The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony...

23
SINTEF Byggforsk The first apartment house renovation with Passive House components in Norway 14th International Passive House Conference Dresden, May 28, 2010 Michael Klinski Tor Helge Dokka

Transcript of The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony...

Page 1: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

The first apartment house renovation with Passive House components in Norway

14th International Passive House Conference

Dresden,May 28,2010

MichaelKlinski

Tor HelgeDokka

Page 2: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk 2

168flats,

one-bedrooms(55 m²) and

two-bedrooms(68 m²)

7 similar blocks, 3 storeys high with unheated cellar, built 1968-70

Myhrerenga housing cooperative at Skedsmokorset, 15 km north east of Oslo, nearly same climate with annual mean temperature around 6 °C

Page 3: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Fine …

… and sad

Page 4: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk 4

Many damages

Cracks

Rot Moisture

Page 5: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk 5

Myhrerenga before renovation

Complaints about poor indoor climate, draft problems and cold floor

Exhaust ventilation system Central heating with radiators High energy consumption

(275 – 300 kWh/m²år, overall) 2006: The cooperative wants a facade

rehabilitation and larger balconies Housing Bank and SINTEF suggest

retrofit with PH-components Demonstration project within EKSBO

and IEA SHC task 37 – Construction work starts in February 2010

Page 6: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Building fabric before renovation 5 – 10 cm insulation in

floors towards cellar,walls and roof construction

Poor air tightness Lot of thermal bridges

Page 7: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk 7

Renovationconcept

Added insulation in cellar ceiling,walls and roof

Passive Housewindows and doors

Increased air tightnessand reduction of thermal bridges

Highly efficient balanced ventilation Replacement of oil and electric boilers with air to water

heat pumps and solar collectors Reuse of existing heat distribution system Individual energy accounting (heat and electricity)

Page 8: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Airtightbuilding envelope

including staircase in the cellar

Page 9: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Many details to design

Insulation Insulation blown in

No insulation below, but on wall

Airtightbuilding envelope

including staircase in the cellar

Page 10: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Test wall

Air tightness:expanding foam caulking

Page 11: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

PH-window and vapor permeable wall

Air tightness:expanding foam caulking

OSB-boards and20 cm unbroken 20 cm unbroken insulation on the insulation on the

existing 10 cm stud wallexisting 10 cm stud wall+ new facade lining

Arkitektskap AS

Existing construction

Page 12: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Airtight window/wall solutionafter discussion on-site Existing

construction

Page 13: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Roof and balcony

Air tightness measures:

Air tightening OSB – frameand between stories

Insulation blown in

Existing construction

Page 14: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Air tightness measures:

Balcony and window/door

Existingconstruction

Balcony supports

Page 15: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Calculated U-values [W/m²K]

1.202.7Entry doors

0.802.8Windows and balcony doors

0.230.58Floor construction*

0.110.35Roof

0.15~ 0.45External walls gable

0.120.40External walls main façade

U-value after renovation

U-value before

renovation

Construction

* U-value included the thermal resistance of the unheated cellar

Page 16: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk 16

Balancedventilation

One central air handling unit per block, placed in the cellar Double cross flow heat exchanger (probably)

with high efficient heat recovery ( > 80 %, SFP < 1,5 kW/m³/s

Air supply through old garbage chute Air extract through existing extract shaft >> limited interior work

Page 17: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Energy supply

Only one radiator in theliving room (1-1,5 kW)+ existing radiatorin the bath room

Individual energy accounting (heat and electricity) Renovated boiler house:

3 air-to-water heat pumps(25 kW each, run in cascade)

44 vacuum solar collectors on the nearest block roof 1 electric boiler kept (peak load)

Reuse of existing heat distribution system

Page 18: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

New andlargerbalconies

Arkitektskap AS

Page 19: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Newentrances

Arkitektskap AS

Page 20: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Calculated energy demand

80105275 – 300Sum

404040Electricity use (lighting and appliances)

101010Fans and pumps153030DHW1525195 – 220Space Heating

Delivered energy

Net energy demand

After renovation** (simulated)

Before renovation

(measured)*

Energy Demand [kWh/m²a]

* Varying from year to year** To be measured after renovation

- 88 %

- 72 %

Page 21: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

Increased investment cost for PH-retrofit, in addition to façade renovation – but ...

160131014.3Net additional cost PH-retrofit755906.4Allowances from ENOVA

235190020.7Gross additional cost PH-retrofit615494053.8Conventional façade renovation850684074.5Overall investment cost PH-retrof.504104.5Design + construction supervision

800643070.0Overall construction cost

Cost EUR/m²

Cost NOK/m²

Project cost million NOK

VAT included

Page 22: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

… lower rent per month …

Page 23: The first apartment house renovation with Passive House … · 2014-11-17 · Windows and balcony doors 2.8 0.80 Floor construction* 0.58 0.23 Roof 0.35 0.11 External walls gable

SINTEF Byggforsk

… and additional advantages like:

Increased comfort and indoor climate Lower maintenance cost Substantially higher marked value for the flats,

maybe increased by 2000 kr/m²

Preliminary conclusions: Cost effective renovation with PH-components is possible

in Norwegian average climate Decision making and design/optimization process is more

challenging than in Central-Europe