The FIDIC Red Book – Development from 1987 Standard … - Mr. Toby Randle... · The FIDIC Red...

download The FIDIC Red Book – Development from 1987 Standard … - Mr. Toby Randle... · The FIDIC Red Book – Development from 1987 Standard Form to 2010 MDB Harmonised Edition Toby Randle

If you can't read please download the document

Transcript of The FIDIC Red Book – Development from 1987 Standard … - Mr. Toby Randle... · The FIDIC Red...

  • The FIDIC Red Book Development from 1987 Standard Form to 2010 MDB Harmonised Edition

    Toby RandleToby Randle

  • What is FIDIC?

    Federation Internationaledes Ingenieurs-Conseilsdes Ingenieurs Conseils

    Produces a suite of contractscontracts

    Founded by international i 1913engineers 1913

    First FIDIC Red Book 1973

  • The FIDIC Suite

  • Why Choose FIDIC?

    International favourite

    Well known to funders

    Well respected

    No learning curveg

  • Other Options

    IChemE

    NEC 3

    ICEICE

    ENNA Japan

    AIA, EJDC & AGC USA

    RAIC Canada RAIC - Canada

  • When to Use FIDIC Red/Pink?

    Build-only

    Detailed design provided by Employer / Engineer

    Major civil engineering

    Infrastructure

    NuclearNuclear

  • Key Features of Red Book

    Financial protection for Contractor (clause 2)

    Employer not impartial (clause 3)

    Any Contractor designed works Any Contractor designed works fit for purpose (clause 4)

    Re-measurement (clause 12)

    Payment and progress reports (sub-clauses 4.21 and 14.3)

    Claims (clause 20)Claims (clause 20)

  • Key Features of Pink Book

    Engineers authority unlimited (clause 3)( )

    Financial protection for Contractor (sub-clause 8.1)Co t acto (sub clause 8. )

    Fradulent, corrupt, collusive, coercive collusive, coercive practices (sub-clause 15.6)

    Difficult to terminate (sub-Difficult to terminate (subclause 16.2)

  • Pitfall 1: Loss and Expense

    Sub-clause 20.1 no prolongation cost (also time bar)

    Sub-clause 8.4 no prolongation cost

    Sub-clause 8.9 increased cost for suspension very limitedfor suspension very limited

    Sub-clause 2.1 cost and reasonable loss of profit for delay in accessing sitey g

    Sub-clause 1.9 Contractor friendly provision for cost and reasonable loss of profit for delayed drawings or instructionsdelayed drawings or instructions

  • Pitfall 2: Appendix to Tender

    Complete Appendix to Tender ProperlyTender Properly

    Changes in Cost (cl 13.8)

    Sectional Completion (cl 8.2 and 8.7)

  • Main complaints in relation to Red Book

    Are DAB decisions enforceable?

    FIDIC Guidance

    Attitude of English court

  • Conclusion

    Flexible contract

    Well known to funders Well known to funders

    BUT, enforcement may be difficult

  • If you only remember these things.

    Be careful with loss and expense

    Fill in the Appendix to Tender properlyFill in the Appendix to Tender properly

    Choose your jurisdiction clause wisely

  • And Finally.

    Choice of Contract no substitute for:-substitute for:

    Quality team

    Clarity of design obligations

    Good contract management

    Effective communication

  • The FIDIC Red Book Development from 1987 Standard Form to 2010 MDB Harmonised Edition

    Toby RandleToby Randle