage.

▪ Fire-sources are not permitted anywhere near the formwork. Heating appliances are only allowed if properly and expertly used, and set up a safe dis-tance away from the formwork.

▪ The work must take account of the weather condi-tions (e.g. risk of slippage). In extreme weather, steps must be taken in good time to safeguard the equipment, and the immediate vicinity of the equip-ment, and to protect employees.

▪ All connections must be checked regularly to ensure that they still fit properly and are functioning cor-rectly. It is very important to check all screw-type connec-tions and wedge-clamped joins whenever the con-struction operations require (particularly after excep-tional events such as storms), and to tighten them if necessary.

▪ It is strictly forbidden to weld Doka products – in par-ticular anchoring/tying components, suspension components, connector components and castings etc. – or otherwise subject them to heating. Welding causes serious change in the microstruc-ture of the materials from which these components are made. This leads to a dramatic drop in the failure load, representing a very great risk to safety.The only articles which are allowed to be welded are those for which the Doka literature expressly points out that welding is permitted.

Assembly

▪ The equipment/system must be inspected by the customer before use, to ensure that it is in suitable condition. Steps must be taken to rule out the use of any components that are damaged, deformed, or weakened due to wear, corrosion or rot.

▪ Combining our formwork systems with those of other manufacturers could be dangerous, risking damage to both health and property. If you intend to combine different systems, please contact Doka for advice first.

▪ The equipment/system must be assembled and erected in accordance with the applicable laws, Standards and rules by suitably skilled personnel of the customer's, having regard to any and all required safety inspections.

▪ It is not permitted to modify Doka products; any such modifications constitute a safety risk.

Erecting the formwork

▪ Doka products and systems must be set up so that all loads acting upon them are safely transferred!

Pouring

▪ Do not exceed the permitted fresh-concrete pres-sures. Over-high pouring rates overload the form-work, cause greater deflection and risk breakage.

Striking the formwork

▪ Do not strike the formwork until the concrete has reached sufficient strength and the person in charge has given the order for the formwork to be struck!

▪ When striking the formwork, never use the crane to break concrete cohesion. Use suitable tools such as timber wedges, special pry-bars or system features such as Framax stripping corners.

▪ When striking the formwork, do not endanger the stability of any part of the structure, or of any scaf-folding, platforms or formwork that is still in place!

Page 5: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15 Introduction

5999806002 - 10/2013

Transporting, stacking and storing

▪ Observe all regulations applying to the handling of formwork and scaffolding. In addition, the Doka slinging means must be used - this is a mandatory requirement.

▪ Remove any loose parts or fix them in place so that they cannot be dislodged or fall free!

▪ All components must be stored safely, following all the special Doka instructions given in the relevant sections of this manual!

Maintenance

▪ Only original Doka components may be used as spare parts. Repairs may only be carried out by the manufacturer or authorised facilities.

Miscellaneous

We reserve the right to make alterations in the interests of technical progress.

Symbols used

The following symbols are used in this booklet:

Important noteFailure to observe this may lead to malfunc-tion or damage.

CAUTION / WARNING / DANGERFailure to observe this may lead to material damage, and to injury to health which may range up to the severe or even life-threaten-ing.

InstructionThis symbol indicates that actions need to be taken by the user.

Sight-checkIndicates that you need to do a sight-check to make sure that necessary actions have been carried out.

TipPoints out useful practical tips.

ReferenceRefers to other documents and materials.

Page 6: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

6 999806002 - 10/2013

Introduction User Information Dokaflex 15

Doka servicesSupport in every stage of the project

Doka offers a broad spectrum of services, all with a sin-gle aim: to help you succeed on the site.Every project is unique. Nevertheless, there is one thing that all construction projects have in common – and that is a basic structure with five stages. We at Doka know our clients' varying requirements. With our consulting, planning and other services, we help you achieve effective implementation of your formwork assignment using our formwork products – in every one of these stages.

Project Development Stage Bidding Stage Project Management Planning Stage

Taking well-founded decisions thanks to professional advice and consulting

Optimising the preliminary work with Doka as an experienced part-ner

Controlled, regular forming oper-ations, for greater efficiency resulting from realistically calculated formwork concepts

Find precisely the right formwork solutions, with the aid of ▪ help with the bid invitation ▪ in-depth analysis of the initial sit-

uation ▪ objective evaluation of the plan-

ning, execution, and time-risks

Draw up potentially winning bids, by ▪ basing them on realistically calcu-

lated guideline prices ▪ making the right formwork

choices ▪ having an optimum time-calcula-

tion basis

Plan cost-effectively right from the outset, thanks to ▪ detailed offers ▪ determination of the commission-

ing quantities ▪ co-ordination of lead-times and

handover deadlines

1 2 3

Page 7: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15 Introduction

7999806002 - 10/2013

The advantages for you thanks to professional advice and consulting

▪ Cost savings and time gains When we advise and support you right from the word "go", we can make sure that the right formwork systems are chosen and then used as planned. This lets you achieve optimum utilisation of the formwork equipment, and effec-tive forming operations because your workflows will be correct.

▪ Maximised workplace safety The advice and support we can give you in how to use the equip-ment correctly, and as planned, leads to greater safety on the job.

▪ Transparency Because our services and costs are completely transparent, there is no need for improvisation dur-ing the project – and no unpleas-ant surprises at the end of it.

▪ Reduced close-out costs Our professional advice on the selection, quality and correct use of the equipment helps you avoid damage, and minimise wear-and-tear.

Concrete Construction Stage Project Close-out Stage

Optimum resource utilisation with assistance from the Doka Formwork Experts

Seeing things through to a posi-tive conclusion with professional support

Workflow optimisation, thanks to ▪ thorough utilisation planning ▪ internationally experienced pro-

ject technicians ▪ appropriate transport logistics ▪ on-site support

Doka Services are a byword for transparency and efficiency here, offering ▪ jointly handled return of rented

formwork ▪ professional dismantling ▪ efficient cleaning and recondition-

ing using special equipment

4 5

Page 8: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

8 999806002 - 10/2013

User Information Dokaflex 15

Product descriptionDokaflex 15 - the versatile hand-set system for floor-slabs

Dokaflex 15 can easily be adapted to fit any layout, simply by telescoping the Doka H16 beams. ▪ no structural-design work is needed, as '1-2-5'

shows you the maximum spacings for all slabs up to 15 cm thick

▪ you can tell at a glance whether the formwork has been set up correctly

Further advantages: ▪ infill zones are managed within the system, making it

easy to accommodate walls and columns ▪ for shoring heights of up to 3.80 m ▪ any type of form-facing can be used ▪ no need to measure up ▪ flexible adaptation possible for larger slab thick-

nesses

Small number of system components - all perfectly co-ordinated

98060-206-01

AB

C D

E

F

Page 9: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15

9999806002 - 10/2013

(A) DokaPly eco

▪ special surface coating for superb-quality concrete faces

▪ can be used on both sides ▪ easy to clean, with high-pressure spray cleaner ▪ space-saving storage and handling ▪ alternatively, it is also possible to use Doka formwork

sheets 3-SO

(B) Doka beams H16 P

▪ are used as both primary and secondary beams ▪ tried-and-tested end-reinforcement with bevelled

beam-ends and extra plastic rivet in beam-flange ▪ pre-defined positioning points as reference marks for

setting-up and checking the formwork

a ... 16 cmb ... 6.5 cmc ... 3.5 cm

(C) 4-way head DF15

▪ stabilises the primary beams so that these cannot tip over on their sides

(D) Supporting head DF15

▪ easy to mount to the floor prop ▪ for fixing intermediate props to the primary beam

(E) Doka floor props Eco 15

Doka floor props Eco are extendable floor props made of steel. They are designed for use as vertical props for temporary structures.The main features: ▪ high load-bearing capacity

- permitted capacity of Eco 15: 15 kN as per trials to US Standards (ANSI)

▪ Quick connection: Head adapters of various types can be attached in a crane-handling-safe manner with the spring-locked connecting pin

▪ Drop-out latch: For safety reasons, Doka props have latches to pre-vent the inner tube sliding out of the outer tube.

▪ special thread geometry, which makes the prop eas-ier to release even when it is under high load

▪ holes in the adjusting nut to make it easier to operate ▪ When the prop is pushed in all the way, it still leaves

a clear 10 cm gap so that the operator's hands are not trapped.

▪ Galvanised, long-life constructional design

(F) Removable folding tripod DF15

▪ for holding Eco 15 floor props upright ▪ swing-out legs allow flexible placement in con-

stricted situations such as along edges and in cor-ners

Permitted values: ▪ Permitted bending moment: 2.7 kNm ▪ Permitted shear force: 8.5 kN

Follow the directions in the "Timber formwork beams" User Information booklet!

Single H16 primary beam Overlapping H16 primary beams

98060-231-01

a

b

c

9806

0-22

3-01

9806

0-22

2-01

WARNING➤ It is not permitted to use the Floor prop

extension 0.50m.

98060-218-02

Page 10: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

10 999806002 - 10/2013

User Information Dokaflex 15

System logic for all floor-slabs up to 15 cm thickThe set-up procedure has an easy-to-understand logic which reduces the amount of design and operations-scheduling work that is needed.

Spacing and positions of the component parts

No matter whether the beams are resting on, between or next to the marks, the maximum spacing is always plain to see.You can tell at a glance whether the formwork has been erected correctly, and without having to measure up.

x ... 0.5 m

Primary and secondary beams

The 3.90m long Doka beam H16 P is used as a pri-mary beam, and the 3.30m long H16 P beam as a secondary beam.

Format of the formwork sheets

The DokaPly eco (18 or 21mm) sheets are sized to fit exactly into the grid of the Dokaflex system.

A Mark

1 mark = 0.5 m ▪ max. spacing of secondary beams ▪ max. cantilever of edge-beam ▪ min. cantilever in primary-beam overlap zone

2 marks = 1.0 m ▪ max. spacing of props

5 marks = 2.5 m ▪ max. spacing of primary beams

x

98060-224-01

A

A Floor prop Eco 15 + 4-way head DF15 + Removable folding tri-pod DF15

B Floor prop Eco 15 + Supporting head DF15C Doka beam H16 P 3.30m (secondary beam)D Doka beam H16 P 3.90m (primary beam)

The primary beams should be orientated at right angles to the direction of an uneven length/width of room (5 m, 7 m, 9 m, etc.). This makes more efficient use of the potential of the system.

11

1

2 2

1

1

C

D

98060-200-01

B A

5

5

Page 11: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15

11999806002 - 10/2013

Instructions for assembly and useErecting the formwork

Putting up the floor props➤ Roughly adjust the height of the floor prop, using the

fastening clamp.

➤ Insert the 4-way head DF15 into the prop.

➤ Place primary and secondary beams along the edges.The marks on the beams show you the maximum spacings: - 5 marks for primary beams - 6 marks (3 x 2) for props held in a removable folding tripod

➤ Put up each removable folding tripod.

➤ Put the prop into the tripod and fix it in place with the clamping bracket (tap this with the hammer). Before anybody steps onto the formwork, check again to make sure that the props have been cor-rectly fixed in the tripods.

Setting up tripods in corners or against walls

If it is not possible to completely unfold the legs of the tripod – e.g. at the edges of a structure or at floor break-throughs etc. – we recommend fastening this tripod to an adjacent floor prop instead, where there is room for the legs to be completely unfolded.

Make sure that the nut is in the right position. To back off the prop, it must be possible to lower the nut by at least another 4 cm, by turn-ing it with the fastening clamp.

CAUTION➤ If you transport floor props with the 4-way

heads still attached, you must secure these with a Spring-locked connecting pin 16 mm to prevent them dropping out. This is partic-ularly important when they are transported in the horizontal.

9806

0-20

7-02

�4 c

m

98060-208-01

☞ ➤ Do not oil or grease clamping connections.

A Primary beamB Secondary beam

98060-207-01

98060-205-01

5

22

2

A B

98060-210-01 98060-210-02

Page 12: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

12 999806002 - 10/2013

User Information Dokaflex 15

Inserting the primary beams➤ Using beam-forks, place the primary beams into the

4-way heads.

The 4-way heads can hold both single beams (on edge-of-room props) and double beams (at over-laps).

➤ Adjust the primary beams to the correct floor-slab height.

Placing the secondary beams on the primary beams➤ Use the beam forks to place the secondary beams

on the primary beams, with an overlap.Maximum spacing of secondary beams: 1 mark

WARNING➤ It is not permitted to set down any loads on

the floor-slab formwork (e.g. beams, form-work sheets, reinforcement steel) until after the intermediate props have been set up!

▪ Wheel-around scaffold DF:- collapsible wheelaround platform made

of light alloy- variable working heights of up to 3.50 m

(max. platform height 1.50 m)- width of scaffold: 0.75 m- When work is being carried out near

drop-off edges (i.e. at a distance of < 2 m), the 'Wheel-around scaffold DF accessory set' (consisting of a toeboard and intermediate guardrail) is needed.

- Follow the directions in the User Informa-tion booklet!

98060-204-01

9720

-004

Especially in edge zones, 'Bracing frames Eco' can be used as a sturdy alternative to 'Remov-able folding tripods'.

Planks can be attached to the floor props as diagonal braces, using the Bracing clamp B.

➤ If it is planned to lay the panels on the sec-ondary beams working from below, always lay only as many secondary beams in place as are needed for placing the next row of panels.

Be sure to place a beam (or double beam) wherever there is to be a joint between the panels.

9776-201-01

98060-225-01

98060-203-01

Page 13: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15

13999806002 - 10/2013

Putting up the intermediate props➤ Place a Supporting head DF15 on the inside tube of

the prop and secure it with a Spring-locked connect-ing pin 16 mm.

Maximum prop spacing: 2 marks apart

Mounting slab stop-ends and fall-arrest railings

➤ Mount the slab stop-ends➤ Mount guard rails around all exposed edges.➤ Lay DokaPly eco sheets at right angles to the sec-

ondary beams.

➤ Spray the DokaPly eco sheets with concrete release agent.

Pouring

To protect the surface of the form-facing, we recom-mend using a vibrator with a protective rubber cap.

☞ Important note:➤ Put up the intermediate props so that they

force-fit. It is not allowed to make some props higher than others!

A Supporting head DF15B Doka beam H16 PC Spring-locked connecting pin 16 mm

98060-230-01

98060-202-01

9806

0-21

8-01

AB

C

2

☞ ➤ Use personal fall arrest systems to protect against fall hazards when working on unse-cured slab-edges (e.g. Doka personal fall-arrest set).

Where necessary (e.g. edge zones), secure the form-ply with nails.Recommended nail lengths ▪ Sheet thickness 18 - 21 mm - approx. 50 mm

☞ Windproofing ▪ For increased stability, in larger rooms, the

full erection sequence of "primary beams + secondary beams + formwork sheets" should be carried out progressively for suc-cessive sub-areas of the room. When doing this, provide suitable bracing to walls or columns.

▪ If there is any risk of the formwork being blown over, all free-standing, non-enclosed areas of slab formwork must be secured dur-ing work-breaks and when work finishes for the day.

▪ Horizontal forces at exposed slab-edges, drop beams or steps in ceiling slabs must be restrained by strutting or back-stays.

98060-201-01

Page 14: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

14 999806002 - 10/2013

User Information Dokaflex 15

Striking

Removing the intermediate props➤ Back off and remove the intermediate props.

Lowering the floor-slab formwork➤ Back off the props and lower the floor-slab formwork

approx. 4 cm.

Removing parts that are no longer needed➤ Turn the secondary beams over onto their sides, pull

them out and put them in the stacking pallet. Leave the beams under the panel-joints in place.

➤ Remove the DokaPly eco sheets.

➤ Remove the remaining secondary beams and the primary beams.

☞ Comply with the stripping times stipulated by the structural designer.

98060-214-01

9806

0-20

7-02

4 c

m

98060-215-01

4 c

m

98060-217-01

Page 15: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15

15999806002 - 10/2013

Removing the floor props1) Hold the inner tube with one hand.2) Open the fastening clamp to unfix the inner tube.

Guide this by hand while lowering it into the outer tube.

Reshoring

➤ Before pouring the next floor-slab (i.e. above the one that has just been stripped), put up reshoring props as stipulated by the structural designer.

98060-207-04

1

2

Page 16: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

16 999806002 - 10/2013

User Information Dokaflex 15

Setting up the system using Bracing frames Eco

Especially in edge zones, 'Bracing frames Eco' can be used as a sturdy alternative to 'Removable folding tri-pods'.Features: ▪ Only suitable for mounting to the outer tube. ▪ Captively integrated quick-fixing mechanism (clamp-

ing bracket with wedge). ▪ Is used together with Diagonal crosses 9.xxx.

Assembly

➤ Join together 2 Bracing frames Eco with 2 suitable Diagonal crosses 9.xxx (Close-up 1).

➤ Fix the Floor props Eco onto the Bracing frame Eco with the quick-fixing mechanisms (Close-up 2).

➤ Mount the superstructure.

a ... e.g. 150 cm (with Diagonal crosses 9.150)b ... 125 cmc ... 88 cm

Close-up 1: Connecting the diagonal cross

Close-up 2: Quick-fixing mechanism open

Quick-fixing mechanism closed

☞ Important note: ▪ Only allowed to be used as a set-up aid. ▪ Not suitable for sustaining horizontal loads

during pouring.

A Bracing frame EcoB e.g. Diagonal cross 9.150C e.g. Doka floor prop Eco 15 300D Quick-fixing mechanism (clamping bracket with wedge)

ab

c

A

B

C

Tr94

8-20

0-01

1

2

B

Tr948-200-02

A

C

Tr948-202-01

A

D

Tr948-200-03

A

D

C

Page 17: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15

17999806002 - 10/2013

Bracing clamp B

Planks can be attached to the floor props as diagonal braces, using the Bracing clamp B.

Possible plank/floor-prop combinations with the Bracing clamp B

☞ Important note: ▪ Only allowed to be used as a set-up aid. ▪ Not suitable for sustaining horizontal loads

during pouring. ▪ Always hammer in the wedge from top to bot-

tom!

A Bracing clamp BB Doka floor prop Eco 15C Plank

Eco 15Plank

2.4 x 15 3 x 15 4 x 15 5 x 10 5 x 12 5 x 15IT OT IT OT IT OT IT OT IT OT IT OT

300 — ✓ — ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓

350 — ✓ — ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓

Legend:IT Inner tubeOT Outer tube✓ Possible to combine— Not possible to combine

B

98060-241-01

A

C

Page 18: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

18 999806002 - 10/2013

User Information Dokaflex 15

AdaptabilityClosures and adjustments

Infill zones are solved within the system - with no spe-cial accessories needed. The necessary adaptation is made by overlapping the Doka beams and inserting strips of formwork sheeting.

Grid and flexibility - in one system

Dokaflex also adapts to difficult layouts.

Adaptation along edge Adaptation around columns

A DokaPly ecoB Fitting boards in the closure zone

☞ When using formwork sheets whose load capacity is directionally dependent, make sure that these are laid in the right direction.

9806

0-21

9-01

98060-220-01

A

B

98060-221-01

A

B

9720-211-01

Page 19: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15

19999806002 - 10/2013

Dokaflex 15 system components – also for slab thicknesses of over 15 cmOnly one system in use on the site

Up to a slab thickness of 15 cm, no structural design work is needed. However, it is also possible to compute the exact quantities – of the same system components – that will be needed for any given thickness of slab, with reference to the table. In this way, only as much formwork equipment is used as is really needed, as dictated by the slab load.

On the site, the easy-to-use slide-rule is ideal for deter-mining the permissible spacing of primary beams and props.

The table allows for a live load of 1.5 kN/m2. Mid-span deflection has been limited to l/500.

d ... max. 0.50 m

98060-101

Sla

b th

ickn

ess

[cm

]

Sla

b lo

ad[k

N/m

2 ]

Max. permitted spacing of primary beams b [m]

for a secondary-beam spacing c [m] of

Max. permitted spacing of props a [m]for a pre-selected primary-beam spacing b of

0.33 m 0.50 m 0.63 m 1.50 m 1.75 m 2.00 m 2.25 m 2.50 m 2.75 m 3.00 m

10 4.30 3.20 3.02 2.80 1.83 1.69 1.58 1.49 1.40 1.27 1.1611 4.55 3.20 2.93 2.72 1.78 1.65 1.54 1.45 1.32 1.20 1.1012 4.80 3.20 2.86 2.65 1.73 1.60 1.50 1.39 1.25 1.14 1.0413 5.05 3.19 2.79 2.59 1.69 1.56 1.46 1.32 1.19 1.08 0.9914 5.30 3.12 2.72 2.53 1.65 1.53 1.42 1.26 1.13 1.03 0.9415 5.55 3.05 2.67 2.48 1.61 1.49 1.35 1.20 1.08 0.98 0.9016 5.80 2.99 2.61 2.43 1.58 1.46 1.29 1.15 1.03 0.94 —17 6.05 2.94 2.57 2.38 1.54 1.42 1.24 1.10 0.99 0.90 —18 6.30 2.89 2.52 2.34 1.51 1.36 1.19 1.06 0.95 0.87 —19 6.55 2.84 2.48 2.30 1.48 1.31 1.15 1.02 0.92 0.83 —20 6.80 2.79 2.44 2.25 1.46 1.26 1.10 0.98 0.88 0.80 —

cc d

c

a a

c

C

D

98060-200-01

B A

b

b

A Floor prop Eco 15 + 4-way head DF15 + Removable folding tri-pod DF15

B Floor prop Eco 15 + Supporting head DF15C Doka beam H16 P 3.30m (secondary beam)D Doka beam H16 P 3.90m (primary beam)

Page 20: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

20 999806002 - 10/2013

User Information Dokaflex 15

Floor formwork around edges and drop beamsSlab stop-ends

Universal end-shutter support 30cm

Configuration A: Fastened with nails

d ... slab thickness max. 20 cm

Configuration B: Fastened with Spax screws

d ... slab thickness max. 20 cm

Structural designA Universal end-shutter support 30cmB Nail 3.1x80C Formwork sheet

Tip for striking formwork:➤ Take out the nails on the stop-end side.➤ Put the claw of a hammer under the corner

(put a piece of wood under it to protect the formwork sheeting)

➤ Lever up the end-shutter support

98060-226-01

d

B

A

B

C

98060-228-01

A Universal end-shutter support 30cmC Formwork sheetD Spax screws 4x40 (fully threaded)E Doka beam H16

Max. influence width: afor slab thickness of [cm]

How fastened: Configuration 20 25 304 nails 3.1x80 A 90 50 304 Spax screws 4x40 (fully threaded) B 220 190 160

98060-227-01

d

D

A

D

CE

98060-229-01

a

Page 21: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15

21999806002 - 10/2013

With edge drop-beam

Supported by load-bearing tower

The Load-bearing tower Staxo 40 system can be readily combined with Dokaflex 15 for forming drop beams.

Supported by Dokaflex 15 and Bracing frames Eco

Using 'Bracing frames Eco' with 'Diagonal crosses 9.xxx' increases the stability of the floor props. This allows drop-beam constructions to be formed more quickly at slab-edges, and provides greater safety dur-ing system set-up.

A Dokaflex 15B Load-bearing tower Staxo 40C Lashing strap 5.00mD Doka Express anchor 16x125mm and Doka coil 16mmE Handrail post XP 1.20m with Step bracket XPF Handrail clamp S

WARNING➤ Where formwork beams cantilever out a long

way, secure them against accidental lift-out.

98060-211-01

E

F

B

C

A

D

A Dokaflex 15B Bracing frame EcoC Lashing strap 5.00mD Doka Express anchor 16x125mm and Doka coil 16mmE Handrail post XP 1.20m with Step bracket XPF Handrail clamp SG Diagonal cross 9.xxx

98060-239-01

E

F

B

C

A

D

G

Page 22: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

22 999806002 - 10/2013

User Information Dokaflex 15

Supported by Dokaflex 15 Using Dokaflex on edge zones

When using Dokaflex, remember the following points: ▪ In order to be able to transfer the horizontal forces,

the superstructure components must be firmly attached to one another.

▪ The back-stay can be fastened to either the second-ary or primary beam.

A Dokaflex 15B Board with Bracing clamp BC Lashing strap 5.00mD Doka Express anchor 16x125mm and Doka coil 16mmE Handrail post XP 1.20m with Step bracket XPF Handrail clamp S

98060-212-01

F

E

A

D

BC

WARNING➤ For work at dangerous heights, the second-

ary-beam elements with the working plat-forms must be preassembled on the ground.

➤ Where working platforms are erected on cantilevering floor-slab formwork, the form-work must be secured against accidental lift-out.

➤ Secondary beams with stop-end formwork must be secured against horizontal pull-out.

➤ In addition, put up a protection platform on the structure, e.g. Folding platform K

Page 23: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15

23999806002 - 10/2013

Drop beams in mid-slab

using Beam-forming head D15

Permitted dimensions of the drop-beam when using Beam-forming head DF15 with Floor prop Eco 15

using Bracing frame Eco

A Dokaflex 15B Beam-forming head DF15C Floor prop Eco 15D Removable folding tripod DF15

Dro

p-be

am h

eigh

t [cm

] inc

l. flo

or-s

lab

heig

ht

Drop-beam width [cm]

V Prop spacing 2.00 mW Prop spacing 1.75 mX Prop spacing 1.50 mY Prop spacing 1.25 mZ Prop spacing 1.00 m

Permitted load-bearing capacity of Floor prop Eco 15 with Beam-forming head DF15: 6.5 kN

98060-213-01

AA

D

B

C

V

W

X

Y

Z

10 15 20 25 30 35 40

85

80

75

70

65

60

55

50

45

40

35

30

98060-100

A Dokaflex 15B Bracing frame EcoC Floor prop Eco 15D Diagonal cross 9.xxx

98060-240-01

AA

B

D

C

Page 24: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

24 999806002 - 10/2013

User Information Dokaflex 15

Tie-back solution

e.g. with Lashing strap 5.00m

For transferring low horizontal loads (stabilisation, V/100, windproofing etc.).

H Horizontal loadV Vertical loadA Back-stay force

Max. tie-back load: 5 kN

WARNING➤ Never attach the tie-back directly to a 4-way

head or floor prop

98060-232-01

H

AV

98060-232-02

Page 25: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

User Information Dokaflex 15

25999806002 - 10/2013

Fall-arrest systems on the structureHandrail post XP 1.20m

▪ Attached with Screw-on shoe XP, railing clamp, Handrail-post shoe or Step bracket XP

▪ Protective grating XP, guard-rail boards or scaffold tubes can be used as the safety barrier

a ... > 1.00 m

Handrail clamp S

▪ Attached with integral clamp ▪ Guard-rail boards or scaffold tubes can be used as

the safety barrier

a ... > 1.00 m

Handrail post 1.10m

▪ Fixed in a Screw sleeve 20.0 or Attachable sleeve 24mm

▪ Guard-rail boards or scaffold tubes can be used as the safety barrier

a ... > 1.00 m

Follow the directions in the "Edge protection system XP" User Information booklet!

Follow the directions in the “Handrail clamp S” User information!

9803

1-20

0-01

a

geprüfte

Sicherheit

9756

-206

-01

a

geprüfte

Sicherheit

Follow the directions in the "Handrail post 1.10m" User Information!

9771

-200

-01

a

geprüfte

Sicherheit

Page 26: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

Article n°[kg] Article n°[kg]

26 999806002 - 10/2013

Component overview User Information Dokaflex 15

Component overview[kg]Article n°Dokaflex 15

Doka floor prop Eco 15 300 10.7 586290000Length: 172 - 300 cmDoka floor prop Eco 15 350 13.3 586291000Length: 197 - 350 cmDoka-Deckenstützen Eco 15

Removable folding tripod DF15 9.4 586294000Stützbein DF15

4-way head DF15 1.6 586292000Vierwegkopf DF15

Supporting head DF15 0.48 586293000Haltekopf DF15

Spring locked connecting pin 16mm 0.25 582528000Federbolzen 16mm

Beam forming head DF15 4.1 586295000Balkenkopf DF15

Bracing frame Eco 17.0 586297000Aufstellrahmen Eco

Diagonal cross 9.060 3.1 582322000Diagonal cross 9.100 4.1 582772000Diagonal cross 9.150 5.2 582773000Diagonal cross 9.165 5.7 582627000Diagonal cross 9.175 6.1 582334000Diagonal cross 9.200 6.6 582774000Diagonal cross 9.250 7.7 582775000Diagonal cross 9.300 9.0 582323000Diagonalkreuz

Bracing clamp B 1.4 586195000Verschwertungsklammer B

Universal end-shutter support 30cm 1.0 586232000Universal-Abschalwinkel 30cm

Handrail clamp S 11.5 580470000Schutzgeländerzwinge S

Galvanised

GalvanisedHeight: 67.5 cmDelivery condition: folded closed

GalvanisedLength: 20 cmWidth: 13 cmHeight: 24 cm

GalvanisedLength: 14 cmWidth: 7 cmHeight: 14 cm

GalvanisedLength: 15 cm

GalvanisedLength: 60 cmWidth: 9 cmHeight: 28 cm

GalvanisedWidth: 137 cmHeight: 88 cm

GalvanisedDelivery condition: folded closed

Painted blueLength: 36 cm

GalvanisedHeight: 21 cm

GalvanisedHeight: 123 - 171 cm

Page 27: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

Article n°[kg] Article n°[kg]

27999806002 - 10/2013

User Information Dokaflex 15 Component overview

Handrail post 1.10m 5.5 584384000Schutzgeländer 1,10m

Attachable sleeve 24mm 0.03 584385000Steckhülse 24mm

Screw sleeve 20.0 0.03 584386000Schraubhülse 20,0

Lashing strap 5.00m 2.8 586018000Zurrgurt 5,00m

Doka express anchor 16x125mm 0.31 588631000Doka-Expressanker 16x125mm

Doka coil 16mm 0.009 588633000Doka-Coil 16mm

Wheel-around scaffold DF 44.0 586157000Mobilgerüst DF

Wheel-around scaffold DF accessory set 13.3 586164000Zubehörset Mobilgerüst DF

Doka beam H16 P 1.80m 6.7 189969000Doka beam H16 P 2.45m 9.1 189961000Doka beam H16 P 2.90m 10.7 189962000Doka beam H16 P 3.30m 12.2 189963000Doka beam H16 P 3.90m 14.4 189966000Doka beam H16 P 4.90m 18.1 189967000Doka beam H16 P 9.00m 33.3 189970000Doka beam H16 P .....m 4.3 189960000Doka-Träger H16 P

Doka beam H16 N 1.80m 6.3 189851000Doka beam H16 N 2.45m 8.6 189802000Doka beam H16 N 2.90m 10.2 189803000Doka beam H16 N 3.30m 11.6 189807000Doka beam H16 N 3.90m 13.7 189805000Doka beam H16 N 4.90m 17.2 189813000Doka beam H16 N 9.00m 31.5 189852000Doka beam H16 N .....m 3.5 189850000Doka-Träger H16 N

Beam fork H16 1.2 176004000Trägergabel H16

DokaPly eco 18mm 250/125cm 28.1 185059000DokaPly eco 21mm 250/62.5cm 16.4 185065000DokaPly eco 21mm 250/125cm 32.8 185058000DokaPly eco

Doka formwork sheet 3-SO 21mm 200/50cm 10.5 186009000Doka formwork sheet 3-SO 21mm 250/50cm 13.1 186011000Doka formwork sheet 3-SO 21mm 250/125cm 32.8 186097000Doka formwork sheet 3-SO 21mm 244/122cm 31.2 186096000Doka-Schalungsplatte 3-SO 21mm

Doka personal fall-arrest set 3.6 583022000Doka-Sicherheitsgeschirr

GalvanisedHeight: 134 cm

GreyLength: 16.5 cmDiameter: 2.7 cm

YellowLength: 20 cmDiameter: 3.1 cm

Yellow

GalvanisedLength: 18 cmFollow fitting instructions!

GalvanisedDiameter: 1.6 cm

AluminiumLength: 185 cmWidth: 80 cmHeight: 255 cmDelivery condition: folded closed

AluminiumTimber parts varnished yellowLength: 189 cm

Varnished yellow

Varnished yellow

Length: 150 cm

Follow the directions in the "Operat-ing Instructions"!

Page 28: The Formwork Experts. Dokaflex 15€¦ · The Formwork Experts. User Information Instructions for assembly and use (Method statement) Dokaflex 15 98060-201-02. 2 ... 10 System logic

999806002 - 10/2013Doka GmbH | Josef Umdasch Platz 1 | 3300 Amstetten | Austria | T +43 7472 605-0 | F +43 7472 66430 | [email protected] | www.doka.com

Near to you, worldwide

Doka is one of the world leaders in developing, manu-facturing and distributing formwork technology for use in all fields of the construction sector.With more than 160 sales and logistics facilities in over 70 countries, the Doka Group has a highly efficient dis-tribution network which ensures that equipment and

technical support are provided swiftly and profession-ally.An enterprise forming part of the Umdasch Group, the Doka Group employs a worldwide workforce of more than 5600.